DANIELI
IIC Steel For Steel Plant Management
PROJECT
NEW MINIMILL DANIELI (MI.DA)
FOR THE PRODUCTION OF 830,000 TPY LIQUID
STEEL AND 500,000 TPY REBARS
BENI SWEIF INDUSTRIAL ZONE - EGYPT
BUYER : IIC Steel14B Cleopatra St., Elkorba, Heliopolis, Cairo Egypt
SELLER : DANIELI & C. Officine Meccaniche S.p.A
SUMMARY OF WORK PROGRESS No. 14
CUT-OFF DATE 31 MAY 2014
REFERENCE CONTRACT No. DP0C1B01 - DP0FTE01 - DP0GS601
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
2/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
2
TABLES OF CONTENTS
1 SAFETY, QUALITY & QM ................................................................................................................................... 3
1.1 Site Safety.......................................................................................................................................................... 3
2 MAJOR EVENTS ................................................................................................................................................ 3
3 OFFSHORE SUPPLY CONTRACT DP0C1B00........................................................................................................4
3.1 Engineering ....................................................................................................................................................... 4
3.2 Procurement & Manufacturing......................................................................................................................... 4
3.3 Inspections ........................................................................................................................................................4
3.4 Equipment Ready for Delivery ..........................................................................................................................6
3.5 Shipments Status............................................................................................................................................... 7
3.6 Contract Financial Status................................................................................................................................... 8
4 TURN KEY SERVICES CONTRACT DP0GS600...................................................................................................... 9
4.1 Engineering ....................................................................................................................................................... 9
4.2 Procurement & Manufacturing......................................................................................................................... 9
4.3 Inspection..........................................................................................................................................................9
4.4 Equipment Ready for Delivery ........................................................................................................................ 10
4.5 Shipments Status............................................................................................................................................. 12
4.6 Contract Financial Status................................................................................................................................. 13
5 CRANES AND COMPONENTS CONTRACT DP0FTE00 ....................................................................................... 14
5.1 Engineering ..................................................................................................................................................... 14
5.2 Procurement & Manufacturing....................................................................................................................... 14
5.3 Inspection........................................................................................................................................................ 14
5.4 Equipment Ready for Delivery ........................................................................................................................ 15
5.5 Shipments Status............................................................................................................................................. 15
5.6 Contract Financial Status................................................................................................................................. 166 VARIATION ORDERS (APPROVED) .................................................................................................................. 17
Make up water tank: .......................................................... .............................................................. ....................... 17
Weighting Bridge:.............................. ............................................................... ....................................................... 17
Substation: .............................................................. .............................................................. .................................. 17
7 DANIELI CONTRACTS FINANCIAL SUMMARY.................................................................................................. 18
8 WORKS EXECUTION & ERECTION ................................................................................................................... 19
8.1 Building Permits .............................................................................................................................................. 19
8.2 Construction Works.........................................................................................................................................19
9 OVERALL PROGRESS....................................................................................................................................... 59
9.1 Overall Engineering ......................................................................................................................................... 59
9.2 Engineering distribution and progress by discipline ....................................................................................... 59
