draft environmental impact assessment and emp … · 2019-03-11 · draft environmental impact...
TRANSCRIPT
DRAFT ENVIRONMENTAL IMPACT
ASSESSMENT AND EMP REPORT
FOR
PROPOSED GREEN FIELD PROJECT OF COMMON INTEGRATED
LANDFILL (7,82,181 MT) AND INCINERATION FACILITY (1 MT/HR)
AT
SURVEY NO. 2483, 2500, 2501, 2503, 2482, 2484, 2499, 2502, 2504, 2486, 2485, 2487,
2488, 2498, 2497, 2505, 2506, 2490, 2491, 2496, 2509, 2510, 2523, 2528/1, 2528/2, 2524,
VILL. – CHANASMA, TAL. – CHANASMA, DIST. PATAN, GUJARAT
PROJECT CATEGORY: A, 7(d), COMMON HAZARDOUS WASTE
TREATMENT, STORAGE & DISPOSAL FACILITIES (TSDFs)
STUDY PERIOD:
OCTOBER, 2018 TO DECEMBER, 2018
PROJECT PROPONENT:
NORTH GUJARAT ENVIRO PROJECTS
PREPARED BY:
en-VISIOn ENVIRO TECHNOLOGIES PVT. LTD.
2nd
FLOOR, SHRI RAM COMPLEX, ABIVE BANK OF INDIA,
NEAR KARGIL CHOWK, SURAT-DUMAS ROAD,
PIPLOD, SURAT-395007
GUJARAT.
Phone No.: (0261) 2223003, 2224004
Email Add.: [email protected]
Website: www.en-vision.in
Accreditation by
QCI / NABET Certificate No. NABET /EIA/1821/RA 0102
February 2019
190209_RP06_0
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT Q-1
Declaration by Experts contributing to the EIA/EMP Report
For Proposed Green Field Project of Common Integrated Landfill (7,82,181 MT) and Incineration Facility
(1 MT/hr) at Survey No. 2483, 2500, 2501, 2503, 2482, 2484, 2499, 2502, 2504, 2486, 2485, 2487, 2488,
2498, 2497, 2505, 2506, 2490, 2491, 2496, 2509, 2510, 2523, 2528/1, 2528/2, 2524, Vill.– Chanasma, Tal.
– Chanasma, Dist. Patan, Gujarat.
Project Category: 7(d) “A”
I, hereby, certify that I was a part of the EIA team in the following capacity that developed the above EIA.
EIA Coordinator
Name : Nihar Doctor
Signature and Date :
Name of Associate EIA
coordinator
: Jignesh Patel
:
Period of involvement : June – 2018 to February – 2019
Contact information : ENVISION ENVIRO TECHNOLOGIES PVT. LTD.
3rd
Floor, Shree Ram Complex, Above Bank of India,
Near Kargil Chowk, Surat-Dumas Road,
Piplod, Surat-395007, Gujarat.
Phone No.: (0261) 2223003, 2224004
E-mail: [email protected]
Website: www.en-vision.in
Functional Area Experts
Sr.
No.
Functional
Areas
Name of the
Expert/S
Involvement
(Period Task) Signature
1 AP Nihar Doctor
Period: June – 2018 to February – 2019
Site visit; technical guidance to associate EIA coordinator
and team member, verify FAE report, Review and
comment on EIA report.
2
WP
Nihar Doctor
Period: June – 2018 to February – 2019
Site visit; technical guidance to associate EIA coordinator
and team member, verify FAE report, Review and
comment on EIA report.
3 SHW Nihar Doctor
Period: June – 2018 to February – 2019
Site visit; technical guidance to associate EIA coordinator
and team member, verify FAE report, Review and
comment on EIA report.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT Q-2
Sr.
No.
Functional
Areas
Name of the
Expert/S
Involvement
(Period Task) Signature
4 SE Arif Shaikh
Period: June – 2018 to February – 2019
Site visit; socioeconomic data collection; identification of
impact and suggesting mitigative measures of project on
community, Impact aspect evaluation, preparation of
CER plan; finalization of FAE report.
5 EB Manoj Eledath
Period: October to December – 2018
Site visit; EB data collection; Identification of Impacts and
suggested mitigation measures; finalization of FAE report.
6 HG Ravikant
Sharma
Period: October to December – 2018
Collection of Secondary data and its verification during site
visit and based on ground water analysis reports; Geology
& Geomorphological analysis based on Secondary data;
Preparation of FAE report
7 GEO Ravikant
Sharma
8 SC Dr. B. K. Patel Not utilized as per Scheme
9 AQ Nihar Doctor
Period: January – 2019
Based on project specific emission technical guidance to
associate EIA coordinator and team member to run the
model. Verify FAE report, Review and comment on EIA
report.
10 N Ananta Desai
Period: June – 2018 to February – 2019
Site visit; Identifying possible source of noise pollution at
various stages of development & operation. Impact
identification and suggesting mitigation measures;
finalization of FAE report.
11 LU Dr. Y.
Ramamohan
Period: October to December – 2018
Site visit; Collection of secondary data; preparation of land
use/land cover map from the satellite image based on site
visit. Identification of impacts and suggesting mitigation
measures.
12 RH Jignesh Patel
Period: June – 2018 to February – 2019
Site visit; Collection of technical data; Identified potential
risk due to proposed activities at various stage of
development. Suggesting safety measures. Finalization of
FAE report.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT Q-3
Declaration by the Head of the accredited consultant organization/ Authorized Person
I, Nihar Doctor, hereby, confirm that the above mentioned experts prepared the EIA of proposed Common
Hazardous Waste Treatment, Storage & Disposal Facilities (TSDFs) unit by “North Gujarat Enviro
Projects (NGEP)”. “It is certified that no unethical practice like ‘copy and paste’, and used external data /
text without proper acknowledgement, while preparing this EIA report”. I also confirm that the consultant
organization shall be fully accountable for any mis-leading information mentioned in this statement.
Signature :
Name : Nihar Doctor
Designation : Director
Name of the EIA consultant
organization
: Envision Enviro Technologies Pvt. Ltd.
NABET Certificate No. & Issue
Date
: NABET/EIA/1821/RA 0102 valid up to December 06, 2020
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT Q-4
UNDERTAKING
I, Patel Dharnendrabhai Natwarlal, Partner of North Gujarat Enviro Projects (NGEP) willing to submit this
undertaking with respect to the Terms of References (TOR) prescribed by MOEF/CC, India, vide ToR letter no. 10-
39/2018-IA-III dated 29/08/2018 for the proposed project located at Survey No. 2483, 2500, 2501, 2503, 2482, 2484,
2499, 2502, 2504, 2486, 2485, 2487, 2488, 2498, 2497, 2505, 2506, 2490, 2491, 2496, 2509, 2510, 2523, 2528/1,
2528/2, 2524, Vill. – Chanasma, Tal. – Chanasma, Dist. Patan, Gujarat. Further, we have not received any additional
TOR for this project except this.
North Gujarat Enviro Projects (NGEP) is also undertake that information and data contained in this EIA
report are factual and correct and any content of this report pertaining to this project is not copied from any
other report and we own entire responsibility for the same.
Date: 04/02/2019 For, North Gujarat Enviro Projects (NGEP).
Place: Chanasma
Patel Dharnendrabhai Natwarlal Partner
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT I-1
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION ..................................................................................................................... 1-1
1.1 Purpose of EIA ....................................................................................................................... 1-1
1.2 Project Proponent ................................................................................................................... 1-1
1.2.1 Promoter’s Background ..................................................................................................... 1-2
1.3 Identification of Project ......................................................................................................... 1-2
1.3.1 Nature, Size and Location .................................................................................................. 1-2
1.3.2 Importance of Project to Region ........................................................................................ 1-2
1.4 Regulatory Frame Work ........................................................................................................ 1-3
1.4.1 Applicable CPCB’s Guideline ........................................................................................... 1-4
1.4.2 Applicability of EIA Notification ...................................................................................... 1-4
1.5 Scope and methodology of EIA Study ................................................................................... 1-4
1.5.1 Baseline Study ................................................................................................................... 1-4
1.5.2 Identification of Impact and Mitigation ............................................................................. 1-6
1.5.3 Environmental Management Plan ...................................................................................... 1-6
1.5.4 Additional Studies .............................................................................................................. 1-6
1.5.5 Structure of EIA Report ..................................................................................................... 1-6
CHAPTER 2 PROJECT DESCRIPTION ......................................................................................................... 2-7
2.1 introduction ............................................................................................................................ 2-7
2.1.1 Waste Generation and Management in Gujarat ................................................................. 2-7
2.1.2 TSDF/Incineration Facility in Gujarat ............................................................................... 2-7
2.2 proposed project ..................................................................................................................... 2-8
2.2.1 Need of project ................................................................................................................... 2-8
2.2.2 Justification of Project site ................................................................................................. 2-9
2.2.3 Project location ................................................................................................................ 2-10
2.2.4 Project Site History .......................................................................................................... 2-15
2.2.5 Salient Feature ................................................................................................................. 2-17
2.3 project size ........................................................................................................................... 2-17
2.3.1 Justification for capacity .................................................................................................. 2-18
2.4 project component ................................................................................................................ 2-18
2.5 Land fill................................................................................................................................ 2-18
2.5.1 Component of Landfill ..................................................................................................... 2-18
2.6 Incineration .......................................................................................................................... 2-20
2.7 handling of hazardous waste ................................................................................................ 2-22
2.7.1 Hazardous waste acceptance criteria ................................................................................ 2-22
2.7.2 Pre-treatment of hazardous waste .................................................................................... 2-23
2.7.3 General Pathway of the waste .......................................................................................... 2-24
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT I-2
2.8 hazardous waste transportation ............................................................................................ 2-26
2.8.1 Packing ............................................................................................................................. 2-26
2.8.2 Labelling .......................................................................................................................... 2-26
2.8.3 Manifest System............................................................................................................... 2-27
2.9 project phase ........................................................................................................................ 2-27
2.9.1 Pre-construction Activity ................................................................................................. 2-27
2.9.2 Construction Activity ....................................................................................................... 2-27
2.9.3 Technical detail of landfill cell ........................................................................................ 2-28
2.9.4 Operation Phase ............................................................................................................... 2-31
2.9.5 Closure of landfill cell ..................................................................................................... 2-31
2.10 general guideline for daily activity ...................................................................................... 2-31
2.11 resorce requirement .............................................................................................................. 2-32
2.11.1 Capital investment ........................................................................................................... 2-32
2.11.2 Land ................................................................................................................................. 2-32
2.11.3 Water ................................................................................................................................ 2-33
2.11.4 Electricity/Power .............................................................................................................. 2-35
2.11.5 Machineries ...................................................................................................................... 2-35
2.11.6 Fuel .................................................................................................................................. 2-35
2.11.7 Manpower ........................................................................................................................ 2-35
2.11.8 Chemical .......................................................................................................................... 2-35
2.11.9 Laboratory ........................................................................................................................ 2-35
2.12 pollution load and mitigation measures ............................................................................... 2-36
2.12.1 Wastewater ....................................................................................................................... 2-36
2.12.2 Leachate Management ..................................................................................................... 2-39
2.12.3 Observatory Well Groundwater Monitoring stations ....................................................... 2-41
2.12.4 Air emission ..................................................................................................................... 2-41
2.12.5 Waste generation .............................................................................................................. 2-42
2.13 ecology and bio divercity ..................................................................................................... 2-43
2.13.1 Green belt ......................................................................................................................... 2-43
2.14 noise pollution ...................................................................................................................... 2-43
2.15 project implementation ........................................................................................................ 2-43
2.15.1 Organization Structure ..................................................................................................... 2-45
CHAPTER 3 DESCRIPTION OF ENVIRONTMENT ...................................................................................... 3-1
3.1 Introduction ............................................................................................................................ 3-1
3.1.1 Objectives of Baseline Monitoring .................................................................................... 3-1
3.1.2 Data Collection Methodology ............................................................................................ 3-1
3.1.3 Study Area ......................................................................................................................... 3-2
3.2 Meteorological Environment ................................................................................................. 3-2
3.2.1 Climate of Study Area ....................................................................................................... 3-2
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT I-3
3.3 Air Environment .................................................................................................................... 3-6
3.3.1 Sampling Methodology and Analysis ................................................................................ 3-6
3.3.2 Selection of Monitoring Locations .................................................................................... 3-6
3.3.3 Results and Discussion ...................................................................................................... 3-8
3.4 Water Environment .............................................................................................................. 3-11
3.4.1 Sampling Methodology and Analysis .............................................................................. 3-11
3.4.2 Selection of Monitoring Location .................................................................................... 3-12
3.4.3 Results-Ground Water and Surface Water ....................................................................... 3-15
3.5 Noise Environment .............................................................................................................. 3-21
3.5.1 Selection of Monitoring Locations and Results ............................................................... 3-22
3.5.2 Discussion of Noise Levels .............................................................................................. 3-25
3.5.3 Traffic Study .................................................................................................................... 3-25
3.6 Soil Environment ................................................................................................................. 3-27
3.6.1 Sampling Methodology and Analysis .............................................................................. 3-27
3.6.2 Discussion and interpretation ........................................................................................... 3-31
3.7 Discussion-Soil Environment .............................................................................................. 3-31
3.8 Land Environment ............................................................................................................... 3-32
3.8.1 Methodology of Study ..................................................................................................... 3-32
3.8.2 Data Used ......................................................................................................................... 3-33
3.8.3 Land Use / Land Cover Map ............................................................................................ 3-33
3.9 Hydrology and ground water ............................................................................................... 3-36
3.9.1 Geomorphology, Drainage & Watershed: ....................................................................... 3-37
3.9.2 Geotechnical Studies: ....................................................................................................... 3-38
3.9.3 Hydrogeology .................................................................................................................. 3-40
3.10 Ecology and Bio-diversity ................................................................................................... 3-42
3.10.1 Biodiversity of Terrestrial Environment .......................................................................... 3-42
3.10.2 Biological Diversity ......................................................................................................... 3-42
3.10.3 Ecological Impact Assessment......................................................................................... 3-43
3.10.4 Period of the study and Study area................................................................................... 3-43
3.10.5 Methodology .................................................................................................................... 3-43
3.10.6 Presence –Absence ........................................................................................................... 3-44
3.10.7 DAFOR Scale .................................................................................................................. 3-45
3.10.8 Biodiversity of Terrestrial Environment .......................................................................... 3-45
3.10.9 Floral Diversity of the Study Area ................................................................................... 3-53
3.10.10 Faunal Diversity of Study Area ....................................................................................... 3-61
3.10.11 Sampling Methodology Adopted: .................................................................................... 3-71
3.10.12 Samples Processing For Chlorophyll Estimation: ........................................................... 3-71
3.11 Socio-economic Environment .............................................................................................. 3-75
3.11.1 Major Objectives of the Study ......................................................................................... 3-75
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT I-4
3.11.2 Identification of Stakeholders’ ......................................................................................... 3-75
3.11.3 Methodology .................................................................................................................... 3-75
