INDUSTRIAL TRAINING PRESENTATIONON
CONSTRUCTION OF AMBEDKAR BHAWANAT
BABASAHEB BHIMRAO AMBEDKAR UNIVERSITY
BY:SACHIN KUMAR GUPTA1312200088CE-73
SUBMITTED TO:NEELESH KUMAR SINGH(SENIOR LECTURER)
![Page 2: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/2.jpg)
INTRODUCTION OF COMPANY The Central Public Works Department of India, commonly
referred as the CPWD, is a central government owned authority in charge of public sector works.
The Central Public Works Department, under the ministry of Urban Development, builds and maintains public buildings.
CPWD came into existence in July 1854 when Lord Dalhousie established a central agency for execution of public works.
In the Indian history both pre and post independence CPWD has a glorious era and has been serving the
nation for last 162 years with dedicated, energetic and committed corps of Engineers and Architects.
![Page 3: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/3.jpg)
CPWD consists of three wings in execution field 1). E&M 2). B&R 3). Horticulture
There are three cadre in CPWD under Mould. 1). CAS (CENTRAL ARCHITECTURE SERVICES) 2). CES (CENTRAL ENGINEERING SERVICES) 3).CEMES (CENTRAL ELECTRICAL AND
MECHANICAL ENGINEERING SERVICES)
![Page 4: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/4.jpg)
Afghanistan Parliament made by CPWD
![Page 5: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/5.jpg)
![Page 6: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/6.jpg)
ABOUT THE MAIN PROJECT The main project in which I performed my summer training is
the construction of Ambedkar Bhawan. Ambedkar Bhawan is an educational building situated inside
the Babasaheb Bhimrao Ambedkar University (BBAU), Lucknow.
Ambedkar Bhawan is a four star graded green building therefore all green buildings norms is kept in mind during the construction of the building.
The building have pile foundation and circular
in shape.
![Page 7: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/7.jpg)
PROPOSED LOOK OF BUILDING
![Page 8: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/8.jpg)
DESIGN CRITERIACircular form with minimum surface area and maximum
volumeto increase e ciency of building reducing the heat gain. Use offfismart shading device with sandwiched solar cell lamination.Rainwater harvesting and recycling treated water. Use ofreflective external paint for energy e ciency.ffi
SPACE ECONOMICSRadial grid to obtain circular sectoral spaces developed base onthe space requirement module (SRM) i.e. Requirement fractionworks out to be common multiple of various space requirementsin square meter
![Page 9: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/9.jpg)
Proposed space management of construction site
Front elevation
![Page 10: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/10.jpg)
FACT FILE ABOUT PROJECT
![Page 11: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/11.jpg)
![Page 12: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/12.jpg)
TRAINING WORK DONE
Main training work which is done is shuttering and casting of third floor.
Testing of beams by non destructive test which is pulse velocity test.
Following the green norms while constructing the building.
![Page 13: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/13.jpg)
Actual photo of construction site
![Page 14: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/14.jpg)
Reinforcement for beams and columns
Reinforcement for casting for slabshuttering for stairs and floor for third floor
Space for lift/Elevator
![Page 15: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/15.jpg)
TESTS PERFORMED
ULTRASONIC PULSE VELOCITY TESTAn ultrasonic pulse velocity test is an in-situ, non
destructive test to check the quality of concrete and natural rocks.
In this test, the strength and quality of concrete or rock is assessed by measuring the velocity of an ultrasonic pulse passing through a concrete structure or natural rock formation
Higher velocities indicate good quality and continuity of the material, while slower velocities may indicate concrete with many cracks or voids.
![Page 16: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/16.jpg)
Ultrasonic Pulse Velocity Instrument
![Page 17: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/17.jpg)
Determination of pulse velocity is done by using formula
The object of this method is basically to measure to velocity of pulses of longitudinal vibration passing through the concrete.
![Page 18: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/18.jpg)
Ways of measuring velocity
![Page 19: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/19.jpg)
General Guidelines for Concrete Quality based on UPV
PULSE VELOCITY CONCRETE QUALITY
>4.0 km/s Very good to excellent
3.5 – 4.0 km/s Good to very good, slight porosity may exist
3.0 – 3.5 km/s Satisfactory but loss of integrity is suspected
<3.0 km/s Poor and los of integrity exist.
![Page 20: training report of building of central publics works department(CPWD)](https://reader033.vdocument.in/reader033/viewer/2022050900/58eed27a1a28ab16748b4671/html5/thumbnails/20.jpg)
CONCLUSION
Here I have learned about :-o Standards followed by CPWD in building construction.o Execution of work.o Green building norms.o Application of pile foundation.o Non destructive method of testing of Concrete.