Download - West Look Ahead Schedule 03.31.15
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13
Mar Apr May
13 14 15 16 17 18 19 20
ID DescriptionOrigDura
Start Act Start Finish PredecessorsSuccessors
% Compl
STOStartVari
ORENCO PODIUM WEST 10.10.14HOLLAND CRITICAL DECISION MATRIXCOMMON AREA FINISHESNo value assignedHDC1170 AC & CCTV 34 01/13/15A 01/13/15 05/08/15 HCD1020FF 61% Storepoint 17
BID & AWARDNo value assigned
BA1050 Bid Doors, Frames & Hardware 39 01/05/15A 01/05/15 05/01/15 HCD1020FS+20dBA1090FS*, BA1055FS67% Storepoint 17
BA1060 Bid Custom Millwork 46 01/06/15A 01/06/15 05/27/15 HCD1020FS+40dBA1100FS* 55% Storepoint 17
BA1070 Bid Cabinets 41 01/06/15A 01/06/15 04/09/15 HCD1020FS+10dBA1080FS* 82% Storepoint 17
BA1080 Award Cabinet Contract 20 04/10/15 05/07/15 HDC1030FS, BA1070FS*PS1040FS* 0% Storepoint 17
BA1090 Award Doors, Frames & Hardware Supplier Contract 10 05/04/15 05/15/15 BA1050FS* PS1050FS* 0% Storepoint 17
BA1140 Bid Drywall & Metal Stud 15 03/25/15 04/14/15 HCD1020FS+20d, BA1130SSBA1180FS* 0% Storepoint 17
BA1160 Award Siding Contract 16 03/25/15 04/15/15 BA1120FS PS1090FS* 0% Storepoint 17
BA1180 Award Drywall & Metal Stud Contract 15 04/15/15 05/05/15 BA1140FS* PS1130FS* 0% Storepoint 17
BA1190 Bid Windows 10 03/25/15A 03/25/15 03/25/15 HCD1020FS+20dBA1200FS* 0% Storepoint 17
BA1200 Award Window Contract 15 03/26/15 04/15/15 BA1190FS* PS1140FS* 0% Storepoint 17
BA1310 Bid Gypcrete 10 01/05/15A 01/05/15 04/23/15 HCD1020FS+60dBA1320FS* 72% Storepoint 17
BA1320 Award Gypcrete 15 01/28/15A 01/28/15 05/14/15 BA1310FS* PS1250FS* 81% Storepoint 17
BA1330 Bid Trash Chute & Compactor 29 12/23/14A 12/23/14 04/27/15 HCD1020FS+30dBA1340FS* 73% Storepoint 17
BA1340 Award Trash Chute & Compactor 15 04/28/15 05/18/15 BA1330FS* PS1260FS*, PS1270FS*0% Storepoint 17
BA1350 Bid Storefront 15 03/25/15 04/14/15 HCD1020FS+30dBA1360FS* 0% Storepoint 17
BA1360 Award Storefront 34 02/17/15A 02/17/15 06/01/15 BA1350FS* PS1230FS* 55% Storepoint 17
BA1370 Bid Bath Accessories 15 03/25/15 04/14/15 HCD1020FS+30dBA1380FS* 0% Storepoint 17
BA1380 Award Bath Accessories 12 04/15/15 04/30/15 BA1370FS* PS1280FS* 0% Storepoint 17
BA1390 Bid Counter Tops 10 11/25/14A 11/25/14 04/07/15 HCD1020FS+10dBA1400FS* 90% Storepoint 17
BA1400 Award Counter Tops 10 02/17/15A 02/17/15 04/21/15 BA1390FS* PS1290FS* 78% Storepoint 17
BA1410 Bid Backsplash & Floor Ceramic Tile 10 02/02/15A 02/02/15 04/07/15 HCD1020FS+10dBA1420FS* 79% Storepoint 17
BA1420 Award Backsplash & Floor Tile 25 04/08/15 05/12/15 BA1410FS* PS1300FS* 0% Storepoint 17