9.3 Engineering progress by Plant Unit................................................................................................................. 60
9.4 Overall Progress Curve ....................................................................................................................................61
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
3/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
3
1 SAFETY, QUALITY & QM
1.1 Site Safety
On 19/05/2014 has been held a Safety Audit on Site by DANIELI Safety Advisor Adam Giro.
See report R-455-01.02 in attachment
2 MAJOR EVENTS
13/03/2012 1st
Down Payment (2.322.970 ) Off Shore Contract;
24/04/2012 Kick off Meeting for DP0C1B Off Shore Heliopolis;
13/07/2012 2nd
Down Payment (6.974.755 ) Off Shore Contract;
05/09/2012 Signature of TKS DP0GS6 Technical Specification;
19/12/2012 Signature of TKS DP0GS6 commercial contract;
19/01/2013 1st
Down Payment (5.800.000 ) TKS Contract;
01/04/2013 1st
LC opened and Effectiveness date (8.903.483 ) Off Shore Contract;
01/04/2013 1st
LC opened and Effectiveness date (15.660.000 ) TKS Contract;
06/04/2013 Kick Off Meeting for TKS portion Buttrio;
14/05/2013 Kick Off Meeting with local execution contractor Hassan Allam Sons and start date of
contractor contract Cairo;
04/07/2013 EGYPTIAN ELECTRICITY TRANSMISSION COMPANY (EETC) allocation of 84.4 MW for IIC Beni
Sweif project;
15/09/2013 Effective Starting Date of Excavation;
25/09/2013 DAN/IIC/UNGER Joint visit to Unger Steel Factory Sharjah IIC inspection of the workshop;
03/10/2013 the 1st
memorandum of understanding for the project way forward has been signed by the
parties noting the condition precedents to the progress of the contract and project way forward;
09/10/2013 IIC obtain Work Permit from authorities;
17/12/2013 OFFSHORE and TKS contracts LG extension;
18/12/2013 1st
LC OFFSHORE modified and value incremented an amount of (20.774.792 )
to reach (29.678.275 ) Off Shore Contract, 1st
LC TKS modified and value incremented an amount of
(20.880.000 ) to reach (37.200.000 ) TKS Contract (missing 15M)
04/01/2014 First Major delivery to site;
26/01/2014 the 2nd
memorandum of understanding for the project way forward has been signed by the
parties noting the condition precedents to the progress of the contract and project way forward;
28/01/2014 Erection of first steel structure column;
19/02/2014 Safety Audit Onsite;
03/03/2014 1st
LC TKS modified and value incremented an amount of (5.000.000 ) to reach (42.200.000 )
TKS Contract (still outstanding 10M);
04/04/2014 Safety Audit Onsite;
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
4/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
4
3 OFFSHORE SUPPLY CONTRACT DP0C1B00
3.1 Engineering
EVENT DESCRIPTION EVENT
STATUS
EVENT COMPLETION
DATE
PAYMENT
STATUS
PAYMENT
DATE
EQUIPMENT CIVIL
BASIC Complete 06/05/2013 Paid
10/12/2013
EQUIPMENT ASSEMBLY
DRAWINGS Complete 12/06/2013 Paid
10/12/2013
3.2 Procurement & Manufacturing
ALL LPL010
PLANT UNIT DAN JOB NO. PURCHASING &
MANUFACTURINGMELTSHOP FOR 500.000 TPY DP0C1B01 98%
NEW CONT. CAST MACHINE FOR
500.000 TPY DP0C1B02 94%
FTP FOR 500.000 TPY DP0C1B03 97%
ROLLING MILL FOR MIDA DP0C1B04 86%
PLANT TOTALS DP0C1B00 91%
3.3 Inspections
The inspections mentioned are those finally agreed during the meeting DP0C1B-DAB-IIC-M00009 held on 14th
November 2013.
Sec. Contr_Item Sub_Item Job TPC_pos Full_Description Plan / Exp.
Date
Inspection
Status
14.1b 14.1b.3.2.1.1 DP0C1B01 202 Furnace Tilting Platform 20/04/2014 Wavier
14.1b 14.1b.3.2.1.3 DP0C1B01 212 Upper Shell 20/04/2014 Wavier
14.1b 14.1b.3.2.1.4 DP0C1B01 213 Lower Shell 20/04/2014 Wavier
14.1b 14.1b.3.2.1.5 DP0C1B01 221 Watercooled Panels, Standard Type 20/04/2014 Wavier
14.1b 14.1b.3.2.1.11 DP0C1B01 242 Water Cooled Roof 20/04/2014 Wavier
14.1b 14.1b.3.2.1.13 DP0C1B01 261 Roof & Electrode Lifting & Rotation Unit 20/04/2014 Wavier
14.1b 14.1b.3.2.1.14 DP0C1B01 282 Electrode Arms for EAF, Conductive Type 20/04/2014 Wavier
14.1b 14.1b.3.2.1.15 DP0C1B01 291 Furnace Secondary Circuit for LF 20/04/2014 Wavier
14.1b 14.1b.3.2.1.17.A DP0C1B01 4151 Ladle Transfer Car 20/04/2014 Wavier
14.1b 14.1b.3.2.1.29.A DP0C1B01 6007 Upper Shell 20/04/2014 Wavier
14.1b 14.1b.3.2.1.29.B DP0C1B01 6008 Lower Shell 20/04/2014 Wavier
14.1b 14.1b.3.2.1.29.C DP0C1B01 6009 Watercooled Panels, Spare (*) 20/04/2014 Wavier
14.1b 14.1b.3.3.1.1 DP0C1B01 1611 Roof & Electrode Lifting System 20/04/2014 Wavier
14.1b 14.1b.3.3.1.2 DP0C1B01 1631 Ladle Furnace Roof, Inert Type 20/04/2014 Wavier
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
5/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
5
14.1b 14.1b.3.3.1.4 DP0C1B01 1642 Electrode Arms for LF, Bus Bar Type 20/04/2014 Wavier
14.1b 14.1b.3.3.1.7.A DP0C1B01 4451 Ladle Transfer Car 20/04/2014 Wavier
14.1b 14.1b.3.5.1.1.A DP0C1B01 4601 Ladle 20/04/2014 Wavier
14.2 14.2.3.2.1.1.A DP0C1B03 2201 Primary fumes water-cooled ducts 20/04/2014 Wavier
14.3 14.3.3.1.A DP0C1B02 2811 Fixed ladle turret assembly 20/04/2014 Wavier
14.3 14.3.3.4 DP0C1B02 2825 Liftable tundish car 20/04/2014 Wavier
14.3 14.3.3.16 DP0C1B02 2936 Mould assembly 130x130 (including
14.3.10.2.d) 10/06/2014 Remaining
14.3 14.3.3.17 DP0C1B02 2978
Oscillating table (Fast Cast Cube)
hydraulically actuated (including
14.3.3.15, 14.3.10.2.c)
10/06/2014 Remaining
14.3 14.3.3.18 DP0C1B02 2973 Oscillating table assembly (including
14.3.10.2.e/f) 10/06/2014 Remaining
14.3 14.3.3.25 DP0C1B02 3151 Withdrawal and straightening unit
(including 14.3.10.2.k) 20/04/2014 Remaining
14.4 14.4.3.1.1.1.A DP0C1B04 112 Induction furnace 30/07/2014 Remaining
14.4 14.4.3.2.2.7.A DP0C1B04 2351 Roll cartridge 14/08/2014 Remaining
14.4 14.4.3.2.2.12.A DP0C1B04 2491 Roll cartridge 14/08/2014 Remaining
14.4 14.4.3.2.2.13.F DP0C1B04 2233 Gearbox / pinion stand (including
14.4.3.2.2.13.I) 14/08/2014 Remaining
14.4 14.4.3.2.2.14.D DP0C1B04 2414 Gearbox / pinion stand (including
14.3.2.2.14.F) 14/08/2014 Remaining
Inspection overview and status, the below chart is illustrative of the inspection classified into complete for the
equipment inspected, wavier for the inspection not performed and Remaining for equipment to be inspected.
