dr-fb-rs-cs rrpmom 40 (2011) pre-print
TRANSCRIPT
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 1/9
1
An Application of the SMED Methodology in an Electric Power Controls CompanyDomingos Ribeiroa, Fernando Bragaa, Rui Sousab, S. Carmo-Silvab
a General Electric Power Controls Portugalb Production and Systems Department, Engineering School, University of Minho
Postal address: Dr. S. Carmo-Silva, Production and Systems Department, Engineering School,
University of Minho. Campus de Gualtar, 4710-057 Guimaraes, Portugal.Email: [email protected]
AbstractLean production is a strategy for high competiveness in manufacturing. The capability for economical
manufacture in small batch sizes is an essential requirement for achieving lean production. This facilitates mixed
production of several kinds of products to match varying product demand and can have a major impact in
reducing inventories. An obvious requirement for this is the high frequency of equipment setups or product
changeovers. This will not be attractive unless set-up times and costs can be reduced to competitive levels. The
application of SMED can achieve this. SMED is a well-established methodology involving a set of techniques,
methods and guidelines to achieve fast product changeovers at machines. This paper describes the application of
SMED in the production process of plastic and metal components required for the assembly of several types of
circuit breakers. The work was carried out during a short period of a few months under a master thesis project.Several important SMED strategies and solutions were implemented and evaluated in terms of their impact on
productivity and on other manufacturing performance measures. Three specific machines were involved: a
punch-bending machine, a punch press and an injection moulding machine. An important contribution was made
by introducing innovative and simple solutions such as adapting tools and normalizing changeover operations.
Most of the achieved results exceeded the initial expectations. Beyond the purely technical and economic
benefits of SMED, better workstations’ ergonomic conditions were also attained. Besides the usual
quantification of setup time reduction, other indicators were calculated, namely: work-in-process (WIP), annual
setup cost and distance travelled by operators during the changeover process. Reductions of setup time varying
from 59% to 90% were achieved. WIP of metal components was reduced from 17.05 to 7.74 days reducing more
than 50% on the corresponding costs. A more impressive reduction on WIP was obtained for plastic parts,
actually from 5 to 1.09 days of work corresponding to a WIP cost reduction of over 80%. The distance travelledby operators during the changeover process was dramatically reduced too: typically a reduction from 300 m to
10 m and less. The total annual cost savings projection, in this small area of parts production, is near 20,000 €.Although large benefits were obtained from the study, scope for further improvement still exists. In fact the
objective of product changeover times below 10 minutes aimed by SMED was not achieved in one case.
KeywordsMachine setup, Quick changeover, SMED, Mass customization, Lean manufacturing.
IntroductionIt becomes increasingly evident and is generally accepted that mass production, which has dominated the
industry for a long period, in the last century, has become obsolete [1]. More than ever, companies must be able
to manufacture a large variety of products, in small quantities, in order to respond to market requirements [2].
However production costs must be competitive, otherwise a company may not be able to subsist in the current
economic markets within the global competition paradigm of today. Well known new manufacturing paradigms,
namely lean and agile manufacturing, emerged to cope with the challenges of competition within the new marketparadigm. Among other aspects, it is obvious that the necessary time to change production from one product to
another, commonly referred as product changeover time, must be kept as short as possible for allowingmanufacturing in very small quantities of a great variety of products at competitive production costs. This is the
purpose of the SMED methodology, one important tool initially though for lean manufacturing but of great value
to agile manufacturing. SMED aims to substantially reducing product changeover time towards achieving single
digit time values, i.e., less than 10 minutes.
The main objective of this paper is to describe an industrial application and implementation of the SMED
methodology in a company of electric power controls, more specifically within a production process of plastic
and metal components involving three machines: a punch-bending machine, a punch press and an injection
moulding machine. Besides the usual measurement of the setup time reduction, a clear objective of this work isthe quantification of other indicators, such as: work-in-process (WIP), annual setup cost and distance travelled
by operators during the changeover process. The annual setup cost is of particular importance for the company
administration.
