BUILDING STRONG®

Morrison Creek Construction Along Union Pacific Railroad

Construction started May 1st.

Coordinated with Union House Elementary School for placement of crossing guards.

Construction scheduled for completion in October 2012.

Page 3: SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

BUILDING STRONG®

Post Authorization Change Report (PACR)

Preliminary FEMA floodplain information provided by the City of Sacramento contract indicates that a PACR will not be required.

Corps will complete verification of FEMA floodplain model by December 2012.