Donaldson Run Tributary BStream Restoration Project Update – February, 2020
![Page 2: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/2.jpg)
Project area map
• Project length is 1,355 linear feet
• N. Upton St to Tributary A confluence
![Page 3: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/3.jpg)
• NC Approved Project - 2007
• Stormwater Master Plan
• Protect existing infrastructure
• 30” water main
• Sanitary sewer
• Trail
• Repair storm infrastructure
• Address active stream erosion
• Control invasive plants
• Provide for improved long-term forest health
• Improve water quality- Bay cleanup
• Addresses key, regulated pollutants – sediment & nutrients
Project Description
Exposed
water main
![Page 4: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/4.jpg)
2010 2019
![Page 5: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/5.jpg)
2010
2019
![Page 6: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/6.jpg)
2010 2019
![Page 7: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/7.jpg)
2010
2019
![Page 8: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/8.jpg)
2010 2019
![Page 9: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/9.jpg)
Stream stabilization tools
• Step pools
• Stacked stone walls
• Floodplain benches
Step pools
Stacked stone wall
& floodplain bench
![Page 10: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/10.jpg)
Stream stabilization tools
• Plunge pools
• Live staking
Plunge pools
Live staking
![Page 11: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/11.jpg)
Site-specific
Challenges
• EXTREMELY tight space to work within
• Steep slopes
• Elevation change
• Approximately 44’ of change from upstream to downstream end of project
• Infrastructure
![Page 12: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/12.jpg)
Infrastructure
Challenges
• Protect 30" water main
• Repair N. Upton Street outfall
• Repair two additional eroded stormwateroutfalls
• Improve trail
• Provide for adequate slope and under trail drainage
• Protect sanitary crossings and main
![Page 13: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/13.jpg)
Recent Work
• Stormwater pipe outfall repair
design for N. Upton street
• Final stream design coordination
o Outfall protection
o Grading revision
o Protect sanitary sewer
• Design QA/QC
• Tree preservation plan review &
update
• Planting plan revised
• Additional easement acquisition
• Re-authorization – U.S. Army Corps
of Engineers
• Local and state permitting
Tributary B’s final bend before joining
Tributary A
![Page 14: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/14.jpg)
![Page 15: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/15.jpg)
![Page 16: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/16.jpg)
Design QA/QC
• Update survey
✓ Review tree preservation plan.
✓ Review grading plan.
✓ Computations for design are conservative.
✓ Improve structures
• Plant down further into stream channel and use more erosion control matting
✓ Review stormwater pipe orientations
✓ Model 100-yr storm
![Page 17: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/17.jpg)
Trees
• Tree inventory completed in
2015, reviewed October 2019
• 21 trees dead since 2017
o Erosion & storm damage
• 10 of those trees >24 in dbh
• Tree removals – 86 trees
• Potential removals – 16 trees
• More realistic evaluation of impacts
• Grading revisions
![Page 18: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/18.jpg)
Trees
Tree impacts
• 86 total trees
• 12 trees >24 inches
• 44% less than 12 in
• 14 in poor condition*
• 60% tulip poplars
• TBD tree removals near
confluence
*trees <12 in, no condition rating
Sanitary
sewer
![Page 19: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/19.jpg)
Planting plan
Trees required
• 161 Trees
Diverse, Native Plantings
• 332 Trees
• 150 Live Stakes
• 120 Shrubs
• 2,800+ Ferns & Perennials
• Native Seed Mix
![Page 20: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/20.jpg)
Post-construction
• Maintenance – 5 years
• Supplemental planting in
Yrs 3 and 5
• Tree watering
• Deer protection
• Invasive control
Arrowwood
Viburnum dentatum
Christmas fern
Polystichum acrostichoides
![Page 21: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/21.jpg)
Schedule
• Local permitting (in process)
• Additional survey
• Outreach
• Companies bid on construction
• Board awards contract
• Construction begins Fall 2020
![Page 22: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/22.jpg)
Construction Impacts
• Trail closure along Tributary B
• Anticipated to last 6 months
• Construction staging
o Material & equipment
storage on N. Vermont
![Page 23: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/23.jpg)
Trib A vs. Trib B Tributary B
Tributary A
June 2010
![Page 24: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/24.jpg)
Christin Jolicoeur
703-228-3558
Aileen Winquist
703-228-3610
http://projects.arlingtonva.us/projects/donaldson-run-stream-restoration-tributary-b/
Contacts
![Page 25: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/25.jpg)
Additional slides
Tributary A: Before and After
![Page 26: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/26.jpg)
Tributary A Outfall from Utah St. – before restoration
![Page 27: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/27.jpg)
After restoration
![Page 28: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/28.jpg)
After restoration – looking downstream from outfall
![Page 29: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/29.jpg)
Tributary A - Rip rap
and erosion of trees
above confluence
before restoration
![Page 30: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/30.jpg)
After restoration
![Page 31: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/31.jpg)
Tributary A and
B Confluence
with rip rap, before
restoration
![Page 32: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/32.jpg)
After restoration
![Page 33: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/33.jpg)
Broken sanitary sewer pipe and steep eroded banks – DS of confluence
Tributary A
before
restoration.
Note person in
photo –
Banks are over 6
feet high
![Page 34: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/34.jpg)
After restoration
![Page 35: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/35.jpg)
Tributary A
before restoration
Old stone wall, rip rap, and erosion below. Near location of current ped bridge.
![Page 36: Stream Restoration Project Update February, 2020 · • 2,800+ Ferns & Perennials • Native Seed Mix. Post-construction • Maintenance –5 years • Supplemental planting in Yrs](https://reader033.vdocument.in/reader033/viewer/2022050603/5faa47c3a6e9790be01f2a1e/html5/thumbnails/36.jpg)
After restoration