BA1430 Bid Roofing & Deck Coatings 25 11/11/14A 11/11/14 04/07/15 HCD1020FSBA1440FS* 91% Storepoint 17
BA1440 Award Roofing & Deck Coatings 39 01/05/15A 01/05/15 06/02/15 BA1430FS* PS1310FS* 63% Storepoint 17
BA1450 Bid Landscape 10 01/05/15A 01/05/15 06/16/15 HCD1020FS+50dBA1460FF+1d*, BA1490FS-15d*49% Storepoint 17
PREPARE & SUBMITNo value assigned
PS1040 Generate Cabinet Shop Drawings 20 05/08/15 06/04/15 BA1080FS* RA1040FS* 0% Storepoint 17PS1070 Generate Structural Steel Shop Drawings 24 03/30/15 04/30/15 BA1150FS* FD1050SS+20d*0% Storepoint 17PS1090 Generate Siding Submittal 15 04/16/15 05/06/15 BA1160FS* RA1090FS* 0% Storepoint 17
PS1120 Generate CMU & Terracotta Submittals 15 03/25/15 04/14/15 BA1170FS FD1070FS, RA1110FS*0% Storepoint 17
PS1130 Generate Metal Stud & Drywall Submittal 15 05/06/15 05/26/15 BA1180FS* RA1100FS* 0% Storepoint 17
PS1140 Window Shops 15 04/16/15 05/06/15 BA1200FS* RA1120FS* 0% Storepoint 17
PS1150 HVAC 20 12/09/14A 12/09/14 04/09/15 BA1270FS RA1130FS* 86% Storepoint 17
PS1160 Electrical 20 08/12/14A 08/12/14 04/21/15 BA1250FS RA1140FS* 89% Storepoint 17
PS1220 Initial Storm Drain Submittal 5 03/25/15 03/31/15 BA1300FS UGU1000FS* 0% Storepoint 17
PS1250 Gypcrete 10 01/05/15A 01/05/15 07/01/15 BA1320FS* RA1190FS* 73% Storepoint 17
PS1280 Bath Accessories 15 05/01/15 05/21/15 BA1380FS* RA1230FS* 0% Storepoint 17
PS1290 Counter Tops 15 04/22/15 05/12/15 BA1400FS* RA1240FS* 0% Storepoint 17
PS1300 Backsplash & Floor Tile 15 05/13/15 06/02/15 BA1420FS* RA1250FS* 0% Storepoint 17
PS1310 Roofing 15 01/05/15A 01/05/15 06/16/15 BA1440FS* RA1260FS* 91% Storepoint 17
PS1320 Landscape 15 01/05/15A 01/05/15 08/07/15 BA1460FS* RA1270FS* 76% Storepoint 17
PS1330 Carpet, Sheet Goods & Base 15 04/08/15 04/28/15 BA1480FS* RA1280FS* 0% Storepoint 17
PS1350 Pool 20 01/05/15A 01/05/15 05/29/15 BA1520FS RA1300FS* 54% Storepoint 17
REVIEW & APPROVENo value assigned
RA1090 Review & Approve Siding Submittal 15 10/06/14A 10/06/14 06/10/15 PS1090FS* FD1080FS*, RA1095FS*86% Storepoint 17
RA1095 Review & Approve metal panels and Terracotta 1 01/05/15A 01/05/15 07/06/15 RA1090FS* 86% Storepoint 17
RA1110 Review & Approve CMU 10 04/15/15 04/28/15 PS1120FS* FD1070FS* 0% Storepoint 17
RA1120 Review & Approve Windows 10 05/07/15 05/20/15 PS1140FS* FD1110FS+30d*0% Storepoint 17
To
day
Da
ta D
ate
AC & CCTV
Bid Doors, Frames & Hardware
Bid Cabinets
Award Cabinet Contract
Bid Drywall & Metal Stud
Award Siding Contract
Award Drywall & Metal Stud Contract
Bid Windows