3.11.4 Limitations ....................................................................................................................... 3-77
3.11.5 The Project Influence Area .............................................................................................. 3-77
3.11.6 Findings of Community Consultations ............................................................................ 3-81
3.11.7 Population Density ........................................................................................................... 3-82
3.11.8 Sex Ratio .......................................................................................................................... 3-82
3.11.9 Population Distribution (Rural & Urban) ........................................................................ 3-82
3.11.10 Quality of life ................................................................................................................... 3-85
3.11.11 People’s Perception .......................................................................................................... 3-85
3.11.12 Conclusions Socio-Economic Survey .............................................................................. 3-88
CHAPTER 4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ............... 4-1
4.1 Introduction ............................................................................................................................ 4-1
4.1.1 Objective ............................................................................................................................ 4-1
4.1.2 Environmental Aspect and Impacts ................................................................................... 4-1
4.1.3 Environmental Indices ....................................................................................................... 4-1
4.1.4 Environmental Impact Assessment .................................................................................... 4-1
4.2 Impact Identification .............................................................................................................. 4-2
4.2.1 Identification Matrix .......................................................................................................... 4-2
4.3 Impact Quantification ............................................................................................................ 4-5
4.3.1 Scoring the Overall Impact ................................................................................................ 4-5
4.3.2 Probability of Occurrence of the Impact ............................................................................ 4-6
4.3.3 Impact Signification Criteria .............................................................................................. 4-7
4.4 Significance of Impacts & Proposed Mitigation Measures ................................................... 4-8
4.4.1 Land Environment ............................................................................................................. 4-8
4.4.2 Soil Environment ............................................................................................................... 4-9
4.4.3 Water Environment .......................................................................................................... 4-11
4.4.4 Hydro Geological Environment ....................................................................................... 4-12
4.4.5 Noise Environment .......................................................................................................... 4-14
4.4.6 Ecological Environment ................................................................................................... 4-16
4.4.7 Socio Economic Environment ......................................................................................... 4-18
4.4.8 Risk & Hazard.................................................................................................................. 4-20
4.4.9 Occupational Health & Safety ......................................................................................... 4-20
4.4.10 Solid & Hazardous Waste Management .......................................................................... 4-22
4.4.11 Air Environment .............................................................................................................. 4-23
4.5 Cumulative Impact ............................................................................................................... 4-25
4.5.1 Conclusion ....................................................................................................................... 4-26
4.6 Air Quality Modelling ......................................................................................................... 4-26
4.6.1 AERMOD ........................................................................................................................ 4-26
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT I-5
4.6.2 Methodology .................................................................................................................... 4-27
4.6.3 Mixing Height .................................................................................................................. 4-27
4.6.4 Maximum Ground Level Concentration .......................................................................... 4-27
4.7 Air Quality index ................................................................................................................. 4-36
CHAPTER 5 ANALYSIS OF ALTERNATIVES (TECHNOLOGY AND SITE) ................................................. 5-1
5.1 Introduction ............................................................................................................................ 5-1
5.2 Analysis for Site Alternative .................................................................................................. 5-1
5.2.1 Site Evaluation Criteria ...................................................................................................... 5-5
5.2.2 Siting Criteria ..................................................................................................................... 5-6
5.3 Analysis for Technology Alternative ..................................................................................... 5-7
CHAPTER 6 ENVIRONMENTAL MONITORING PROGRAM ....................................................................... 6-1
6.1 Introduction ............................................................................................................................ 6-1
6.2 Environmental Monitoring Program ...................................................................................... 6-1
6.2.1 Env. Monitoring Budget .................................................................................................... 6-3
6.2.2 Records .............................................................................................................................. 6-4
6.2.3 Laboratory Facility ............................................................................................................. 6-4
CHAPTER 7 ADDITIONAL STUDIES .................................................................................................... 7-1
7.1 PUBLIC Consultation ............................................................................................................ 7-1
7.2 Social Impact Assessment and R & R Action Plan ............................................................... 7-1
7.3 RISK ASSESSMENT STUDIES .......................................................................................... 7-1
7.3.1 Background ........................................................................................................................ 7-1
7.3.2 Risk Assessment: An Overview ......................................................................................... 7-1
7.3.3 Objective of the Study ....................................................................................................... 7-2
7.3.4 Project Description ............................................................................................................. 7-2
7.3.5 Identification of Hazards .................................................................................................... 7-3
7.3.6 Storage, Handling and Transportation of Hazardous Materials ......................................... 7-3
7.3.7 Major Hazards and Damage Criteria ................................................................................. 7-6
7.3.8 Hazard Indices ................................................................................................................... 7-7
7.3.9 Software Used For Calculations ...................................................................................... 7-10
7.3.10 Natural Hazards and Its Control Measures ...................................................................... 7-12
7.3.11 Risk Mitigation Measures ................................................................................................ 7-13
7.3.12 Disaster Management Plan .............................................................................................. 7-14
7.3.13 Occupational Health and Safety Program for the Project ................................................ 7-22
CHAPTER 8 PROJECT BENEFITS ............................................................................................................... 8-1
8.1 General ................................................................................................................................... 8-1
8.2 Environmental Benefits ......................................................................................................... 8-1
8.3 Physical Benefits .................................................................................................................... 8-1
8.4 Social Benefits ....................................................................................................................... 8-1
8.5 Corporate environment responsibility .................................................................................... 8-2
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT I-6
8.6 Other Tangible Benefits ......................................................................................................... 8-1
CHAPTER 9 ENVIRONMENTAL COST BENEFIT ANALYSIS ........................................................ 9-1
9.1 Investment in project ............................................................................................................. 9-1
9.2 Cost benefit analysis .............................................................................................................. 9-1
9.2.1 Financial Pattern ................................................................................................................ 9-1
9.2.2 Environmental Cost Analysis............................................................................................. 9-1
CHAPTER 10 ENVIRONMENTAL MANAGEMENT PLAN .............................................................. 10-1
10.1 Introduction .......................................................................................................................... 10-1
10.1.1 Objectives of EMP ........................................................................................................... 10-1
10.1.2 Components of EMP ........................................................................................................ 10-1
10.2 Environment Management Plan ........................................................................................... 10-2
10.2.1 Land Environment ........................................................................................................... 10-2
10.2.2 Soil Environment ............................................................................................................. 10-4
10.2.3 Water Environment .......................................................................................................... 10-6
10.2.4 Hydro Geological Environment ....................................................................................... 10-7
10.2.5 Ecological Environment ................................................................................................... 10-9
10.2.6 Socio Economic Environment ....................................................................................... 10-15
10.2.7 Risk & Hazard and Occupational Health & Safety ........................................................ 10-16
10.2.8 Solid and Hazardous Waste Management ..................................................................... 10-17
10.2.9 Air Environment ............................................................................................................ 10-18
10.3 Environmental Management Cell (EMC) .......................................................................... 10-19
10.3.1 Environment Policy and its Standard Operating Procedure ........................................... 10-20
10.3.2 Reporting System ........................................................................................................... 10-20
10.3.3 Reporting System ........................................................................................................... 10-20
10.4 Budget for Environment Protection ................................................................................... 10-20
CHAPTER 11 SUMMERY AND CONCLUSION ................................................................................... 11-1
11.1 Project description ............................................................................................................... 11-1
11.2 Project Requirement ............................................................................................................ 11-1
11.2.1 Pollution Potential ............................................................................................................ 11-1
11.3 baseline environment ........................................................................................................... 11-2
11.3.1 Existing Environment Quality ......................................................................................... 11-2
11.4 alternative site study ............................................................................................................ 11-3
11.5 Identification of impact and mitigation measures ................................................................ 11-3
11.6 Monitoring plan and additional study .................................................................................. 11-4
11.7 Environmental Management plan ........................................................................................ 11-4
CHAPTER 12 DISCLOSURE OF CONSULTANTS ENGAGED ....................................................................... 12-1
12.1 EIA team .............................................................................................................................. 12-3
12.2 Laboratory Involved ............................................................................................................ 12-4
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT F-1
LIST OF TABLES
Table 1-1: Scope of Baseline Study ................................................................................................................. 1-5
Table 2-1: Total Hazardous Waste Generation in Gujarat ............................................................................... 2-7
Table 2-2: Common Hazardous Waste TSDF [Treatment Stabilization Disposal and Facilities] ................... 2-7
Table 2-3: HWIF [Common Hazardous Wastes Incineration Facility] in Gujarat .......................................... 2-8
Table 2-4: Key Feature around the Project Site ............................................................................................. 2-17
Table 2-5: Hazardous waste acceptance criteria ............................................................................................ 2-22
Table 2-6: Manifest System ........................................................................................................................... 2-27
Table 2-7: Technical Design of Landfill ........................................................................................................ 2-28
Table 2-8: Liner Design ................................................................................................................................. 2-29
Table 2-9: Project cost ................................................................................................................................... 2-32
Table 2-10: Financial Model .......................................................................................................................... 2-32
Table 2-11: Area Breakup .............................................................................................................................. 2-33
Table 2-12: Land Acquisition ........................................................................................................................ 2-33
Table 2-13: Water Consumption ................................................................................................................ 2-34
Table 2-14: Fuel Source ................................................................................................................................. 2-35
Table 2-15: Laboratory Equipment required for Environmental Monitoring ................................................ 2-36
Table 2-16: Wastewater Generation .............................................................................................................. 2-36
Table 2-17: Effluent Characteristic ................................................................................................................ 2-37
Table 2-18: Technical detail of ETP .............................................................................................................. 2-37
Table 2-19: Stage-wise effluent characteristic ............................................................................................... 2-38
Table 2-20: Details of Flue gas emission ....................................................................................................... 2-41
Table 2-21: List of Hazardous waste ............................................................................................................. 2-42
Table 2-22: Project Implementation Schedule ............................................................................................... 2-44
Table 3-1: Summary of Site Specific Meteorological Data ............................................................................. 3-4
Table 3-2: Air – Parameters analyzed and sampling duration ......................................................................... 3-6
Table 3-3: Ambient Air Quality - Methodology .............................................................................................. 3-6
Table 3-4: Ambient Air Monitoring Locations ................................................................................................ 3-7
Table 3-5: Ambient Air Quality Status ............................................................................................................ 3-9
Table 3-6: Ambient Air result Summery Table ............................................................................................. 3-11
Table 3-7: Sample Collection and Analysis of Water Sample ....................................................................... 3-12
Table 3-8: Monitoring Locations for Ground Water and Surface Water ....................................................... 3-12
Table 3-9: Water Quality – Physico-chemical Analysis of Ground Water .................................................... 3-15
Table 3-10: Water Quality – Physico-chemical Analysis of Surface Water .................................................. 3-17
Table 3-11: Summary for ground water ......................................................................................................... 3-19
Table 3-12: Summery table for surface water ................................................................................................ 3-20
Table 3-13: Noise Monitoring Methodology ................................................................................................. 3-21
Table 3-14: Ambient Noise Quality Standards for Different Areas/Zones .................................................... 3-22
Table 3-15: Noise Monitoring Locations ....................................................................................................... 3-23
Table 3-16: Noise Levels ............................................................................................................................... 3-24
Table 3-17: Noise level due to transportation ................................................................................................ 3-24
Table 3-18: Summery table for Noise study .................................................................................................. 3-25
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT F-2
Table 3-19: Traffic Counts (up and down) .................................................................................................... 3-26
Table 3-20: Existing Traffic Scenario ............................................................................................................ 3-26
Table 3-21: Level of Service .......................................................................................................................... 3-27
Table 3-22: Methodology of Testing of Soil Samples ................................................................................... 3-28
Table 3-23: Soil Sampling Location .............................................................................................................. 3-28
Table 3-24: Physicochemical Characteristics of the Soil ............................................................................... 3-30
Table 3-25: Details of Sources & the Maps Prepared .................................................................................... 3-33
Table 3-26: Land Use / Land Cover Statistics of the Study Area (10 km Radius) ........................................ 3-33
