Adapting a genetic algorithm to schedule variants of the manufacturing shop.
P. R. Drake* and I. A. ChoudhryP. R. Drake* and I. A. Choudhry
Intelligent Systems Laboratory,Intelligent Systems Laboratory,
Systems Division, School of Engineering, University of Wales Cardiff,Systems Division, School of Engineering, University of Wales Cardiff,
Queen's Buildings, Cardiff, CF2 3TE.Queen's Buildings, Cardiff, CF2 3TE.
Abstract
Whilst it is well documented how genetic algorithms (GA's) can be
applied to scheduling jobs for simple manufacturing shop models,
this paper shows how they can be used to schedule jobs for some of
the more complex standard models. The simplicity of the methods
presented, and the use of proprietary spreadsheet software and GA
'add-in' to implement them, support the conjecture that GA's can
provide a highly flexible and user-friendly solution to the general
shop scheduling problem.
1 Introduction
Since the late 1980s there has been a growing interest in genetic
algorithms (GA's) - optimisation algorithms based on the principles of
natural (Darwinian) evolution. As they are based on evolutionary
learning they come under the heading of Artificial Intelligence. They
have been used widely for parameter optimisation, classification and
learning in a wide range of applications. More recently, production
scheduling has emerged as an application. In particular, such
applications have started to appear in this journal (Jain and
Elmaraghy 1997) (Lee, Piramuthu and Tsai 1997). Whilst it is well
documented how GA's can be applied to simple job sequencing
problems, this paper shows how they can be implemented to
sequence jobs/operations for manufacturing shops with precedence
constraints among manufacturing tasks, alternative routeings
(machines), sequence dependent set-up times and scheduled
machine downtime. The methods presented are very simple and
easy to implement and therefore support the conjecture that GA's
can provide a highly flexible and user-friendly solution to the general
shop scheduling problem.
The work presented here is carried out using standard spreadsheet
software and an 'add-in' to provide the basic GA. The use of this
proprietary software demonstrates how simple it is to implement the
GA approach to schedule optimisation - very little software skill is
required. Spreadsheets are used widely in manufacturing industry
2
and they are particularly suitable for production scheduling because
they store and manipulate data in tables.
2 The Sequence Optimisation GA
Detailed introductions to GA's are given by Goldberg (1989) and
Davis (1991). The flowchart for the particular GA used here is given
in Figure 1. First, an initial population of randomly generated
sequences of the tasks in the schedule is created. These individual
schedules form 'chromosomes' which are to be subjected to a form of
Darwinian evolution. The size of the population is user-defined and
the fitness of each individual schedule in the population is calculated
according to a user-defined fitness function such as: total makespan;
mean tardiness; maximum tardiness; number of tardy jobs. The
schedules are then ranked according to the value of their fitness
function.
Once an initial population has been formed, 'selection', 'crossover'
and 'mutation' operations are repeatedly performed until the fittest
member of the evolving population converges to an optimal fitness
value. Alternatively, the GA may run for a user defined number of
iterations.
3
The 'selection' process consists of selecting a pair of parents from the
current population using a rank-based mechanism to control the
probability of selection. These parents then mate to produce a child
by applying (in this particular implementation) the 'uniform order-
based' crossover operator (Davis 1991). This is based on using a
randomly generated bit string (zero-one) template to determine for
each parent which genes are carried forward into their child. The
operator is explained by the example in Figure 2. Here, the bit string
template contains a one at positions {2, 3, 5, 6}. The genes (jobs) in
these positions in parent-1 are carried straight across into the child.
The template contains zeros at positions {1, 4, 7, 8}. In these
positions parent-1 has genes {1, 4, 7, 8}. These genes are copied
into the child in the same order as they appear in parent-2 {8, 4, 7,
1}. The proportion of the jobs in the child coming from the first
parent is defined by the crossover rate which has a value between 0
and 1.
Following crossover, the resultant child may be mutated. The
particular mutation operation used here is 'order-based' mutation. In
this operation two jobs change positions in the chromosome. The
probability that a job is mutated is defined by the user defined
mutation rate which lies in the range 0 to 1. The purpose of mutation
is to ensure that diversity is maintained within the population. It
gives random movement about the search space thus preventing the
GA becoming trapped in 'blind corners' or 'local optima'. Finally, the
new 'child' schedule replaces the weakest (least fit) schedule in the
current pool or 'population' of schedules.