Award Window Contract
Bid Gypcrete
Bid Trash Chute & Compactor
Bid Storefront
Bid Bath Accessories
Award Bath Accessories
Bid Counter Tops
Award Counter Tops
Bid Backsplash & Floor Ceramic Tile
Award Backsplash & Floo
Bid Roofing & Deck Coatings
Generate Structural Steel Shop Drawings
Generate Siding Submittal
Generate CMU & Terracotta Submittals
Window Shops
HVAC
Electrical
Initial Storm Drain Submittal
Counter Tops
Carpet, Sheet Goods & Base
Review & Approve CMU
Start Date: 05/13/14Finish Date: 06/30/16Data Date: 03/25/15Run Date: 03/31/15
Orenco West Podium .2015.03.26.ppx Page 1A
ORENCO PODIUM WEST 03/27/2015
west podium apartments construction schedule
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13
Mar Apr May
13 14 15 16 17 18 19 20
ID DescriptionOrigDura
Start Act Start Finish PredecessorsSuccessors
% Compl
STOStartVari
RA1130 HVAC 10 04/10/15 04/23/15 PS1150FS* FD1120FS* 0% Storepoint 17
RA1140 Electrical 10 09/15/14A 09/15/14 05/25/15 PS1160FS* FD1130FS* 87% Storepoint 17
RA1150 Plumbing 10 10/20/14A 10/20/14 04/24/15 PS1170FS FD1140FS 83% Storepoint 17
RA1160 Fire Protection 10 10/15/14A 10/15/14 04/27/15 PS1180FS FD1150FS* 83% Storepoint 17
RA1190 Gypcrete 10 01/05/15A 01/05/15 07/21/15 PS1250FS* FD1170FS* 90% Storepoint 17
RA1240 Counter Tops 10 05/13/15 05/26/15 PS1290FS* FD1210FS* 0% Storepoint 17
RA1260 Roofing 10 12/17/14A 12/17/14 07/23/15 PS1310FS* FD1230FS* 83% Storepoint 17
RA1270 Landscape 10 01/05/15A 01/05/15 09/08/15 PS1320FS* FD1240FS* 88% Storepoint 17
RA1280 Carpet & Flooring 10 04/29/15 05/12/15 PS1330FS* FD1250FS+100d*0% Storepoint 17
RA1300 Pool 15 01/05/15A 01/05/15 08/21/15 PS1350FS* FD1280FS* 64% Storepoint 17
FABRICATE & DELIVERNo value assigned
FD1020 Fabricate ATS Rods 10 03/25/15 04/07/15 RA1030FS 0% Storepoint 17
FD1050 Fabricate Structural Steel 60 04/27/15 07/17/15 PS1070SS+20d*PSA1010SS+20d0% Storepoint 17
FD1070 Manufactor CMU 30 04/29/15 06/09/15 RA1110FS*, PS1120FSWP1L1500FS* 0% Storepoint 17
FD1100 Fab & Deliver Elevators 60 03/25/15 06/16/15 RA1010FS+40dELEV1030FS 0% Storepoint 17
FD1120 HVAC 20 04/24/15 05/21/15 RA1130FS* 0% Storepoint 17
FD1130 Electrical 20 12/08/14A 12/08/14 08/21/15 RA1140FS* 65% Storepoint 17
FD1150 Fire Protection 20 04/28/15 05/25/15 RA1160FS* 0% Storepoint 17
UNIT FINISHESNo value assignedHDC2070 AC & CCTV 45 10/01/14A 10/01/14 03/31/15 HCD1020FF 96% Storepoint 17
HDC2120 A/V Package Complete 60 03/25/15 06/16/15 HCD1010FF 0% Storepoint 17
WEST - UNDERGROUND UTILITIESUGU1000 Storm 5 01/12/15A 01/12/15 04/02/15 PS1220FS*, SW1010FS, SD1020F97% Storepoint 17