Table 3-27: Trees in the Study area ............................................................................................................... 3-54
Table 3-28: List of the Shrubs in the Study Area .......................................................................................... 3-56
Table 3-29: List of Herbaceous Species Observed in the Study Area ........................................................... 3-57
Table 3-30: List of Climbers observed in the Study Area ............................................................................. 3-60
Table 3-31: Birds of the Study Area .............................................................................................................. 3-61
Table 3-32: Migratory Birds of the Study Area ............................................................................................. 3-66
Table 3-33: Butterflies in the Study Area ...................................................................................................... 3-66
Table 3-34: Reptiles observed in the study area ............................................................................................ 3-67
Table 3-35: Mammals in the Study Area ....................................................................................................... 3-67
Table 3-36: Threatened Fauna Of The Study Area ........................................................................................ 3-68
Table 3-37: Species provided Protection as per Wild Life Protection Act 1972 ........................................... 3-69
Table 3-38: Sampling stations within 2km radius from the project site ........................................................ 3-70
Table 3-39: List of Phytoplankton in study area ............................................................................................ 3-73
Table 3-40: Evaluation of phyto plankton population ................................................................................... 3-73
Table 3-41: List of zooplankton in study area ............................................................................................... 3-74
Table 3-42: Evaluation of zooplankton population ........................................................................................ 3-74
Table 3-43: list of villages where Socio-economic study conducted ............................................................. 3-76
Table 3-44: List of Villages in PIA (Census 2011)........................................................................................ 3-78
Table 4-1: Environmental Impacts ................................................................................................................... 4-3
Table 4-2: Overall Impact Scoring System ...................................................................................................... 4-5
Table 4-3: Impact scoring for Ecology and Biodiversity ................................................................................. 4-5
Table 4-4: Occurrence Frequency Assessment- Ecological ............................................................................. 4-6
Table 4-5: Occurrence Frequency Assessment-Others .................................................................................... 4-6
Table 4-6: Impact Significance Criteria ........................................................................................................... 4-7
Table 4-7: Environmental Risk Categorization ............................................................................................... 4-7
Table 4-8: Ecological Risk Categorization ...................................................................................................... 4-7
Table 4-9: Assessment of Proposed Traffic Load .......................................................................................... 4-15
Table 4-10: Traffic Scenario .......................................................................................................................... 4-15
Table 4-11: Weighted Environmental Impacts without Mitigation Measures ............................................... 4-25
Table 4-12: Weighted Environmental Impacts without Mitigation Measures ............................................... 4-25
Table 4-13: Details of Stacks ......................................................................................................................... 4-26
Table 4-14: Maximum Ground Level Concentration (Average 24 hourly) ................................................... 4-27
Table 4-15: Predicted 24 hourly Short Term Incremental Concentrations from Proposed Source................ 4-35
Table 4-16: Air quality index ......................................................................................................................... 4-36
Table 5-1: Summery of Alternative Sites ........................................................................................................ 5-1
Table 5-2: Knock-out criteria for TSDF site .................................................................................................... 5-2
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT F-3
Table 5-3: Site Evaluation for Finalize the Project Location ........................................................................... 5-5
Table 5-4: Siting Criteria for Chansma Project Site ........................................................................................ 5-6
Table 6-1: Environmental Monitoring Programme.......................................................................................... 6-1
Table 6-2: Frequency of monitoring at Incinerator .......................................................................................... 6-2
Table 6-3: Environmental Monitoring Plan ..................................................................................................... 6-3
Table 7-1: Storage Details of Hazardous Materials ......................................................................................... 7-3
Table 7-2: Hazards of Other Types and Its Control ......................................................................................... 7-6
Table 7-3: Damages to Human Life Due to Heat Radiation ............................................................................ 7-8
Table 7-4: Effects Due to Incident Radiation Intensity ................................................................................... 7-8
Table 7-5: Possible Accident Scenario ............................................................................................................ 7-9
Table 7-6: Summary of Consequence Analysis - Fire end points .................................................................. 7-11
Table 7-7: Natural Hazard Occurrence in the District & its Impacts ............................................................. 7-13
Table 7-8: Proposed Fire Fighting Equipments ............................................................................................. 7-14
Table 7-9: General Emergency Response Plan .............................................................................................. 7-21
Table 7-10: Occupational Health Monitoring ................................................................................................ 7-23
Table 7-11: List Of Personnel Protective Equipment .................................................................................... 7-23
Table 8-1: Corporate Environment Responsibility (CER) Plan for Five Years ............................................... 8-1
Table 10-1: Recommended Plant Species for Greenbelt ............................................................................. 10-12
Table 10-2: Greenbelt Development Plan .................................................................................................... 10-14
Table 10-3: Roles and Responsibility of in Existing EMC Cell .................................................................. 10-19
Table 10-4: Capital cost for EMS ................................................................................................................ 10-20
Table 10-5: Recurring cost for EMS ............................................................................................................ 10-21
Table 12-1 EIA Team .................................................................................................................................... 12-3
Table 12-2 Details of Laboratory ................................................................................................................... 12-4
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT F-4
LIST OF FIGURES
Figure 2-1: Composition of Hazardous Waste Generated in Gujarat .............................................................. 2-9
Figure 2-2: Location Map .............................................................................................................................. 2-10
Figure 2-3: Google image showing the project site ....................................................................................... 2-11
Figure 2-4: Plant Layout ................................................................................................................................ 2-13
Figure 2-5: Topography Map Showing 10 km Radius Study area of Project Sit ........................................... 2-14
Figure 2-6: Earthquake hazard zone map of India ......................................................................................... 2-15
Figure 2-7: Detail of Landfill Cell ................................................................................................................. 2-20
Figure 2-8: Flow diagram of incinerator ........................................................................................................ 2-21
Figure 2-9: General Pathway of the waste ..................................................................................................... 2-25
Figure 2-10: Bottom liner .............................................................................................................................. 2-30
Figure 2-11: Final cover ................................................................................................................................. 2-30
Figure 2-12: Water Balance Diagram ............................................................................................................ 2-34
Figure 2-13: ETP Flow Diagram ................................................................................................................... 2-38
Figure 2-14: Organizational Structure ........................................................................................................... 2-45
Figure 3-1: Annual Wind Rose of Daily Surface Data (8:30 a.m.) at Ahemedabad Station (1971-2000)....... 3-3
Figure 3-2: Annual Wind Rose of Daily Surface Data (5:30 p.m.) at Ahemedabad Station (1971-2000) ...... 3-4
Figure 3-3: Primary Wind rose Diagram (October-December 2018) .............................................................. 3-5
Figure 3-4: Google Image Showing Ambient Air Quality Locations .............................................................. 3-7
Figure 3-5: Google Image Showing Ground Water Sampling Locations ...................................................... 3-13
Figure 3-6: Google Image Showing Surface Water Sampling Locations ...................................................... 3-13
Figure 3-7: Google Image Showing Noise Sampling Locations ................................................................... 3-23
Figure 3-8: Google Image Showing Location of Traffic Survey ................................................................... 3-25
Figure 3-9: Google Image Showing Soil Sampling Locations ...................................................................... 3-29
Figure 3-10: Land use/Land Cover Map of 10 km Radius Study Area ......................................................... 3-34
Figure 3-11: Satellite Imaginary of 10 km Radius Study Area ...................................................................... 3-35
Figure 3-12: Hydrogeology study within Study area ..................................................................................... 3-36
Figure 3-13: Soil at Project Site ..................................................................................................................... 3-39
Figure 3-14: Drainage Map of study area ...................................................................................................... 3-41
Figure 3-15: Ecology at and near project site ................................................................................................ 3-46
Figure 3-16: Water bodies in study area ........................................................................................................ 3-47
Figure 3-17: Biodiversity of Study Area ........................................................................................................ 3-53
Figure 3-18: Sampling at Khari river near Vadavli ...................................................................................... 3-71
Figure 3-19: Villages in Study Area .............................................................................................................. 3-76
Figure 4-1: Spatial Distribution of 24-Hour Average PM10 Concentration (µg/m3) ...................................... 4-28
Figure 4-2: Spatial Distribution of 24-Hour Average SO2 Concentration (µg/m3) ........................................ 4-29
Figure 4-3: Spatial Distribution of 24-Hour Average NOx Concentration (µg/m3) ....................................... 4-30
Figure 4-4: Spatial Distribution of 24-Hr Average HCl Concentration (µg/m3) ............................................ 4-31
Figure 4-5: Spatial Distribution of 24-Hr Average CO Concentration (µg/m3) ............................................. 4-32
Figure 4-6: Spatial Distribution of 24-Hr Average NH3 Concentration (µg/m3) ........................................... 4-33
Figure 4-7: Spatial Distribution of 24-Hr Average HF Concentration (µg/m3) ............................................ 4-34
Figure 5-1: Locations for Alternative sites ...................................................................................................... 5-1
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT F-5
Figure 5-2: Closure view of Site 1 ................................................................................................................... 5-3
Figure 5-3: Closure view of Site 2 ................................................................................................................... 5-3
Figure 5-4: Closure view of Site 3 ................................................................................................................... 5-4
Figure 5-5: Closure view of Site 4 ................................................................................................................... 5-4
Figure 7-1: Threat zone of Maximum Credible Accident Scenario for FO – Pool Fire ................................ 7-11
Figure 7-2: Threat zone of Worst Case Scenario for FO – Pool Fire ............................................................ 7-12
Figure 10-1: Environment Management Cell .............................................................................................. 10-19
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT F-6
LIST OF PHOTOGRAPHS
Photograph 2-1 Project Site Photograph ........................................................................................................ 2-12
Photograph 3-1 Ambient Air Quality Monitoring ........................................................................................... 3-8
Photograph 3-2 Surface & Ground Water Sampling ..................................................................................... 3-14
Photograph 3-3 Noise Monitoring and Traffic Study .................................................................................... 3-24
Photograph 3-4 Soil Sampling ....................................................................................................................... 3-29
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT A-1
LIST OF ANNEXURE
Annexure 1 TOR letter ......................................................................................................................... A-2
Annexure 2 List of hazardous waste to be managed at proposed TSDF .............................................. A-3
Annexure 3 CGWA application copy ................................................................................................... A-4
Annexure 4 Conservation plan for schedule – i fauna .......................................................................... A-5
Annexure 5 Write up on confirmation of complying with conditions of protocol ............................... A-6
Annexure 6 Land Doocuments ............................................................................................................. A-7
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT T-1
TOR COMPLIANCE
ToR letter no. 10-39/2018-IA-III dated 29/08/2018
TOR
No. TOR condition ToR Compliance Section/Page no.
A Specific and General TOR
1 Importance and benefits of the project Section no. 1.3.2
Page no. 1-2
Chapter – 1
2 The E.I.A would address to the
conformity of site to the stipulations as
made in the Hazardous and Other
Wastes (Management and
Transboundary Movement) Rules, 2016
and will have a complete chapter
indicating conformity to the said rules.
For the proposed project total
four sites were identified. Based
on CPCB knock out criteria, two
sites were rejected and other two
sites were further evaluated in
detailed, and based on suitability
proposed site located at
Chansma village is selected.
Section no. 5.2
Page no. 5-1
Chapter – 5
3 Project proponents would also submit a
write up on how their project proposal
conform to the stipulations made in the
“protocol for Performance evolution and
monitoring of the Common Hazardous
Waste Treatment Storage and Disposal
facilities including common Hazardous
Waste incinerators”, published by the
CPCB on May 24,2010.
Write up on how their project
proposal conforms to the
stipulations made in the protocol
is attached in EIA report.
Annexure 5
A-6
4 Details of various waste management
units with capacities for the proposed
projects.
Landing of total capacity -
7,82,181 MT Hazardous waste
Incineration (solid and liquid
waste): 1 MT/hr capacity.
Section no.2.4
Page no. 2-18
Chapter – 2
5 List of waste to be handled and their
source along with mode of
transportation.
All hazardous waste listed in
SCHEDULE - I of Hazardous
and Other solid wastes
(management and Trans
boundary Movement) Rules,
2016 will be handled at
proposed project. Waste will be
transported by road through
trucks/tankers covered with
tarpaulin with all safety
precautions.
Annexure 2
A-3
6 Other chemicals and materials required
with quantities and storage capacities.
Chemicals and materials will be
required are lime, alum,
polyelectrolyte to be required
for ETP, lime, flyash, bentonite
(clay), cement and saw dust.
Storage quantity will be 7 days.
Section no. 2.11.8
Page no. 2-35
Chapter – 2
7 Details of temporary storage facility for
storage of hazardous waste at project
site
Around 500 sq.m. area is
provided as temporary storage
facility having impervious layer
and leachate collection system.
Section no.2.9.4.1
Page no. 2-31
Chapter – 2
8 Details of pre-treatment facility of
hazardous waste at TSDF..
Pre-treatment facility consists of
neutralization, stabilization will
be provided for hazardous waste
at TSDF.
Section no. 2.7.2
Page no. 2-23
Chapter – 2
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT T-2
TOR
No. TOR condition ToR Compliance Section/Page no.
9 Details of air emissions, effluents,
hazardous/solid waste generation and
their management.
Details of air emission,
effluents, hazardous/solid waste
generation and their
management are incorporated.
Section no. 2.12
Page no. 2-36
Chapter – 2
10 Requirement of water, power, with
source of supply, status of approval,
water balance diagram, man power
requirement (regular and contract).
Project requirement,
• Water: 43 KLD from bore
well
• Power: 400 KVA from
UGVCL
• Fuel: FO 1200 kg/day and
coal 200 kg/hr from local
suppliers
• Manpower: 100 nos. from
local region.
Section no. 2.11
Page no. 2-32
Chapter – 2
11 Process description along with major
equipments and machineries, process
flow sheet (quantitative) from waste
material for disposal to be provided.
Process description along with
major equipments and
machineries, process flow sheet
(quantitative) from waste
material for disposal is provide.
Section no. 2.5 &
2.6
Page no. 2-18 &
2-20
Chapter – 2
12 Hazard identification and details of
proposed safety systems.
Major hazard associated with
the proposed project are fire due
to handling and storage of
incinerable hazardous waste.
To prevent fire hazard adequate
safety system is proposed.
Section no.
7.3.7.1
Page no. 7-6
Chapter – 7
13 Details of Drainage of the project up to
5 km radius of study area. If the site is
within 1 km radius of any major river,
peak and lean season river discharge as
well as flood occurrence frequency
based on peak rainfall data of the past
30 years. Details of Flood Level of the
project site and maximum Flood Level
of the river shall also be provided.
Nearest rivers,
• Khari river at 2.22 km
• Pushpavati River at 8.12
km.
These rivers are tributary of
Rupen River and flowing within
the study area of proposed
project.
Chapter – 3
Figure 3-14
3-41
14 Ground water quality monitoring in and
around the project site.
For ground water quality
monitoring, eight water samples
were collected from the study
area during October 2018 to
December 2018.
Table 3-9
Page no.3-15
Chapter – 3
15 The Air Quality Index shall be
calculated for base level air quality.
Air Quality Index is calculated
for base level air quality for all
the locations.
Table 4-16
Page no. 4-36
Chapter – 4
16 Status of the land purchases in terms of
land acquisition Act and study the
impact.
Entire land is/will be purchased
from private owners through
mutual agreement.
Section no. 2.11.2
Page no. 2-32
Chapter – 2
17 Status of acquisition of land. If
acquisition is not complete, stage of the
acquisition process and expected time of
complete possession of the land.
Major part of project area is
already purchased from private
land owner. Procurement of rest
part is under process.