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 2/9
Tfundame
the electr
fourth se
Fundam
Ldevelope
specially
chain of
identifies
inventor
waiting.
wasting
comprom
W
manufact
more an
requires
changeosuccess [
S
changeo
changeogood par
equipme
intangibl
identify
Intangibl
and equi
A
knowled
and, (iii)operators
equipme
cannot b
processe
therefore
serious o
S
if the equ
methodol
internal
is consid
many ch
when theoperationlast stage
Standardi
1 demon
die heigh
e structuretals on lean
ic power con
tion. On the
entals of Lea
an manufactd at Toyota
focused on t
a product. W
seven types
, transport (
The expressi
less time, u
ising the pro
ith today’s
uring philos
more impor
supplying s
ers. So, freq11, 12].
ED is a m
ers of produ
er is a produin a given b
t and tools,
. The first c
he following
e costs inclu
ment stress.
cording to S
e about the t
knowledge’ motivation
t designed f
e achieved if
[14]. It is al
unable to id
bstacle to SM
ED classifie
ipment is sto
logy compreh
perations int
red the most
angeover pro
equipment is are thorougis the rationa
ization of dim
trate the use
t (320mm).
f the paperroduction an
rols compan
last section s
n Manufact
ring [3, 4] isotor Compa
e identificati
aste is consid
of waste:
of materials)
on “less is
sing less pr
ucts’ quality
ressure for
phy, improv
tant [10]. As
all quantitie
ent product
ethodology
cts. The met
ction set-upatch and the
setups, runni
an be expres
tangible cos
e the costs i
kine and Ar
chnical aspe
about the mfor collabora
r quick setu
the operator
so recognize
ntify profits
ED studies a
s the change
ped, and ext
ends three s
external op
important [1
esses observ
stopped thahly analysedlization of all
ensional asp
of shims atta
is as followd SMED. Th
. The main r
me concludin
ring and SM
the western dny after the
on and elimi
ered any acti
verproductio
, movement
ore” represe
duction are
cost and deli
reducing no
ing performa
previously r
s of a great
hanges and s
ut forward
hodology is
activity extenirst good par
g of trial pa
ed in monet
ts: lost produ
herent to: re
i [11], the ef
ts of equipm
thod (how tting and acc
s and an ad
s do not coo
that many o
associated to
d implement
ver operation
ernal operatio
ages: (i) sep
rations (whe
], and can le
ed in the ind
could be exowards convthe operation
cts is one of
hed to dies to
2
s. After thise third sectio
sults of the i
g remarks ar
ED
esignation foecond Worl
nation of was
vity or event
n (in terms
(of people),
nts the idea
, as well a
very [9].
n-adding val
nce acting u
ferred, the t
variety of
hort product
by Shingo [
upported by
ded over thet of the follo
rts and adjus
ry units whi
ction, lost c
sponse time t
ficiency of ch
nt and tools,
o do). An ipting new w
equate work
perate and r
rganizations
the changeov
tions.
s in two type
ns, which ca
aration of in
ever possibl
ad to a chang
ustry, it is c
cuted with trting them is (both inter
he issues fre
obtain both
introduction,n describes th
mplementatio
outlined.
r TPS - ToyotWar [8]. It
te, also know
that does no
of earliness
over-processi
of the Japan
s less mater
ue activities,
on products'
pe of deman
products, lik
changeovers
] focused o
a set of tec
time intervaing batch, a
ments [13].
le the second
pacity, inven
o client, risk
angeover is d
(ii) work org
portant reqorking practi
organization,
cognize inhe
o not take i
er time reduc
s: internal op
be executed
ernal and ex
), and, (iii) r
eover time re
mmon to id
e machine rto external oal and extern
uently addre
standard cla
the seconde industrial a
n are present
a Productionis considered
n as “muda“,
add value t
nd/or exces
ng (or inad
se productio
ial and hum
which mea
changeover
d that charac
ly demandi
become key r
achieving
niques, meth
l between thed, typically,
hangeover c
cannot [16].
tory, labour,
of market sh
etermined by
nization (wh
irement fores and meth
efficient and
rent advanta
nto account c
tion [15]. Thi
rations, whi
while the eq
ernal operati
tionalization
uction of 30
ntify operati
nning [20]. Ies whenever
al) to make th
sed in chang
mping height
section provipplication of
d and discus
System [5, 6,a systematic
, along the v
the product.