UGU1030 Gas 10 01/08/15A 01/08/15 03/26/15 SW1010FS 96% Storepoint 17
WEST - FOUNDATION / CONCRETEWEST - LEVEL 1 / SUBGRADE PARKING SEQUENCED EAST TO WESTNo value assigned
WP1L1160.0 Ex Columns/Perim Ftngs North of Ramp 1-7 Line 10 12/03/14A 12/03/14 03/25/15 99% Storepoint 17
WP1L1160.1 FRPS Columns North of ramp 1-7 Line 8 12/16/14A 12/16/14 03/27/15 WP1L1160.2FS*96% Storepoint 17
WP1L1160.2 Backfill/Rough Grade Columns North of Ramp 1-7 Line 3 03/11/15A 03/11/15 04/01/15 WP1L1160.1FS*WP1L1160.3FS*81% Storepoint 17
WP1L1160.3 MEP Underground Rough In North of ramp 1-7 Line 4 03/11/15A 03/11/15 04/02/15 WP1L1160.2FS*WP1L1160.5FS*, WP1L1160.4FF94% Storepoint 17
WP1L1160.4 Inspect MEP Underground Rough In North of ramp 1-7 Line 0 04/02/15 WP1L1160.3FF*WP1L1160.5FS*0% Storepoint 17
WP1L1160.5 Fine Grade SOG North of ramp 1-7 Line P7 5 03/31/15A 03/31/15 04/03/15 WP1L1160.4FS*, WP1L1160.3FS*WP1L1160.6SS+1d*75% Storepoint 17
WP1L1160.6 Form/Rebar SOG North of ramp 1-7 Line P7 2 04/01/15 04/02/15 WP1L1160.5SS+1d*WP1L1160.8FS*, WP1L1160.7FF0% Storepoint 17
WP1L1160.7 Inspect Rebar SOG North of ramp 1-7 Line P7 0 04/02/15 WP1L1160.6FF*WP1L1160.8FS*0% Storepoint 17
WP1L1160.8 Place/Finish & Sawcut SOG North of ramp 1-7 Line P7 2 04/03/15 04/06/15 WP1L1160.6FS*, WP1L1160.7FS*WP2L1116.0FS*0% Storepoint 17
WP1L1284 Permanent Power To SP-1 & 2, St-1 12 01/27/15A 01/27/15 04/09/15 WP1L1280FSWP1L1282FS77% Storepoint 17
WP1L1602 COH Water Pressure Test/Clorination 5 03/24/15A 03/24/15 03/25/15 WP1L1601FS 50% Storepoint 17
WEST - LEVEL 2 PARKINGNo value assigned
WP2L1011.7 Walls, Columns & Crash Walls Ramp 3.5-11Line L2P2 6 03/25/15 04/01/15 WP2L1011.6FS-1dWP2L1011.8FS-1d*0% Storepoint 17
WP2L1011.8 Remove Perimeter Deck Ramp 3.5-11Line L2P2 5 04/01/15 04/07/15 WP2L1011.7FS-1d* 0% Storepoint 17
WP2L1112.6 Stress & Strip Grids G-K/5-12 - L2P3 2 03/30/15A 03/30/15 03/31/15 WP2L1012.5SS+3d*WP2L1112.7FS-1d*50% Storepoint 17
WP2L1112.7 Walls, Columns & Crash Walls Grids G-K/5-12 - L2P3 10 03/31/15 04/13/15 WP2L1112.6FS-1d*WP2L1112.8FS-1d*0% Storepoint 17
WP2L1112.8 Remove Perimeter Decks Grids G-K/5-12 - L2P3 5 04/13/15 04/17/15 WP2L1112.7FS-1d* 0% Storepoint 17
WP2L1113.2 Rebar & Tendons 10-16/A-D - L2P4 5 03/26/15A 03/26/15 03/26/15 WP2L1113.1SS+1d*WP2L1113.4FF*0% Storepoint 17
WP2L1113.3 MEP Completion / Inspections 10-16/A-D - L2P4 0 03/31/15 WP2L1113.1FF*WP2L1113.5FS*0% Storepoint 17
WP2L1113.4 COH Inspection Reinforcing 10-16/A-D - L2P4 0 03/26/15 WP2L1113.2FF*WP2L1113.5FS0% Storepoint 17
