Wayne Chase, P.E.WisDOT Bureau of Project Development
WTBA Conference – January 18, 2019
![Page 2: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/2.jpg)
BPD Construction Oversight Staff Standard Spec Part 1 Revisions for 2019ASP-6 Timely Decision MakingUpcoming Training
2
![Page 3: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/3.jpg)
Doak Christenson – SW RegionChris Fredrick – SE RegionBrian DuPont – SE FreewaysCraig Pringle – NE RegionDavid Pilon – NC RegionMatt Dapp – NW RegionMike Hall – Standard SpecificationsMark Zander – Construction & Materials Manual
3
![Page 4: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/4.jpg)
All revisions are highlighted in the specification Table of Contents.
4
![Page 5: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/5.jpg)
Revised portions of 104.10 for CRIs (effective with December 2017 ASP-6).
Eliminate CRIs for department-generated ideas.
Pavement design changes not allowed.
Need to use prices that represent the fair value of the work when computing CRI savings.
5
![Page 6: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/6.jpg)
Revised 109.4.5 to include accumulated wages and FUTA & SUTA multipliers for force account work.
6
![Page 7: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/7.jpg)
ASP-6 is found in all contract special provisions & modifies the standard spec.
Please review the ASP-6 in your specific contract prior to beginning work!!
7
![Page 8: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/8.jpg)
107 Legal Relations & Responsibility 109 Measurement & Payment 305 Dense-Graded Base 420 Diamond Grinding 450 General Requirements – Asphalt Pavements 455 Asphaltic Materials 460 Hot Mix Asphalt Pavement 506 Steel Bridges 646 Pavement Marking 650 Construction Staking
8
![Page 9: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/9.jpg)
WisDOT-Doing Business-Engineers-Resources-Standards-Contract Admin
Meetings (Agendas, etc.)Line of CommunicationDesignated Materials PersonLook-ahead SchedulesRequests for Information (RFI)Evaluations
9
![Page 10: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/10.jpg)
Green Bay – February 27Wisconsin Rapids – March 6Rhinelander – March 7 Superior – March 13 Eau Claire – March 14Madison – March 19 & April 1 La Crosse – March 21Waukesha – March 26 & 27
10
![Page 12: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/12.jpg)
PROPOSAL MANAGEMENT UPDATES
CONTRACTOR ENGINEER CONFERENCE
JANUARY 17-18, 2019
![Page 13: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/13.jpg)
PROPOSAL MANAGEMENT UPDATES
• Prequalification Reminders• Preliminary Plan Posting• Questions/Answers• ASP 3• ASP 9• Prime Contractor Participation
![Page 14: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/14.jpg)
Prequalification Reminders
• WisDOT’s prequalification period is 2 years• Prequalification Statements must be
submitted 10 BUSINESS days prior to the letting in which you wish to bid.
• Affidavits should contain original signatures, be notarized and include the notary seal
• Work History needs to indicate the specific type of work performed on each job.
![Page 15: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/15.jpg)
Preliminary Plan Posting
• Link to preliminary plans page– http://wisconsindot.gov/Pages/doing-
bus/contractors/hcci/prelim-plans.aspx
![Page 16: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/16.jpg)
Question/Answer on Bid Express
• Information can be found at: – http://wisconsindot.gov/Pages/doing-
bus/contractors/hcci/qa.aspx– Please use the system within Bid Express to
submit questions or email [email protected]
• WisDOT has 5 days to respond after a question is submitted
![Page 17: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/17.jpg)
ASP 3 Disadvantaged Business Enterprise
(DBE) Program Implementation• Last Revision January 2017
– http://wisconsindot.gov/hccidocs/contracting-info/asp-3.pdf
• Currently being reviewed– Compliance with Federal requirements
• ASP 3 updates anticipated – during the 2019 calendar year
![Page 18: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/18.jpg)
ASP 9 Electronic Certified Payroll of Labor
Data Submittal• Revised January 2019
– https://wisconsindot.gov/hccidocs/contracting-info/asp-9.pdf
• Contracts with Federal Funds– Enter payroll and labor data in CRCS
• Contracts with State Funds Only– Enter labor data in CRCS
![Page 19: Wayne Chase, P.E. WisDOT Bureau of Project Development ......Wayne Chase, P.E. WisDOT Bureau of Project Development. WTBA Conference – January 18, 2019 BPD Construction Oversight](https://reader034.vdocument.in/reader034/viewer/2022042215/5ebd4754338af51add5bb6d8/html5/thumbnails/19.jpg)
Prime Contract Participation
• Please review standard specification 108.1.2– http://wisconsindot.gov/rdwy/stndspec/ss-01-
08.pdf#ss108– SPV items in contracts are not necessarily
considered specialty work.