March 16, 2009 Solenoid Report-Zisman 2

Status (1)•Making slow but steady progress on first Spectrometer Solenoid (“Magnet 2”)— fabrication work on turret completed

o welding radiation shield and LN2 reservoir connections doneo wrapping in MLIo welding outer vacuum covers

— already doneo cold mass leak checkedo condenser sleeves and magnet leads completed

— to doo complete instrumentation feedthroughso complete fill/vent connectionso add weld preps to end plates (under way; weld rings already in place in vacuum vessel)

Page 3: Spectrometer Solenoid Report and Coupling Coil Update

March 16, 2009 Solenoid Report-Zisman 3

Status (2)

•Expect final assembly of radiation shield and vacuum vessel completed this week— leak check next week (week of March 23)— first cool-down expected week of March 30

o keep your fingers crossed!

•Other news— tried tracker go-no-go gauge in Magnet 1 (the earlier one)

o bore was out of magnet but still welded to patch panel and plate– fit fine! (see photo later)

— test will be repeated in Magnet 2 this week after warm bore installed

Page 4: Spectrometer Solenoid Report and Coupling Coil Update

Magnet turret inner components wrapped in MLI

Page 5: Spectrometer Solenoid Report and Coupling Coil Update

Magnet power leads at top of turret

Page 6: Spectrometer Solenoid Report and Coupling Coil Update

Weld ring in place for vacuum vessel end plate (patch panel end)

Page 7: Spectrometer Solenoid Report and Coupling Coil Update

Welding of radiation shield and LN2 reservoir connections

Page 8: Spectrometer Solenoid Report and Coupling Coil Update

Tracker ‘go-no go’ gage in warm bore of Magnet #1

Page 9: Spectrometer Solenoid Report and Coupling Coil Update

March 16, 2009 Solenoid Report-Zisman 9

Coupling Coil Update

•Visited likely vendor for magnet fabrication— Qihuan Mechanical and Electronic Engineering Corporation (QMEEC)

o located in Beijing— Derun Li, Steve Virostek, MZ, Li Wang and ShiXian Zheng were

there

•Company statistics— 29 employees; 2200 m2 floor space— 20 years experience with superconducting magnets

o MRI magnetso BEPC-II detector magnet (3 m diameter, 4 m long)o completing MRI magnet of their own design now (see photos)

•Impressions— quite favorable; they are interested and knowledgeable

o but, we still want Li Wang to manage the work!

Page 10: Spectrometer Solenoid Report and Coupling Coil Update

Coil winding form parts at QMEEC ready for welding

Page 11: Spectrometer Solenoid Report and Coupling Coil Update

High bay at QMEEC showing magnet assembly area

Page 12: Spectrometer Solenoid Report and Coupling Coil Update

Coil array for 1.5T MRI magnet nearing completion at QMEEC

Page 13: Spectrometer Solenoid Report and Coupling Coil Update

Iron vacuum vessel for 1.5T MRI

Page 14: Spectrometer Solenoid Report and Coupling Coil Update

Coil winding facility at QMEEC

Page 15: Spectrometer Solenoid Report and Coupling Coil Update

Aluminum weld samples for coupling coil cooling lines and cold mass cover plates

Page 16: Spectrometer Solenoid Report and Coupling Coil Update

March 16, 2009 Solenoid Report-Zisman 16

Test Coil at ICST

•Close to being able to test the “long coil” in Harbin