Page 1 of 20
HARYANA ELECTRICITY REGULATORY COMMISSION PANCHKULA
Notification
The 16th July 2004 Regulation No. HERC/04/2004
STANDARDS OF PERFORMANCE FOR THE DISTRIBUTION LICENSEE
In exercise of the powers conferred under Section 57 and 59 read with subsection 2(za)
and 2(zb) of section 181 of the Electricity Act 2003 (Act No.: 36 of 2003) and all other powers enabling in this behalf, the Haryana Electricity Regulatory Commission specifies through these Regulations the Standards of Performance for the Distribution Licensee.
PART – I
GENERAL 1. Short title, Commencement and Interpretation (1) These regulations may be called the Haryana Electricity Regulatory Commission
(Standards of Performance for the Distribution Licensee) Regulations, 2004. (2) These regulations shall be applicable to all licensees engaged in distribution & retail
supply of electricity in the State of Haryana. (3) These regulations shall extend to the State of Haryana. (4) These regulations shall come into force on the date of their publication in the Haryana
Government. Gazette. (5) The Punjab General Clauses Act 1898 (Act 1 of 1898), as applicable to the state of
Haryana shall apply to the interpretation of these regulations.
2. Definitions 2.1 In these regulations, unless the context otherwise requires: -
(a) “Act” means the Electricity Act, 2003; (b) “Area of supply” means the area within which a licensee is authorised by his
license to supply electricity; (c) “Commission” means the Haryana Electricity Regulatory Commission; (d) “Consumer” means any person who is supplied with electricity for his own use
by a licensee or the Government or by any other person engaged in the business
Page 2 of 20
of supplying electricity to the public under this Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a licensee, the Government or such other person, as the case may be;
(e) “Extra High Tension/Extra High Voltage” means the voltage exceeding 33000 volts under normal conditions;
(f) “High Tension/High Voltage” means the voltage exceeding 440 Volts but not exceeding 33000 volts under normal conditions;
(g) “Licensee” means the Distribution and/or Retail supply Licensee; (h) “Low Tension/Low Voltage” means the voltage not exceeding 440 Volts under
normal conditions; (i) “Period of Load Shedding” means a period during which the demand is more
than supply and there is no spare/reserve capacity available to meet the surplus demand and SLDC have directed the licensee to reduce load and/or to avoid overloading. During this period licensee should adhere to rotational load shedding or any other means so that the same consumer does not suffer continuously for a period as specified in the regulation. A period of grid failure will not be covered under it;
(j) “Period of Scheduled outage” means a period during which there is a reduction of capacity or taking out-of-service of a generating unit, power station or part of the transmission system or distribution system for scheduled repairs and preventive maintenance in a planned manner. If the above repair and maintenance activity could not be carried out within the time frame laid down in this regulation on account of abnormal circumstances of a given job, the area in-charge need to obtain approval of CE/ SE (Operation) for the extended period of outage. The licensee would submit a monthly report of such cases to the Commission. Period of forced outage will not be covered under it.
(k) All other expressions used herein but not specifically defined herein but defined in the Act shall have the meaning assigned to them in the Act. The other expressions used herein but not specifically defined in these regulations or in the Act but defined under the Haryana Electricity Reform Act, 1997 shall have the meaning assigned to them under the said Act, provided that such definitions in the Haryana Electricity Reform Act, 1997 are not inconsistent with the provisions of the Electricity Act, 2003.
Page 3 of 20
CHAPTER II
STANDARDS OF PERFORMANCE
3. Guaranteed and Overall standards of performance 3.1 The Standards of Performance specified shall be the minimum standard of service with
reference to quality, continuity and reliability of services that a licensee shall achieve in discharge of his obligations as a licensee.
3.2 Standards of Performance specified in Schedule I relates to Guaranteed Standards of
Performance for which consumers against whom no arrear is pending on the date of violation are eligible for compensation in the manner provided in the Schedule I in case the Licensee fails to achieve the Standards of Performance.
3.3 In case of applications requiring supply under agriculture category (Agriculture Pump
sets) licensee’s obligation shall be limited to the number of connections that can be covered within the target fixed by the State Government for release of agricultural connections for a financial year. The target for an ensuing year should be fixed and made public at least 2 months before the commencement of the year. The licensee shall inform the applicants in writing within 15 days of receipt of applications, if the applicants’ case cannot be covered in the programme of release of Agriculture Pump set connections fixed for the year.