4
A population size of 50, a crossover rate of 0.65 and a mutation rate
of 0.006 are used in the experiments presented here.
3 Why use GA's for Shop Scheduling ?
It is a characteristic of the schedule optimisation process that once
fairly good solutions have been formed their features will be carried
forward into better solutions, and lead ultimately to optimal
solutions. It is in the nature of the GA that new solutions are formed
from the features of known good solutions. Therefore, it follows that
GA's are particularly attractive for scheduling.
Compared with other optimisation methods, GA's are suitable for
traversing large search spaces since they can do this relatively
rapidly and because the mutation operator diverts the method away
from local minima, which will tend to become more common as the
search space increases in size. Being suitable for large search spaces
is a useful advantage when dealing with schedules of increasing size
since the solution space will grow very rapidly, especially when this is
compounded by such features as alternative machines/routes. It is
important that these large search spaces are traversed as rapidly as
possible to enable the practical and useful implementation of
automated schedule optimisation. If the optimisation is done quickly
then production managers can try out 'what-if' scenarios and detailed
sensitivity analysis as well as being able to react to 'crises' as soon
as possible.
5
For a simple n jobs and m machines schedule the upper bound on the
number of solutions is (n!)m. Without n and m being very large this
value soon becomes massive, e.g. for 20 jobs and 5 machines the
value is 8.52x1091. Traditional approaches to schedule optimisation
such as mathematical programming and 'branch and bound' are
computationally very slow in such a massive search space.
4 Example 1: A Flow Shop
Table 1 gives the job data for this example and the objective is to
minimise the makespan for the schedule. When the GA is applied to
this example the best sequence is 3-6-4-7-2-8-1-5 which yields a
makespan of 584 units of time. The result of applying the 'network
scheduling technique' to this example was recently reported and the
best sequence found was 3-6-4-7-8-2-1-5 which produces a
makespan of 595 units of time (Akpan 1996). This was also the best
result reported when using a heuristic method (Campbell, Smith and
Dudek 1970).
5 Precedence Constraints
The normal sequence optimising GA will rearrange freely the jobs in a
schedule. However, in most production scheduling situations there
will be precedence constraints on the order of operations within a
particular job. For example, holes must be drilled before they are
tapped. To implement such constraints, a precedence table is
6
introduced as in Table 2 for the example considered in the next
section. This table shows that, for example, task 5 must be done
before tasks 6 and 7. When the GA creates a child the precedence
table is checked. If any precedence constraints are broken then tasks
which must be performed earlier in the sequence are moved up the
schedule.
6 Example 2: Alternative Machines
There may be a choice of machines that can be used for a particular
operation as illustrated in Table 3. In this example operation 2 for job
A can be performed on machine 1 or 3, operation 2 for job B on
machine 1 or 2, and so on. Table 4 presents the same information in
the form of a 20 job-operation sequence. Note, five of these
operations {tasks 3,7,13,15,19} will not in fact be performed. They
are present in the table solely for the purpose of making the
alternatives available to future generations. The first occurrence of a
duplicated operation is taken to be an 'actual' occurrence that must
be included in the calculation of the fitness function while subsequent
occurrences are ignored. However, all occurrences are included in
the crossover and mutation operations.
Using integer programming, Jiang and Hsiao (1994) produce two
optimised schedules for this example - one to minimise the total
absolute deviation from the due dates and one to minimise the total
finishing times of the individual jobs. They show that the minimum
total absolute deviation is four time units and the minimum total
7
finishing time is ten time units. The GA produced the same results.
Figures 3 and 4 show the schedules generated to optimise the two
fitness functions. Table 5 illustrates how the GA presents the optimal
solution for the minimum total finishing times schedule. As explained
before, this is a sequence of 20 operations including 5 duplicated
operations that are to be ignored.
7. Example 3: Sequence Dependent Set-up Times
Inter-operation set-up times may depend on the type of operation
that has just been completed, as well as on the type of operation to
be performed. In such situations it is not valid to absorb the set-up
time for a job into its processing time. To accommodate sequence
dependent set-up times, look-up tables containing the times are
introduced. Then, fitness functions such as total makespan (lead-
time) can be calculated for a schedule by combining process times
with the appropriate set-up times in the look-up table.
