dp0c1b - iic - workprogress nr 14_may 2014

Upload: khaled-rahim

Post on 10-Oct-2015

15 views

Category:

Documents


0 download

TRANSCRIPT

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    1/61

    DANIELI

    IIC Steel For Steel Plant Management

    PROJECT

    NEW MINIMILL DANIELI (MI.DA)

    FOR THE PRODUCTION OF 830,000 TPY LIQUID

    STEEL AND 500,000 TPY REBARS

    BENI SWEIF INDUSTRIAL ZONE - EGYPT

    BUYER : IIC Steel14B Cleopatra St., Elkorba, Heliopolis, Cairo Egypt

    SELLER : DANIELI & C. Officine Meccaniche S.p.A

    SUMMARY OF WORK PROGRESS No. 14

    CUT-OFF DATE 31 MAY 2014

    REFERENCE CONTRACT No. DP0C1B01 - DP0FTE01 - DP0GS601

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    2/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    2

    TABLES OF CONTENTS

    1 SAFETY, QUALITY & QM ................................................................................................................................... 3

    1.1 Site Safety.......................................................................................................................................................... 3

    2 MAJOR EVENTS ................................................................................................................................................ 3

    3 OFFSHORE SUPPLY CONTRACT DP0C1B00........................................................................................................4

    3.1 Engineering ....................................................................................................................................................... 4

    3.2 Procurement & Manufacturing......................................................................................................................... 4

    3.3 Inspections ........................................................................................................................................................4

    3.4 Equipment Ready for Delivery ..........................................................................................................................6

    3.5 Shipments Status............................................................................................................................................... 7

    3.6 Contract Financial Status................................................................................................................................... 8

    4 TURN KEY SERVICES CONTRACT DP0GS600...................................................................................................... 9

    4.1 Engineering ....................................................................................................................................................... 9

    4.2 Procurement & Manufacturing......................................................................................................................... 9

    4.3 Inspection..........................................................................................................................................................9

    4.4 Equipment Ready for Delivery ........................................................................................................................ 10

    4.5 Shipments Status............................................................................................................................................. 12

    4.6 Contract Financial Status................................................................................................................................. 13

    5 CRANES AND COMPONENTS CONTRACT DP0FTE00 ....................................................................................... 14

    5.1 Engineering ..................................................................................................................................................... 14

    5.2 Procurement & Manufacturing....................................................................................................................... 14

    5.3 Inspection........................................................................................................................................................ 14

    5.4 Equipment Ready for Delivery ........................................................................................................................ 15

    5.5 Shipments Status............................................................................................................................................. 15

    5.6 Contract Financial Status................................................................................................................................. 166 VARIATION ORDERS (APPROVED) .................................................................................................................. 17

    Make up water tank: .......................................................... .............................................................. ....................... 17

    Weighting Bridge:.............................. ............................................................... ....................................................... 17

    Substation: .............................................................. .............................................................. .................................. 17

    7 DANIELI CONTRACTS FINANCIAL SUMMARY.................................................................................................. 18

    8 WORKS EXECUTION & ERECTION ................................................................................................................... 19

    8.1 Building Permits .............................................................................................................................................. 19

    8.2 Construction Works.........................................................................................................................................19

    9 OVERALL PROGRESS....................................................................................................................................... 59

    9.1 Overall Engineering ......................................................................................................................................... 59

    9.2 Engineering distribution and progress by discipline ....................................................................................... 59

    9.3 Engineering progress by Plant Unit................................................................................................................. 60

    9.4 Overall Progress Curve ....................................................................................................................................61

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    3/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    3

    1 SAFETY, QUALITY & QM

    1.1 Site Safety

    On 19/05/2014 has been held a Safety Audit on Site by DANIELI Safety Advisor Adam Giro.

    See report R-455-01.02 in attachment

    2 MAJOR EVENTS

    13/03/2012 1st

    Down Payment (2.322.970 ) Off Shore Contract;

    24/04/2012 Kick off Meeting for DP0C1B Off Shore Heliopolis;

    13/07/2012 2nd

    Down Payment (6.974.755 ) Off Shore Contract;

    05/09/2012 Signature of TKS DP0GS6 Technical Specification;

    19/12/2012 Signature of TKS DP0GS6 commercial contract;

    19/01/2013 1st

    Down Payment (5.800.000 ) TKS Contract;

    01/04/2013 1st

    LC opened and Effectiveness date (8.903.483 ) Off Shore Contract;

    01/04/2013 1st

    LC opened and Effectiveness date (15.660.000 ) TKS Contract;

    06/04/2013 Kick Off Meeting for TKS portion Buttrio;

    14/05/2013 Kick Off Meeting with local execution contractor Hassan Allam Sons and start date of

    contractor contract Cairo;

    04/07/2013 EGYPTIAN ELECTRICITY TRANSMISSION COMPANY (EETC) allocation of 84.4 MW for IIC Beni

    Sweif project;

    15/09/2013 Effective Starting Date of Excavation;

    25/09/2013 DAN/IIC/UNGER Joint visit to Unger Steel Factory Sharjah IIC inspection of the workshop;

    03/10/2013 the 1st

    memorandum of understanding for the project way forward has been signed by the

    parties noting the condition precedents to the progress of the contract and project way forward;

    09/10/2013 IIC obtain Work Permit from authorities;

    17/12/2013 OFFSHORE and TKS contracts LG extension;