Wavier
69%
Remaining
31%
Inspection Status
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
6/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
6
3.4 Equipment Ready for Delivery
CSP017- forecast for the equipment ready to be shipped breakdown for the consecutive 3 months
Calculated Weight in Tons
PLANT UNIT JOB 2014/06 2014/07 2014/08
MELTSHOP FOR 500.000 TPY DP0C1B01 1492,7 121,2 95,8
NEW CONT. CAST MACHINE FOR
500.000 TPY DP0C1B02 149,7 246,3 209,3
FTP FOR 500.000 TPY DP0C1B03 600,5 81,2 2,4
ROLLING MILL FOR MIDA DP0C1B04 82,0 631,4
CSP017- forecast for the equipment ready to be shipped
CSP017- Equipment effectively packed, ready to be shipped and handling activities complete prior to shipping
0,0
0,5
1,0
1,5
2,0
2,5
3,0
3,5
4,0
4,5
0,0
0,5
1,0
1,5
2,0
2,5
2014/05
2014/06
2014/07
2014/08
2014/09
2014/10
2014/11
2014/12
2015/01
2015/02
2015/03
2015/04
ThousandsTONS
DP0C1B OFFSHORE
MONTHLY
DP0C1B OFFSHORE
CUMULATIVE MONTHLY
PROCESSED
12%
PENDING
88%
DP0C1B OFFSHORE SHIPMENT PROCESSING PROGRESS
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
7/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
7
3.5 Shipments Status
TK010 the graph below is illustrative of the date of shipment vs. shipment weight (in tons weight axis on the right)
and cumulative weight (in tons weight axis on the left).
TK010 the graph below is illustrative of the date of shipment vs. shipment invoices (in millions of euros for each
shipment on the right) and cumulative invoices (in millions of euros for each shipment on the left). Please note these
values consider the various engineering and performances included in these invoices
0,00
2,00
4,00
6,00
8,00
10,00
12,00
14,00
16,00
0,00
2,00
4,00
6,00
8,00
10,00
12,00
14,00
16,00
5/31/2014
6/1/2014
6/2/2014
6/3/2014
6/4/2014
6/5/2014
6/6/2014
6/7/2014
6/8/2014
6/9/2014
6/10/2014
6/11/2014
6/12/2014
6/13/2014
6/14/2014
6/15/2014
6/16/2014
6/17/2014
6/18/2014
6/19/2014
Consignments Weights
Sum of Shipped Weight (Tons) Cumulative of Shipped Weight (Tons)
00,020,040,060,080,10,120,140,160,18
00,020,040,060,08
0,10,120,140,160,18
5
/31/2014
6
/1/2014
6
/2/2014
6
/3/2014
6
/4/2014
6
/5/2014
6
/6/2014
6
/7/2014
6
/8/2014
6
/9/2014
6
/10/2014
6
/11/2014
6
/12/2014
6
/13/2014
6
/14/2014
6
/15/2014
6
/16/2014
6
/17/2014
6
/18/2014
6
/19/2014
Millions
Millions
Consignments Value Invoiced
Sum EURO Cumulative of EURO
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
8/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
8
3.6 Contract Financial Status
CONTRACTS IIC OFF % EURO TRANS DATE
38.976.0001st DP 6% 2.322.970 CASHED 13 MAR 2013
2nd DP 18% 6.974.755 CASHED 13 SEPT 2012
LC1 76% 29.678.275
28 FEB 2013
mod. 18 DEC 2013
BASIC CIVIL 1% 322.970 CASHED 10 DEC 2013
ASSEMBLY DWG 11% 4.322.970 CASHED 10 DEC 2013
GOODS 55% 21.613.362CASHED 94.643,86
REMAINING 21.518.718,14
PAC RM 2% 683.790PAC SMP 3% 1.025.697
FAC 4% 1.709.486
FINANCIAL SUMMARY
CURRENT LC BALANCE 24.937.691
TOTAL OUTSTANDING 0
TOTAL CASHED 14.038.309
CURRENT LC
BALANCE
64%
TOTAL
OUTSTANDING
0%
TOTAL CASHED
36%
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
9/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
9
4 TURN KEY SERVICES CONTRACT DP0GS600
4.1 Engineering
The various engineering activities have been completed with the communication of transmittals DP0C1B-DAB-IIC-
T00043 for the civil basic engineering and the DP0C1B-DAB-IIC-T00052 for the equipment assembly drawings
EVENT DESCRIPTION EVENT
STATUS
EVENT COMPLETION
DATE
PAYMENT
STATUS
PAYMENT
DATE
EQUIPMENT CIVIL
BASIC Complete 21/05/2013 Paid
9/12/2013
EQUIPMENT DETAIL
BASIC
In
progress 30/08/2014
EQUIPMENT ASSEMBLY
DRAWINGS Complete 21/06/2013 Paid
9/12/2013
4.2 Procurement & Manufacturing
ALL LPL010
PLANT UNIT DAN JOB NO. PURCHASING &
MANUFACTURING
AUX PLANTS FOR MINIMILL DP0GS601 65%
TURNKEY FOR MIDA MELTSHOP DP0GS602 73%
TURNKEY FOR MIDA CONT. CASTING
MACHINE DP0GS603 87%
TURNKEY FOR MIDA FUME
TREATMENT PLANT DP0GS604 89%
TURNKEY FOR MIDA ROLLING
MACHINE DP0GS605 94%
TURNKEY FOR MIDA CRANES DP0GS606 55%
PLANT TOTALS DP0GS600 78%
4.3 Inspection
The inspections mentioned are those finally agreed during the meeting DP0C1B-DAB-IIC-M00009 held on 14th
November 2013.
