dpe 42inch synopsis rev a
TRANSCRIPT
- Spool Fabrication - Fixed and Metrology
- Installation Aids
- Fabricate new Riser Clamp @ -39.6m
Pre Engineering Survey - ROV approach Survey
- Cut and Remove existing 42" Pipeline, to allow new tie-
in spools
- Removal of Obstructions and Debris
- Bow String Installation
- Cut and retrieve existing 42" Swivel Flange at SPM2
- Change Out of Riser Clamp at KhaZan
- Free Span Corrections
- Tie-in / Closing Spool
- Installation of 52 Concrete Sleepers
- 6km of 42" Pipelines
- Flood, Clean and Gauge of Pipeline
- Hydrotest
- Inhibit Pipeline
As-Built Survey - ROV and CP Potential Surveys
By: Sander PATER Rev.: A
42" EXPORT PIPELINE FROM K3 TO SPM3 - SYNOPSIS
SCOPE OF WORK:
G1201
Pre-Commissioning
Dubai Drydocks World
DSV Works