Page 1: WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

WEEKLY REPORT St. Philip’s College THCA

August 17—23rd

This week activities: Next week activities:

• SPC THCA Building:

• Continue with punch list levels 1-4.

• Continue with inspections and closing permits.

• Continue installing OFOI/OFCI items.

• Installed gate at CPS gas meter screen wall.

• Completed alcove for the dryer/washer.

• Continue sealing concrete floors.

• Finish installing grass and rocks.

• Owner’s training/demonstration — Elevator

Click here for drone footage!

SPC THCA Building:

• Continue with punch list levels 1-4.

• Continue with inspections and closing permits. Fire final second half 08/26.

• Continue installing OFOI/OFCI items.

• Paint gate at CPS gas meter screen wall.

• Exterior building plaque delivery.

• Finish installing border tile in all restrooms.

• Owner’s training — Landscape Irrigation

Page 2: WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

West Elevation Overview

East Elevation Overview

Page 3: WEEKLY REPORT...• Owner’s training — Landscape Irrigation . West Elevation Overview East Elevation Overview . THCA West Elevation Gas Meter Gate Installation Lecture Hall LVT

THCA West Elevation

Gas Meter Gate Installation Lecture Hall LVT Flooring