Sec. Contr_Item Sub_Item Job TPC_pos Full_Description Plan / Exp.
Date
Inspection
Status
14.5T 14.5T.6.2.2.1 DP0GS601 6401 Air Compressors (including
14.5T.6.2.2.2/4/5/6) 20/05/2014 Complete
14.5T 14.5T.6.2.8.1 DP0GS601 7052 Mechanical Workshop Equipment (CNC
Equipment) 20/02/2014 Complete
14.5T 14.5T.6.2.12.C.1.4.A DP0GS601 7711
Main bldgs & secondary bldgs (including
14.5T - 6.2.12.C.1.1.A, 6.2.12.C.1.2.A,
6.2.12.C.1.3.A, 6.2.12.C.1.5.A,
6.2.12.C.1.6.A, 6.2.12.C.1.7.A,
6.2.12.C.1.8.A, 6.2.12.C.2.1.A,
6.2.12.C.2.2.A, 6.2.12.C.2.3.A,
6.2.12.C.2.5.A)
Complete
14.6 14.6.4.1.4.0.4.1.1.A DP0GS601 5703 Incoming Line Bay GIS type (including
14.6.4.1.4.0.4.1.1.C/B/D/E/(G)/F/(H)/(I)/(L)) 10/09/2014 Remaining
14.6 14.6.4.1.4.0.4.1.2 DP0GS601 5705 66/22 kV Transformer 10/09/2014 Remaining
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
10/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
10
14.6 14.6.4.1.4.0.4.1.3.(C) DP0GS601 5704 Circuit Breaker for disconnecting SVC 10/09/2014 R emaining
14.6 14.6.4.3.4.0.4.1.5.2 DP0GS601 5710 LV Power Centre Switchboard (including
14.6.4.4.4.0.4.1.5.2, 14.6.4.5.4.0.4.1.5.2) 30/05/2014 Complete
Inspection overview and status, the below chart is illustrative of the inspection classified into complete for the
equipment inspected, wavier for the inspection not performed and Remaining for equipment to be inspected.
4.4 Equipment Ready for Delivery
CSP017- forecast for the equipment ready to be shipped breakdown for the consecutive 3 months
Calculated Weight in Tons
PLANT UNIT JOB 2014/06 2014/07 2014/08
AUX PLANTS FOR MINIMILL DP0GS601 658,2 2,6
TURNKEY FOR MIDA MELTSHOP DP0GS602 724,4 19,8 2,7
TURNKEY FOR MIDA CONT. CASTING
MACHINE DP0GS603
168,7 162,3 76,6
TURNKEY FOR MIDA FUME TREATMENT
PLANT DP0GS604
456,6 120,6
TURNKEY FOR MIDA ROLLING MACHINE DP0GS605 440,1 27,7
Complete
50%
Remaining
50%
Inspection Status
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
11/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
11
CSP017- forecast for the equipment ready to be shipped
CSP017- Equipment effectively packed, ready to be shipped and handling activities complete prior to shipping
0,0
1,0
2,0
3,0
4,0
5,0
6,0
0,0
0,5
1,0
1,5
2,0
2,5
2
014/05
2
014/06
2
014/07
2
014/08
2
014/09
2
014/10
2
014/11
2
014/12
2
015/01
2
015/02
2
015/03
2
015/04
Thousand
sTONS
DP0GS6 TURN KEY
SERVICES MONTHLY
DP0GS6 TURN KEY
SERVICES CUMULATIVE
MONTHLY
PROCESSED
-19%
PENDING
81%
DP0GS6 TURN KEY SERVICES SHIPMENT PROCESSING
PROGRESS
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
12/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
12
4.5 Shipments Status
TK010 the graph below is illustrative of the date of shipment vs. shipment weight (in tons weight axis on the right)
and cumulative weight (in tons weight axis on the left).
TK010 the graph below is illustrative of the date of shipment vs. shipment invoices (in millions of euros for each
shipment on the right) and cumulative invoices (in millions of euros for each shipment on the left). Please note these
values consider the various engineering and performances included in these invoices.