sive quantity
quate proces
n philosophy
an resources
ns to imple
activities is
terizes curre
g a great n
equirements
very quick
ods and gui
productioninvolves pre
osts can be t
Yang and
trial parts an
are loss, and,
three key el
o does what a
the SMEDods. In fact,
effective ch
es of new c
hangeover c
is fact may c
h can only b
ipment is ru
ons, (ii) con
of operations
to 50% [19].
ons that are
n stage (ii) tpossible. Them more effi
eover process
(80mm) and
des someSMED in
sed on the
7] mostlyapproach
lue added
Ohno [5]
, defects,
sing) and
, meaning
, without
ent lean
becoming
t markets
umber of
o achieve
roduction
elines. A
f the lastaration of
angible or
eane [17]
d defects.
operators
ments: (i)
nd when),
uccess iseven with
angeovers
angeover
sts, being
nstitute a
executed
ning. The
ersion of
. Stage (i)
In fact, in
erformed
e internalthird andient [18].
es. Figure
a standard
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 3/9
T
and time
that allo
of centri
T
studies th
of functi
be point
operation
that can
these and
SMED cT
results an
In
reportedperform
internalstorage.
quite far
reduction
B
here rep
in a redu
W
companicapacity
demand
dependenchangeo
frequent
finish an
of invent
handling
variation
the mach
importan
compani
and oppo
SMED a
Tcompany
e correct pla
consuming t
quick setup
g jigs applie
e cases repre
at can drama
nal clamps, i
d up the i
s of the sam
bring about
other SMED
se studiese SMED me
d reports of t
the area of
by Kays anddetailed ana
and externalhe main ach
from the sin
s in product l
ian [23] desc
rted. A chan
tion of the m
ith a succes
s can be achiand the prod
[24]. It is re
t on changeoers to avoid
product chan
WIP levels
ory turnover,
and increase
of changeov
ines restart c
t additional
s’ competiti
rtunity costs [
pplication at
e main purpin Portugal
Fig
ement or po
sk that may
and adjustm
as illustrated
sented in Fig
ically reduce
mprovement
portant imp
changeover
onsiderable
novel ideas
hodology ha
his work can
plastic moul
Kara [22]. Ilysis of the ch
operations, iievement wa
le digit time
ead time at m
ribes an appli
eover time r
achines’ non
sful implem
eved. The firctivity incre
cognized tha
ver times. Tyig losses on
eovers. As a
[19]. Additio
(ii) improve
of producti
r time. With
n be avoided
enefits expe
eness is the
25].
GE Power
se of this waiming at im
re 1: Standardi
itioning of p
involve a nu
nts, have bee
in Figure 2,
Figur
ures 1 and 2
the changeov
of parts/tools
ct of imple
process carri
eduction in
nd solution c
been studie
e found in th
ing machine
this particulangeover pro
mprovements the reducti
value aimed
achines and a
cation case o
duction from
productive ti
ntation of t
t clear benefise [17] and t
t inventory l
ically, largeproduction c
consequence
ally, as poin
ent of the u
ity and (iv)
simple and e
. Quality and
ted from ad
substantial re
ontrols Port
rk was the iroving perf
3
ized height of d
rts and the s
ber of adjus
n developed.
hus eliminati
e 2: Centring ji
re two exam
er times of di
storage and
enting para
d out simult
hangeover ti
an be found i
and applied
e literature.