--
18 R&R details in respect of land in line
with state government policy.
Entire land is/will be purchased
from private owners through
mutual agreement hence R&R
study is not applicable.
--
19 Details of effluent treatment and
recycling process.
In-house ETP having primary,
secondary, tertiary followed by
Section no. 2.12.1
Page no. 2-36
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT T-3
TOR
No. TOR condition ToR Compliance Section/Page no.
RO and spray dryer unit will be
installed. No effluent will be
sent to outside premises.
Chapter – 2
20 Leachate study report and detailed
leachate management plan to be
incorporated.
Around 15 KLPD Leachate will
be generated from the landfill
and it will be treated in ETP
followed by RO and spray dryer.
Section no.
2.12.2
Page no. 2-39
Chapter – 2
21 Action plan for measures to be taken for
excessive leachate generation during
monsoon period.
A guard pond of 250 m3 is
proposed to take care excessive
leachate generation during
monsoon period, which will be
gradually taken to ETP.
Section no.
2.9.4.1
Page no. 2-31
Chapter – 2
22 Detailed Environmental Monitoring
Plan as well as Post Closure monitoring
Plan.
Detailed Environmental
Monitoring Plan as well as Post
Closure monitoring Plan is
prepared and incorporated.
Section no. 6.2
Page no.6-1
Chapter – 6
23 Action plan for any pollution of ground
water is noticed during operation period
or post closure monitoring period.
Action plan for GW pollution is
incorporated in EIA report.
Section no.
10.2.4.1
Page no. 10-7
Chapter – 10
24 A certificate of adequacy of available
power from the agency supplying power
to the project along with the load
allowed for the project.
No such adequacy certificated is
being issued by the power
supplying agency. However it is
assured to supply required
power load.
--
25 The EMP would also include proposals
for creating a solar power generation
farm.
In post closure phase solar panel
will be installed for the
generation of power.
Section no. 2.9.5
Page no. 2-31
Chapter – 2
26 A detailed plan for green belt
development. Impact of tree felling, if
any, along with a management plan.
About 33 % of total project area
(35,123 m2) shall be developed
as green belt at facility
boundary, road side, around
offices & buildings.
Section
no.10.2.5.1
Page no. 10-10
Chapter – 10
27 A certificate from the local body
supplying water, specifying the total
annual water availability with the local
authority, the quantity of water already
committed, the quantity of water allotted
to the project under consideration and
the balance water available. This should
be specified separately for ground water
and surface water sources, ensuring that
there is no impact on other users.
Application for obtaining No
objection certificate from
Central Ground Water Authority
is submitted.
Annexure 3
A-4
28 Public hearing to be conducted and
issues raised and commitments made by
the project proponent on the same
should be included in EIA/EMP Report
in the form of tabular chart with
financial budget for complying with the
commitments made.
This is draft EIA report,
submitted for Public hearing.
This point will be complied after
public hearing.
--
29 The project proponents shall satisfactory
address to all the complaints
/suggestions that have been received
against the project till the date of
submission of proposals for appraisal.
Details of all the complaints
/suggestions if any will be
incorporated.
--
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT T-4
TOR
No. TOR condition ToR Compliance Section/Page no.
30 Any litigation pending against the
project and/or any direction/order
passed by any Court of Law against the
project, if so, details thereof shall also
be included.
There is no litigation and
direction/order passed by any
Court of Law against the
proposed Greenfield Project.
--
31 Plan for Corporate Environmental
Responsibility (CER) as specified under
Ministry’s Office Memorandum vide
F.No. 22-65/2017-IA.III dated 1st may
2018 shall be prepared and submitted
along with EIA Report
Plan for Corporate
Environmental Responsibility
(CER) as specified under
Ministry’s Office Memorandum
vide F.No. 22-65/2017-IA.III
dated 1st may 2018 is prepared
and incorporated in EIA Report.
Section no. 8.5
Page no. 8-2
Chapter – 8
32 A tabular chart with index for point wise
compliance of above TORs
A tabular chart with index for
point wise compliance of TORs
is prepared and incorporated.
--
B Standard Terms of Reference
1 Reasons for selecting the site with
details of alternate sites
examined/rejected/selected on merit
with comparative statement and
reason/basis for selection. The
examination should justify site
suitability in terms of environmental
damages. Resources sustainability
associated with selected site as
compared to rejected sites. The analysis
should include parameters considered
along with weightage criteria for short-
listing selected site.
For the proposed project total
four sites were identified. Based
on CPCB knock out criteria, two
sites were rejected and other two
sites were further evaluated in
detailed, and based on suitability
proposed site located at
Chansma village is selected
Section no. 5-1
Page no. 5-1
Chapter – 5
2 Submit the details of the road/rail
connectivity along with the likely
impacts and mitigative measures.
Project site is well connected
with road network. However,
approach road of 2 km from
village road to project site will
be developed.
Table 2-4
Page no. 2-17
Chapter – 2
3 Submit the present land use and
permission required for any conversion
such as forest, agriculture etc.
Present land use of is Single
crop agricultural which will be
converted into Non-agricultural
activities land use.
Figure 3-11
Page no. 3-35
Chapter – 3
4 Examine the details of transportation of
Hazardous wastes and its safety in
handling.
Hazardous waste will be
transported with safety as per
the Guidelines for transportation
of hazardous waste prescribed
by CPCB.
--
5 Examine and submit the details of on
line pollutant monitoring
As per CPCB guidelines online
pollutant monitoring system will
be implemented for the
parameters like Temperature,
Carbon monoxide, Excess
oxygen, Pressure, Total
particulate matter, HCl, SO2,
NOx as per applicable.
Table 6-1
Page no.6-1
Chapter – 6
6 Examine the details of monitoring of
Dioxine and Furan.
Dioxine and Furan will be
monitored Twice a year under
critical operating conditions
through NABL/MoEF&CC
Table 6-1
Page no.6-1
Chapter – 6
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT T-5
TOR
No. TOR condition ToR Compliance Section/Page no.
accredited agency.
7 MoU for disposal of ash through the
TSDF.
No MOU of TSDF is required,
as fly ash it will be disposed in
proposed landfill site within
premises.
--
8 MoU for disposal of scrubbing waste
water through CETP.
As proposed scrubbing waste
water will be treated in in-house
ETP having primary, secondary,
tertiary followed by RO and
spray dryer unit. No effluent
will be sent to outside premises.
--
9 Examine and submit details of
monitoring of water quality around the
landfill site.
Three observatory well around
the landfill site are proposed for
regular Water quality
monitoring to examine the
impact on the ground water.
Section no. 6.2
Page no. 6-1
Chapter – 6
10 Examine and submit details of the odour
control measures.
Odour control measures are as
follows,
• Daily waste covering with soil
• Spraying of Odour
suppression chemicals.
• Greenbelt containing odour
capturing species
Section no.
2.12.4.3
Page no. 2-42
Chapter – 2
11 Examine and submit details of impact
on water body and mitigative measures
during rainy season.
A guard pond of 500 m3 is
proposed to take care excessive
leachate generation during
monsoon period, which will be
gradually taken to ETP. Hence
there will not be any significant
impact on water body.
Section no.
2.9.4.1
Page no. 2-31
Chapter – 2
12 Environmental Management Plan
should be accompanied with
Environmental Monitoring Plan and
environmental cost and benefit
assessment. Regular monitoring shall be
carried out for odour control.
- Environmental Management
Plan is prepared covering
Environmental Monitoring
Plan and environmental cost
and benefit assessment
- Regular monitoring shall be
carried out for odour control
Section no. 10.2
Page no. 10-2
Chapter – 10
13 Water quality around the landfill site
shall be monitored regularly to examine
the impact on the ground water.
Three observatory well around
the landfill site are proposed for
regular Water quality
monitoring to examine the
impact on the ground water.
Table 6-1
Page no. 6-1
Chapter – 6
14 The storage and handling of hazardous
waste shall be as per the Hazardous
Waste Management Rules.
The storage and handling of
hazardous waste will be carried
out as per the Hazardous Waste
Management Rules.
Section no. 2.7
Page no. 2-22
Chapter – 2
15 Submit details of a comprehensive
Disaster Management Plan including
emergency evacuation during natural
and manmade disaster.
Details comprehensive Disaster
Management Plan including
emergency evacuation during
natural and manmade disaster is
prepared and incorporated.
Section no. 7.3.12
Page no. 7-14
Chapter – 7
16 Public hearing to be conducted for the
project in accordance with provisions of
Environmental Impact assessment
This draft EIA report is
submitting to conduct public
hearing as per provision made in
--
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT T-6
TOR
No. TOR condition ToR Compliance Section/Page no.
notification, 2006 and the issues raised
by the public should be addressed in the
Environmental Management Plan. The
public Hearing should be conducted
based on the ToR letter issued by the
Ministry and not on the basis of minutes
of the Meeting available on the web site.
EIA notification.
Issues to be raised by the public
will addressed in the final EIA.
17 A detailed draft EIA/EMP report should
be prepared in accordance with the
above additional TOR and should be
submitted to the Ministry in accordance
with the Notification.
A detailed draft EIA/EMP report
is prepared in accordance with
additional TOR.
--
18 Details of litigation pending against the
project, if any, with direction/order
passed by any Court of Law against the
Project should be given.
There is no litigation and
direction/order passed by any
Court of Law against the
Project.
--
19 The cost of the project (capital cost and
recurring cost) as well as the cost
towards implementation of EMP should
be clearly spelt out.
Total cost of the project is Rs.
38.45 Crores. And capital cots
cost towards implementation of
EMP is Rs. 3.25 Crores and
recurring is Rs. 66 Lakh Per
Annum.
Table 10-4 &
Table 10-5
Page no.10-21
Chapter – 10
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-1
EXECUTIVE SUMMERY
1 INTRODUCTION North Gujarat Enviro Projects (NGEP) has proposed to set up Common Hazardous Waste Treatment,
Storage and Disposal Facility (TSDF) comprising of land filling and incinerator located at Survey No.
2483, 2500, 2501, 2503, 2482, 2484, 2499, 2502, 2504, 2486, 2485, 2487, 2488, 2498, 2497, 2505, 2506,
2490, 2491, 2496, 2509, 2510, 2523,2528/1,2528/2, 2524 Village. – Chanasma, Taluka. – Chanasma,
District- Patan, Gujarat. Proposed facility falls under Category “A”, 7(d) as it is comprising TSDF and
incineration facility, as per EIA notification dated 14th September, 2006 & its subsequent amendments time
to time.
En-vision Enviro Technologies Pvt. Ltd. (NABET Accreditation no. : NABET/EIA/1821/RA 0102), was
appointed as environmental consultant to carry out the Environmental Impact Assessment (EIA) study for
their proposed project.
2 PROJECT DESCRIPTION
2.1 PROJECT DETAILS
Maximum Capacity of the
Land fill and incineration
Land fill : 7,82,181 MT Hazardous waste
Incineration (solid and liquid waste): 1 MT/hr capacity.
Hazardous waste to be
handled
All hazardous waste listed in SCHEDULE - I of Hazardous and Other
solid wastes (management and Trans boundary Movement) Rules, 2016
will be handled at proposed project. Waste will be transported by road
through trucks/tankers covered with tarpaulin with all safety precautions.
Land area Total plot area : 1,06,432 m2 (considering survey no. 2482/1, 2482/2,
2486, 2483/1, 2483/2, 2500, 2499, 2498, 2496/1, 2496/2, 2497, 2502,
2501, 2503, 2506, 2509, 2510, 2523, and 2491/1)
land fill area : 49,903 m2
Project cost Rs. 38.45 Crore
Cost for EMS Capital Cost: Rs. 3.25 Crores
Recurring cost: Rs. 66 Lakh Per Annum.
Cost for CSR activity Rs. 76.90 Lacs (for first five years)
2.2 Environmental Setting :
No. Description
From Project Site
Remarks Distance
(km)
Direction
1. National High Way (NH 15) 43.31 NW -
2. State High Way (SH-7) 1.38 WSW -
State High Way (SH-55) 2.36 NE -
3. Railway Station (Chansma) 4.0 NNW -
4. Airport (Ahmedabad) 84.7 SE -
5. River (non-perennial river)
Pushpavati River 8.12 SSE Nr. Mahadevpura village
Khari River 2.22 East Nr. Zilliyavasana village
Karoda Lake 1.60 WSW In Karoda village
6. Sea (Gulf of Khambhat) 203.9 South -
7. Village (Ziliyavasna village) 1.45 East Population – 709 nos.
8. City (Chansma) 4.0 NNW -
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-2
No. Description
From Project Site
Remarks Distance
(km)
Direction
9.
Heritage site/ Archeological Site
12.33 South Modhera Sun Temple
15.33 NNW Rani ki Vav
17.91 NNW Sahastralinga Talao
14.63 North Jami Masjid
10. Reserve Forests Non within 10 km radius of the project site.
11. National Park/Wild Life Sanctuary Non within 10 km radius of the project site.
12. Bird Sanctuary Non within 10 km radius of the project site.
13. Eco Sensitive Area Non within 10 km radius of the project site.
14. Industries in surrounding Non within 2 km radius of the project site.
2.3 PROJECT REQUIREMENT:
Water & its source Source: Bore well.
Construction phase
• Domestic – 10 KLD
• Construction and other activity – 25 KLD
• Total – 35 KLD
Operation phase
• Domestic – 8 KLD
• Industrial activity – 20 KLD
• Greenbelt – 15 KLD
• Total – 43 KLD 22 KLD fresh + 21 KLD recycle)
Electricity & its
source
Source: Uttar Gujarat Vij Company Ltd. (UGVCL).
• Construction phase – 350 KVA
• Operation phase – 400 KVA
(Backup power: D.G. set – 1 no 1500 KVA.)
Manpower • Construction phase : Total 195 Nos.
