dpr-23-01-13
DESCRIPTION
DPR-23-01-13TRANSCRIPT
DAILY REPORTFROM SITE
DAILYREPORTFROM SITE
S.No:30 Date 23.01.2013Site: M/s Baldev alloys pvt. LTD.Vwta020,VWHA052,053,054
1.Details of communications received on (E-mail, Fax, Courier, Post, by hand etc.,):Nil.
2.Details of communications sent to HO on:Nil.
3.Details of consignments / materials received from HO / others:Nil.
4.Details of payments received from HO / others:Nil.
5.Attendance with details
5.1Staff (VEESONS):MR.M.E.MANIKANDAN(2141)Mr. DINESH KUMAR.S (1832)
5.2Contract Workers (Contractor wise):Utkal Engineers: Boiler: Supervisor:01 IBR Welder -00;Fitter-03;Welder-00; Riger-02;grinder-0 Helper-05(Total=11)
6.Important brief feedback about Fabrication / Erection / Commissioning (delay with reference to schedule, major problems etc.,):1.contractor man power shortage2. Radiography film required from contractor.3.customer side insert plates5. Insulation work man power required for Seal box area LRB matters work completion purpose.
7.Materials, documents, payments urgently required from HO with details:1. Utkal engg Contractor payment.
8.Any urgent / important site complaints: UTKAL Engineering Should be increasing his manpower.Refractory contractor required for 3XWHRB boiler ABC Ducts.
Site status:VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM1) Feed piping support erection work U/P.2) DEA. Outlet to feed pump suction piping erection work U/P.
ESP; 1) D.E.R.M Hammer shaft & hammers erection work U/P.
Prepared by (Name): M.E.MANIKANDANSignature:Staff No : 2141
Checked & Approved by (Name) :M.E.MANIKANDANSignature:Staff No. :2141