s, the descri
lar case, chancess. Special
of water con of change
by SMED, t
lso substantia
the SMED
30,4 to 9,68
e, which wa
he SMED
t is the reducto better com
evels are di
changeover tipacity. Obvi
batch sizes c
ed out by Shi
e of space a
elimination
ficient chang
safety impro
quate SME
duction in ch
ugal
plementatiormance of m
ie and clampin
tup of tools o
tments. To o
One commo
ng the need f
igs [7]
les of typica
es. Other pra
transportation
llel operation
aneously by
me whenever
Shingo’s re
by academici
tion of an i
geover teamattention has
nnections anver time fro
he reduction
l increase in
ethodology t
minutes was
s used in fav
ethodology
ion of unprodanies’ capabi
ectly related
mes, lead to lously, reducti
n be reduced
ingo [7], low
ea (less stora
of safety inv
eovers, error
ements and r
implementa
angeover cos
n of the SMetallic and p
g [7]
r dies in a m
ercome diffi
ly used in S
r adjustment
l solutions fr
tical techniq
and automat
s. Parallel o
ifferent oper
it can be im
erence book [
ans and peop
dustrial app
were organibeen given to
moulds’ cl365 to 73
was quite im
achine capa
o punch pres
attained. Thi
ur of the clie
everal imm
uctive time.lity to respon
to batch siz
arge batch sizon of change
substantially
r inventory l
ge area), (iii)
entory due t
are reduced
duction of p
ions [18]. P
ts, which inc
D methodollastic parts p
chine can be
ulties, novel
ED solution
s.
quently used
ues may inclu
ion [21]. It s
perations are
ators. This is
plemented.
7].
le from indus
lication of S
zed to collecthe separatio
lamping, tranminutes. Des
pressive ena
ity and utiliz
ses relevant t
s improveme
t.
diate benefi
his leads tod to changes
es which, in
es and smallover times all
, the same ha
vels allow: (i
reduction of
o changeove
and the trial
rocesses’ vari
rticularly be
lude labour,
gy at a powroduction and
a difficult
solutions,
s is a pair
in SMED
de the use
ould also
different
a strategy
Details of
try. Many
ED was
data andn between
sport andpite being
ling large
ation.
the work
t resulted
s for the
roductionin market
turn, are
number of ows more
pening to
) increase
inventory
mistakes
ests when
ability are
eficial to
quipment
r controlsreducing
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 4/9
inventormouldin
In
Video re
changeo
operators
lack of csaid to th
A
context o
to this.
represent
T
costs (
(1).
finally,annual sa
A
an organi
process
charts”.
were esti
A
to operat
a few id
below.
Punc
Incleaning
operation
S
to the e
machine
In
and, wh
replacedfaster.
T
improve
levers w
connecti
. Three specimachine.
order to clea
ordings wer
er procedure
to collect an
hangeover ine organizatio
s WIP reduct
f the ongoin
hus the ini
ing 80% of to
allow the q
) associated
represents
the machinvings per eac
nother releva
zed and opti
s little as po
ased on dir
mate.
fter the analy
ors’ involvem
as for impr
h-bending m
the punch-beand several
s.
me internal
istence of sp
are running.
terms of op
never possib
by bell crank
(a) (b)
e use of gau
some operati
as proposed
ns.
ific machines
rly understan
also made f
were not eff
look for die
structions anand location
ion in the ar
lean manufa
ial average
tal productio
antification
to the initial
he lost produ
e cost. The ah minute of r
t aspect in th
ized change
ssible. Opera
ct observatio
is of the initi
ent. From thi
vement cam
achine
nding machiarts’ preasse
perations inv
are sliding u
rations strea
le, the holes
s (Figure 3(b
Figure 3: (
es was intro
ns, not only i
and imple
were involv
d the change
r detailed an
icient. In addi
s, tooling and
workstationof tooling an
ea of metal
cturing impr
values for th
in the corres
f the moneta
cenario were
(1)
ction cost,
nnual changeduction in th
e assessment
ver, an opera
tors’ movem
n and analysi
al scenario, th
s and mainly
up. Some
e, internal anmbling are n
olving slidin
nits which a
lining, most
were modifi
)). Tools bec
) Use of screw
uced to elimi
n terms of ti
ented (Figu
4
ed: a punch-
ver processe
alysis and m
tion to high
other auxilia
s’ organizatid other elem
nd plastics
vement proj
is indicator
ponding area
ry gains obta
determined.
the labour c
over cost asschangeover
of changeove
tor should m
nts were sh
is of video r
e SMED met
following so
f the solutio
d external opow carried o
units were c
e now set-u
of the traditi
d for easy s
me unnecess
s with knob, (b
nate trial and
e spent but a
e 4(b)). Qu
ending mach
s, several cha
asuring of ch
hangeover ti
ry devices an
n could cleants associate
arts was one
cts, the SME
were also
s.