3.4 Schedule II relates to Overall Standards of Performance, which indicates the level of
performance the licensee shall seek to achieve in the discharge of his obligations as a licensee.
4. Power to modify
The Commission may, at any time, add, vary, alter, modify or amend any of the provisions of these regulations including the contents of the Schedule I, II and III.
5. Exemption 5.1 The standards of performance specified in these regulations shall remain suspended
during Force Majeure conditions such as war, mutiny, civil commotion, riot, flood, cyclone, lightning, earthquake or other causes beyond the control of the Licensee and strike, lockout, fire affecting the licensee’s installations and activities.
Page 4 of 20
5.2 The Commission may by a general or special order, issued for the purpose, after hearing the Licensee and the affected consumer group relieve the Licensee from the liability to compensate the consumers for any default in the performance of any standard if the Commission is satisfied that such default is for reasons other than those attributable to the Licensee & beyond the control of the Licensee and further that the Licensee has otherwise made efforts to fulfill his obligations.
CHAPTER III
COMPENSATION 6. Compensation 6.1 If the Licensee fails to meet the Standards of Performance specified in Schedule I, the
licensee shall pay to the affected consumer against whom no arrear is pending on the date of violation, the compensation as indicated against each of the Standards of Performance in Schedule I.
6.2 The Licensee shall register every complaint of a consumer. The Licensee shall
computerise the registration of every complaint of a consumer through automatic answering machine or any other such means intimating the complaint number to the consumer automatically.
6.3 The Licensee shall maintain relevant records consumer-wise regarding the Standards of
performance in order to give a fair treatment to all consumers and avoid any dispute regarding violation of standards.
6.4 All payment of compensation shall be made by way of adjustment against existing,
current and/or future bills for supply of electricity.
Provided the compensation shall be paid in Cash/ Demand draft wherever the claimant ceases to be the consumer of the utility. Provided that all the compensation shall be made within 90 days from the date of violation of a guaranteed standard of performance. If the Compensation is not adjustable in the existing, current and/or future bills of the supply of electricity the same should be paid in cash / demand draft to ensure that the compensation is paid within 90 days from the date of violation of a guaranteed standard of performance.
Page 5 of 20
7. Procedure for payment of compensation 7.1 The claim for compensation shall be dealt with in the following manner 7.2 Automatic
This mode of payment requires the Licensee to pay the compensation amount to the affected consumer automatically in the next billing cycle, following non-compliance of a particular standard.
7.3 To be Claimed
This mode of payment requires the consumer to bring to the notice of the Licensee that the standard has been violated and accordingly claim the compensation amount from the Licensee. In respect of payment of compensation, the Licensee shall take a decision and, if found liable, shall pay the compensation to the consumer within 90 (ninety) days from the date of violation of a guaranteed standard of performance.
CHAPTER IV
FURNISHING INFORMATION, ISSUE OF ORDERS
8. Information on Standards of Performance 8.1 Every Licensee shall furnish to the Commission the following information in the
Performa placed at Schedule-III.
(a) The level of performance achieved in respect of matters covered in schedule I and II of these Regulations shall be furnished quarterly.
(b) The number of cases in which compensation was paid under these Regulations and amount of the compensation in each case, shall be furnished quarterly.
8.2 The Commission shall arrange for publication of the above information, at least once in a
year, in the manner as deemed fit. 8.3 Reliability Indices
(a) The following reliability/outage indices are prescribed by the Institute of Electrical and Electronics Engineers (IEEE) Standard 1366 of 1998. The licensee
Page 6 of 20
shall compute and report the value of these indices as per the formula and methodology specified below from 2004-05 onwards:
(i) System Average Interruption Frequency Index (SAIFI): (ii) System Average Interruption Duration Index (SAIDI): (iii) Momentary Average Interruption Frequency Index (MAIFI):
(b) Method to compute Distribution System Reliability Indices The Indices shall be computed for the Distribution licensee as a whole by stacking, for each month, all the 11 KV feeders in the supply area, excluding those serving predominantly agricultural loads, and then aggregating the number and duration of all interruptions in that month for each feeder. The Indices would then be computed using the following formula:
n
6 (Ai*Ni) i=1
1. SAIFI = Nt
Where, Ai = Total number of sustained interruptions (each longer than 5 minutes) on
ith feeder for the month Ni = Connected load of ith feeder affected due to each interruption Nt = Total connected load at 11KV in the Distribution licensee’s supply area
n = Number of 11KV feeders in the licensed area of supply (excluding those serving predominantly agricultural loads)
n
6 (Bi*Ni) i=1
2. SAIDI = Nt
Where, Bi = Total duration of all sustained interruptions on ith feeder for the month.