(170 no. of skilled and semi skilled workers, 25 no. technical people)
• Operation phase: 100 no. of technical staff
Fuel Construction phase : High Speed Diesel: 100 liter/Hr in D.G. Set
Operation phase :
• Furnace Oil: 1200 kg/day in Incinerator
• High Speed Diesel (HSD) : 300 liter/Hr in D.G. Set
• Coal: 200 kg/Hr (Spray Dryer with Inbuilt HAG)
2.4 WASTEWATER GENERATION Approximately 35 KLD of wastewater will be generated. Waste water generation is mainly from washing
(5 KLD), domestic (4 KLD), scrubber of incinerator/spray dryer (15 KLD) and leachate from landfil (15
KLD). Industrial waste water will be treated in proposed Effluent/leachate treatment plant followed by RO
and spray dryer. Domestic wastewater will be collected and disposd off through septik tank followed by
soak pit.
2.5 AIR EMISSION & CONTROL MEASURES The air emission from the proposed project will be landfill gas (VOC and H2S), control system will be
provided to collect and extract gas from the landfill and vent hole pipe network will be installed for the
same. Air emission from incinerator would be controlled by providing cyclone separator, bag filter, Wet
scrubber and alkali scrubber. Air Emission from Spray Dryer/Hot air generator would be controlled by
providing cyclone separator and Bag filter and air emission from D. G. set would be controlled by
providing adequate stack height and acoustic enclosure during emergency only.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-3
2.6 HAZARDOUS WASTE GENERATION AND ITS DISPOSAL Solid / hazardous waste i.e. Spent/used oil (200 Lit/Yr.) will be reused as a lubricant/ sent to recyclers.
ETP Sludge (180 MTPA) will be disposed to own landfill site. Incineration ash (360 MTPA) will be
generated which will be disposed in own TSDF site. Spray dyer sludge (220 MTPA) will be disposed at
proposed landfill site within premises. Discarded containers & bags (72 MTPA) Sell to
approved/registered recycler.
3 DESCRIPTION OF ENVIRONMENT The baseline environmental quality of air, water, soil noise and Ecology & Bio diversity, etc has been
assessed in a Post-monsoon season (October 2018 to December 2018). Study area of 10 km radial distance
from the project site is selected along with socioeconomic and ecology status during study period.
3.1 AMBIENT AIR QUALITY
No. of AAQM station – 8
Criteria
Pollutant Unit
Maximum
value
Minimum
value
98th
Percentile
Prescribed
Standard Observation
PM10 µg/m3 80.8 60 80.43 100 concentrations
were found
well below
the stipulated
standards
PM2.5 µg/m3 45.83 30 45.83 60
SO2 µg/m3 12.8 7 12.62 80
NOx µg/m3 30.5 19.5 30.5 80
VOC, CO, HG, HCl, Cl2, NH3, HBr, Br2, H2S, HC, HF are found below detectable limit (BDL)
3.2 WATER QUALITY No. of ground water samples collected – 5 and No. of surface water samples collected – 7
Criteria Pollutant (Ground water) Unit Maximum
value
Minimum
value
pH - 7.7 7.42
Total Dissolve Solids (TDS) mg/L 2820 2020
Total Suspended Solids (TSS) mg/L 25 20
Total Hardness (TH) mg/L 882 750
Clorides mg/L 1106.8 620.4
Fluoride mg/L 1.2 0.8
Heavy metals like Iron (as Fe), Lead (as Pb),
Copper (as Cu), Total Arsenic (as As), Cynide (as
CN) etc.
mg/L BDL BDL
Criteria Pollutant (Surface water) Unit Maximum value Minimum
value
pH - 7.88 7.35
Dissolve Oxygen (DO) mg/L 5.7 4.9
Biochemical Oxygen Demand(BOD) mg/L 3.5 3
Chemical Oxygen Demand (COD) mg/L 13.9 12.2
Total Dissolve Solids (TDS) mg/L 272 176
Total Suspended Solids (TSS) mg/L BDL BDL
Total Hardness (as CaCO3) mg/L 162.4 107.8
Clorides mg/L 18.1 12.4
Fluoride mg/L 0.68 0.51
Total Alkalinity (as CaCO3) mg/L 147.2 133.7
Sodium mg/L 29.7 19.6
Lead mg/L BDL BDL
copper mg/L BDL BDL
zinc mg/L BDL BDL
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-4
3.3 BACKGROUND NOISE LEVEL No. of soil samples collected – 5
Criteria
Pollutant
Noise level dB(A) Leq
Maximum Minimum
Leq (Day) 58.5 45.8
Leq (Night) 44.2 40.1
3.4 SOIL QUALITY No. of soil samples collected – 6
Criteria Pollutant Unit Maximum
value
Minimum
value
pH - 8.5 7.6
N (Nitrogen) mg/kg 273.7 159.4
P (Phosphorous) mg/kg 82.2 8.3
K (Potassium) mg/kg 77 64
Electric Conductivity µS/cm 785 180.1
3.5 LAND USE PATTERN Land use within 10 km radius of the study area has been determined with the help of satellite imagery, and
broadly consists of single crop (80.1%), Tank/River/Major canal (6.8%), settlements (4.7%), and waste
land with scrub/ without scrub(8.4%). Predominant land use is Single crop.
3.6 SOCIO-ECONOMIC STUDY The PIA for the concerned project comprises 55 major villages and urban areas in 10 km radius around the
proposed project in Ziliya village, Chanasma Taluka of Patan district. Total population in the study area
was 10,62,653 with a sex ratio of 938 females per 1000 males and total literacy rate was found 72.30 as per
Census 2011.
3.7 BIOLOGICAL ENVIRONMENT There is no ecological sensitive area within 10 km radius of the project site. The vegetation of this area
can be classified on the basis of habitats as; open fallow lands, areas under cultivations, hedge vegetation
and scrub vegetation. The tree species, herbs and shrubs and major crops, were documented during this
base line study. The dominant trees growing in this area were Prosopis cineraria (Khyigdo), Azadirachta
indica,. Acacia nilotica (Baval), Salvadora oleoides (Piludi), and Salvadora persica (Piludo) Shrubs are the
dominant perennials of this area, represented mainly by, Prosopis juliflora, Capparis decidua, Senna
auriculata (Aval), Senna occidentalis (Sundro), Zizyphus nummularia (Chanibor) Calotropis procera,
Calotropis gigantea, (Akado) and Lantana camara.
Some of the sighted fauna within study area was given protection by the Indian Wild Life (Protection) Act,
1972 by including them in different schedules. Among the birds in the study area, Pea fowl (Pavo
cristatus), Eurasian Spoonbill (Platalea leucorodia) are included in schedule I, while many other birds are
included in schedule IV of Wild life protection Act (1972). Among the reptiles, (Indian Mud or Flap shell
Turtle Lissemys punctate) were provided protection as per Schedule-I of Wild life protection act, (1972).
Conservation plan for the said fauna is incorporated in EIA report.
3.8 HYDROGEOLOGY Major water bearing formation of Patan district is quaternary alluvium. Phreatic aquifer (is the area in an
aquifer, below the water table, in which relatively all pores and fractures are saturated with water) of study
area and surroundings is 1.7 to 32.01 DTW in pre-monsoon while in post monsoon it is 1.0 to 20.98 DTW.
Ground water is available at depth 40 – 618.9 mtr, while discharge is 6 – 2616 LPM. Chansma is fall under
over exploited zone of GW. The surface water resources are very limit at and around the PS. Ground
water is major and only source of irrigation, but GW found in the area is predominantly high in
bicarbonate and Floride.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-5
4 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES An effort has been made to identify various environmental, social and ecological impacts due to proposed
project during construction and operation phases considering present environmental scenario as baseline.
The corresponding mitigation measures to take care of the adverse impacts are also discussed in following
sections.
4.1 IMPACTS & MITIGATION MEASURES - CONSTRUCTION PHASE Dust will be the main pollutant affecting the ambient air quality of the surrounding area during the
construction phase. Impact during construction phase on air quality is limited to fugitive dust generated by
earth moving activities, hauling of materials, base course surfacing and moving of construction vehicles.
Motor vehicle transportation (to, from and around the site) particularly the traffic of trucks at the site,
material movement into the site will introduce particulates and other exhaust gases into the local ambient
air and there is some likelihood that during the construction period local air quality may be temporarily
affected by these emissions. To reduce air pollution during this phase following mitigation measures will
be implemented.
• Suitable surface treatment to ease the traffic flow and regular sprinkling of water to be carried out to
control dust/fugitive emission.
• To reduce fugitive dust emission, construction activity shall be covered
• Construction material to be stored in covered shed.
• Condition of all vehicles, generators and compressors to be maintained and regularly serviced.
4.2 IMPACT & MITIGATION MEASURES - OPERATION PHASE
4.2.1 AIR ENVIRONMENT
Impact Impacting Activity Mitigation
Flue gas emission
from stacks
Operation of Incineration, spray
dryer and D. G. Set; Vehicular
movement
• Quencher, Carbon Column, Droplet Separator,
Cyclone Separator, Bag Filter, Ventury
Scrubber, Alkali Scrubber will be installed as
APCM with incinerator.
• Cyclone Separator, Bag Filter will be installed
with flue gas emission control
• HDPF perforated vent pipes to collect land fill
gas and its regular monitoring
• Development of green belt
• Internal pucca road and only PUC certified
vehicles will allowed in premises
Fugitive dust
emission
Waste transportation, handling
and disposal
VOC gas
generation
Landfill
4.2.2 NOISE ENVIRONMENT
Impact Impacting Activity Mitigation
Increase in
noise level
- Handling and disposal of
hazardous waste.
- Transportation of waste
- Operation of pumps,
motors, engines, auxiliary
equipment’s, etc
• All vehicles entering into the project will be informed to
maintain speed limits, and not blow horns unless it is
required. The noise level within facility would be kept
less than 75 dBA
• Acoustic enclosures will be provided to D. G. sets to
reduce the noise level
• Development of greenbelt
4.2.3 WATER ENVIRONMENT
Impact Impacting Activity Mitigation
Stress on ground
water source
Water consumption • Reuse of treated effluent (21 KLD), which is approx.
50% of water requirement
• Installation of flow meter to check daily water
consumption
• Water conservation through rainwater harvesting, which
will help to reduce fresh water demand
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-6
Contamination of
surface water as
well as ground
water
Transportation and
handling of
hazardous waste
• Storm water management
• Impervious layer and Leachate collection facility at
Temporary waste storage area
Wastewater
generation • Domestic and
industrial use of
water
• Leachate
generation from
landfilling cell
• Domestic effluent will be treated in ETP along with
industrial effluent
• Installation of trenches, cells, etc. and proper leachate
collection and control system so that it will not cause any
contamination of surface water as well as ground water
• Industrial effluent (26 KLD) will be treated in ETP
followed by RO plant.
• Leachate (15 KLD) and RO reject (5 KLD) will be
treated in spray dryer
• Reuse of treated effluent (21 KLD)
4.2.4 SOIL ENVIRONMENT
Impact Impacting Activity Mitigation
Generation of
solid/hazardous
waste
- Operation of ETP
- Incineration of waste
- Operation of spray dryer
- Operation of utility and
machineries
- Handling and disposal of
waste
• Separate designated storage area will be provided with
sign boards/labels for solid and liquid hazardous
wastes
• Regular training of employee will be ensured
• Hazardous waste generation and disposal as per SOP
• Maintain printed logbook for any spillage
Contamination
of soil due to
accidental
spillage
- Transportation, handling
and disposal of
hazardous waste
• In case of such condition entire contaminated soil will
be removed and disposed within land fill cell to
reduce impact
• Use of spill kit
4.2.5 BIOLOGICAL ENVIRONMENT 33 % of total project area (35,123 m
2) will be developed as green belt at facility boundary, road side,
around offices & buildings. In Green belt area about 10418 trees shall be planted.
4.2.6 SOCIO-ECONOMIC ASPECT Impact on Socio-Economic aspect will be mainly on population, migration, culture, economic status,
health, education, drinking water facility, drainage facility, primary infrastructure, etc. Due to proposed
facility, impact on socioeconomic environment will be nominal. However, proposed CER activities will
improve socioeconomic status of the area.
5 ALTERNATIVE SITE STUDY For the proposed project following four sites were identified.
Site-1 : Village: Ziliyavasna, Taluka: Chansma, Dist: Patan (Guj.)
Site-2 : Village: Kamboi, Chansma-Harij road, Taluka: Chansma, Dist: Patan (Guj.)
Site-3 : Village: Vadavli, Taluka: Chansma, Dist: Patan (Guj.)
Site-4 : Village: Chansma, Taluka: Chansma, Dist: Patan (Guj.)
Based on CPCB knock out criteria, site -1 and site – 3 is rejected due to existence of water body and
agricultural land. Site – 2 and site – 4 are further evaluated in detail and site – 4 located at Chansma village
are found more suitable for development of TSDF compare to site – 2, hence it is selected.
6 ENVIRONMENTAL MONITORING PROGRAMME Regular monitoring of environmental parameters like air, water, noise, vegetation and soil as well as
performance of pollution control facilities and safety measures in the facility is important for proper
environmental management of any project. Env. monitoring programme as mentioned in EIA report will be
implemented.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT E-7
7 ADDITIONAL STUDIES
7.1 RISK ASSESSMENT The management is very much aware of their obligation to protect all persons at work and others in the
neighborhood that may be affected by an unfortunate and unforeseen incidence occurring at the works.
Any hazard either to employees or environment arising from project activities at the facility shall, as far as
possible, be handled by the management of the company and prevented from spreading any further. Safety
audit and compliance of recommendation of audit will be ensured by all the persons worked in plant.
Personnel protective equipment will be provided and ensure its use.
7.2 ENVIRONMENTAL PUBLIC HEARING Public hearing will be conducted as per TOR condition and public hearing document will be incorporate in
final EIA report.
7.3 TRAFFIC MANAGEMENT PLAN
Hazardous waste from various industries will be received approx. 200 MT/day i.e. approx. 18 Nos. of
trucks will be required per day for transportation of waste. Approx. 25 Nos. of Cars will move per day. The
water sprinkling will be done and all vehicles will be of valid PUC.
8 PROJECT BENEFITS
• Indirect employment generation for surrounding villagers.