ined after SM
The tangible
ost, the sc
ciated to eactime was det
r efficiency i
ove out of his
wn and mea
cords, the tr
hodology wa
e brainstorm
ns and propo
erations wereut while the
onverted into
, i.e., assem
onal screws
etting (Figur
ary and the p
) Application o
error adjustm
lso regarding
ick coupling
ine, a punch
ngeover occu
angeover tim
es, high dist
documents.
ly be improvto changeov
of the com
D project sh
easured. Thi
ED impleme
osts were ca
rap cost,
h machine inrmined.
related to o
working are
sured using t
velled distan
applied. Spe
ing sessions
sals for impr
clearly separmachine is r
external ones
led with be
ere replaced
3(a)). In ot
rocess of tig
f bell cranks
ents, as illust
the ergonomi
s were adop
press and an
rrences were
es. It was cle
ances were tr
Moreover, th
ed. The samers.
any’s prioriti
uld strongly
s was based
ntation, the c
lculated usin
the inventor
volved and t
erators’ mov
during the c
he so-called
ces during c
cial attention
ith the opera
ovement are
ated. Lookinunning, i.e. a
. This was po
rings and ca
by screws
her cases sc
tening/loose
rated in Figu
ic conditions,
ted for the
injection
observed.
ar that the
avelled by
re were a
could be
es, in the
contribute
on parts
hangeover
Equation
cost and,
e average
ments. In
angeover
“spaghetti
angeover
was given
tors, quite
described
for tools,s external
ssible due
ms, while
ith knobs
ews were
ing much
e 4(a). To
the use of
hydraulic
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 5/9
Di
delays di
T
improve
standardi
departme
O
changeo
Punc
Fmachine,
particula
operation
the mac
machine.
T
adjustme
in the pr
carry out
opening/
P
possible
there we
ies exchange
s exchange c
e standardiz
ents in the
zation of sup
nt of the com
her improve
er process of
h press
llowing theinternal and
, a small su
s into extern
ine, with th
streamline
nts, both in th
ss was impl
the centring
losing of die
rallel operati
for two main
e enough ope
(a)
Fig
at the machi
onsiderably.
tion of supp
hangeover p
ort plates wa
pany.
ments, inclu
the punch-be
SMED stratexternal ope
pport plate
l ones. When
machine st
he changeov
e press and i
mented. Thi
operation.
s, Figure 6(a)
(a)
Figure 6:
ons were als
reasons. First
rators availab
re 4: (a) Appli
nes were aid
igure 5: Non-
ort plates for
rocess and s
s made to the
ding the int
nding machin
gy for imprrations were
or a countin
a single sup
pped, and fi
r operations
a raw materi
made the ce
oreover, the
Figure 6(b) s
(a) Use of hyd
o implement
the changeo
le to carry ou
5
cation of gaug
ed by non-s
tandard suppo
dies was re
eeding up t
company. T
roduction of
e.
oving changidentified fo
sensor wa
ort was avai
xed in the n
the height o
ial feeder. Ad
ntring much
application
hows the use
raulic cylinder
d in the cha
er process o
t the parallel
s, (b) Use of l
andard supp
rt plates for di
ognized as
e exchange
is is currentl
parallel op
eovers, as alr the change
duplicated
lable this had
ew die, whi
f dies was st
ditionally a p
faster since
f hydraulic c
of a typical s
s (b) Tools sha
ngeover proc
erations coul
operations str
(b)
vers
rt plates (Fi
s
ery suitable
of dies. Due
being dealt
ration, wer
ready donever process
or allowing
to be remov
h would rep
ndardized, e
oka-yoke sys
reviously a
ylinders allo
hadow board
(b)
ow board
esses of the
physically a
tegy
ure 5). This
solution for
to this, a pr
with by the e
implement
for the puncof the punch
conversion
d from the di
lace the for
liminating th
tem for centri
icrometre w
ed a faster
to organize th
punch press.
llow it; secon
approach
ubstantial
posal for
gineering
d in the
h-bendingpress. In
f internal
e setup in
er in the
us several
ng the die
as used to
nd easier
e tools.