Page 7 of 20
n
6 (Ci*Ni) i=1
3. MAIFI = Nt
Where, Ci = Total number of momentary interruptions (each less than or equal to 5
minutes) on ith feeder for the month
Note: The feeders must be segregated into rural and urban and the value of the indices must be reported separately for each month. However interruptions due to load restrictions, power cut, shut down shall not be taken into account while calculating the indices (i) The licensee shall compute the value of these indices separately for
feeders serving predominantly agricultural loads. The methodology for computation of indices shall remain the same as in the case of other feeders.
(ii) Based on the information provided by the licensees, the Commission would notify the target levels for these indices annually.
9. Issue of orders and ‘practice’ directions
Subject to the provisions of the Act and these regulations, the Commission may, from time to time, issue orders and ‘practice’ directions in regard to the implementation of the Regulations and Procedures to be followed.
10. Power to remove difficulties 10.1 If any difficulty arises in giving effect to any of the provisions of these regulations, the
Commission may, by general or special order, direct the licensee to do anything not being inconsistent with the provisions of the Act, which appears to it to be necessary or expedient for the purpose of removing the difficulties.
10.2 The Licensee may make an application to the Commission and seek suitable orders to
remove any difficulty that may arise in implementation of these Regulations.
Page 8 of 20
11. Implementation / Transition Period The standard indicating the maximum time limit for rendering the service is in line with the documents already approved by the Commission. Thus the licensee should not face any difficulty in the implementation of the same. However, the Licensee would be allowed a period of six months from the date of notification of this regulation for putting the required infrastructure in place. From 1st February 2005 the mock exercise would be carried out to make the system perfect and implementable. The actual payment of monetary compensation to the consumer w.r.t the provisions of these regulations would start from 1st August 2005 for urban consumers and from 1st August 2006 for rural consumers.
12. Savings
Nothing in these regulations shall affect the rights and privileges of the consumers under any other law including the Consumer Protection Act, 1986 (Act 68 of 1986).
By order of the Commission
Sd/- Secretary
HERC
Page 9 of 20
SCHEDULE – I
GUARANTEED STANDARDS OF PERFORMANCE Sr. No.
Nature of Service Standard (indicating Maximum time limit for rendering service)
Amount of Compensation payable to affected consumer
Manner of payment
Cities and Towns
Within 4 hours
1 Normal Fuse Off
Rural Area Within 8 hours
Rs. 100 in each case of default
Automatic
Cities and Towns
Within 8 hours (12 hrs if pole gets broken)
2 Line Breakdowns
Rural Area Within 16 hours (24 hrs if pole gets broken)
Rs. 100 to each affected consumer
Automatic
Cities and Towns
Within 24 hours
3 Distribution Transformer Failure Rural Area Within 48
hours Cities and Towns
4 Major Power Failure involving Power Transformer / Equipment etc.
Rural Area
Within 7 days. Alternate arrangement, to restore the supply to the affected area, to be made within 24 hrs.
Within 2 hrs. of receipt of complaint, complainant shall be informed about the likely time to be taken for restoration of supply if asked for by the complainant.
Rs. 100 per day or part thereof to each affected consumer subject to a maximum of Rs 3000/-
Automatic
Page 10 of 20
5 Period of Load Shedding
Not to exceed 4 hrs. per day continuously for 4 days
Normal supply to be restored within 72 hrs.