WP2L1113.5 Place & Finish 10-16/A-D - L2P4 1 04/01/15 04/01/15 WP2L1113.3FS*, WP2L1113.4FSWP2L1113.6SS+3d*, WP2L1113.0% Storepoint 17
WP2L1113.6 Stress & Strip 10-16/A-D - L2P4 3 04/06/15 04/08/15 WP2L1113.5SS+3d*WP2L1113.7FS*0% Storepoint 17
WP2L1113.7 Walls, Columns & Crash Walls 10-16/A-D - L2P4 6 04/09/15 04/16/15 WP2L1113.5FS, WP2L1113.6FS*WP2L1113.8FS*0% Storepoint 17
WP2L1113.8 Remove Perimeter Decks Grids 10-16/A-D - L2P4 1 04/17/15 04/17/15 WP2L1113.7FS* 0% Storepoint 17
WP2L1114.0 Form Grids D-K/10-16 - L2P5 8 03/24/15A 03/24/15 04/01/15 WP1L1051.8FSWP2L1114.1SS+4d*, WP2L1115.14% Storepoint 17
WP2L1114.1 MEPF Layout / Rough-in D-K/10-16 - L2P5 4 03/30/15 04/02/15 WP2L1114.0SS+4d*WP2L1114.2SS+1d*0% Storepoint 17
WP2L1114.2 Rebar & Tendons D-K/10-16 - L2P5 4 03/31/15 04/03/15 WP2L1114.1SS+1d*WP2L1114.3FF*0% Storepoint 17
WP2L1114.3 MEP Completion / Inspections D-K/10-16 - L2P5 0 04/03/15 WP2L1114.2FF*WP2L1114.5FS*, WP2L1114.4FF0% Storepoint 17
WP2L1114.4 COH Inspection Reinforcing D-K/10-16 - L2P5 0 04/03/15 WP2L1114.3FF*WP2L1114.5FS*0% Storepoint 17
WP2L1114.5 Place & Finish D-K/10-16 - L2P5 1 04/06/15 04/06/15 WP2L1114.3FS*, WP2L1114.4FS*WP2L1114.6FS*, WP2L1114.7FS0% Storepoint 17
WP2L1114.6 Stress & Strip D-K/10-16 - L2P5 3 04/07/15 04/09/15 WP2L1114.5FS*WP2L1330FS, WP3L1010.0FS+20% Storepoint 17
WP2L1114.7 Walls, Columns & Crash Walls D-K/10-16 - L2P5 6 04/06/15 04/13/15 WP2L1114.5FS-1d*WP2L1114.8FS*0% Storepoint 17
WP2L1114.8 Remove Perimeter Decks Grids D-K/10-16 - L2P5 1 04/14/15 04/14/15 WP2L1114.7FS* 0% Storepoint 17
To
day
Da
ta D
ate
HVAC
Plumbing
Fire Protection
Carpet & Flooring
Fabricate ATS Rods
AC & CCTV
Storm
Gas
Ex Columns/Perim Ftngs North of Ramp 1-7 Line
FRPS Columns North of ramp 1-7 Line
Backfill/Rough Grade Columns North of Ramp 1-7 Line
MEP Underground Rough In North of ramp 1-7 Line
Inspect MEP Underground Rough In North of ramp 1-7 Line
Fine Grade SOG North of ramp 1-7 Line P7
Form/Rebar SOG North of ramp 1-7 Line P7
Inspect Rebar SOG North of ramp 1-7 Line P7
Place/Finish & Sawcut SOG North of ramp 1-7 Line P7
Permanent Power To SP-1 & 2, St-1
COH Water Pressure Test/Clorination
Walls, Columns & Crash Walls Ramp 3.5-11Line L2P2
Remove Perimeter Deck Ramp 3.5-11Line L2P2
Stress & Strip Grids G-K/5-12 - L2P3
Walls, Columns & Crash Walls Grids G-K/5-12 - L2P3
Remove Perimeter Decks Grids G-K/5-12 - L2P3
Rebar & Tendons 10-16/A-D - L2P4
MEP Completion / Inspections 10-16/A-D - L2P4
COH Inspection Reinforcing 10-16/A-D - L2P4