• Proposed greenbelt developed and rainwater harvesting at PS will have positive impact on
environment
• Creation of community assets/facility under CER plan. Rs. 76.90 Lacs will utilize for the CER
activities for the first five years
9 ENVIRONMENTAL MANAGEMENT PLAN
9.1 ENVIRONMENTAL MANAGEMENT PLAN (ADMINISTRATIVE ASPECTS) Environmental monitoring of different parameters will be done regularly and the activity will be
coordinated by the Environmental Management Cell (EMC). Mitigation of environmental impact has to be
implemented according to the suggestions and will be monitored regularly to prevent any lapse. The EMC
will be under the overall supervision of CEO. The cell will report on a regular basis to the management.
The EMC will prepare a formal report on environmental management and mitigation at six month
intervals. The company will undertake various training programme for improving the performance of the
working personnel. Special training will be arranged in regular intervals to combat emergency scenarios
that may occur during the operation.
10 CONCLUSION Company has committed to implement all the pollution control measures to protect the surrounding
environment and hence there will be negligible impact on the same.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 1-1
CHAPTER 1 INTRODUCTION
Hazardous wastes are extremely harmful for the environment and cause significant health hazards. Rapid
industrialization has resulted in the generation of huge quantity of wastes, both solid and liquid form.
Many industrial processes have the potential to produce hazardous waste which includes any material that
is render useless during a manufacturing process. It is presumed that about 10 – 15% of wastes produced
by industries are hazardous and the generation of hazardous wastes is increasing at the rate of 2 – 5 % per
year.
In India, absence of adequate infrastructure for scientific disposal and recycling of hazardous waste has
resulted in poor waste handling. Burning of hazardous waste at landfills is still one of the most common
and primitive methods of disposing, resulting in immense harm for health and environment. Despite
requirements for pollution control measures, these wastes are generally dumped on land or discharged into
water bodies, without adequate treatment, and thus become a large source of environmental pollution and
health hazard. To overcome such situations, integrated waste management facilities are developed. The
capacity of an integrated waste management facility should be decided based on availability of hazardous
waste in the State/in nearby area. Such a facility should comprise a secured landfill, arrangements for
treatment, incinerator, a laboratory capable of comprehensive analysis, and arrangement for transportation
and handling of wastes including supporting infrastructure.
Obtaining Environmental Clearance before setting up industrial plant as per EIA notification is statutory
requirement. The Environmental Impact Assessment (EIA) study is carried out as a part of the process to
obtain Environmental Clearance for the proposed waste management facility.
1.1 PURPOSE OF EIA
The Environmental Impact Assessment (EIA) study is carried out as a part of the process to obtain
Environmental Clearance for the proposed Green field project of common Integrated Landfill and
Incineration facility by North Gujarat Enviro Projects (NGEP).
Proposed project falls under category “A” of activity 7(d) as this project having incineration & landfill as
per EIA Notification dated 14th September, 2006 and its subsequent amendments.
The purpose of the EIA study is to identify and assess the adverse impacts of a project in the planning
stage itself, so that necessary mitigation measures to prevent or minimize these adverse impacts can be
planned early and cost-effectively. EIA report has been prepared in line with ToR letter vide 10-39/2018-
IA-III dated 29/08/2018 issued by MoEFCC, New Delhi. Further, Technical EIA Guidance Manual for
Common Hazardous Waste TSDF - IL&FS, August, 2010 is also referring to prepare EIA report. ToR
letter is attached as Annexure – 1 with EIA report.
1.2 PROJECT PROPONENT
The company North Gujarat Enviro Projects (NGEP) has been established in the year 2017 by persons who
has experience in the field of waste management, chemical industry etc.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 1-2
1.2.1 Promoter’s Background
Following are the partners involved in management and decision maker of the company.
1) Dharnendrabhai Natvarlal Patel
2) Dharmendrabhai Kantilal Patel
3) Santosh Mahanandu Naik
4) Samirbhai Govindbhai Patel
5) Mishal Govindbhai Patel
1.3 IDENTIFICATION OF PROJECT
Industrialization is lead to generation of solid/hazardous waste day by day which has to be collected,
transported, treated and disposed in a properly designed TSDF as per the Hazardous and Other Wastes
(Management and Transboundary Movement) Rules, 2016 under Environment (Protection) Act, 1986.
CPCB have laid down a procedure for collection, storage, transportation and disposal of hazardous wastes.
The scientifically proven method either incineration or disposal in a secured landfill are used for disposal
of hazardous waste. Such facility requires proper design and operation according to existing guidelines.
Proposed common Integrated Landfill and Incineration Facility will cater environmentally and
economically sound option for industrial waste disposal.
1.3.1 Nature, Size and Location
NGEP proposes Greenfield common integrated Landfill and Incineration facility for disposal of industrial
waste to be generated from various industries located in and around Ahmedabad & North Gujarat region.
Design capacity of the proposed landfill is 7,82,181 MT in 6,51,353 m3 which is based on a bulk
compaction factor of 1.2 MT/m3. Further one incinerator (1 MT/hr.) for the incineration of liquid and solid
waste will be installed.
After detailed alternative site study, project proponent decided to develop proposed facility at Survey No.
2482/1, 2482/2, 2486, 2487, 2483/1, 2483/2, 2491/1, 2491/2, 2500, 2499, 2498, 2496/1, 2496/2, 2497,
2502, 2501, 2503, 2506, 2509, 2510, 2523 Vill. – Chanasma, Tal. – Chanasma, Dist. Patan, Gujarat.
Alternative site selection study is described in chapter – 5 of EIA report.
1.3.2 Importance of Project to Region
Hazardous wastes generated from various industries in and around Ahmedabad and Mehsana, need to be
disposed in an environmentally safe manner. GPCB data shows that TSDF sites located in Surendranagar
and Nandesari (Vadodara) is in operation. A new landfill facility is required for hazardous waste disposal
as existing facilities has utilized their maximum design capacity. Presently non-landfillable waste which is
voluminous and toxic is incinerating in common incineration facility by BEIL, Ankleshwar and NECL,
Nandesari-Vadodara. Both facilities located around 313 km and 203 km respectively from proposed
project site. It is unwanted transportation burden on the industries for economic point as well as risk on the
existing road network on environment point of view. In view of above scenario, proposed integrated
facility will be set up at advantageously location i.e. at Chanasma, near Patan district.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 1-3
1.4 REGULATORY FRAME WORK
Proposed Green field project is waste treatment facility; hence the regulatory framework related with the
hazardous or toxic chemicals/wastes as well as regulatory provision of risk, safety & emergency
management is applicable. The major regulatory provisions applicable to the proposed project are tabulated
as under:
Sr. No. Legal Provision Concern Authority or Bodies
1 Air (Prevention and Control of Pollution) Act,
1981 amended 1987
CPCB and GPCB
2 Air (Prevention and Control of Pollution)
(Union Territories) Rules, 1983
CPCB and GPCB
3 Water (Prevention and Control of Pollution)
Act, 1974 amended 1988
CPCB and GPCB
4 Water (Prevention and Control of Pollution) Act,
1974 and its subsequent amendments
CPCB and GPCB
5 Water (Prevention and Control of Pollution) Rules,
1975 and its subsequent amendments
CPCB and GPCB
6 The Environment (Protection) Act, 1986,
amended 1991
Ministry of Environment and Forests, & Climate
Change (MoEF&CC), CPCB and GPCB
7 Environmental (Protection) Rules, 1986
(Amendments in 1999, 2001, 2002, 2002, 2002,
2003, 2004)
Ministry of Environment and Forests, & Climate
Change (MoEF&CC), CPCB and GPCB
8 Hazardous Waste (Management and
Handling) Rules, 1989 amended 2000 and 2003
MoEF&CC, CPCB, SPCB,
9 Chemical Accidents (Emergency Planning
Preparedness and Response) Rules, 1996
CCG, SCG, DCG, LCG and MAH Units
10 EIA Notification, 2006 and its subsequent
amendments
Ministry of Environment and Forests, & Climate
Change (MoEF&CC), GPCB
11 Public Liability Insurance Act, 1991
amended 1992
Ministry of Environment & Forests, District
Collector
12 Public Liability Insurance Rules, 1991
amended 1993
Ministry of Environment & Forests, District
Collector
13 The Factories Act, 1948 Ministry of Labor, DGFASLI and Directorate of
Industrial Safety and Health/Factories Inspectorate
14 The Explosive Act ,1884 Ministry of Commerce and Industry (Department
of Explosives)
15 The Explosive Rules, 1983 Ministry of Commerce and Industry and Chief
Controller of Explosives, port conservator,
customs collector, railway administration
16 The Motor Vehicle Act, 1988 Ministry of Shipping, Road Transport and
Highways
17 The Central Motor Vehicle Rules, 1989 Ministry of Shipping, Road Transport and
Highways
18 Hazardous and Other Wastes (Management and
Transboundary Movement) Rules, 2016
MoEF&CC, CPCB, GPCB
19 Gaseous Emission Norms for Common Hazardous
Waste Incinerators notified as
Environment (Protection) Fifth Amendment Rules,
2008 dated 26 June 2008
CPCB and GPCB
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 1-4
1.4.1 Applicable CPCB’s Guideline
Following guideline published by CPCB and time to time amendment in it was referred partially or whole
to prepare EIA report of proposed integrated TSDF project.
• Guidelines for Setting up of Operating Facility: Hazardous Waste Management
• Guidelines for the Selection of Site for Land filling
• Guidelines for Conducting Environmental Impact Assessment : Site Selection for Common Hazardous
Waste Management Facility
• Revised Guidelines for Pre-processing and Co-processing of Hazardous and Other Wastes in Cement
Plant as per H&OW(M & TBM) Rules, 2016
• Guidelines on Implementing Liabilities for Environmental Damages due to Handling & Disposal of
Hazardous Waste and Penalty
• Guidelines for Common Hazardous Waste Incineration
• Criteria for Hazardous Waste Landfills
• Protocol for performance Evaluation and Monitoring of the Common Hazardous Waste Treatment
Storage and Disposal Facilities including Common Hazardous Waste Incinerators
• Guidelines for Proper Functioning and Upkeep of Disposal Sites
• Guidelines for Environmental Sound Recycling of Hazardous Waste as per Schedule-V of Hazardous
Waste (Management Handling and Transboundary Movement) Rules, 2008
• Guidelines for Transportation of Hazardous Wastes
• Guidelines for Storage of Incinerable Hazardous Wastes by the Operators of Common Hazardous
Waste Treatment, Storage and Disposal Facilities and Captive HW Incinerators
1.4.2 Applicability of EIA Notification
Proposed project activities attract the provisions of EIA notifications 2006 (SO – 1533) and as amended
thereafter. Proposed project activities fall under 7(d) – {Common hazardous waste treatment, storage and
disposal facilities (TSDFs)} category – A {All integrated facilities having incineration & landfill or
incineration alone} as per notification. Public hearing is applicable to proposed project as project site
located in Chansma village. Proponent shall follow the regulatory frame work as mentioned in above table
as well as referred mandatory provision time to time impose by regulatory authority.
Public hearing shall be conducted as per provision of EIA notification and issues raised as well as
commitments made by the project proponent on the same will be included in final EIA/EMP Report.
1.5 SCOPE AND METHODOLOGY OF EIA STUDY
EIA study is conducted to incorporate all relevant critical issues of the proposed project. EIA report
incorporate field monitoring of environmental parameter for one season (excluding monsoon months),
impact-mitigation and Environment Management Plan. Project proponent has appointed Envision Enviro
Technologies Pvt. Ltd. (EETPL) for conducting EIA study for proposed project. EETPL is QCI approved
environmental consultant and authorized organized to represent the proposed project to MoEFCC. QCI
Accreditation certificate is incorporated in chapter – 12 of EIA report.
1.5.1 Baseline Study
Baseline data collection and environmental monitoring was undertaken to gather relevant information from
available sources from the project site and surrounding areas during October to December – 2018.
Environmental attributes, frequency of monitoring and scope of the baseline study is mentioned in Table
1-1.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 1-5
Table 1-1: Scope of Baseline Study
S.
No.
Environmen
tal
Component
Sampling
parameters
Sampling
period
Sampling
Frequency
Sampling
Locations Objective
1 Meteorology • Temperature,
• Wind Speed,
• Wind Direction,
• Precipitation,
• Rain fall,
• Relative Humidity,
• Cloud Cover
3 months • Hourly
except
Rainfall.
• Rainfall data
daily
1 Site specific meteorological
status of the study was
carried out for prediction of
ground level concentration in
downwind direction.
2 Ambient Air
Quality
PM10, PM2.5, SO2,
NO2
Twice in
week
for 12 weeks
24 hr 8 Prediction of impacts on air
quality due to proposed
project activities and
suggestion for mitigative
measures based on air quality
models results.
NH3 Once in
Month
24 hr
CO, VOC Once in
Month
8 hr
Cl2, HCl, HG, HC
HF, H2S, HBr, Br2,
Once in
Month
24 hr
3. Water
Quality
pH, TDS, temperature
and other Physico-
chemical and
biological parameters
Once in a
baseline
period
- 5 Ground
Water
8 Surface
Water
To established water quality
data with respect to physico-
chemical, biological
parameters and heavy metals
for assessing the impact of
the proposed project
activities on water
environment.
4. Noise Leq 24 hourly
composite
Once during
Study period
5 To established baseline status
of noise and it was used in
assessing the impact of noise
of the surrounding.
5. Soil Soil profile, Chemical
constituents
- Once during
Study period
6 To established
physiochemical characteristic
of soil to understand soil
quality as well as assessing
the impact of the proposed
project activities on soil
environment.
6. Ecology and
Bio-diversity
(EB)
Flora and Fauna of
the study area
- Once during
Study period
Study area
(10 km
from PS)
Primary survey of Flora and
fauna species and established
EB data based on primary as
well as available secondary
information.
7. Socio-
Economic
aspects
demographic
structure, provision of
basic amenities,
health status
-- Once during
Study period
Study area
(10 km
from PS)
To understand the socio-
economic status of study
area; perceptions of people
about the impact of proposed
project activities and suggest
CER plan accordingly.
8. Land use Trend of land use
change for different
categories
-- Once during
Study period
Study area
(10 km
from PS)
To understand the existing
land use pattern and changes
to be occurred due to
proposed project activities.