Rs. 100 per day or part thereof to each affected consumer subject to a maximum of Rs 3000/-
Automatic
Maximum duration at a stretch
Not to exceed 8 hours on any day
6 Period of Scheduled outages
Restoration of supply
By 6 PM on any day
Consumers to be informed, at least, 24 hrs. in advance
Rs. 200 to each affected consumer
Automatic
Where no expansion of network is involved
Within 4 hrs. in cities & towns & 8 hrs. in rural area
Rs. 100 in each case of default
Where up-gradation of LT distribution system is required
Within 60 days
Where up-gradation of High Tension/ EHT distribution system is required
Within 180 days
Within 2 hrs. of receipt of complaint, complainant shall be informed about the likely time to be taken for redressal of complaint
Rs. 100 per day or part thereof in each case of default to each affected consumer subject to a maximum of Rs 3000/-
7 Voltage Variations LT= +/- 6 % HV = +6 % & - 9% EHV = +10% & -12.5 %
Opening of neutral and neutral voltage exceeding 2% of supply voltage
Within 4 hour Rs. 100 in each case of default
Automatic
Inspect and check correctness
Within 7 days of receipt of meter testing fee
Replace slow/fast meters
Within 7 days of its being so established on checking.
8 Meter Complaints
Replace creeping or stuck meters
Within 7 days of its being so established on checking.
Rs.100 for each day of delay subject to a maximum of Rs 3000/-.
Automatic
Page 11 of 20
Replace burnt meters if cause not attributable to consumer
Within 7 days of receipt of complaint
Replace burnt meters in all other cases
Within 24 hours of payment of charges by consumer
Rs.200 in each case of default
Release of supply where service is feasible from existing network
Within one month of receipt of application complete in all respect along with prescribed charges
Rs. 200 for each day of default, subject to Section 44 of Act and also subject to a maximum of Rs 3000/-.
Automatic
Release of supply where Distribution Network expansion / Commissioning of New Sub Station required for providing connection
Immediately after expansion/ Commissioning or with in such period as specified by the Commission
Rs. 200 for each day of default in case of LT, Rs. 500 for each day of default in case of HT & EHT & Rs. 1000 for each day of default in case of Commissioning of New Sub Station subject to Section 44 of Act
9 Application for new connection/ additional load/ Temporary Connection
Agriculture Pump Sets
Within 30 days after attaining seniority (The no. of new connections shall be limited to the target fixed for the year)
Rs.100 for each day of default subject to Section 44 of Act and also subject to a maximum of Rs 3000/-.
To be claimed
10 Transfer of ownership, change of category
Within 7 days of receipt of application complete in all respect
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
Automatic
11 Conversion of LT single phase to LT three phase, Conversion from LT to HT and vice-versa
Within 30 days from the date of payment of charges
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
Automatic
Page 12 of 20
If no additional information is required
Within 24 hours of receipt of complaint
12 Redressal of consumer’s complaint regarding billing
If additional information is required
Within 7 days of receipt of complaint
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
Automatic
Cities and Towns
Within 6 hours of receipt of payment from consumer
13 Reconnection of supply following disconnection
Rural Area Within 12 hours of receipt of payment from consumer
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
Automatic
14 Refund of Advance Consumption Deposits/ Consumption Security, meter Security
Within 30 days after receipt of request
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
To be claimed
15 Issue of No Due Certificates Latest by 5PM next day of receipt of request
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
To be claimed
Shifting of meter/ Service Connection
Within 15 days after receipt of request along with prescribed charges
Automatic
Shifting of LT / HT Lines
Within 45 days after receipt of request along with prescribed charges
16 Shifting of meter/ Service Connection/ Lines/ Equipments
Shifting of Transformer Structure
Within 60 days after receipt of request along with prescribed charges
Rs. 100 for each day of default subject to a maximum of Rs 3000/-.
To be claimed
Page 13 of 20
SCHEDULE – II
OVERALL STANDARDS OF PERFORMANCE S. N.
Nature of Service Standard (Indicating Time Limit for rendering Service)
Overall Standards of Performance
Cities and Towns Within 4 hours 1 Normal fuse-off Rural Area Within 8 hours
99%
Cities and Towns Within 8 hours (12 hrs. if pole gets broken)
2 Line Breakdowns
Rural Area Within 16 hours (24 hrs. if pole gets broken)
95%
Cities and Towns Within 24 hours 3 Distribution Transformer Failure Rural Area Within 48 hours
95%
Cities and Towns 4 Major Power Failure involving Power Transformer / Equipment etc.