This was
d because
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 6/9
InjecIn
tooling a
machine
operation
die to be
and inserwas runn
previousl
C
8(b), tool
machine’
and closi
In
like 5S [
Results
A
having i
necessar
impleme
indicatora change
ion mouldinthe injection
nd auxiliary
is running.
s required st
changed. Thu
ting it, whening, i.e., as a
y performed i
ncerning the
ls shadow bo
s control pan
ng the die, pr
general term
6] were appli
nd discussiofter SMED i
to considera
data was g
ted. As pre
s were considover. Table 1
g machinemoulding m
set-up devic
dditionally,
pping the m
s, the first co
needed, inton external op
nside the mo
Figu
streamline o
rds were app
el. These par
ssure and oth
igure 8: (a) Se
s, checklists a
ed in order t
nprovement
tion the initi
athered befo
iously referr
ered, namelyshows the at
chine, like in
s needed to
two internal
chine and re
nversion was
he die to beeration. The
lding machi
e 7: Connector
changeover
lied and a set
ameters inclu
ers.
curity clampin
nd changeov
improve wor
proposals we
al values of
re, as above
ed, in additi
WIP, annualtained impro
6
the other ma
quickly perf
operations
oving the si
attained sim
sed next. Thisecond conv
e and is now
between clam
operations, cl
of pre-establi
ded temperat
(a)
(b)
system for tr
r instruction
kstations’ or
re implemen
the perform
referred, an
n to change
changeover cements on th
chines, all pr
orm the chan
ere converte
ngle availabl
ly by manuf
is assembly crsion involve
executed out
ing cylinder a
lamping syste
ished values
ure, amount
nsport, (b) die
were created
anization.
ted, their im
nce measure
after the S
over times, o
osts and distae changeove
paratory wor
geover, is n
d into extern
connector to
cturing anoth
uld then bed pre-heating
ide.
d die
ms were imp
as defined f
f material in
lamping syste
for all the m
act on perf
s selected an
MED impro
ther three qu
nce travelledtime, for ea
k, for making
ow executed
al ones. On
be inserted i
er connector
one while thof the die,
roved, Figure
or the parame
ected, time
m
achines, and t
rmance was
d above ref
ement propo
antitative pe
by the operath machine, f
ready the
while the
of these
n the next
(Figure 7)
machinehich was
s 8(a) and
ters in the
f opening
echniques
evaluated
rred. The
sals were
rformance
ors duringor each of
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 7/9
7
three stages of evolution of the SMED study. The improvements results are, in general, impressive, i.e., 58,7,
89,7 and 83,7 % improvement respectively for the Punch-Bending, Punch Press and Injection, moulding
machines. Nevertheless, in the case of punch-bending machine the solutions adopted didn’t achieve the single
digit value for changeovers as aimed at by SMED. This simply means that there is still scope for improvement.In the other two machines the objective was accomplished.
Table 1. Improvements on changeover time for the three improvement stages.
Machines
Changeover time (min) Overall
Changeover time
improvement (%)Initial 1st stage 2nd stage 3rd stage
Punch-Bending Machine 188,15 146,02 108,00 77,80 58,7
Punch Press 61,80 54,00 52,33 6,35 89,7
Injection Moulding Machine 58,14 54,48 17,72 9,80 83,1
In addition to the improvements of changeover times, productivity, workstations ergonomic conditions
and work organization were considerably improved too. In particular a clear and systematic procedure was
established for each changeover in each machine, supported by checklists strictly followed by operators.
As expected, the reduction of batch sizes allowed by the decrease of changeover times has led to a
reduction of WIP. Table 2 compares WIP values for metallic and plastic parts, before and after SMED study and
implementation. The comparison reveals very significant WIP reductions, i.e., approximately 55 and 80% forboth time and money, in the areas of metal and plastic components, respectively.
Table 2. Impact of the SMED solutions on WIP: Comparing before with after performance
Production area
Average WIP (days) Average WIP (€)
Before AfterImprove-
ment (%)
Before After Improve-
ment (%)
Metal parts 17,05 7,74 54,6 318,75 144,38 54,7
Plastic parts 5,00 1,09 78,2 439,00 87,80 80,0
Changeover costs were also evaluated. Calculations were based on Equation (1). Results are shown in
Table 3.