0
200
400
600
800
1000
1200
1400
1600
0
1000
2000
3000
4000
5000
6000
7000
8000
11/20/2013
11/27/2013
12/4/2013
12/11/2013
12/18/2013
12/25/2013
1/1/2014
1/8/2014
1/15/2014
1/22/2014
1/29/2014
2/5/2014
2/12/2014
2/19/2014
2/26/2014
3/5/2014
3/12/2014
3/19/2014
3/26/2014
4/2/2014
4/9/2014
4/16/2014
4/23/2014
4/30/2014
5/7/2014
5/14/2014
5/21/2014
Consignments Weights
Sum of Shipped Weight (Tons) Cumulative of Shipped Weight (Tons)
0
0,5
1
1,5
2
2,5
3
0
2
4
6
8
10
12
14
16
11/20/2013
12/4/2013
12/18/2013
1/1/2014
1/15/2014
1/29/2014
2/12/2014
2/26/2014
3/12/2014
3/26/2014
4/9/2014
4/23/2014
5/7/2014
5/21/2014
Millions
Millions
Consignments Invoiced Value
Sum EURO Cumulative of EURO
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
13/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
13
4.6 Contract Financial Status
CONTRACTS IIC TKS % TRANS DATE
58.000.000
1st DP 10% 5.800.000 CASHED 19 JAN 2013
LC1 73% 42.200.000
28 FEB 2013
mod. (1) 18 DEC 2013
mod. (2) 05 MAR 2014
BASIC CIVIL 3% 1.450.000 CASHED 09 DEC 2013
DETAILS CIVILS 3% 1.450.000 FORECAST 30 AUG 2014
ASSEMBLY DWG 3% 1.450.000 CASHED 09 DEC 2013
GOODS 62% 35.743.651CASHED 11.814.007,78
REMAINING 23.929.643,23
PAC RM 1% 631.905
PAC SMP 1% 631.905
FAC 1% 842.540
LC1 Modified #2 (Pending) 17% 10.000.000
GOODS 16% 9.206.349
PAC RM 0,41% 238.095
PAC SMP 0,41% 238.095
FAC 1% 317.460
FINANCIAL SUMMARY
CURRENT LC BALANCE 27.485.992
TOTAL OUTSTANDING 10.000.000
TOTAL CASHED 20.514.008
CURRENT LC
BALANCE
48%
TOTAL
OUTSTANDING
17%
TOTAL CASHED
35%
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
14/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
14
5 CRANES AND COMPONENTS CONTRACT DP0FTE00
5.1 Engineering
The definition is pending of the spare parts list need to be defined within and no later the end of the November 2014.
5.2 Procurement & Manufacturing
ALL LPL010
PLANT UNIT DAN JOB NO. PURCHASING &
MANUFACTURING
CRANES FOR MELTSHOP DP0FTE01 89%
1 YEAR SPARES FOR MELTSHOP DP0FTE02 NA
1 YEAR SPARES FOR CONT.
CASTING MACHINE DP0FTE03 NA
1 YEAR SPARES FOR FUME
TREATMENT PLANT DP0FTE04 NA
1 YEAR SPARES FOR ROLLINGMILL
DP0FTE05 NA
PLANT TOTALS DP0FTE00 NA
5.3 Inspection
The inspections mentioned are those finally agreed during the meeting DP0C1B-DAB-IIC-M00009 held on 14th
November 2013.
Sec. Contr_Item Sub_Item Job TPC_pos Full_Description Plan / Exp.
Date
Inspection
Status
14.5L 14.5L.3.5.1.1.2.B DP0FTE01 6132 Main & Auxiliary
Hoist Gearboxes 15/07/2014 Remaining
14.5L 14.5L.3.5.1.1.2.D DP0FTE01 6146 Electrical Control
panel & Drives 15/07/2014 Remaining
Remaining
100%
Inspection Status
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
15/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
15
5.4 Equipment Ready for Delivery
CSP017- forecast for the equipment ready to be shipped breakdown for the consecutive 3 months
Calculated Weight in Tons
PLANT UNIT JOB 2014/06 2014/07 2014/08
CRANES FOR MELTSHOP DP0FTE01 NA NA NA
1 YEAR SPARES FOR MELTSHOP DP0FTE02 NA NA NA
1 YEAR SPARES FOR CONT. CASTING
MACHINE DP0FTE03 NA NA NA
1 YEAR SPARES FOR FUME TREATMENT
PLANT DP0FTE04 NA NA NA
1 YEAR SPARES FOR ROLLING MILL DP0FTE05 NA NA NA
CSP017- forecast for the equipment ready to be shipped
Note: this section is under development, awaiting the confirmation of the replacement agreement of the cranes
5.5 Shipments Status
TK010 the graph below is illustrative of the date of shipment vs. shipment weight (in tons weight axis on the right)
and cumulative weight (in tons weight axis on the left).
Note: this section is under development, awaiting the confirmation of the replacement agreement of the cranes
TK010 the graph below is illustrative of the date of shipment vs. shipment invoices (in millions of euros for eachshipment on the right) and cumulative invoices (in millions of euros for each shipment on the left). Please note these
values consider the various engineering and performances included in these invoices.