Place & Finish 10-16/A-D - L2P4
Stress & Strip 10-16/A-D - L2P4
Walls, Columns & Crash Walls 10-16/A-D - L2P4
Remove Perimeter Decks Grids 10-16/A-D - L2P4
Form Grids D-K/10-16 - L2P5
MEPF Layout / Rough-in D-K/10-16 - L2P5
Rebar & Tendons D-K/10-16 - L2P5
MEP Completion / Inspections D-K/10-16 - L2P5
COH Inspection Reinforcing D-K/10-16 - L2P5
Place & Finish D-K/10-16 - L2P5
Stress & Strip D-K/10-16 - L2P5
Walls, Columns & Crash Walls D-K/10-16 - L2P5
Remove Perimeter Decks Grids D-K/10-16 - L2P5
Page 2A
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13
Mar Apr May
13 14 15 16 17 18 19 20
ID DescriptionOrigDura
Start Act Start Finish PredecessorsSuccessors
% Compl
STOStartVari
WP2L1115.0 Form Grids C-K/1-5 - L2P6 10 03/31/15A 03/31/15 04/15/15 WP2L1114.0FS+1d*WP2L1115.1SS+5d*25% Storepoint 17
WP2L1115.1 MEPF Layout / Rough-in Grids C-K/1-5 - L2P6 4 04/07/15 04/10/15 WP2L1115.0SS+5d*WP2L1115.2FS*0% Storepoint 17
WP2L1115.2 Rebar & Tendons Grids C-K/1-5 - L2P6 5 04/13/15 04/17/15 WP2L1115.1FS*WP2L1115.3FF*0% Storepoint 17
WP2L1115.3 MEP Completion / Inspections Grids C-K/1-5 - L2P6 0 04/17/15 WP2L1115.2FF*WP2L1115.5FS*, WP2L1115.4FF0% Storepoint 17
WP2L1115.4 COH Inspection Reinforcing Grids C-K/1-5 - L2P6 0 04/17/15 WP2L1115.3FF*WP2L1115.5FS*0% Storepoint 17
WP2L1115.5 Place & Finish Grids C-K/1-5 - L2P6 1 04/20/15 04/20/15 WP2L1115.3FS*, WP2L1115.4FS*WP2L1115.7FS, WP2L1115.6FS*0% Storepoint 17
WP2L1115.6 Stress & Strip Grids C-K/1-5 - L2P6 2 04/21/15 04/22/15 WP2L1115.5FS*WP2L1115.7FS-1d*, WP3L1030.00% Storepoint 17
WP2L1115.7 Walls, Columns & Crash Walls Grids C-K/1-5 - L2P6 6 04/22/15 04/29/15 WP2L1115.5FS, WP2L1115.6FS-1WP2L1115.8FS*0% Storepoint 17
WP2L1115.8 Remove Perimeter Decks Grids C-K/1-5 - L2P6 1 04/30/15 04/30/15 WP2L1115.7FS* 0% Storepoint 17
WP2L1116.0 Form Grids A-H/1-10 - L2P7 12 04/07/15 04/22/15 WP1L1160.8FS*WP2L1116.1SS+4d*0% Storepoint 17
WP2L1116.1 MEPF Layout / Rough-in Grids A-H/1-10 - L2P7 3 04/13/15 04/15/15 WP2L1116.0SS+4d*WP2L1116.2FS*0% Storepoint 17
WP2L1116.2 Rebar & Tendons Grids A-H/1-10 - L2P7 5 04/16/15 04/22/15 WP2L1116.1FS*WP2L1116.3FS*0% Storepoint 17
WP2L1116.3 MEP Completion / Inspections Grids A-H/1-10 - L2P7 1 04/23/15 04/23/15 WP2L1116.2FS*WP2L1116.5FS, WP2L1116.4FS*0% Storepoint 17
WP2L1116.4 COH Inspection Reinforcing Grids A-H/1-10 - L2P7 1 04/24/15 04/24/15 WP2L1116.3FS*WP2L1116.5FS*0% Storepoint 17
WP2L1116.5 Place & Finish Grids A-H/1-10 - L2P7 1 04/27/15 04/27/15 WP2L1116.4FS*, WP2L1116.3FSWP2L1116.7FS, WP2L1116.6FS*0% Storepoint 17
