THE ENGINEERED FLOODPLAIN
BENCH
![Page 2: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/2.jpg)
Conceptually, for an incised system you can: raise the stream,
lower the floodplain, or a little of both
Lower either one or both banks of the floodplain
Or, construct bankfull floodplain benches on either one or both banks
![Page 3: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/3.jpg)
Some designs are very complex, here is a three-
stage channel
Mini floodplain
bench
active channel
Wet meadow
Floodplain bench elevation at height
of channel forming discharge
![Page 4: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/4.jpg)
NARROW FLOODPLAIN
BENCH ON THE OTTAWA RIVER, OTTAWA HILLS,
OHIO
![Page 5: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/5.jpg)
Mini floodplain
bench
![Page 6: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/6.jpg)
Looking DS on the Ottawa River, OH, (sand-gravel, less than 1% slope, urban, pool-riffle-pool) note slower water within the veg along left bank, Ottawa River, Ottawa Hills, OH
River thalweg delineated by bubble trails
![Page 7: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/7.jpg)
Looking DS, close-up shot Ottawa River, note drag from plants vectoring thalweg away from the bank
(second black arrow)
Dense plants on narrow floodplain bench
effectively reducing near- bank flood velocities!!
![Page 8: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/8.jpg)
Looking DS @ narrow Ottawa River floodplain bench @ low flow. Derrick-7/26/2007
![Page 9: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/9.jpg)
HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER
ERODING STREAM THREATENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT
OF THE ROAD, PROJECT CONSTRUCTED IN 1 DAY, MARCH 10, 2009
BY PIKE COUNTY PUBLIC WORKS DEPT, LaDON ATKINSON, ROAD
SUPERVISOR
![Page 10: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/10.jpg)
HAW CREEKGENERAL INFORMATION
Bank erosion is threatening county road, threatening public safety
Stream wildly meandering in response to historic straightening
Decent riparian areas in places Bed material: gravel-sand. Channel is incised Pool-riffle-pool regime, slope less than 1% Average width 30-40 ft, 14 ft tall banks Funding, equipment, and manpower provided by
Pike County, MO
![Page 11: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/11.jpg)
PRE-PROJECT PHOTOSby
JAYNIE DOERR, REGULATORY,
ST. LOUIS DISTRICT FEBRUARY 25, 2009
![Page 12: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/12.jpg)
Looking DS @ the lower end of the project bend. The last two trees undercut & fell in water
PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09
![Page 13: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/13.jpg)
Looking US @ the project bend. Road is 4 ft from 14 ft tall eroding bank.
PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09
![Page 14: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/14.jpg)
QUESTIONABLE STONE
Stone used for keys & LPSTP was a sub-standard shot rock of questionable hardness. The amount of fine material was close to 20-30%. This was a self-filtering stone (too many
fines), but not well-graded, & not self-adjusting.
![Page 15: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/15.jpg)
Stone is not well-graded & too many fines. The stone is self-filtering, but not self-adjusting, but only $4.70/ton delivered.
CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09
![Page 16: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/16.jpg)
STONE COSTS However, the stone was extremely inexpensive. The 432 tons of rock
used in the project, at $4.70 per ton (delivered) total cost of stone =
$2032. Very cost effective for what was accomplished. Almost like we
paid for hauling & they threw in the stone for free!!
![Page 17: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/17.jpg)
HAW CREEKMETHODS EMPLOYED
110 ft of Longitudinal Peaked Stone Toe Protection (LPSTP), crest built to 4 ft above the base flow water surface elevation
Locked Logs A vegetated floodplain bench, planted on a grid Live Siltation Live Willow Pole Plantings Living Dikes Single-Stone & Short Bendway Weirs Vegetated & curved upstream key, straight DS key After the fact Joint Planting in DS riprap bank
![Page 18: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/18.jpg)
We will construct from
upstream (US) to
downstream (DS)
![Page 19: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/19.jpg)
LONGITUDINAL PEAKED
STONE TOE PROTECTION
(LPSTP)
![Page 20: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/20.jpg)
Stream channel
Top bank
Eroding bank
ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)
Road
![Page 21: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/21.jpg)
Two fallen trees were angled downstream 30
degrees from the bank with the root wads upstream
against the eroding bank
ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)
Road
![Page 22: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/22.jpg)
LONGITUDINAL PEAKED STONE
TOE PROTECTION {LPSTP} Description: A continuous stone dike placed
longitudinally at, or slightly streamward of, the toe of the eroding bank. Cross-section is triangular. The LPSTP does not necessarily follow the toe exactly, but can be placed to form a "smoothed" alignment through the bend. Smoothed alignment might not be desirable from the environmental or energy dissipation points of view . Amount of stone used (2 tons/linear ft, 1 ton/ft, or less) depends on depth of scour at the toe, estimated stream forces (impinging flow) on the bank, and flood durations and stages.