Rural Area
Within 7 days. Alternate arrangement, to restore the supply to the affected area, to be made within 24 hrs.
95%
5 Period of Load Shedding Not to exceed 4 hrs. per day continuously for 4 days
Normal supply to be restored with in 72 hrs.
95%
Maximum duration at a stretch
Not to exceed 8 hours on any day
6 Period of Scheduled outage
Restoration of supply By 6 PM on any day
99%
Where no expansion of network is involved
Within 4 hrs. in cities & towns & 8 hrs. in rural area
95%
Where up-gradation of LT distribution system is required
Within 60 days 90%
Where up-gradation of High Tension /EHT distribution system is required
Within 180 days 85%
7 Voltage Variations
Opening of neutral and neutral voltage exceeding 2% of supply voltage
Within 4 hrs. 99%
8 Meter Complaints Inspect and check correctness
Within 7 days of receipt of meter testing fee
95%
Page 14 of 20
Replace slow/fast meters
Within 7 days of its being so established on checking.
Replace creeping or stuck meters
Within 7 days of receipt of complaint
Replace burnt meters if cause not attributable to consumer
Within 7 days of receipt of complaint
Replace burnt meters in all other cases
Within 24 hours of payment of charges by consumer
Release of supply where service is feasible from existing network
Within one month of receipt of application complete in all respect along with prescribed charges
95%
Release of supply where Distribution Network expansion / Commissioning of New Sub Station required for providing connection
Immediately after expansion/ Commissioning or with in such period as specified by the Commission
95%
9 Application for new connection/Additional load connection/ Temporary
Agriculture Pump Sets Within 30 days after attaining seniority (The no. of new connections shall be limited to the target fixed for the year)
80%
10 Transfer of ownership, change of Category
Within 7 days of receipt of application complete in all respect
99%
11 Conversion of LT single phase to LT three phase, Conversion from LT to HT and vice-versa
Within 30 days from the date of payment of charges
99%
If no additional information is required
Within 24 hours of receipt of Complaint
99% 12 Redressal of consumer’s complaint regarding billing
If additional information is required
Within 7 days of receipt of Complaint
99%
Cities and Towns Within 6 hours of receipt of payment from consumer
99% 13 Reconnection of supply following disconnection
Rural Areas Within 12 hours of receipt of payment from consumer
99%
14 Refund of Advance Consumption Deposits/ Consumption Security, meter Security
Within 30 days after receipt of request
99%
15 Issue of No Due Certificates Latest by 5PM next day of receipt of request
99%
Page 15 of 20
Shifting of meter/ Service Connection
Within 15 days after receipt of request along with prescribed charges
Shifting of LT / HT Lines
Within 45 days after receipt of request along with prescribed charges
16 Shifting of meter/ Service Connection/ Lines/ Equipments
Shifting of Transformer Structure
Within 60 days after receipt of request along with prescribed charges
95%
Urban areas Shall not exceed 5% p.a.
17 Distribution Transformer failure rate
Rural area Shall not exceed 10% p.a.
18 Faulty Meters (MNR, Burnt, Sticky, etc.)
Shall not exceed 1 % of metered installations
19 Billing Mistakes Shall not exceed 0.1% of consumers billed
20 Voltage variations at supply point
The voltage variation shall be within the limits stipulated hereunder a) LT system, between +6% to -6% b) HT system between +6% to –9% c) EHT system, between +10% to 12.5 %
Page 16 of 20
21 Reliability Indices The reliability indices mentioned hereunder shall be computed separately for urban and rural feeders. a) Average number of interruptions in 11KV feeders. b) Average duration of interruptions in 11KV feeders c) Average number of interruptions per consumer d) Average duration of interruption per consumer,
The Commission will lay down the standards separately later on.
Page 17 of 20
SCHEDULE – III FORMAT FOR ASSESSING OVERALL PERFORMANCE LEVEL OF DISTRIBUTION LICENSEE
Report for the month of _____________ Name of the Licensee : Total No. of services : Total No. of Distribution Transformers : S. N.