    18/12/2013 1st

    LC OFFSHORE modified and value incremented an amount of (20.774.792 )

    to reach (29.678.275 ) Off Shore Contract, 1st

    LC TKS modified and value incremented an amount of

    (20.880.000 ) to reach (37.200.000 ) TKS Contract (missing 15M)

    04/01/2014 First Major delivery to site;

    26/01/2014 the 2nd

    memorandum of understanding for the project way forward has been signed by the

    parties noting the condition precedents to the progress of the contract and project way forward;

    28/01/2014 Erection of first steel structure column;

    19/02/2014 Safety Audit Onsite;

    03/03/2014 1st

    LC TKS modified and value incremented an amount of (5.000.000 ) to reach (42.200.000 )

    TKS Contract (still outstanding 10M);

    04/04/2014 Safety Audit Onsite;

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    4/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    4

    3 OFFSHORE SUPPLY CONTRACT DP0C1B00

    3.1 Engineering

    EVENT DESCRIPTION EVENT

    STATUS

    EVENT COMPLETION

    DATE

    PAYMENT

    STATUS

    PAYMENT

    DATE

    EQUIPMENT CIVIL

    BASIC Complete 06/05/2013 Paid

    10/12/2013

    EQUIPMENT ASSEMBLY

    DRAWINGS Complete 12/06/2013 Paid

    10/12/2013

    3.2 Procurement & Manufacturing

    ALL LPL010

    PLANT UNIT DAN JOB NO. PURCHASING &

    MANUFACTURINGMELTSHOP FOR 500.000 TPY DP0C1B01 98%

    NEW CONT. CAST MACHINE FOR

    500.000 TPY DP0C1B02 94%

    FTP FOR 500.000 TPY DP0C1B03 97%

    ROLLING MILL FOR MIDA DP0C1B04 86%

    PLANT TOTALS DP0C1B00 91%

    3.3 Inspections

    The inspections mentioned are those finally agreed during the meeting DP0C1B-DAB-IIC-M00009 held on 14th

    November 2013.

    Sec. Contr_Item Sub_Item Job TPC_pos Full_Description Plan / Exp.

    Date

    Inspection

    Status

    14.1b 14.1b.3.2.1.1 DP0C1B01 202 Furnace Tilting Platform 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.3 DP0C1B01 212 Upper Shell 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.4 DP0C1B01 213 Lower Shell 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.5 DP0C1B01 221 Watercooled Panels, Standard Type 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.11 DP0C1B01 242 Water Cooled Roof 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.13 DP0C1B01 261 Roof & Electrode Lifting & Rotation Unit 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.14 DP0C1B01 282 Electrode Arms for EAF, Conductive Type 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.15 DP0C1B01 291 Furnace Secondary Circuit for LF 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.17.A DP0C1B01 4151 Ladle Transfer Car 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.29.A DP0C1B01 6007 Upper Shell 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.29.B DP0C1B01 6008 Lower Shell 20/04/2014 Wavier

    14.1b 14.1b.3.2.1.29.C DP0C1B01 6009 Watercooled Panels, Spare (*) 20/04/2014 Wavier

    14.1b 14.1b.3.3.1.1 DP0C1B01 1611 Roof & Electrode Lifting System 20/04/2014 Wavier

    14.1b 14.1b.3.3.1.2 DP0C1B01 1631 Ladle Furnace Roof, Inert Type 20/04/2014 Wavier

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    5/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    5

    14.1b 14.1b.3.3.1.4 DP0C1B01 1642 Electrode Arms for LF, Bus Bar Type 20/04/2014 Wavier

    14.1b 14.1b.3.3.1.7.A DP0C1B01 4451 Ladle Transfer Car 20/04/2014 Wavier

    14.1b 14.1b.3.5.1.1.A DP0C1B01 4601 Ladle 20/04/2014 Wavier

    14.2 14.2.3.2.1.1.A DP0C1B03 2201 Primary fumes water-cooled ducts 20/04/2014 Wavier

    14.3 14.3.3.1.A DP0C1B02 2811 Fixed ladle turret assembly 20/04/2014 Wavier

    14.3 14.3.3.4 DP0C1B02 2825 Liftable tundish car 20/04/2014 Wavier

    14.3 14.3.3.16 DP0C1B02 2936 Mould assembly 130x130 (including

    14.3.10.2.d) 10/06/2014 Remaining

    14.3 14.3.3.17 DP0C1B02 2978

    Oscillating table (Fast Cast Cube)

    hydraulically actuated (including

    14.3.3.15, 14.3.10.2.c)

    10/06/2014 Remaining

    14.3 14.3.3.18 DP0C1B02 2973 Oscillating table assembly (including

    14.3.10.2.e/f) 10/06/2014 Remaining

    14.3 14.3.3.25 DP0C1B02 3151 Withdrawal and straightening unit

    (including 14.3.10.2.k) 20/04/2014 Remaining

    14.4 14.4.3.1.1.1.A DP0C1B04 112 Induction furnace 30/07/2014 Remaining

    14.4 14.4.3.2.2.7.A DP0C1B04 2351 Roll cartridge 14/08/2014 Remaining

    14.4 14.4.3.2.2.12.A DP0C1B04 2491 Roll cartridge 14/08/2014 Remaining

    14.4 14.4.3.2.2.13.F DP0C1B04 2233 Gearbox / pinion stand (including

    14.4.3.2.2.13.I) 14/08/2014 Remaining

    14.4 14.4.3.2.2.14.D DP0C1B04 2414 Gearbox / pinion stand (including

    14.3.2.2.14.F) 14/08/2014 Remaining

    Inspection overview and status, the below chart is illustrative of the inspection classified into complete for the

    equipment inspected, wavier for the inspection not performed and Remaining for equipment to be inspected.