Table 6 presents an example schedule with the corresponding
sequence dependent set-up times being given in Tables 7 to 9. The
smallest total makespan found by the GA is 45 time units with the
task sequence {1,7,8,9,4,5,10,11,12,2,3,6}. Again, it is a relatively
simple matter to implement the fitness function required to enable
the GA to optimise this schedule.
8. Example 4: Scheduled Machine Downtime
8
Scheduled machine downtime may be requested for preventive or
reactive maintenance. In the model considered here, the downtime
must be inserted into the production schedule according to the
following two rules.
i. If there is no production scheduled for a machine at the start of
a requested downtime, then the downtime is allocated as
requested. Any production scheduled to start during the
downtime is moved to the end of the downtime.
ii. If production is already scheduled at the start time of the
requested downtime, then the downtime is moved to the end
of this operation.
Other rules may be used as desired. The important principle being
demonstrated here is how these rules are applied with the GA.
Consider, the 3-job, 4-machine job shop example in Table 10 taken
from Pinedo (1995). The precedence constraints for this example are
defined in Table 11. The best makespan found by Pinedo for this
example is 28. He uses disjunctive graphs and proves that this
solution is optimal. The GA finds the same solution but with a
different sequence of operations. The Gantt charts for the two
solutions are given in Figure 5.
Now consider that before the execution of the schedule the
maintenance department request machines 1, 2 and 4 for the times
9
given in Table 12. This machine downtime is inserted into the
schedule according to the above two rules to give the schedule in
Figure 6. This increases the makespan to 55 time units. Rerunning
the GA to optimise this schedule, the makespan is reduced to 51 as
shown in Figure 7.
9 Conclusion
The adaptation of a GA to schedule jobs in manufacturing shops with
precedence constraints among tasks, alternative routeings, sequence
dependent set-up times and scheduled machine downtime has been
demonstrated. The simplicity of the methods used supports the
conjecture that GA's can provide a highly flexible and user-friendly
solution to the general shop scheduling problem. The use of
proprietary spreadsheet software and a proprietary 'add-in' to
implement the GA has shown how simple it is to implement this
approach to scheduling.
References
AKPAN, E. O. P., 1996, Job-shop sequencing problems via network
scheduling technique, International Journal of Operations and
Production Management, 16, 76-86.
10
CAMPBELL, H. G., SMITH, M. L., DUDEK, R. A., 1970, A heuristic
algorithm for the N jobs, machine sequencing problem, Management
Science, 16, B630-B637.
DAVIS L, 1991, Handbook of Genetic Algorithms, New York: Van
Nostrand Reinhold.
GOLDBERG, D. E., 1989, Genetic Algorithms in Search, Optimisation
and Machine Learning, Reading, MA: Addison-Wesley.
JAIN A. K., ELMARAGHY H.A., 1997, Production
scheduling/rescheduling in flexible manufacturing, International
Journal of Production Research, 35, 281-309.
JIANG J. and HSIAO W., 1994, Mathematical Programming for the
Scheduling Problem with Alternative Process Plans in FMS, Computers
& Industrial. Engineering, 27, 15-18.
LEE C.-Y., PIRAMUTHU S. and TSAI Y. -K., 1997, Job shop scheduling
with a genetic algorithm and machine learning, International Journal
of Production Research, 35, 1171-1191.
PINEDO, M., 1995, Scheduling: Theory, Algorithms and Systems,
Prentice Hall, New Jersey.
Acknowledgements
11
The authors would like to thank the Pakistan Government for their
assistance in this research.
12
Figure 1: The Genetic Algorithm (GA) for Schedule Optimisation
13
Position in Chromosome1 2 3 4 5 6 7 8
Parent-1
Binary Template
Parent-2
Child
1 2 3 4 5 6 7 8
0 1 1 0 1 1 0 0
8 6 4 2 7 5 3 1
8 2 3 4 5 6 7 1
Figure 2: Schedule Chromosomes and the Crossover Operator
Figure 3 : Schedule to minimise absolute deviation from due dates.
14
Figure 4 : Schedule to minimise total finishing times.
Figure 5 : Gantt Chart for Pinedo’s Solution and the GA Solution
15
Figure 6 : Modified schedule with machine downtime inserted
Figure 7 : Modified schedule after rerunning the GA
16
Table 1: Job Data for 8-job, 7-machine flow line example.