Note: this section is under development, awaiting the confirmation of the replacement agreement of the cranes
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
16/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
16
5.6 Contract Financial Status
CONTRACTS IIC CRANES / SPARES % TRANS DATE
5.250.0001st Lot 19% 1.000.000 FORECAST 30 JUN 2014
2nd Lot 19% 1.000.000 FORECAST 30 SEPT 2014
3rd Lot LC 62% 3.250.000CASHED 0,00
REMAINING 3.250.000,00
FINANCIAL SUMMARY
CURRENT LC BALANCE 0
TOTAL OUTSTANDING 5.250.000
TOTAL CASHED 0
CURRENT LC
BALANCE
0%
TOTAL
OUTSTANDING
100%
TOTAL CASHED
0%
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
17/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
17
6 VARIATION ORDERS (APPROVED)
Make up water tank:
The parties agreed for the Automatic solution modification of the Makeup water tank of 30.000.
Weighting Bridge:
The parties agreed for the increased capacity of the plant weighting bridge.
Substation:
Substation of 220 KV in Air with Double Bus Bar respect to contractual one GIS 66 KV
The parties agree that 1.7M will be taken out from the DAN scope as an exchange for the improvement of Gate Weighting
Stations of 100 ton, automation of the Makeup water tank of 30.000 m3 and changes required to accommodate the
substation 220kV technical specification and relocation DPOC1B-YB01-E9100-ES108 .Rev04.
The takeout positions from DAN Scope of Supply under the TKS contract DP0GS600 have been agreed by the parties and are
as follows:
5720 - INDOOR LIGHTING SYSTEMS (NORMAL/EMERG.)
5721 - OUTDOOR LIGHTING SYSTEMS(PERIPH./SHEDS)
5725 - LIGHTNING PROTECTION SYSTEMS
5726 - MV ELECTRIC CABLES
5730 - ELECTRIC CABLES FOR SUBSIDIARY SYSTEMS
7131 - MS LABORATORY (Spectrometer equipment only)
5734 - AUXILIARIES ELECTRICAL INSTALLATION MATERIALS
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
18/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
18
7 DANIELI CONTRACTS FINANCIAL SUMMARY
OVERALL CONTRACTS % TRANS STATUS
DOWN PAYMENTS 15.097.725 PAID
CRANE GOODS AGAINST CASH 2.000.000CASHED 0,00
REMAINING 2.000.000,00
TOTAL LC OPEN 71.878.275 EFFECTIVE
TOTAL BASIC CIVIL 1.772.970 PAID
TOTAL DETAIL CIVIL 1.450.000
TOTAL ASSEMBLY DRAWINGS 5.772.970 PAID
GOODS AGAINST OPEN LC 57.357.013CASHED 11.908.651,63
REMAINING 45.448.361,37
PAC RM OPEN LC 1.315.695
PAC SMP OPEN LC 1.657.602FAC OPEN LC 2.552.026
TOTAL OUTSTANDING LC 13.250.000
GOODS AGAINST OUTSTANDING LC 12.456.349
PAC RM OUTSTANDING LC 238.095
PAC SMP OUTSTANDING LC 238.095
FAC OUTSTANDING LC 317.460
OVERALL FINANCIAL SUMMARY
CURRENT LC BALANCE 52.423.683
TOTAL OUTSTANDING 15.250.000
TOTAL CASHED 34.552.317
CURRENT LC
BALANCE
51%
TOTAL
OUTSTANDING
15%
TOTAL CASHED
34%
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
19/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
19
8 WORKS EXECUTION & ERECTION
8.1 Building Permits
The permits issuing is ongoing and permits currently enables the site works to proceed according to the schedule.
8.2 Construction Works
8.2.1 Mobilization
The Commencement Date of the Works relevant to the Contract Misr Sons Development S.A.E. (Hassan Allam
Construction) is the 14th May 2013.
The parties agreed to follow the breakdown submitted by HAC ref. DP0C1B-HAC-ENG-L0022 for Interim Payment.
Subject to monthly verification by ENG.
Internet connection already established by 01/12/2013. ENG requires HAC to guarantee 24 hour, 7 days continuous
power supply of servers and guarantee continuous internet operation.
8.2.2 Shop Drawings
ENG evidenced that HAC accumulated a strong delay with the shop drawings submission which impacted on the
Works schedule.
ENG specified that shop drawing submission was critical and could delay the start date of related construction
activities. The Technical Office team was not adequate to the Works to be performed and has been requested to
increase in order to do not jeopardize the agreed schedule.
No quantity are recognized without approved shop drawings and related BOQs.
8.2.3 Permanent Works
Site Works Chronology Actual Date Planned Date
Effective Starting Date of Excavation (JA01_F01-F02) 15.09.2013 15.09.2013
Issuing Date of Excavation Work Permit 09.10.2013 11.09.2013
First Blinding Concrete Casting (XB11_F01) 23.10.2013 02.10.2013
Rebars Cutting & Bending Starting Date 30.10.2013 -
First R.C. Foundation Casting (JA01_F01-F02) 11.11.2013 12.10.2013
First R.C. Pedestal Casting (XB11_F01) 08.12.2013 28.10.2013
Starting of Steel Structures Arrival at Site 04.01.2014 16.11.2013
Starting of Steel Structures Preassembling on Ground 21.01.2014 10.12.2013
Starting of Steel Structures Erection (JA01_F01-F02, Lot A4, Lot B4) 28.01.2014 10.12.2013
Starting of Steel Structures Erection (GA01_F01-F02, Lot A1) 30.01.2014 03.02.2013
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
20/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
20
8.2.3.1 Civil Works
The Progress of the Works during May 2014 is behind the schedule
The following chart explain in detail the actual progress of the concrete works performed with cut off 29/05/14,
Actual vs Planned quantities according to the target concrete casting curve (including blinding).