9. Geology &
Geo-
Hydrology
Ground water status
along with geological
features of the study
area
- Once during
Study period
Study area
(10 km
from PS)
Geological and geo-
hydrological investigation to
know the status of the study
area and it was used in
assessing the impact.
10. Risk and
Hazard
Analysis
Risk due to proposed
project and its
quantitative/qualitativ
e analysis of potential
hazards
- Once during
Study period
Plant
premises
and
immediate
surroundin
gs
To evaluate risk, assess its
impact associated to the
proposed project activity and
plan the appropriate action to
control risk by the most
economical means.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 1-6
1.5.2 Identification of Impact and Mitigation
Analysis of technical information of proposed project and project activities has been done to link it with
the existing environmental status in order to list out the risk to affect environmental parameters. Likely
impacts on such parameters are assessed based on it and accordingly mitigation measures are suggested to
comply with statutory standards.
1.5.3 Environmental Management Plan
Environmental Management Plan (EMP) is preparing in such a way so that successful implementation of
suggested mitigative measures will be achieved. The EMP envisages the plans for the proper
implementation of mitigation measures to reduce the adverse impacts arising out of the project activities
during construction and operational activities.
1.5.4 Additional Studies
Any specific study suggested by committee in ToR letter after looking the proposed project scenario will
conducted after consultation with subject specific expert and detail of the same is incorporate in EIA
report.
1.5.5 Structure of EIA Report
EIA report of proposed project has been prepared accordingly generic structure given in Appendix – III of
EIA notification for MoEFCC scrutiny and judging the environmental compatibility of the project as per
ToR letter issued by them.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-7
CHAPTER 2 PROJECT DESCRIPTION
2.1 INTRODUCTION
Along with encouraging the industrial growth, the Government of Gujarat is also aware about the
environmental considerations of the industries. Gujarat tops the list of Hazardous waste generating states in
India with 42 % contribution to the country’s overall hazardous waste generation. In view of the same, it
had taken steps to establish Common integrated landfill and incineration facilities for treatment & disposal
of solid/hazardous Waste.
2.1.1 Waste Generation and Management in Gujarat
Hazardous waste can be broadly classified into three categories, Incinerable, Recyclable and Landfillabe.
Gujarat is one of the most industrialized states in India, in which industrial growth has been consistently
increased on faster rate over the last decade. 28.76% of India’s total landfillable hazardous waste as well as
26.12% of India’s total incinerable hazardous waste has been generated by industrial units located in
Gujarat. Following table shows Hazardous Waste generated scenario in the Gujarat State.
Table 2-1: Total Hazardous Waste Generation in Gujarat
Type of waste Unit 2006 2007
Landfill MMTPA 0.795 1.137
Incinerable MMTPA 0.106 0.106
Reclyclable MMTPA 0.375 0.524
Total 1.276 1.767 Source: Hazardous waste Inventory as on 31.08.2007- Gujarat state by GPCB
MMTPA – Million Metric Tone per Annum
From table, approx. 60 – 65 landfillable and 5 – 10% incinerable wastes generated which required proper
disposal method which will not harmful to environment.
Currently, Seven Common Hazardous Waste TSDF [Treatment, Stabilization, and Disposal Facilities] and
Six Common Hazardous Wastes Incineration Facilities mentioned below are operated in Gujarat.
The hazardous waste generated by industries in Gujarat cannot be accommodated adequately at the
existing TSDF sites, hence another TSDF site has been proposed at Chanasama village in Chanasma
Taluka & Dist – Patan .The proposed facility is located at Chanasma, Dhanodharda to Ziliya vasna Road
and it will help in the disposal of hazardous waste generated from various industrial premises in and
around North Gujarat and Madhya Gujarat.
2.1.2 TSDF/Incineration Facility in Gujarat
Hazardous waste Facilities in Gujarat as on Decmber-2016 are as follow:
Table 2-2: Common Hazardous Waste TSDF [Treatment Stabilization Disposal and Facilities]
Sr. No. Operator of TSDF Status
1. Bharuch Enviro Infrastructure Ltd, Ankleshwar In Operation
2. Vapi Green Enviro Ltd. Vapi In Operation
3. Nandesari Environment Control Ltd. Nandesari, Vadodara, In Operation
4. Gujarat Maritime Board, Alang, Bhavnagar. In Operation
5. Saurashtra Enviro projects Pvt. Ltd, Bhachau, Kutch In Operation
6. Bharuch Enviro Infrastructure Ltd. Dahej, Bharuch. In Operation
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-8
Sr. No. Operator of TSDF Status
7. Eco care Infrastructures Pvt. Ltd. Dasada , Surendranagar In Operation
8. Naroda Enviro Project Ltd., Odhav, Ahmedabad. Capped and Closed
9. The Green Environment Services Co. Op. Society Ltd. Vatva Ahmedabad. Capped and Closed
10. Gujarat Enviro protection & infrastructure Ltd. Surat. Closed
Source: GPCB website (January 2019)
Table 2-3: HWIF [Common Hazardous Wastes Incineration Facility] in Gujarat
Sr. Operator of CHWIF Status
1. Bharuch Enviro Infrastructure Ltd, Ankleshwar In Operation
2. Nandesari Environment Control Ltd. Nandesari, Vadodara, In Operation
3. Gujarat Maritime Board, Alang, Bhavnagar In Operation
4. Saurashtra Enviro projects Pvt. Ltd, Bhachau, Kutch In Operation
5. Saurashtra Enviro projects Pvt. Ltd, Dahej, Bharuch In Operation
6. Geohybrid Industrial Solutions Private Limited. Plasana,Surat In Operation
7. Gujarat Enviro protection & infrastructure Ltd. Surat. Closed
Source: GPCB website (January 2019)
Apart from above Common TSDFs and Incinerators, there are total 16 Captive Hazardous Waste
Treatment and Disposal Facilities and 72 Captive Incinerators in Gujarat.
2.2 PROPOSED PROJECT
North Gujarat Enviro Projects (NGEP) proposes common integrated TSDF, Incineration facility
comprising of landfill which will cater to environmentally and economically sound disposal of waste
generated in Ahmedabad & North Gujarat region, minimizing long distance haulage of waste. Proposed
facility shall be developed at Survey No. 2482/1, 2482/2, 2486, 2487, 2483/1, 2483/2, 2491/1, 2491/2,
2500, 2499, 2498, 2496/1, 2496/2, 2497, 2502, 2501, 2503, 2506, 2509, 2510, 2523 Vill. – Chanasma, Tal.
– Chanasma, Dist. Patan, Gujarat. As per EIA notification, it is necessary to get Environmental Clearance
(EC) prior to commissioning of the proposed project. For this purpose the application is made for obtaining
the Environmental Clearance.
2.2.1 Need of project
Approx. 22.64 lakh Metric Tonnes of hazardous waste was treated/disposed from 2008-09 to 2011-12, out
of which almost 92% was landfillable; 6.6% was incinerable; 0.9% was landfillable after treatment and
0.6% was co-processed in Gujarat1. There was approx. 150793.65 MMTPA and 30498.99 MMTPA
landfillable wastes generated from Ahmedabad and Vadodara region in the year 2011 – 12.
In recent time Saurashtra and North Gujarat are the new destinations for the Red Category (Polluting)
industrial units in the Gujarat. There are ecologically fragile in terms of prevailing arid conditions and
unique bio-diversity and will have more deleterious impact on the environment due to polluting industries
compared to other regions. Hence, it is most important that hazardous wastes generated from various
industries in and around Ahmedabad, Vadodara and Mehsana district to be disposed in an environmentally
1 GPCB, 2012 report
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-9
safe manner. As a matter of consequence, a need is arising to develop a common environmental
infrastructure to treat and dispose the hazardous waste. The hazardous waste generated by industries may
not be accommodated adequately at TSDF sites operated in Gujarat. Current scenario shows that most of
TSDF sites have been closed or about to reach at their maximum design capacity. With each passing day
industrial waste generation will increase and in absence of proximity to TSDF site, the proposed project is
well justified in meeting the current and increasing waste management demand.
Source: Hazardous waste Inventory as on 31.08.2007- Gujarat state by GPCB
Figure 2-1: Composition of Hazardous Waste Generated in Gujarat
From above figure and detail mentioned in section 1.1.1, it is observed that major landfillable waste
generation in three region of Gujarat state i.e. from central Gujarat, North Gujarat and Kutch region.
Proposed facility at Chanasma located advantageously in centre of all three regions and directly receives
the hazardous waste to be generated from said regions. Considering above scenario project proponent
understand that there is need of common facility to manage hazardous waste. Proposed project developed
by NGEP is Greenfield project having following components,
• Landfill of 7,82,181 MT overall capacities, to be developed in cellular fashion, in phase-wise.
• Incinerator of 1 MT/Hr.
2.2.2 Justification of Project site
Project site has been finalized after detailed study of site alternative. Although following points are justify
the selected project site,
• Well established transportation network2
• No R & R will be required; as no displacement of settlement.
• Sensitive environmental locations like national park or wildlife Habitats, reserve forest, coral reef,
sanctuary is not fall within 10 km radial distance from project site.
• Easy availability of skilled and unskilled manpower from nearby area
2 Although strengthening of existing road (approx. 2.63 km) and development of road (approx. 1.00 km) to assess project site will
be required.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-10
2.2.3 Project location
Project site is located at 23°41'18.31" North latitude and 72° 8'36.02" East longitude. Location map
showing project site is depicted as Figure 2-2 Short view of the project site on Google earth is depicted as
Figure 2-3. Plant layout shows detail of entry, exit, internal road, waste storage area, land fill and process
area, greenbelt, treatment area, admin and laboratory, observatory well etc. and the same is depicted as
Figure 2-4. Topography map of 10 km radious from the project site is given as Figure 2-5
Figure 2-2: Location Map
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-11
Identification Latitude Longitude
23°41'18.31"N 72° 8'36.02"E
A 23°41'26.42"N 72° 8'30.52"E
B 23°41'23.68"N 72° 8'31.69"E
C 23°41'20.44"N 72° 8'33.15"E
D 23°41'21.39"N 72° 8'36.82"E
E 23°41'24.87"N 72° 8'36.27"E
F 23°41'25.37"N 72° 8'37.80"E
G 23°41'24.81"N 72° 8'38.73"E
H 23°41'25.18"N 72° 8'43.40"E
I 23°41'19.74"N 72° 8'43.77"E
J 23°41'19.46"N 72° 8'43.04"E
K 23°41'15.83"N 72° 8'43.45"E
L 23°41'15.59"N 72° 8'41.62"E
M 23°41'19.24"N 72° 8'41.22"E
N 23°41'19.16"N 72° 8'39.73"E
O 23°41'17.02"N 72° 8'39.81"E
P 23°41'16.16"N 72° 8'34.84"E
Q 23°41'13.81"N 72° 8'35.29"E
R 23°41'14.63"N 72° 8'39.84"E
S 23°41'12.67"N 72° 8'40.40"E
T 23°41'10.93"N 72° 8'39.87"E
U 23°41'10.32"N 72° 8'37.99"E
V 23°41'9.88"N 72° 8'35.64"E
W 23°41'12.38"N 72° 8'34.60"E
X 23°41'12.04"N 72° 8'32.79"E
Y 23°41'23.09"N 72° 8'29.91"E
Z 23°41'26.00"N 72° 8'29.15"E
Figure 2-3: Google image showing the project site
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-12
Kuchcha Road Access to PS Kuchcha Road Access to PS
Junction of Zilliyavasana village road & approach road
connecting PS
Project site with existing trees
Project site Irrigation surrounding PS through Narmda canal water
Berry shrubs on the way to PS Cotton crop near to PS
Photograph 2-1 Project Site Photograph
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-13
Figure 2-4: Plant Layout
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-14
Figure 2-5: Topography Map Showing 10 km Radius Study area of Project Sit
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-15
2.2.4 Project Site History
Proposed project will be developed at Chansma village. Project site history with respect to various
environmental attributes are described as under,
2.2.4.1 Topography
Toposheet no. 46 A/1 and 46 A/2; issued by Survey of India covered the project site and 10 km radial area.
The entire study area is almost flat and no hilly area observed. Maximum elevation above Means Sea Level
is 61 mtr. Major physiography of Patan district is Alluvial plain and Rann. It is found that major soil of
area is sandy, saline and alkaline soils. No electrical/ high tension line passes through the centre of
proposed project area.
2.2.4.2 Seismic Zone
The latest version of seismic zoning map of India given in the earthquake resistant design code of India [IS
1893 (Part 1) 2002] assigns four levels of seismicity for India in terms of zone factors. The map shows that
proposed project site fall under Seismic Zone – IV, which is the considered to be the high seismic zone.
Precautionary measures as per guideline will be considered during detailed engineering design of TSDF
site.
Figure 2-6: Earthquake hazard zone map of India
2.2.4.3 Land use
Land use of project site and surrounded area is prominently of agricultural land (80% of study area) with
very less industrial set up. Agriculture land is single crop and major crops are cotton, wheat, bajara, fennel
(Variyali), Rapes (Aerando), Muster, isabgul, cowpea, other cereal and grams etc. 8% of study area is
waste land, while remaining are water bodies and built-up land. During the project site visit by FAEs in the
month of October – 2018, it was obaserved that agricultural activities is being carried out by villagers at
surrounding the project site as well as all the locations visited.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-16
2.2.4.4 Hydro-geology
Major water bearing formation of Patan district is quaternary alluvium. Phreatic aquifer (is the area in an
aquifer, below the water table, in which relatively all pores and fractures are saturated with water) of
study area and surroundings is 1.7 to 32.01 DTW in pre-monsoon while in post monsoon it is 1.0 to 20.98
DTW. Ground water is available at depth 40 – 618.9 mtr, while discharge is 6 – 2616 LPM. Chansma is
fall under over exploited zone of GW. The surface water resources is very limited at and around the PS.
Ground water is major and only source of irrigation, but GW found in the area is predominantly high in
bicarbonate and floride3. Quality of groundwater (ground level to 100 m or more) is not good i.e. mixed
(saline/marginal/slightly saline/good) as per existing sources in core/buffer zone of studied area. As per
inventory groundwater quality becomes highly variable upto deeper depth. Ground water movement is
towards south west and south west west area which is towards little Rann and ultimately to Gulf of
Kachchh. The site is very sensitive from environmental point of view due to highly permeable sub strata.
