dpr-28-02-13.docx
DESCRIPTION
DPR-27-02-13TRANSCRIPT
DAILY REPORTFROM SITE
DAILYREPORTFROM SITE
S.No:48 Date 28.02.2013Site: M/s Baldev alloys pvt. LTD.Vwta020,VWHA052,053,054
1.Details of communications received on (E-mail, Fax, Courier, Post, by hand etc.,):Nil.
2.Details of communications sent to HO on:Daily report.
3.Details of consignments / materials received from HO / others:Nil.
4.Details of payments received from HO / others:Nil.
5.Attendance with details
5.1Staff (VEESONS):MR.M.E.MANIKANDAN(2141)Mr. DINESH KUMAR.S (1832)
5.2Contract Workers (Contractor wise):Utkal Engineers: Boiler: Supervisor:01 IBR Welder -00;Fitter-04;Welder-04; Riger-03;grinder-0 Helper-06(Total=18)
6.Important brief feedback about Fabrication / Erection / Commissioning (delay with reference to schedule, major problems etc.,):1.contractor man power shortage2. Radiography film required from contractor.3.customer side insert plates
7.Materials, documents, payments urgently required from HO with details:
8.Any urgent / important site complaints: UTKAL Engineering Should be increasing his manpower. Utkal engineering tools & tackles Shortage.(welding machine & cutting set, Grinding machine)
Site status:VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM1) Roof truss boxes erection work completed.2) Transporting supports channel cut to make purlin for roof truss.3) Air heater to Sproger header duct welding work u/p.4) Non IBR drain piping fit up work u/p.
ESP; 1) ESP sealing roof erection & fit up work completed. 2) Roof beam man hole door erection work completed.3) Pressure blower & air heater piping support work complete.
Prepared by (Name): M.E.MANIKANDANSignature:Staff No : 2141
Checked & Approved by (Name) :M.E.MANIKANDANSignature:Staff No. :2141