Nature of Service Nos. of complaints received
Nos. of complaints attended
% age attended
Overall Standards of Performance
Cities and Towns 1 Normal fuse-off Calls Rural Area
99%
Cities and Towns 2 Line Breakdowns Calls Rural Area
95%
Cities and Towns 3 Distribution Transformer Failure Rural Area
95%
Cities and Towns 4 Major Power Failure involving Power Transformer / Equipment etc.
Rural Area
95%
5 Period of Load Shedding
Not to exceed 4 hrs. per day continuously for 4 days
95%
Maximum duration at a stretch
6 Period of Scheduled outage
Restoration of supply
99%
Where no expansion of network is involved
95% 7 Voltage Variations
Where up-gradation of LT distribution system is required
90%
Page 18 of 20
Where up-gradation of High Tension / EHT distribution system is required
85%
Opening of neutral and neutral voltage exceeding 2% of supply voltage
99%
Inspect and check correctness
Replace slow/fast meters
Replace creeping or stuck meters
Replace burnt meters if cause not attributable to consumer
8 Meter Complaints
Replace burnt meters in all other cases
95%
Release of supply where service is feasible from existing network
95%
Release of supply where Distribution Network expansion / Commissioning of New Sub Station required for providing connection
95%
9 Application for new connection/Additional load connection/ Temporary
Agriculture Pump Sets
80%
10 Transfer of ownership, change of Category
99%
11 Conversion of LT single phase to LT three phase, Conversion from LT to HT and vice-versa
99%
Page 19 of 20
If no additional information is required
99% 12 Redressal of consumer’s complaint regarding billing
If additional information is required
99%
Cities and Towns
99% 13 Reconnection of supply following disconnection
Rural Areas 99% 14 Refund of Advance Consumption Deposits/
Consumption Security, meter Security 99%
15 Issue of No Due Certificates 99% Shifting of meter/ Service Connection
Shifting of LT / HT Lines
16 Shifting of meter/ Service Connection/ Lines/ Equipments
Shifting of Transformer Structure
95%
Urban areas Shall not exceed 5% p.a.
17 Distribution Transformer failure rate
Rural area Shall not exceed 10 % p.a.
18 Faulty Meters (MNR, Burnt, Sticky, etc.)
Shall not exceed 1% of metered installations
19 Billing Mistakes Shall not exceed 0.1% of consumers billed
Page 20 of 20
20 Voltage variations at supply point
The voltage variation shall be within the limits stipulated hereunder a) LT system, between +6% to -6% b) HT system, between + 6% to -9% c) EHT system, between +10% to –12.5%
21 Reliability Indices The reliability indices mentioned hereunder shall be computed separately for urban and rural feeders. a) Average number of interruptions in 11KV feeders. b) Average duration of interruptions in 11KV feeders c) Average number of interruptions per consumer d) Average duration of interruption per consumer,
The Commission will lay down the standards separately later on.
COMPLAINT HANDLING PROCEDURE RELATING TO DISTRIBUTION AND RETAIL SUPPLY 1. Pursuant to clause 21.2 of the Distribution and Retail Supply Licence, the HVPNL
(herein after referred to as Licensee) hereby lays down the following Complaint Handling Procedure relating to Distribution and Retail Supply. In general, consumers have a right to expect from the licensee certain minimum level of service as indicated here in after.
2. Nature of complaints
The consumer Complaints are categorized under the following eight broad heads:
1. Interruption/failure of power supply
2. Voltage variation
3. Scheduled outage / Load shedding
4. Metering
5. Billing
6. Disconnection / Reconnection
7. New connection/ Extension of load
8. Miscellaneous
3. Procedure for Lodging of complaints:
a) Complaints can be lodged in writing or on telephone with the complaint center or concerned SDO and should have the essential information as per Annexure-I.
b) In the event of non-response or inadequate response by the Complaint Center or the SDO within the time period prescribed for various types of complaints under para - 4 below, the consumer may lodge complaint against the non-redressal of the grievance with the XEN of the area who shall respond within 7 days.
Where to lodge:
The names of the staff and their contact address/number(s) where consumers can lodge their complaints as also the name and contact address/telephone number of concerned XEN who should be approached in case of delay in the redressal of complaint would be notified as under:
• By display/dissemination of the above information on the back of bills and/or separate handouts attached to the bills from time to time.