    Wavier

    69%

    Remaining

    31%

    Inspection Status

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    6/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    6

    3.4 Equipment Ready for Delivery

    CSP017- forecast for the equipment ready to be shipped breakdown for the consecutive 3 months

    Calculated Weight in Tons

    PLANT UNIT JOB 2014/06 2014/07 2014/08

    MELTSHOP FOR 500.000 TPY DP0C1B01 1492,7 121,2 95,8

    NEW CONT. CAST MACHINE FOR

    500.000 TPY DP0C1B02 149,7 246,3 209,3

    FTP FOR 500.000 TPY DP0C1B03 600,5 81,2 2,4

    ROLLING MILL FOR MIDA DP0C1B04 82,0 631,4

    CSP017- forecast for the equipment ready to be shipped

    CSP017- Equipment effectively packed, ready to be shipped and handling activities complete prior to shipping

    0,0

    0,5

    1,0

    1,5

    2,0

    2,5

    3,0

    3,5

    4,0

    4,5

    0,0

    0,5

    1,0

    1,5

    2,0

    2,5

    2014/05

    2014/06

    2014/07

    2014/08

    2014/09

    2014/10

    2014/11

    2014/12

    2015/01

    2015/02

    2015/03

    2015/04

    ThousandsTONS

    DP0C1B OFFSHORE

    MONTHLY

    DP0C1B OFFSHORE

    CUMULATIVE MONTHLY

    PROCESSED

    12%

    PENDING

    88%

    DP0C1B OFFSHORE SHIPMENT PROCESSING PROGRESS

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    7/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    7

    3.5 Shipments Status

    TK010 the graph below is illustrative of the date of shipment vs. shipment weight (in tons weight axis on the right)

    and cumulative weight (in tons weight axis on the left).

    TK010 the graph below is illustrative of the date of shipment vs. shipment invoices (in millions of euros for each

    shipment on the right) and cumulative invoices (in millions of euros for each shipment on the left). Please note these

    values consider the various engineering and performances included in these invoices

    0,00

    2,00

    4,00

    6,00

    8,00

    10,00

    12,00

    14,00

    16,00

    0,00

    2,00

    4,00

    6,00

    8,00

    10,00

    12,00

    14,00

    16,00

    5/31/2014

    6/1/2014

    6/2/2014

    6/3/2014

    6/4/2014

    6/5/2014

    6/6/2014

    6/7/2014

    6/8/2014

    6/9/2014

    6/10/2014

    6/11/2014

    6/12/2014

    6/13/2014

    6/14/2014

    6/15/2014

    6/16/2014

    6/17/2014

    6/18/2014

    6/19/2014

    Consignments Weights

    Sum of Shipped Weight (Tons) Cumulative of Shipped Weight (Tons)

    00,020,040,060,080,10,120,140,160,18

    00,020,040,060,08

    0,10,120,140,160,18

    5

    /31/2014

    6

    /1/2014

    6

    /2/2014

    6

    /3/2014

    6

    /4/2014

    6

    /5/2014

    6

    /6/2014

    6

    /7/2014

    6

    /8/2014

    6

    /9/2014

    6

    /10/2014

    6

    /11/2014

    6

    /12/2014

    6

    /13/2014

    6

    /14/2014

    6

    /15/2014

    6

    /16/2014

    6

    /17/2014

    6

    /18/2014

    6

    /19/2014

    Millions

    Millions

    Consignments Value Invoiced

    Sum EURO Cumulative of EURO

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    8/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    8

    3.6 Contract Financial Status

    CONTRACTS IIC OFF % EURO TRANS DATE

    38.976.0001st DP 6% 2.322.970 CASHED 13 MAR 2013

    2nd DP 18% 6.974.755 CASHED 13 SEPT 2012

    LC1 76% 29.678.275

    28 FEB 2013

    mod. 18 DEC 2013

    BASIC CIVIL 1% 322.970 CASHED 10 DEC 2013

    ASSEMBLY DWG 11% 4.322.970 CASHED 10 DEC 2013

    GOODS 55% 21.613.362CASHED 94.643,86

    REMAINING 21.518.718,14

    PAC RM 2% 683.790PAC SMP 3% 1.025.697

    FAC 4% 1.709.486

    FINANCIAL SUMMARY

    CURRENT LC BALANCE 24.937.691

    TOTAL OUTSTANDING 0

    TOTAL CASHED 14.038.309

    CURRENT LC

    BALANCE

    64%

    TOTAL

    OUTSTANDING

    0%

    TOTAL CASHED

    36%

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    9/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    9

    4 TURN KEY SERVICES CONTRACT DP0GS600

    4.1 Engineering

    The various engineering activities have been completed with the communication of transmittals DP0C1B-DAB-IIC-

    T00043 for the civil basic engineering and the DP0C1B-DAB-IIC-T00052 for the equipment assembly drawings

    EVENT DESCRIPTION EVENT

    STATUS

    EVENT COMPLETION

    DATE

    PAYMENT

    STATUS

    PAYMENT

    DATE

    EQUIPMENT CIVIL

    BASIC Complete 21/05/2013 Paid

    9/12/2013

    EQUIPMENT DETAIL

    BASIC

    In

    progress 30/08/2014

    EQUIPMENT ASSEMBLY

    DRAWINGS Complete 21/06/2013 Paid

    9/12/2013

    4.2 Procurement & Manufacturing

    ALL LPL010

    PLANT UNIT DAN JOB NO. PURCHASING &

    MANUFACTURING

    AUX PLANTS FOR MINIMILL DP0GS601 65%

    TURNKEY FOR MIDA MELTSHOP DP0GS602 73%

    TURNKEY FOR MIDA CONT. CASTING

    MACHINE DP0GS603 87%

    TURNKEY FOR MIDA FUME

    TREATMENT PLANT DP0GS604 89%

    TURNKEY FOR MIDA ROLLING

    MACHINE DP0GS605 94%

    TURNKEY FOR MIDA CRANES DP0GS606 55%

    PLANT TOTALS DP0GS600 78%

    4.3 Inspection

    The inspections mentioned are those finally agreed during the meeting DP0C1B-DAB-IIC-M00009 held on 14th

    November 2013.