Tie-backs are short dikes connecting the LPSTP to the bank at regular intervals. Tie-backs are usually the same height as the LPSTP or elevated slightly toward the bank end, and are keyed into the bank. If tie-backs are long they should be angled upstream to act as Bendway Weirs.
![Page 23: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/23.jpg)
Longitudinal Peaked Stone Toe Protection (LPSTP)
As-built
After a high flow event stream has scoured at the toe & some LPSTP stone has self-adjusted
(armored the scour hole)
![Page 24: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/24.jpg)
Locked Logs are then “locked” under the Longitudinal Peaked Stone Toe Protection (LPSTP).
ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)
Road
![Page 25: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/25.jpg)
Looking US. LPSTP crest is 4 ft above base flow stage
CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09
![Page 26: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/26.jpg)
ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)
Tree or shrub poles (called Live Siltation)
installed on top of LPSTP
Willow, dogwood, river birch poles can then be laid on the stone and up against the bank. Basal ends should be in vadose
zone (capillary zone). Willow only used on this project.
Live poles laid
against eroded bank
Road
![Page 27: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/27.jpg)
Looking US. Class laying willow poles against eroding bank.
CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09
![Page 28: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/28.jpg)
ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)
Backfill material from point bar forms a floodplain bench at the Q-2 flood elevation
Road
![Page 29: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/29.jpg)
Looking DS. Backfilling between LPSTP & bank to form floodplain bench @ the Q-2 elevation.
CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09
![Page 30: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/30.jpg)
Looking US. Installing Living Dikes perpendicular to high flow, Live Siltation & Live Poles are parallel with the stream.
CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09
![Page 31: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/31.jpg)
ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)
At intervals, install willow Living Dikes (densely deep-planted adventitious poles aligned perpendicular to direction of high flow)
![Page 32: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/32.jpg)
A Living Dike (perpendicular to high flow) on the floodplain bench.
CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09
![Page 33: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/33.jpg)
Floodplain bench
planted on a grid
patternF
low
AERIAL VIEW OF ENHANCED LPSTP WITH A FLOODPLAIN BENCH WITH VEGETATION PLANTED ON
A GRID PATTERN.
Living Dikes-plants
perpendicular to flow
Live Siltation
Live Poles
Single-Stone
Bendway Weir
Single-Stone
Bendway Weir
![Page 34: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/34.jpg)
PROJECT CONSTRUCTED
IN 1 DAY, MARCH 10, 2009
![Page 35: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/35.jpg)
4 MONTHS AFTER PROJECT
COMPLETION Looking US to DS Photos by LaDon
Atkinson JULY 11, 2009
![Page 36: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/36.jpg)
4 MONTHS LATER-Looking DS @ the project bend.
4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09
![Page 37: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/37.jpg)
4 MONTHS LATER-Looking DS @ floodplain bench
4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09
![Page 38: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/38.jpg)
4 MONTHS LATER-Looking DS @ the thalweg trace, LPSTP, Bendway Weirs & the floodplain bench. Great growth!
4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09
![Page 39: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/39.jpg)
After 4 months, great growth from the 500 willows we planted! LaDon says the
floodplain bench has about 6 inches of sediment
deposition on it (eroding bank turned into a
depositional feature).
![Page 40: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/40.jpg)
4 MONTHS AFTER PROJECT
COMPLETION Looking DS to US Photos by LaDon
Atkinson JULY 11, 2009
![Page 41: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/41.jpg)
4 MONTHS LATER-Looking US @ SSBW, LPSTP & Live Siltation
4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09
![Page 42: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/42.jpg)
4 MONTHS LATER-Looking US @ project & road
4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09
![Page 43: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/43.jpg)
4 MONTHS LATER-Looking US @ a Living Dike on the floodplain bench
4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09
![Page 44: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/44.jpg)
Haw Creek Project (5 inch rain 48 hours prior to photos)
September 20, 2010Two Growing Seasons After
CompletionPhotos By Rob Gramke, Regulatory,St. Louis District, U.S. Army Corps of
Engineers
![Page 45: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/45.jpg)
Looking upstream from the downstream end of the project
Sep 2010-notice how wide the shoulder appears now
March 2009-bank 4 feet from road
![Page 46: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/46.jpg)
Looking downstreamMarch 2009
September 2010
![Page 47: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/47.jpg)
Looking downstream from left descending bank. The vegetation has almost completely grown over the rock – Sept 2010
![Page 48: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/48.jpg)
Rock toe & short Bendway Weirs
![Page 49: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/49.jpg)
Locked log still in place
![Page 50: THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either](https://reader031.vdocument.in/reader031/viewer/2022013004/56649e3b5503460f94b2d624/html5/thumbnails/50.jpg)
This PowerPoint presentation was developed & built by Dave Derrick.
Any questions or comments, call my personal cell @ 601-218-7717, or email @ [email protected]
Enjoy the information!!