Table 3. Measuring costs and savings from SMED implementation
Machines
Average annual changeover cost(€)
Before AfterImprove-
ment (%)
Savings
(€)
Punch-Bending Machine 19.370,9 8.009,9 58,7 11.361,1
Punch Press 5.076,4 521,6 89,7 4.554,8
Injection Moulding Machine 4.840,0 815,8 83,1 4.024,2
Total 19.940,1
The reduction of operators’ movements was one of the important aspects contributing to the changeovers
improvement. This was achieved by external operations concerned with placing near the machines all the
necessary tools, devices, materials, documents and instructions. Table 4 shows the new values for the operators’travelled distance during a changeover occurrence.
Table 4. Comparing operators’ movements before and after SMED implementation
MachinesTravelled distance (m) Savings
(%)Before After
Punch-Bending Machine 370 10 97,3
Punch Press 260 2 99,2
Injection Moulding Machine 300 10 96,7
When compared with the initial distance travelled values these results from the SMED study show
dramatic savings, i.e., 97,3, 99,2 and 96,7%, respectively for the punch-bending machine, punch press and
injection moulding machine.
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 8/9
8
ConclusionsKeeping up with competition in the economic global market of today, characterized by increasing product
customization, requires efficient use of resources and customer service effectiveness. In manufacturing this is
highly dependent on product flexibility. This means the ability to change production from one product to anotherwithout relevant additional costs. This contributes to both, customer service effectiveness, by providing quick
response to demand, and to production efficiency, at several dimensions. However product flexibility should not
be a burden on production capacity. To manage this SMED technology can give a fundamental contribution.This involves a methodology and a number of techniques and changeover strategies and solutions for quick
product changeover.
This paper describes the application of SMED technology in a power controls industrial company of the
north of Portugal in the production areas of metal and plastic components. After a brief literature review, the
paper puts forward important strategies and techniques of SMED, emphasizing the importance of converting
internal into external operations. Additionally two important strategies of high impact on reducing changeover
times, namely quick centring and adjustment of dies at machines, for fast changeovers, and the use of parallel
changeover operations, are briefly described.
The industrial case studied is described in line with most important SMED strategies and novel solutions.
Many proposals were made with visible and impressive impact on changeover processes, in terms of time and
cost savings, reduction of work-in-process levels and distance travelled by operators during the changeover
process. Most of the proposals were implemented and the real impact of solutions assessed and reported. Quick
changeovers allowed reducing batch sizes and increasing product flexibility, due to the increased number of product changeovers without burdening production capacity. A much smoothed production flow and smaller
lead times were obtained.
In terms of changeover time, reductions ranging from 58 to almost 90% were achieved. The WIP of metal
components was reduced from 17.05 to 7.74 days and from 5 to 1.09 days in the case of plastic components. The
distance travelled by operators during changeover processes was dramatically reduced from 370 to 10 m (punch
bending machine), 260 to 2m (punch press) and 300 to 10m (injection moulding machine).
The involvement of operators, as advocated by SMED, proved to be critical in the success of the studyand its implementation. In addition to operators’ participation in the implementation of solutions their
contribution was also important for generating ideas for good solutions.
Although large benefits were obtained from this project, scope for further improvement still exists. In fact
the objective of changeover times below 10 minutes aimed by SMED was not achieved for the punch-bending
machine.
This project has clearly shown the potential of SMED to improve manufacturing efficiency andeffectiveness of industrial companies.
AcknowledgmentsThis work had the financial support of FCT-Fundação para a Ciência e Tecnologia of Portugal under the
project PEst-OE/EME/UI0252/2011. We also acknowledge the institutional support given by GE Power Controls
Portugal and University of Minho.
Bibliography[1] Duguay C. R., Landry S., Pasin F., “From Mass Production to Flexible/Agile Production”. Journal of
Operations and Production Management. 1997; 17, 12, 1183-1195
[2] Department of Trade and Industry (DTI), 1994, “Competitive Manufacturing – A Practical Approach to the
Development of a Manufacturing Strategy”. DTI, London. 1994.