    Sec. Contr_Item Sub_Item Job TPC_pos Full_Description Plan / Exp.

    Date

    Inspection

    Status

    14.5T 14.5T.6.2.2.1 DP0GS601 6401 Air Compressors (including

    14.5T.6.2.2.2/4/5/6) 20/05/2014 Complete

    14.5T 14.5T.6.2.8.1 DP0GS601 7052 Mechanical Workshop Equipment (CNC

    Equipment) 20/02/2014 Complete

    14.5T 14.5T.6.2.12.C.1.4.A DP0GS601 7711

    Main bldgs & secondary bldgs (including

    14.5T - 6.2.12.C.1.1.A, 6.2.12.C.1.2.A,

    6.2.12.C.1.3.A, 6.2.12.C.1.5.A,

    6.2.12.C.1.6.A, 6.2.12.C.1.7.A,

    6.2.12.C.1.8.A, 6.2.12.C.2.1.A,

    6.2.12.C.2.2.A, 6.2.12.C.2.3.A,

    6.2.12.C.2.5.A)

    Complete

    14.6 14.6.4.1.4.0.4.1.1.A DP0GS601 5703 Incoming Line Bay GIS type (including

    14.6.4.1.4.0.4.1.1.C/B/D/E/(G)/F/(H)/(I)/(L)) 10/09/2014 Remaining

    14.6 14.6.4.1.4.0.4.1.2 DP0GS601 5705 66/22 kV Transformer 10/09/2014 Remaining

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    10/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    10

    14.6 14.6.4.1.4.0.4.1.3.(C) DP0GS601 5704 Circuit Breaker for disconnecting SVC 10/09/2014 R emaining

    14.6 14.6.4.3.4.0.4.1.5.2 DP0GS601 5710 LV Power Centre Switchboard (including

    14.6.4.4.4.0.4.1.5.2, 14.6.4.5.4.0.4.1.5.2) 30/05/2014 Complete

    Inspection overview and status, the below chart is illustrative of the inspection classified into complete for the

    equipment inspected, wavier for the inspection not performed and Remaining for equipment to be inspected.

    4.4 Equipment Ready for Delivery

    CSP017- forecast for the equipment ready to be shipped breakdown for the consecutive 3 months

    Calculated Weight in Tons

    PLANT UNIT JOB 2014/06 2014/07 2014/08

    AUX PLANTS FOR MINIMILL DP0GS601 658,2 2,6

    TURNKEY FOR MIDA MELTSHOP DP0GS602 724,4 19,8 2,7

    TURNKEY FOR MIDA CONT. CASTING

    MACHINE DP0GS603

    168,7 162,3 76,6

    TURNKEY FOR MIDA FUME TREATMENT

    PLANT DP0GS604

    456,6 120,6

    TURNKEY FOR MIDA ROLLING MACHINE DP0GS605 440,1 27,7

    Complete

    50%

    Remaining

    50%

    Inspection Status

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    11/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    11

    CSP017- forecast for the equipment ready to be shipped

    CSP017- Equipment effectively packed, ready to be shipped and handling activities complete prior to shipping

    0,0

    1,0

    2,0

    3,0

    4,0

    5,0

    6,0

    0,0

    0,5

    1,0

    1,5

    2,0

    2,5

    2

    014/05

    2

    014/06

    2

    014/07

    2

    014/08

    2

    014/09

    2

    014/10

    2

    014/11

    2

    014/12

    2

    015/01

    2

    015/02

    2

    015/03

    2

    015/04

    Thousand

    sTONS

    DP0GS6 TURN KEY

    SERVICES MONTHLY

    DP0GS6 TURN KEY

    SERVICES CUMULATIVE

    MONTHLY

    PROCESSED

    -19%

    PENDING

    81%

    DP0GS6 TURN KEY SERVICES SHIPMENT PROCESSING

    PROGRESS

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    12/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    12

    4.5 Shipments Status

    TK010 the graph below is illustrative of the date of shipment vs. shipment weight (in tons weight axis on the right)

    and cumulative weight (in tons weight axis on the left).

    TK010 the graph below is illustrative of the date of shipment vs. shipment invoices (in millions of euros for each

    shipment on the right) and cumulative invoices (in millions of euros for each shipment on the left). Please note these

    values consider the various engineering and performances included in these invoices.