• By display of the above information on notice boards outside the offices of all SDO's and XEN's.
4. Time limits for redressal of complaints/resumption of service:
A) Interruption / failure of power supply
1. In the case of normal fuse-off calls requiring replacement of HT/LT fuses at the distribution transformer or fuses at the consumer premises or for any service faults the power supply shall be restored within 4 hours of receiving the complaint in towns/and cities and within 8 hours in rural areas.
2. In the case of line breakdowns the supply shall be restored within 8 hours of receiving the complaint in towns/cities and within 16 hours of receiving the complaint in rural areas. In either case, within two hours of receiving the complaint, the complainant shall be informed of the likely time by which the power supply may be restored.
3. In the case of failure of distribution transformer, the supply shall be restored within 24 hours of receiving the complaint in towns/cities and within 48 hours of receiving the complaint in rural areas.
4. In case of major failure involving Power transformer, the normal supply shall be restored within 7 days. However, in such cases alternate arrangements to supply power to the affected areas would be made within 24 hours.
B) Voltage variation
1. In case the cause of problem is local, warranting no upgradation of the system, the complaint would be redressed within 4 hours of lodging in towns/cities and within 8 hours in rural areas.
2. If the complaint regarding low voltages warrants upgradation of distribution lines, transformers or installation of capacitors, it would be rectified within 60 days.
3. If redressal of the complaint warrants upgradation of the High Tension (“HT”) distribution system it would be rectified within 180 days.
In case it is not possible to rectify the problem within the period prescribed above, the S.D.O. will communicate in writing within 15 days of lodging the complaint to the complainant the reasons for delay and the likely time period within which the problem would be rectified.
C) Scheduled Outages / Load shedding
Scheduled outage shall be specified through notice publicised within the affected area(s) and shall normally not exceed 8 hours on any day. The power supply shall normally be restored by 6.00 p.m.
In case of recurring load shedding exceeding 4 hours in a day over a consecutive period of 4 days, complaint may be lodged as per procedure laid down in para-3 above. Steps shall be taken to redress the grievance within 72 hours. In case the redressal is likely to take more than 72 hours, the complainant should be informed of the likely time by which the normal supply could be restored.
D) Metering
1 As per Section 26 of the Indian Electricity Act 1910, the responsibility of installing a standard meter and its maintenance is that of the licensee and hence, the Licensee is required to check the meter for proper functioning at regular intervals. However, if a consumer has reasons to believe that the meter is not functioning properly, he may file application for the testing of his meter together with meter testing fee as applicable with the S.D.O. of his area.
2 Within 7 days of filing the application together with the testing fee, a tested check meter would be installed in series with the existing meter. If after a reasonable period of time which would not be less than 7 days, the existing meter is found to be slow or fast beyond the permissible limits, then the same would be removed leaving the check meter in its place for future metering. The account of the consumer would be adjusted suitably as per provisions of the Agreement/Act and the testing fee deposited by the consumer would be refunded. However, if the existing meter is found to be correct, the same would be left in place and the testing fee would be forfeited.
3 In case it is established that the defect in the meter was on account of tampering or deliberate act attributable to the consumer, then apart from the recoveries/penalty leviable under the rules, the cost of the meter would also be recovered from the consumer.
4 If the Licensee has reasons to believe that the meter at a consumer's premises is not functioning properly, he may at any time after giving due notice to the consumer install a check meter in series with the existing meter. If after a reasonable period of time which would not be less than 7 days, the existing meter is found to be slow or fast beyond the permissible limits, then the same would be removed leaving the check meter in its place for future metering. The account of the consumer would be adjusted suitably as per provisions of the Agreement/Act.
5 If the meter is the property of the consumer and its testing with the above procedure indicates the need for its replacement, then the Licensee shall leave the test meter at the premises of the consumer. If the consumer wishes to put his meter again he shall inform the licensee for installation.
For the period the licensee's meter remains at the consumer's premises, he would pay the usual charges as applicable.
E) Billing
Complaint in respect of non-receipt of energy bills/receipt of erroneous bills shall be lodged with SDO in writing, as per procedure laid down in para-3 above.
The dispute shall be resolved within a period of 2 months as per code of practice for payment of bills & procedure for disconnection.