WP2L1116.6 Stress & Strip Grids A-H/1-10 - L2P7 3 04/28/15 04/30/15 WP2L1116.5FS*WP2L1116.7FS-1d*0% Storepoint 17
WP2L1116.7 Walls, Columns & Crash Walls Grids A-H/1-10 - L2P7 6 04/30/15 05/07/15 WP2L1116.6FS-1d*, WP2L1116.5WP2L1116.8FS*0% Storepoint 17
WP2L1116.8 Remove Perimeter Decks Grids A-H/1-10 - L2P7 1 05/08/15 05/08/15 WP2L1116.7FS* 0% Storepoint 17
WEST - LEVEL 3 CONCRETENo value assigned
WP3L1010.0 Form Grids E.5-K/8-16 - L3P1 10 04/14/15 04/27/15 WP2L1114.6FS+2d*WP3L1020.0FS+5d*, WP3L1010.0% Storepoint 17
WP3L1010.1 MEPF Layout / Rough-in Grids E.5-K/8-16 - L3P1 4 04/23/15 04/28/15 WP3L1010.0SS+7d*WP3L1010.2FS*0% Storepoint 17
WP3L1010.2 Rebar & Tendons Grids Grids E.5-K/8-16 - L3P1 5 04/29/15 05/05/15 WP3L1010.1FS*WP3L1010.3FF+1d*0% Storepoint 17
WP3L1010.3 MEP Completion / Inspections Grids E.5-K/8-16 - L3P1 0 05/06/15 WP3L1010.2FF+1d*WP3L1010.4FF*, WP3L1010.5FF0% Storepoint 17
WP3L1010.4 COH Inspection Reinforcing Grids E.5-K/8-16 - L3P1 0 05/06/15 WP3L1010.3FF*WP3L1010.5FF+1d*0% Storepoint 17
WP3L1010.5 Place & Finish Grids E.5-K/8-16 - L3P1 0 05/07/15 WP3L1010.4FF+1d*, WP3L1010.3WP3L1010.6FS+3d*0% Storepoint 17
WP3L1010.6 Stress & Strip Grids E.5-K/8-16 - L3P1 3 05/13/15 05/15/15 WP3L1010.5FS+3d*WP3L1010.7FS-1d*0% Storepoint 17
WP3L1020.0 Form Grids A-E.5/8-16 - L3P2 12 05/05/15 05/20/15 WP3L1010.0FS+5d*WP3L1020.1SS+8d*, WP3L1030.0% Storepoint 17
WP3L1030.0 Form Grids E.5-K/1-8 - L3P3 10 05/14/15 05/27/15 WP3L1020.0SS+7d*, WP2L1115.6WP3L1030.1SS+6d*, WP3L1040.0% Storepoint 17
To
day
Da
ta D
ate
Form Grids C-K/1-5 - L2P6
MEPF Layout / Rough-in Grids C-K/1-5 - L2P6
Rebar & Tendons Grids C-K/1-5 - L2P6
MEP Completion / Inspections Grids C-K/1-5 - L2P6
COH Inspection Reinforcing Grids C-K/1-5 - L2P6
Place & Finish Grids C-K/1-5 - L2P6
Stress & Strip Grids C-K/1-5 - L2P6
Walls, Columns & Crash Walls Grids C-K/1-5 - L2P6
Remove Perimeter Decks Grids C-K/1-5 - L2P6
Form Grids A-H/1-10 - L2P7
MEPF Layout / Rough-in Grids A-H/1-10 - L2P7
Rebar & Tendons Grids A-H/1-10 - L2P7
MEP Completion / Inspections Grids A-H/1-10 - L2P7
COH Inspection Reinforcing Grids A-H/1-10 - L2P7
Place & Finish Grids A-H/1-10 - L2P7
Stress & Strip Grids A-H/1-10 - L2P7
Walls, Columns & Crash Walls Grids A-H/1-1
Remove Perimeter Decks Grids A-H/1-10
Form Grids E.5-K/8-16 - L3P1
MEPF Layout / Rough-in Grids E.5-K/8-16 - L3P1
Rebar & Tendons Grids Grids E.5-K/8-16 - L3P1
MEP Completion / Inspections Grids E.5-K/8-1
COH Inspection Reinforcing Grids E.5-K/8-16 -
Place & Finish Grids E.5-K/8-16 - L3P1
Page 3A