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    0

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    11/20/2013

    11/27/2013

    12/4/2013

    12/11/2013

    12/18/2013

    12/25/2013

    1/1/2014

    1/8/2014

    1/15/2014

    1/22/2014

    1/29/2014

    2/5/2014

    2/12/2014

    2/19/2014

    2/26/2014

    3/5/2014

    3/12/2014

    3/19/2014

    3/26/2014

    4/2/2014

    4/9/2014

    4/16/2014

    4/23/2014

    4/30/2014

    5/7/2014

    5/14/2014

    5/21/2014

    Consignments Weights

    Sum of Shipped Weight (Tons) Cumulative of Shipped Weight (Tons)

    0

    0,5

    1

    1,5

    2

    2,5

    3

    0

    2

    4

    6

    8

    10

    12

    14

    16

    11/20/2013

    12/4/2013

    12/18/2013

    1/1/2014

    1/15/2014

    1/29/2014

    2/12/2014

    2/26/2014

    3/12/2014

    3/26/2014

    4/9/2014

    4/23/2014

    5/7/2014

    5/21/2014

    Millions

    Millions

    Consignments Invoiced Value

    Sum EURO Cumulative of EURO

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    13/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    13

    4.6 Contract Financial Status

    CONTRACTS IIC TKS % TRANS DATE

    58.000.000

    1st DP 10% 5.800.000 CASHED 19 JAN 2013

    LC1 73% 42.200.000

    28 FEB 2013

    mod. (1) 18 DEC 2013

    mod. (2) 05 MAR 2014

    BASIC CIVIL 3% 1.450.000 CASHED 09 DEC 2013

    DETAILS CIVILS 3% 1.450.000 FORECAST 30 AUG 2014

    ASSEMBLY DWG 3% 1.450.000 CASHED 09 DEC 2013

    GOODS 62% 35.743.651CASHED 11.814.007,78

    REMAINING 23.929.643,23

    PAC RM 1% 631.905

    PAC SMP 1% 631.905

    FAC 1% 842.540

    LC1 Modified #2 (Pending) 17% 10.000.000

    GOODS 16% 9.206.349

    PAC RM 0,41% 238.095

    PAC SMP 0,41% 238.095

    FAC 1% 317.460

    FINANCIAL SUMMARY

    CURRENT LC BALANCE 27.485.992

    TOTAL OUTSTANDING 10.000.000

    TOTAL CASHED 20.514.008

    CURRENT LC

    BALANCE

    48%

    TOTAL

    OUTSTANDING

    17%

    TOTAL CASHED

    35%

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    14/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    14

    5 CRANES AND COMPONENTS CONTRACT DP0FTE00

    5.1 Engineering

    The definition is pending of the spare parts list need to be defined within and no later the end of the November 2014.

    5.2 Procurement & Manufacturing

    ALL LPL010

    PLANT UNIT DAN JOB NO. PURCHASING &

    MANUFACTURING

    CRANES FOR MELTSHOP DP0FTE01 89%

    1 YEAR SPARES FOR MELTSHOP DP0FTE02 NA

    1 YEAR SPARES FOR CONT.

    CASTING MACHINE DP0FTE03 NA

    1 YEAR SPARES FOR FUME

    TREATMENT PLANT DP0FTE04 NA

    1 YEAR SPARES FOR ROLLINGMILL

    DP0FTE05 NA

    PLANT TOTALS DP0FTE00 NA

    5.3 Inspection

    The inspections mentioned are those finally agreed during the meeting DP0C1B-DAB-IIC-M00009 held on 14th

    November 2013.

    Sec. Contr_Item Sub_Item Job TPC_pos Full_Description Plan / Exp.

    Date

    Inspection

    Status

    14.5L 14.5L.3.5.1.1.2.B DP0FTE01 6132 Main & Auxiliary

    Hoist Gearboxes 15/07/2014 Remaining

    14.5L 14.5L.3.5.1.1.2.D DP0FTE01 6146 Electrical Control

    panel & Drives 15/07/2014 Remaining

    Remaining

    100%

    Inspection Status

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    15/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    15

    5.4 Equipment Ready for Delivery

    CSP017- forecast for the equipment ready to be shipped breakdown for the consecutive 3 months

    Calculated Weight in Tons

    PLANT UNIT JOB 2014/06 2014/07 2014/08

    CRANES FOR MELTSHOP DP0FTE01 NA NA NA

    1 YEAR SPARES FOR MELTSHOP DP0FTE02 NA NA NA

    1 YEAR SPARES FOR CONT. CASTING

    MACHINE DP0FTE03 NA NA NA

    1 YEAR SPARES FOR FUME TREATMENT

    PLANT DP0FTE04 NA NA NA

    1 YEAR SPARES FOR ROLLING MILL DP0FTE05 NA NA NA

    CSP017- forecast for the equipment ready to be shipped

    Note: this section is under development, awaiting the confirmation of the replacement agreement of the cranes

    5.5 Shipments Status

    TK010 the graph below is illustrative of the date of shipment vs. shipment weight (in tons weight axis on the right)

    and cumulative weight (in tons weight axis on the left).

    Note: this section is under development, awaiting the confirmation of the replacement agreement of the cranes

    TK010 the graph below is illustrative of the date of shipment vs. shipment invoices (in millions of euros for eachshipment on the right) and cumulative invoices (in millions of euros for each shipment on the left). Please note these

    values consider the various engineering and performances included in these invoices.

    Note: this section is under development, awaiting the confirmation of the replacement agreement of the cranes

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    16/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    16

    5.6 Contract Financial Status

    CONTRACTS IIC CRANES / SPARES % TRANS DATE

    5.250.0001st Lot 19% 1.000.000 FORECAST 30 JUN 2014

    2nd Lot 19% 1.000.000 FORECAST 30 SEPT 2014

    3rd Lot LC 62% 3.250.000CASHED 0,00

    REMAINING 3.250.000,00

    FINANCIAL SUMMARY

    CURRENT LC BALANCE 0

    TOTAL OUTSTANDING 5.250.000

    TOTAL CASHED 0

    CURRENT LC

    BALANCE

    0%

    TOTAL

    OUTSTANDING

    100%

    TOTAL CASHED

    0%

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    17/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    17

    6 VARIATION ORDERS (APPROVED)

    Make up water tank:

    The parties agreed for the Automatic solution modification of the Makeup water tank of 30.000.