NOTE:
REAL PERFORMED = Approved quantities included in Monthly Statement
PHYSICAL PERFORMED = Quantities casted but not yet approved
The Contractor is issuing a recovery plan in the next Monthly Report will be revised all the targets
accordingly.
Layout with Progress 29.05.2014 (in annex)
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
21/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
21
PU KEYPLAN UNIT DESCRIPTION PROGRESS %
GA01 GA01-F01 Meltshop Building - Foundation 100,0%
GA01 GA01-F01 Meltshop Building - Slab on grade 0,0%
GB11 GB11-F01 Scrap Yard - Foundation 100,0%
GB11 GB11-C01 Scrap Yard - Electrical Cabin 0,0%
GB11 GB11-F01 Scrap Yard - Technological Foundation 0,0%
GB11 GB11-F01 Scrap Yard - Walls 68,8%
GB51 GB51-F01 Slag Disposal Area 100,0%
GC11 GC11-F01 Ferroalloy - Foundation 100,0%
GC11 GC11-F01 Ferroalloy - Slab on grade 0,0%
GC11 GC11-F02 Alloy Raw Material Handling 48,3%
GC21 GC21-F01 Carbon Powder Injection 0,0%
GC51 GC51-F01 Consteel 62,5%
GD11 GD11-F01 EAF - Technological Foundation 0,0%GD11 GD11-F01 EAF - Platform 0,0%
GE11 GE11-E01 LF - Electrical Cabin & Pulpit 0,0%
GE11 GE11-F01 LF - Technological Foundation 100,0%
GE11 GE11-F02 LF - Platform 0,0%
GS51 GS51-E01 FTP - Electrical Cabin 0,0%
GS51 GS51-F01 Fume Treatement Plant 0,0%
GS51 GS51-F02 Settling Chamber Foundation 0,0%
GY11 GY11-F01 Temporary Shell Parking Station 100,0%
GY11 GY11-F02 Shell Maintenance Station Foundation 86,8%
GY11 GY11-F03 Ladle Horizontal Reheating Foundation 0,0%
GY11 GY11-F04 Ladle Deslagging Area 0,0%
GY11 GY11-F05 Emergency Pit Foundation 0,0%
GY11 GY11-F06 Ladle Relining Station Foundation 0,0%
GY11 GY11-F07 Ladle Wrecking Station Foundation 0,0%
GY11 GY11-F08 Full Ladle Stand Foundation 0,0%
GY11 GY11-F09 Ladle Drying Station Foundation 0,0%
HC11 HC11-E01 CCM - Electrical Cabin & Pulpit 0,0%
HC11 HC11-F01 CCM - Foundation 0,0%
HY11 HY11-F01 Tundish Relining Station Foundation 0,0%
HY11 HY11-F02 Tundish Drying Station Foundation 0,0%
HY11 HY11-F03 Tundish Wrecking Station Foundation 0,0%
HY11 HY11-F04 Mould Maintenance Area Foundation 0,0%
JA01 JA01-F01 Bar Mill General Area 100,0%
JA01 JA01-F01 Bar Mill - Slab on grade 0,0%
JA01 JA01-E01 Bar Mill Electrical Cabin 8,0%
JD21 JD21-F01 Roughing Rolling Mill Area 55,0%
JD31 JD31-F01 Intermediate Rolling Mill Area 35,5%
JD41 JD41-F01 Finishing Rolling Mill Area 26,8%
JD51 JD51-F01 Rolling Mill Exit Area 14,2%
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
22/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
22
JL21 JL21-F01 Cutting To Length 0,0%
JL41 JL41-F01 Bundles Forming - Cooling Bed 0,0%
JL61 JL61-F01 Bundles Evacuation 0,0%
JY11 JY11-F01 Workshop Area 0,0%
WC11 WC11 Roads 0,0%
WC81 WC81 Sewerage and Drainage Network 0,0%
WD41 WD41-F01 Weighing Station 0,0%
WD42 WD42-F01 Weighing Station 0,0%
WE11 WE11-F01 Rolling Mill Laboratory 72,4%
WE11 WE11-F02 Meltshop Laboratory 33,3%
WG11 WG11-F01 General Warehouse & Workshop 100,0%
WG11 WG11-F01-F02 General Warehouse - Slab on grade & Perimetral Walls 50,0%
WG11 WG11-C01 Central Maintenance Workshop Cabin 72,3%
WG11 WG11-C01-S01 Central Maintenance Workshop Office S1 77,4%
WG11 WG11-C01-S02 Central Maintenance Workshop Office S2 68,8%
XA00 XA00-F01 Pipe Racks - Foundation 70,0%
XB11 XB11-E01 WTP - Electrical Cabin 0,0%
XB11 XB11-F01 WTP - Pump Room 100,0%
XB11 XB11-F01 WTP - Slab on grade 0,0%
XB11 XB11-F01 WTP - Cooling Towers 5,0%
XB11 XB11-F02 Sand Filters and Drain Collecting Tank 97,2%
XB11 XB11-F03 Longitudinal Settling Basin 20,0%
XB11 XB11-F04 Scale Pit 87,8%
XB11 XB11-F05 Sludge Thickener 20,0%
XB11 XB11-F06 Drying Beds 99,7%XB11 XB11-F07 Make-up Water System 24,9%
XB11 XB11-F08 Emergency Tower 100,0%
XC81 XC81-F01 CAP - Foundation 100,0%
XC81 XC81-F01 CAP - Slab on grade 0,0%
XC81 XC81-F01 CAP - Technological Foundation 0,0%
YA00 YA00-F01 Diesel Generator Room 0,0%
YA00 YA00-F01 Electrical Underground General System 0,0%
YB01 YB01-C01 Electrical Substation Cabin 0,0%
YB01 YB01-C02 Electrical Substation Cabin 0,0%
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
23/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
23
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
24/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
24
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
25/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
25
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
26/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
26
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
27/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
27
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
28/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
28
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
29/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
29
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
30/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
30
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
31/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
31
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
32/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
32
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
33/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
33
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
34/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
34
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
35/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
35
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
36/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
36
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
37/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
37
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
38/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