Job List
Processing Times for Machine
1 2 3 4 5 6 71 13 79 23 71 60 27 22 31 13 14 94 60 61 573 17 1 - 23 36 8 864 19 28 10 4 58 73 405 94 75 - 58 - 68 466 8 24 3 32 4 94 897 10 57 13 1 92 75 298 80 17 38 40 66 25 88
Table 2: Precedence Constraints for Tasks
Task Numb
er
Must follow
12 13 14 2 35 6 57 5 8 6 79 10 911 10121314 12 1315 12 1316 14 151718 1719 1720 18 19
17
Table 3: The Alternative Machines Schedule
Job-Operati
on
Processing time
for machine
DueDate
1 2 3 4A-1 2A-2 1 2A-3 1 6B-1 1B-2 1 2B-3 1 3C-1 2C-2 2C-3 1 6D-1 1 2D-2 2 1D-3 1 6E-1 1E-2 2 1E-3 2 6
18
Table 4: GA Representation of the Example Alternative Machines Schedule
Job Numb
er
Operation
Machine Process Time
Contribution to
Fitness Function
Task Number
*
A 1 1 2 2 1A 2 1 1 1 2A 2 3 2 - 3A 3 4 1 1 4B 1 2 1 1 5B 2 1 1 1 6B 2 2 2 - 7B 1 1 1 1 8C 1 3 2 2 9C 2 4 2 2 10C 3 1 1 1 11D 1 3 1 1 12D 1 4 2 - 13D 2 2 2 2 14D 2 3 1 - 15D 3 2 1 1 16E 1 2 1 1 17E 2 2 2 2 18E 2 4 1 - 19E 3 3 2 2 20
* This column represents the chromosome used in the crossover and mutation operations.
19
Table 5: GA Optimised Schedule to Minimise Total Finishing Time
Job Numb
er
Operation
Machine Process Time
Contribution to
Fitness Function
Task Number
*
D 1 3 1 1 12A 1 1 2 2 1A 2 1 1 1 2D 1 4 2 - 13A 2 3 2 - 3D 2 3 1 1 14E 1 2 1 1 17E 2 4 1 1 19B 1 2 1 1 5B 2 1 1 1 6D 2 3 1 - 14D 3 2 1 1 16E 2 2 2 - 18E 3 3 2 2 20B 2 2 2 - 7A 3 4 1 1 4C 1 3 2 2 9C 2 4 2 2 10B 3 1 1 1 8C 3 1 1 1 11
* This column represents the chromosome used in the crossover and mutation operations.
20
Table 6: Schedule Data for the Sequence Dependent Set-up Times Example.
Job Operation
Machine Part Type
Process Time
Task Number
*1 1 B 1 4 11 2 A 1 7 21 3 C 1 6 32 1 B 2 9 42 2 C 2 5 52 3 A 2 4 63 1 A 3 1 73 2 B 3 2 83 3 C 3 10 94 1 A 4 8 104 2 C 4 4 114 3 B 4 5 12
* This column represents the chromosome used in the crossover and mutation operations.
21
Table 7: Sequence Dependent Set-up Times for Machine 1
To Part TypeFrom Part
Type 1 2 3 4
None 2 3 2 41 0 3 1 52 1 0 3 23 2 4 0 14 2 4 2 0
Table 8: Sequence Dependent Set-up Times for Machine 2
To Part TypeFrom Part
Type 1 2 3 4
None 2 1 3 11 0 2 3 52 5 0 1 33 4 2 0 14 3 3 4 0
Table 9: Sequence Dependent Set-up Times for Machine 3
To Part TypeFrom Part
Type 1 2 3 4
None 1 3 2 21 0 3 2 52 3 0 4 33 2 2 0 44 2 5 3 0
22
Table 10: Processing times and machine sequences for
3-job, 4-machine example
Operation Processing Times
Machine Sequence
Job 1st 2nd 3rd 4th 1st 2nd 3rd 4th1 10 8 4 - 1 2 3 -2 8 3 5 6 2 1 4 33 4 7 3 - 1 2 4 -
Table 11: Precedence Constraint Table
Job-operation
Must follow job-
operation1-11-2 1-11-3 1-22-12-2 2-12-3 2-22-4 2-33-13-2 3-13-3 3-2
Table 12 : Requested Machine Downtimes
Requested DowntimesMachin
eStart Finish Durati
on
23
1 10 20 102 15 30 154 10 40 30
24