    Weighting Bridge:

    The parties agreed for the increased capacity of the plant weighting bridge.

    Substation:

    Substation of 220 KV in Air with Double Bus Bar respect to contractual one GIS 66 KV

    The parties agree that 1.7M will be taken out from the DAN scope as an exchange for the improvement of Gate Weighting

    Stations of 100 ton, automation of the Makeup water tank of 30.000 m3 and changes required to accommodate the

    substation 220kV technical specification and relocation DPOC1B-YB01-E9100-ES108 .Rev04.

    The takeout positions from DAN Scope of Supply under the TKS contract DP0GS600 have been agreed by the parties and are

    as follows:

    5720 - INDOOR LIGHTING SYSTEMS (NORMAL/EMERG.)

    5721 - OUTDOOR LIGHTING SYSTEMS(PERIPH./SHEDS)

    5725 - LIGHTNING PROTECTION SYSTEMS

    5726 - MV ELECTRIC CABLES

    5730 - ELECTRIC CABLES FOR SUBSIDIARY SYSTEMS

    7131 - MS LABORATORY (Spectrometer equipment only)

    5734 - AUXILIARIES ELECTRICAL INSTALLATION MATERIALS

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    18/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    18

    7 DANIELI CONTRACTS FINANCIAL SUMMARY

    OVERALL CONTRACTS % TRANS STATUS

    DOWN PAYMENTS 15.097.725 PAID

    CRANE GOODS AGAINST CASH 2.000.000CASHED 0,00

    REMAINING 2.000.000,00

    TOTAL LC OPEN 71.878.275 EFFECTIVE

    TOTAL BASIC CIVIL 1.772.970 PAID

    TOTAL DETAIL CIVIL 1.450.000

    TOTAL ASSEMBLY DRAWINGS 5.772.970 PAID

    GOODS AGAINST OPEN LC 57.357.013CASHED 11.908.651,63

    REMAINING 45.448.361,37

    PAC RM OPEN LC 1.315.695

    PAC SMP OPEN LC 1.657.602FAC OPEN LC 2.552.026

    TOTAL OUTSTANDING LC 13.250.000

    GOODS AGAINST OUTSTANDING LC 12.456.349

    PAC RM OUTSTANDING LC 238.095

    PAC SMP OUTSTANDING LC 238.095

    FAC OUTSTANDING LC 317.460

    OVERALL FINANCIAL SUMMARY

    CURRENT LC BALANCE 52.423.683

    TOTAL OUTSTANDING 15.250.000

    TOTAL CASHED 34.552.317

    CURRENT LC

    BALANCE

    51%

    TOTAL

    OUTSTANDING

    15%

    TOTAL CASHED

    34%

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    19/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    19

    8 WORKS EXECUTION & ERECTION

    8.1 Building Permits

    The permits issuing is ongoing and permits currently enables the site works to proceed according to the schedule.

    8.2 Construction Works

    8.2.1 Mobilization

    The Commencement Date of the Works relevant to the Contract Misr Sons Development S.A.E. (Hassan Allam

    Construction) is the 14th May 2013.

    The parties agreed to follow the breakdown submitted by HAC ref. DP0C1B-HAC-ENG-L0022 for Interim Payment.

    Subject to monthly verification by ENG.

    Internet connection already established by 01/12/2013. ENG requires HAC to guarantee 24 hour, 7 days continuous

    power supply of servers and guarantee continuous internet operation.

    8.2.2 Shop Drawings

    ENG evidenced that HAC accumulated a strong delay with the shop drawings submission which impacted on the

    Works schedule.

    ENG specified that shop drawing submission was critical and could delay the start date of related construction

    activities. The Technical Office team was not adequate to the Works to be performed and has been requested to

    increase in order to do not jeopardize the agreed schedule.

    No quantity are recognized without approved shop drawings and related BOQs.

    8.2.3 Permanent Works

    Site Works Chronology Actual Date Planned Date

    Effective Starting Date of Excavation (JA01_F01-F02) 15.09.2013 15.09.2013

    Issuing Date of Excavation Work Permit 09.10.2013 11.09.2013

    First Blinding Concrete Casting (XB11_F01) 23.10.2013 02.10.2013

    Rebars Cutting & Bending Starting Date 30.10.2013 -

    First R.C. Foundation Casting (JA01_F01-F02) 11.11.2013 12.10.2013

    First R.C. Pedestal Casting (XB11_F01) 08.12.2013 28.10.2013

    Starting of Steel Structures Arrival at Site 04.01.2014 16.11.2013

    Starting of Steel Structures Preassembling on Ground 21.01.2014 10.12.2013

    Starting of Steel Structures Erection (JA01_F01-F02, Lot A4, Lot B4) 28.01.2014 10.12.2013

    Starting of Steel Structures Erection (GA01_F01-F02, Lot A1) 30.01.2014 03.02.2013

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    20/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    20

    8.2.3.1 Civil Works

    The Progress of the Works during May 2014 is behind the schedule

    The following chart explain in detail the actual progress of the concrete works performed with cut off 29/05/14,

    Actual vs Planned quantities according to the target concrete casting curve (including blinding).