[3] Womack J. P., Jones D. T. and Roos D., “The machine that changes the world”. Rawson Associates, NY.1990.
[4] Womack J. P., Jones D. T., “Lean Thinking: Banish Waste and Create Wealth in Your Corporation”. Free
Press. 1996.
[5] Ohno T., “Toyota Production System: Beyond Large-Scale Production”, Productivity Press. 1988.[6] Monden Y., “Toyota Production System”. 1st edition, Industrial Engineering and Management Press. 1988.
[7] Shingo S., “Revolution in Manufacturing: Single-minute Exchange of Die System”. Productivity Press.1985.
[8] J. Carlos Sá, J. Dinis-Carvalho and Rui M. Sousa (2011) “Waste Identification Diagrams”, in 6º Congresso
Luso-Moçambicano de Engenharia (CLME'2011), Maputo, Mozambique. 2011.
[9] Rother M., Shook J., “Learning to See: Value Stream Mapping to Add Value and Eliminate Muda”. The
Lean Enterprise Institute. 1999.
[10] Karlsoon C., Ahlstrom P., “Assessing Changes toward Lean Production”. Journal of Operations and
Production Management. 1996: 16, 2, 24-41.[11] Sekine K, Arai K., “Kaizen for Quick Changeover: Going Beyond SMED”. Productivity Press, 1992.
8/2/2019 Dr-fb-rs-cs Rrpmom 40 (2011) Pre-print
http://slidepdf.com/reader/full/dr-fb-rs-cs-rrpmom-40-2011-pre-print 9/9
9
[12] Prasad B., “A structured methodology to implement judiciously the right JIT tactics”. Production Planning
& Control. 1995; 6, 6, 564-577.
[13] Venjara Y., “Setup Savings”. Manufacturing Engineering. 1996; 117, Jul., 96-102.
[14] Van Goubergen D., “Set-up Reduction as an Organization-wide Problem”. Proceedings of the IIE Solutions.2000.
[15] Spence A. M., Porteus E. L., “Setup Reduction and Increased Effective Capacity”. Management Science.
1987: Vol 33, 1291-1301.[16] Fernihough A, Culley S.J., Mileham A.R., “A Financial Model for Setup Reduction Justification”.
Proceedings of the Fourth International FAIM Conference, Blacksburg, 1994.
[17] Yang J., Deane R., “Setup Time Reduction and Competitive Advantage in a Closed Manufacturing Cell”.
European Journal of Operation Research. 1993; 69, 3, 413-423.
[18] Hay E.J., “Any Machine Setup Time Can be Reduced by 75%”. Industrial Engineering, Volume 19, 1987.[19] Shingo S., “Quick Changeover for Operators: The SMED System”. Shopfloor Series, Productivity Press,
1996.
[20] Sousa R. M., Lima R. M., Carvalho D. and Alves A., “An Industrial Application of Resource Constrained
Scheduling for Quick Changeover”. In 2009 IEEE International Conference on Industrial Engineering and
Engineering Management, H. Sun, R. Jiao & M. Xie (Editors), 189-193, Hong Kong, China. 2009.
[21] Termini M. J., “The New Manufacturing Engineer”. Society of Manufacturing Engineers. 1996.
[22] Kays B., Kara S., “Set-Up Reduction in Injection Molding Process – A Case Study in Packaging Industry”.
4th International Conference and Exhibition on Design and Production of Machines and Dies/Molds. 2007.[23] Brian M. T., “Application of Shingo's Single Minute Exchange of Dies (SMED) Methodology to Reduce
Punch Press Changeover Times at Krueger International”. University of Wisconsin-Stout. 2007.
[24] X. A., Vonderembse M. A., “The Impact of organizational Structure on the Level of JIT Attainment:
Toward Theory Development”. International Journal of Production Research. 1998; 36, 10, 2873-2878
[25] Productivity Press, “Improving Flow: Collected Practices and Cases – Insights on Implementation”.
Productivity Press, 1st edition. 2006.
[26] Tapping, D., “The Lean Office Pocket Guide XL”, MCS Media, Inc.. 2005.