F) Disconnection / Reconnection
Where a wrongful disconnection has taken place the supply should be restored within 6 hours of lodging the complaint, Similarly, Complaints in respect of delay in reconnection of power supply shall also be resolved within 6 hours of lodging, if the complainant has submitted the proof of removal of cause, which led to disconnection of power supply. The disconnection shall be done within 6 hours of receiving such request in writing from the consumer, failing which the complaint shall be lodged with the SDO as per the procedure laid down in para-3 above.
G) New connection/ Extension / Reduction of load:
When an applicant is not satisfied with the response regarding release of his new connection /extension of load within the time limit as stipulated in Table below, he may lodge a complaint in writing with the SDO of the area as per para - 3 above.
Time limit for:
S. N.
Type of new connections/extension/reduction
of load
Issue of Demand Notice after receipt of application
Release of connection after receipt of valid test report
1. Domestic and Commercial 10 working days1 15 working days
2. Industrial connection upto 50 KW 1 month1 1 month
3. Industrial connection for loads above 50 KW
2 months1 1 month
4. Agricultural connections:
• involving LT line only. 2 months1 1 month
• involving 11 kV works 3 months1 2 months
5 Reduction of load in any categories
to be effective as per the agreement conditions with the Licensee
• 1 Sub j ec t to t he t echnical & economic f easibili t y
H) Miscellaneous
All complaints concerning power supply/ service other than those mentioned in para A to H above will also be lodged with the SDO of the area in writing who would respond within 10 working days.
5. Filing complaints with Bijli Adalat
If the consumer seeking redressal of his grievances is not satisfied with the response of officer(s) subordinate to the Superintending Engineer of the area, then he can file a petition with the Bijli Adalat in the Office of the concerned Superintending Engineer. The Proforma for filing petition with Bijli Adalat is given in Annexure- II. The petition should be filed in duplicate and at least 15 days before the date of the Bijli Adalat together with a self addressed envelope with necessary postage for issue of notice to him Under Certificate of Posting, for appearance before the Adalat. (Advance notice regarding holding Bijli Adalat on a fixed date, including the scope of the Adalat shall be given by the Superintending of Engineer through local news papers/beating of the drums, for information of general public).
6. Periodic Inspection by next higher authority
A database comprising of the complaints lodged by various categories of consumers, type of complaint, period of redressal etc shall be maintained by the Licensee. The complaint register maintained at the complaint centre/office will be inspected by the next supervisory authorities every month who will record his views regarding the adequacy of the measures taken and the response time.
7. Complaint before HERC
It is the obligation of the Licensee to respond to a consumer's complaint in a timely and effective manner. However, if the consumer is not satisfied with the action taken by the Licensee (up to the XEN level), he may make a complaint to the Haryana Electricity Regulatory Commission in accordance with the procedure prescribed by the Commission.
Annexure-I
PROFORMA FOR COMPLAINTS
1. Name, address and telephone No., if any of the complainant.
2. Consumer account Number(Optional)
3. Brief description of the complaint
__________________
Date : (Signature of Applicant)
- - - - - - - - - - - - - - - - - - Tear at this line - - - - - - - - - - - - -
ACKNOWLEDGEMENT TO BE HANDED OVER TO THE CONSUMER
1. Complaint reference No. (To be given by Licensee)
2. Received on date
3. Complaint received by (Name & Designa t ion)
_________________
(Signature )
Annexure-II
PROFORMA FOR COMPLAINTS TO THE BIJLI ADALAT
Complaint Ref. No_______________________ (To be given by Licensee)
1. Name, address and telephone no if any of the complainant.
2. Consumer account Number
3. Copies of the previous complaints filed with SDO/XEN etc. with copies of the reply received, if any
4. Date since which the complaint is pending
5. Brief description of the present complaint to the Bijli Adalat
__________________
(Signature of Applicant)
Date
- - - - - - - - - - - - - - - - - - Tear at this line - - - - - - - - - - - - -
ACKNOWLEDGEMENT TO BE HANDED OVER TO THE CONSUMER
4. Complaint reference No. (To be given by Licensee)
5. Received on date
6. Complaint received by (Name & Designa t ion)
_________________
(Signature )