    NOTE:

    REAL PERFORMED = Approved quantities included in Monthly Statement

    PHYSICAL PERFORMED = Quantities casted but not yet approved

    The Contractor is issuing a recovery plan in the next Monthly Report will be revised all the targets

    accordingly.

    Layout with Progress 29.05.2014 (in annex)

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    21/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    21

    PU KEYPLAN UNIT DESCRIPTION PROGRESS %

    GA01 GA01-F01 Meltshop Building - Foundation 100,0%

    GA01 GA01-F01 Meltshop Building - Slab on grade 0,0%

    GB11 GB11-F01 Scrap Yard - Foundation 100,0%

    GB11 GB11-C01 Scrap Yard - Electrical Cabin 0,0%

    GB11 GB11-F01 Scrap Yard - Technological Foundation 0,0%

    GB11 GB11-F01 Scrap Yard - Walls 68,8%

    GB51 GB51-F01 Slag Disposal Area 100,0%

    GC11 GC11-F01 Ferroalloy - Foundation 100,0%

    GC11 GC11-F01 Ferroalloy - Slab on grade 0,0%

    GC11 GC11-F02 Alloy Raw Material Handling 48,3%

    GC21 GC21-F01 Carbon Powder Injection 0,0%

    GC51 GC51-F01 Consteel 62,5%

    GD11 GD11-F01 EAF - Technological Foundation 0,0%GD11 GD11-F01 EAF - Platform 0,0%

    GE11 GE11-E01 LF - Electrical Cabin & Pulpit 0,0%

    GE11 GE11-F01 LF - Technological Foundation 100,0%

    GE11 GE11-F02 LF - Platform 0,0%

    GS51 GS51-E01 FTP - Electrical Cabin 0,0%

    GS51 GS51-F01 Fume Treatement Plant 0,0%

    GS51 GS51-F02 Settling Chamber Foundation 0,0%

    GY11 GY11-F01 Temporary Shell Parking Station 100,0%

    GY11 GY11-F02 Shell Maintenance Station Foundation 86,8%

    GY11 GY11-F03 Ladle Horizontal Reheating Foundation 0,0%

    GY11 GY11-F04 Ladle Deslagging Area 0,0%

    GY11 GY11-F05 Emergency Pit Foundation 0,0%

    GY11 GY11-F06 Ladle Relining Station Foundation 0,0%

    GY11 GY11-F07 Ladle Wrecking Station Foundation 0,0%

    GY11 GY11-F08 Full Ladle Stand Foundation 0,0%

    GY11 GY11-F09 Ladle Drying Station Foundation 0,0%

    HC11 HC11-E01 CCM - Electrical Cabin & Pulpit 0,0%

    HC11 HC11-F01 CCM - Foundation 0,0%

    HY11 HY11-F01 Tundish Relining Station Foundation 0,0%

    HY11 HY11-F02 Tundish Drying Station Foundation 0,0%

    HY11 HY11-F03 Tundish Wrecking Station Foundation 0,0%

    HY11 HY11-F04 Mould Maintenance Area Foundation 0,0%

    JA01 JA01-F01 Bar Mill General Area 100,0%

    JA01 JA01-F01 Bar Mill - Slab on grade 0,0%

    JA01 JA01-E01 Bar Mill Electrical Cabin 8,0%

    JD21 JD21-F01 Roughing Rolling Mill Area 55,0%

    JD31 JD31-F01 Intermediate Rolling Mill Area 35,5%

    JD41 JD41-F01 Finishing Rolling Mill Area 26,8%

    JD51 JD51-F01 Rolling Mill Exit Area 14,2%

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    22/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    22

    JL21 JL21-F01 Cutting To Length 0,0%

    JL41 JL41-F01 Bundles Forming - Cooling Bed 0,0%

    JL61 JL61-F01 Bundles Evacuation 0,0%

    JY11 JY11-F01 Workshop Area 0,0%

    WC11 WC11 Roads 0,0%

    WC81 WC81 Sewerage and Drainage Network 0,0%

    WD41 WD41-F01 Weighing Station 0,0%

    WD42 WD42-F01 Weighing Station 0,0%

    WE11 WE11-F01 Rolling Mill Laboratory 72,4%

    WE11 WE11-F02 Meltshop Laboratory 33,3%

    WG11 WG11-F01 General Warehouse & Workshop 100,0%

    WG11 WG11-F01-F02 General Warehouse - Slab on grade & Perimetral Walls 50,0%

    WG11 WG11-C01 Central Maintenance Workshop Cabin 72,3%

    WG11 WG11-C01-S01 Central Maintenance Workshop Office S1 77,4%

    WG11 WG11-C01-S02 Central Maintenance Workshop Office S2 68,8%

    XA00 XA00-F01 Pipe Racks - Foundation 70,0%

    XB11 XB11-E01 WTP - Electrical Cabin 0,0%

    XB11 XB11-F01 WTP - Pump Room 100,0%

    XB11 XB11-F01 WTP - Slab on grade 0,0%

    XB11 XB11-F01 WTP - Cooling Towers 5,0%

    XB11 XB11-F02 Sand Filters and Drain Collecting Tank 97,2%

    XB11 XB11-F03 Longitudinal Settling Basin 20,0%

    XB11 XB11-F04 Scale Pit 87,8%

    XB11 XB11-F05 Sludge Thickener 20,0%

    XB11 XB11-F06 Drying Beds 99,7%XB11 XB11-F07 Make-up Water System 24,9%

    XB11 XB11-F08 Emergency Tower 100,0%

    XC81 XC81-F01 CAP - Foundation 100,0%

    XC81 XC81-F01 CAP - Slab on grade 0,0%

    XC81 XC81-F01 CAP - Technological Foundation 0,0%

    YA00 YA00-F01 Diesel Generator Room 0,0%

    YA00 YA00-F01 Electrical Underground General System 0,0%

    YB01 YB01-C01 Electrical Substation Cabin 0,0%

    YB01 YB01-C02 Electrical Substation Cabin 0,0%

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    23/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    23