38
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
39/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
39
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
40/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
40
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
41/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
41
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
42/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
42
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
43/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
43
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
44/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
44
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
45/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
45
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
46/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
46
8.2.3.2 Steel Structures Progress
The cumulative physical and real progress quantities for Steel Structures Erection Works as of 29.05.2014
are as follows:
BUILDING TARGET
[ton]
DELIVERED
[ton]
PHICALY
PROGRESS
[ton]
REAL
PROGRESS
[ton]
GA01 - MELTSHOP LOT A1 1276 1276 904 690
GA01 - MELTSHOP LOT B1 1316 1316 97 129
GB11 SCRAP YARD LOT A2 479 479 340 257
GB11 SCRAP YARD LOT B2 418 418 199 153
GC11 FERRO ALLOY LOT A3 114 114 74 61
JA01 - ROLLING MILL LOT A4 882 882 808 612
JA01 - ROLLING MILL LOT B4 787 787 581 442
WG11 WAREHOUSE LOT A5 543 543 523 427
XB11 PUMP ROOM LOT A6 58 58 55 44
XB11 PUMP ROOM LOT B6 17 17 0 0,80
XC81 CAP LOT A7 28 28 27 22
TOTAL 5918 5918
100%
3608
61,0%
2838
47,9%
For more details please refer to
STEEL BUILDINGS SUMMARY OF WORK PROGRESS CUT-OFF 29 MAY 2014 in annex.
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
47/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
47
NOTE:
REAL PERFORMED = Approved quantities included in Monthly Statement
PHYSICAL PERFORMED = Quantities erected (tightening/alignment/touch-up to be completed)
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
48/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
48
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
49/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
49
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
50/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
50
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
51/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
51
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
52/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
52
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
53/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
53
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
54/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
54
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
55/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
55
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
56/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
56
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
57/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
57
8.2.4 Permanent Works Overall Progress & Cost Control
EGP 56.701.490
EGP -
EGP -
EGP -
EGP -
EGP -
EGP -
EGP -
EGP 656.734
EGP 6.837.909
EGP -
EGP 36.938.616
EGP -
EGP 15.163.523
EGP -
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
TOTAL WORK PERFORMED
OPTIONS
16 ELECTRICAL
15 MECHANICAL
11 EQUPMENT
10 SPECIALTIES
09 FINISHES
08 DOORS AND WINDOWS
07 THERMAL AND MOISTURE
05 METALS
04 MASONRY
03 CONCRETE
02-2 ROADS WORK
02-1 SITE CONSTRUCTION
01 BUILDINGS
ACWPvs BCWPWORK PERFORMED, Status as of 29.05.2014
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
58/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
58
8.2.5 Critical issues
1. Construction Works Delay
ENG evidences a deceleration of the civil works and the underperformances during the month of May 2014
which is mainly due to:
Workshop drawings submission delays (under recovery)
Lack of resources in technical office team
Lack of resources on field considering the increase of the civil works (in elevation),
Increasing demand of temporary facilities (scaffolding, formworks) and equipment (mobile cranes,
roller compactors, plate compactors) and increase of overlapping activities in several plant units.
ENG highlights that RC casting is under the revised planned quantities to be performed increasing the delay
instead to recover the variance .
ENG evidences that the Construction Time Schedule Level 3 is definitely a critical task and must be
completed immediately in order to drive through an adequate level of detail the Works on site.Moreover, HAC is requested to build up the Recovery Plan in compliance with the end of erection milestones.
In addition HAC is requested to submit the manpower and equipment resourcing in compliance with the
Recovery Plan.
Dedicate workshops has been held on May 2014 between the Parties (IIC/HAC/ENG) in order to issue a
Recovery Plan including the Lev. 3 of MEP erection, with the target to allow to cast the first billet within the
1st
of July 2015.
Within June 2014 will be revised the new targets to be monitored; meanwhile the works has been driven by a
short term look ahead plan focused on the first phases of the recovery.
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
59/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
59
9 OVERALL PROGRESS
9.1 Overall Engineering
9.2 Engineering distribution and progress by discipline
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
60/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
60
9.3 Engineering progress by Plant Unit
-
5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014
61/61
DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx
61
9.4 Overall Progress Curve