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    24/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    24

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    25/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    25

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    26/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    26

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    27/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    27

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    28/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    28

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    29/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    29

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    30/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    30

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    31/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    31

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    32/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    32

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    33/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    33

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    34/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    34

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    35/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    35

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    36/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    36

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    37/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    37

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    38/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    38

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    39/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    39

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    40/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    40

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    41/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    41

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    42/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    42

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    43/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    43

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    44/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    44

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    45/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    45

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    46/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    46

    8.2.3.2 Steel Structures Progress

    The cumulative physical and real progress quantities for Steel Structures Erection Works as of 29.05.2014

    are as follows:

    BUILDING TARGET

    [ton]

    DELIVERED

    [ton]

    PHICALY

    PROGRESS

    [ton]

    REAL

    PROGRESS

    [ton]

    GA01 - MELTSHOP LOT A1 1276 1276 904 690

    GA01 - MELTSHOP LOT B1 1316 1316 97 129

    GB11 SCRAP YARD LOT A2 479 479 340 257

    GB11 SCRAP YARD LOT B2 418 418 199 153

    GC11 FERRO ALLOY LOT A3 114 114 74 61

    JA01 - ROLLING MILL LOT A4 882 882 808 612

    JA01 - ROLLING MILL LOT B4 787 787 581 442

    WG11 WAREHOUSE LOT A5 543 543 523 427

    XB11 PUMP ROOM LOT A6 58 58 55 44

    XB11 PUMP ROOM LOT B6 17 17 0 0,80

    XC81 CAP LOT A7 28 28 27 22

    TOTAL 5918 5918

    100%

    3608

    61,0%

    2838

    47,9%

    For more details please refer to

    STEEL BUILDINGS SUMMARY OF WORK PROGRESS CUT-OFF 29 MAY 2014 in annex.

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    47/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    47

    NOTE:

    REAL PERFORMED = Approved quantities included in Monthly Statement

    PHYSICAL PERFORMED = Quantities erected (tightening/alignment/touch-up to be completed)

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    48/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    48

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    49/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    49

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    50/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    50

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    51/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    51

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    52/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    52

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    53/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    53

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    54/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    54

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    55/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    55

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    56/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    56

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    57/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    57

    8.2.4 Permanent Works Overall Progress & Cost Control

    EGP 56.701.490

    EGP -

    EGP -

    EGP -

    EGP -

    EGP -

    EGP -

    EGP -

    EGP 656.734

    EGP 6.837.909

    EGP -

    EGP 36.938.616

    EGP -

    EGP 15.163.523

    EGP -

    0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    TOTAL WORK PERFORMED

    OPTIONS

    16 ELECTRICAL

    15 MECHANICAL

    11 EQUPMENT

    10 SPECIALTIES

    09 FINISHES

    08 DOORS AND WINDOWS

    07 THERMAL AND MOISTURE

    05 METALS

    04 MASONRY

    03 CONCRETE

    02-2 ROADS WORK

    02-1 SITE CONSTRUCTION

    01 BUILDINGS

    ACWPvs BCWPWORK PERFORMED, Status as of 29.05.2014

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    58/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    58

    8.2.5 Critical issues

    1. Construction Works Delay

    ENG evidences a deceleration of the civil works and the underperformances during the month of May 2014

    which is mainly due to:

    Workshop drawings submission delays (under recovery)

    Lack of resources in technical office team

    Lack of resources on field considering the increase of the civil works (in elevation),

    Increasing demand of temporary facilities (scaffolding, formworks) and equipment (mobile cranes,

    roller compactors, plate compactors) and increase of overlapping activities in several plant units.

    ENG highlights that RC casting is under the revised planned quantities to be performed increasing the delay

    instead to recover the variance .

    ENG evidences that the Construction Time Schedule Level 3 is definitely a critical task and must be

    completed immediately in order to drive through an adequate level of detail the Works on site.Moreover, HAC is requested to build up the Recovery Plan in compliance with the end of erection milestones.

    In addition HAC is requested to submit the manpower and equipment resourcing in compliance with the

    Recovery Plan.

    Dedicate workshops has been held on May 2014 between the Parties (IIC/HAC/ENG) in order to issue a

    Recovery Plan including the Lev. 3 of MEP erection, with the target to allow to cast the first billet within the

    1st

    of July 2015.

    Within June 2014 will be revised the new targets to be monitored; meanwhile the works has been driven by a

    short term look ahead plan focused on the first phases of the recovery.

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    59/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    59

    9 OVERALL PROGRESS

    9.1 Overall Engineering

    9.2 Engineering distribution and progress by discipline

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    60/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    60

    9.3 Engineering progress by Plant Unit

  • 5/20/2018 Dp0c1b - Iic - Workprogress Nr 14_may 2014

    61/61

    DP0C1B - IIC - WORKPROGRESS NR 14_MAY 2014.docx

    61

    9.4 Overall Progress Curve