2.2.4.5 Drainage pattern
Rivers Banas, Khari and Umardasi drain part of the Patan district. All are Ephemeral and non-perenial
rivers in nature. It flows only during good monsoon years. Major part of the Patan districts is devoid of any
drainage network and do not falls in any catchment area. Origin of Rupen River is Tunga hill and end in
the small desert of Katchhchh. Puspavati and Khari is the tributary of Rupen River and flowing within the
study area of proposed project.
2.2.4.6 Flood Scenario
Good monsoon is main source of water in rivers located in the study area and only due to heavy monsoon
brings floods in the river basin. Average rainfall data during 2006 to 2015 for Patan district shows that it
hardly gets 654 mm rain only4. There is no flood history in Chansma last decade.
2.2.4.7 Environmental Sensitive Receptor
S.
No Sensitive Receptor Distance and Direction w.r.t. PS
A Social Infrastructure
Habitation Ziliyavasna village (Population – 709 nos.) at 1.45 km in E direction.
Local Market None within 2 km radius of the project site.
Religious Place • Amba mata temple in Ziliyavasna Village at 1.45 km in E direction.
• Ancient Temple of Nilkantheshwar Mahadev in Jasalpur Village at 3.0
km in NNW direction.
• Religious activities (every punam, salgiri etc.) are frequently performed
at both the places.
Primary School Primary School (approx. 85 students) Ziliyavasna Village at 1.45 km in E
direction.
B Historical Places/
Monuments
Non within 10 km radius of the project site.
C Environmental
Agriculture Land Surrounded by single crop agricultural land
Public Park None within 2 km radius of the project site.
Lake or pond Karoda Lake at 1.60 km in WSW Direction
Critical habitat area Non within 10 km radius of the project site.
3 GW broucher of Patan District, March – 2014 4 Ground water year book (2016 – 170 Gujarat state, March – 2018
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-16A
Based on CPCB & MoEF guidelines for Hazardous waste landfill site (Criteria for hazardous Water Landfills, February 2001), proposed TSDF site is analyzed in addition to above environmental sensitive receptor and details are mentioned as under.
S. No
Site location Criteria as per CPCB Guideline Remarks
1 Lake or Pond No landfill shall normally be constructed within 200 m of any lake or pond.
Nearest lake (Karoda Lake) is at 1.60 km in WSW Direction
2 River No landfill shall be constructed within 100 m of a navigable river or stream.
• No Navigable river within 5 km radius. • Non-perennial Khari river is at 2.22 km
in E direction and Pushpavati river is at 8.12 km in SSE direction.
3 Flood plain Not in flood plain
4 Highway No landfill shall be constructed within 500 m of the right of way of any state or national highway
• Nearest State Highway (SH-7) is at 1.38 km in WSW direction.
• State Highway (SH-55) is at 2.36 km in NE direction.
• Nearest National Highway (NH 15) is at 43.31 km in NW direction
Habitation A landfill site shall be atleast 500 m from a notified habitated area A zone of 500 m around a landfill boundary should be declared a no-deveiopment buffer zone after the landfill location is finalised.
Nearest habitation (Ziliyavasna Village) is at 1.45 km in E direction.
6 Public parks No landfill shall be constructed within 500 m of a public park.
None
7 Critical Habitat Area No landfill shall be constructed within critical habitat areas including reserved forest areas.
• Jessore Sloth Bear Sanctuary is situated at 84.09 km in NNE direction.
• Balaram Ambaji Sanctuary is located at 61.76 km in NNE direction
8 Wetlands No landfill shall be constructed within wetlands.
None
9 Airports No landfill shall be constructed within a zone around Airports as notified by the regulatory authority or the aviation authority
• Nearest airport - Mehsana Airport is at 23.8 km in ESE direction and Ahmedabad Airport is at 84.7 km in SE direction
10 Water Supply Well No landfill shall be constructed within 500 m of any water supply well
None within 500 m radius
11 Coastal Regulation Zone No landfill shall be sited in a coastal regulation zone.
None
12 Ground water table level No landfill shall be located in areas where the ground water table will be less than 2 m below the base of the landfill
Ground water table is more than 20 m Below GL.
13 Other Criteria - Presence of monuments / religious structures • Rani ki Vav is located at 15.33 km in NNW direction.
• Sahastralinga Talao located at 17.91 km in NNW direction
• Jami Masjid is situated at 14.63 km in North direction
• Modhera Sun temple is located at 12.33 km in South direction
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-17
2.2.5 Salient Feature
Defense installation, critically polluted area, protected area notified under the Wild Life (Protection) Act
(1972) & Eco-sensitive area notified under Section 3 of the Environment (Protection) Act- 1986 are not
located within 10 km radius of the project site as per topo-sheet obtained from Survey of India (SOI) and
available secondary data. Key infrastructure like National Highway, State Highways, other roads with the
railway lines etc and Environmental settings like river, water bodies, forest, monuments, heritage palces
around the project site is mentioned in Table 2-4.
Table 2-4: Key Feature around the Project Site
No. Description
From Project Site
Remarks Distance
(km)
Direction
1. National High Way (NH 15) 43.31 NW -
2. State High Way (SH-7) 1.38 WSW -
State High Way (SH-55) 2.36 NE -
3. Railway Station (Chansma) 4.0 NNW -
4. Airport (Ahmedabad) 84.7 SE -
5. River (non-perennial river)
Pushpavati River 8.12 SSE Nr. Mahadevpura village
Khari River 2.22 East Nr. Zilliyavasana village
Karoda Lake 1.60 WSW In Karoda village
6. Sea (Gulf of Khambhat) 203.9 South -
7. Village (Ziliyavasna village) 1.45 East Population – 709 nos.
8. City (Chansma) 4.0 NNW -
9.
Heritage site/ Archeological Site
12.33 South Modhera Sun Temple
15.33 NNW Rani ki Vav
17.91 NNW Sahastralinga Talao
14.63 North Jami Masjid
10. Reserve Forests Non within 10 km radius of the project site.
11. National Park/Wild Life Sanctuary Non within 10 km radius of the project site.
12. Bird Sanctuary Non within 10 km radius of the project site.
13. Eco Sensitive Area Non within 10 km radius of the project site.
14. Industries in surrounding Non within 2 km radius of the project site.
2.3 PROJECT SIZE
Proposed TSDF landfill of capacity 7,82,181 MT and incinerator of capacity 1 MT/Hr. to be developed at
Chansma village. It is assume that hazardous waste disposal in landfill cell and incineration of waste will
be carried out for 16 hr. per day respectively. Landfilling activities will be closed during the monsoon
period; hence it will be in operation for 8 months i.e. 240 days while incineration will be continue
throughout the year except maintenance.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-18
2.3.1 Justification for capacity
There was approx. 150793.65 MMTPA and 30498.99 MMTPA landfillable wastes generated from
Ahmedabad and Vadodara region in the year 2011 – 125. Based on secondary data available for hazardous
waste generation data, it is expected that more than 40000 MTPA hazardous waste will be received by the
proposed project, even after considering capacity of existing common facilities in Gujarat.
Engineering design of proposed TSDF cell has been done considering life span of 20 years.
2.4 PROJECT COMPONENT
Proposed integrated waste management facility comprises of mainly following two components
• Landfill cells
• Incinerator
Other facilities associated with above components are as follows:
• Security and Administrative office equipped with walkie-talkie, internet and other amenities
• Laboratory with latest equipment
• Waste reception area
• Weigh bridge
• Wheel wash facility
• Covered shed for intermediate waste storage (pre-treatment)/ Temporary waste storage
• Waste stabilization facility
• Storm water drain network
• Internal RCC roads and approach road
• Workshop for maintenance (machinery, vehicles, electrical maintenance etc.)
• Sanitation and drinking water facilities
• Observatory well for ground water monitoring
2.5 LAND FILL
A landfill is a site for the disposal of waste by burial. It is a carefully designed and monitored structure that
isolates wastes with the help of a bottom liner and daily covering of soil from the surrounding environment
i.e. groundwater, air, rain etc.
2.5.1 Component of Landfill
The main components of any secured, permitted landfill are bottom liners, landfill cells, Leachate
collection system, storm water drainage etc and it is described in respective sections.
2.5.1.1 Bottom Liner
The bottom liner separates and prevents the buried waste from coming in contact with underlying natural
soils and groundwater. Bottom liners are generally constructed using durable, puncture-resistant synthetic
plastic HDPE (High Density Polyethylene).
2.5.1.2 Cells
This is the area in a landfill that has been constructed and approved for disposal of waste. It is proposed to
develop four cells of 13133 sq.mtr; 12009 sq.mtr; 13486 sq. mtr; and 11274 sq. mtr. area respectively
considering total 200 MTPD waste received at the landfill. Inside larger cells there are smaller cells
known as the daily workface, or sometimes referred to as cells. This is where the waste coming into the
5 GPCB report 2012
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-19
landfill for disposal that day is prepared by placing the material in layers or lifts where the waste is then
compacted and shredded by heavy landfill compaction machinery.
2.5.1.3 Leachate Collection System
Landfill is typically designed in such a way so that the bottom surface of the landfill is sloped to a low
point from where any liquids (leachate) that are trapped inside the landfill are collected and removed from
the landfill. Leachate collection system typically consists of a series of perforated pipes, gravel packs and a
layer of sand or gravel placed in the bottom of the landfill. Once the leachate is removed from the sump, it
is typically pumped or gravity-flowed to a holding tank or pond, where it is either treated on site or hauled
off site to wastewater treatment facility.
Rain falling on active landfill area is collected separately via leachate collection system or sump and
treated it as Leachate only.
2.5.1.4 Storm Water Drainage
This is an engineered system designed to control water runoff during rain or storm events and manage it in
such a way so that it does not drain into the landfill cell from surrounding area. Further water logging or
ponding on landfill covers can be avoided. Surface runoff is directing in channels though culverts and
design in such a way so that the runoff water flow is slowed down or held long enough to allow the
suspended soil particles to settle out before the water is discharged for treatment. Strom water drainage
requires a low permeability lining to prevent leakage in to the landfill.
2.5.1.5 Gas Collection System
Hazardous waste/inert wastes are proposed to be disposed at TSDF site from their landfill gas is generated
due to presence of VOCs in the wastes. Almost at all HW landfill site gaseous emission are anticipated, but
it is not significant. For removal of landfill gases a series of pipes (HDPE perforated vent pipes 50 mm dia)
at every 50 m distance either ways are embedded within the landfill. These pipes shall be connected at the
top of the waste body after closure and a vent shall be provided at top for monitoring of generation of vent
gases if any after closure.
2.5.1.6 Cover (or cap)
Wastes placed in a cell is required to be covered daily with either compacted soil or an alternative daily
cover i.e. application of spray-on cover materials(foam, flame-retardant fiber material etc.); large panels of
tarpaulin-type material that is laid over the waste at the end of each day and removed the next day before
waste is placed. Covering (or capping) is performed in order to isolate the waste from exposure to the air
and to control odors. When the landfill filled upto its capacity, it is permanently covered with a
combination of a layer of polyethylene plastic, compacted soil and a layer of topsoil that will support
growth of vegetation to prevent erosion.
Establishment of a solar power generation farm over final cover will also be explored and if found suitable
Solar panels will be installed to generate power and transfer to grid.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-20
Figure 2-7: Detail of Landfill Cell
2.6 INCINERATION
Wastes having high calorific values is directly incinerate without any pre-treatment at site. 1 MT/Hr
incinerator is proposed considering daily waste receipt of 16 MTPD. Incinerator will be operating for day
time in two shifts. The incinerator consists of following components,
1. Feed section : Feed tank and Heaters
2. Incineration system consist of Primary chamber (Rotary kiln), Secondary chamber, Mixing
chamber/Quench chamber, Waste heat recovery system and Force evaporation (Liquid quenching)
3. Flue gas treatment installing Multi-Cyclone, three stage scrubber and Mist eliminator, finally vent
through chimney
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-21
Figure 2-8: Flow diagram of incinerator
Process Description of Incineration System
� Primary and secondary chamber
• Incinerator system shall consist of primary chamber and secondary combustion chambers in series,
followed by quenching section. Both the combustion chambers shall have refractory lined self-
supported structure. Primary chamber burner and secondary chamber burner shall fire the liquid fuel,
when required. Primary and secondary chambers are wall mounted burners. Air blowers, supply
combustion air to these burners and liquid waste atomizers. Fuel oil flow will be regulated to maintain
the temperature inside the furnaces, with help of modulation control panel
• Combustion air flow will be regulated by manually operated air flow dampers. Temperature in primary
chamber will be maintained at about 800 – 900 ºC.
• Burners will be provided with flame detector, which controls flame and burner for safe and automatic
operation. Liquid waste shall be injected using pumps through nozzle into primary chamber. Atomizing
air will be supplied to it which will helps in proper combustion of the waste. The nozzles shall be
supplied with air to avoid any damage, which also helps for efficient combustion. Primary combustion
chamber, which is a rotary kiln, also has a solid waste charging system with double door automatic
feeding system to ensure safety of a person and equipment as well.
• The flue gases from the primary chamber travel to the secondary chamber which will be further heated
beyond 1150 ºC with help of burner and air supply for complete combustion. The secondary chamber
will be designed in such a way that the residence time of flue gas coming from primary chamber will be
more than 2 sec.
• Ash generated in the incinerator shall fall at the rear end of primary chamber (Rotary Kiln) in ash
collection pit and at the bottom of secondary combustion chamber, which shall be removed periodically
by opening ash removal door at side for its further disposal to a secure landfill site.
• All the operating parameters will be controlled and monitored by PLC based SCADA system.
• Sight glass near burner assembly and minimum two no. of peep holes will be provided in primary
chamber and secondary chamber as well. With help of which, the flame and chamber can be seen from
both the chambers
• Both the chambers will be provided with refractory bricks which can withstand approx. 1500 ºC.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-22
• Explosion window with vent pipe will be provided in both the chambers for safety of the equipment
and personnel, to release the flue gases to safe location and avoid backfire in case of any eventuality of
pressure rise.
� Quench chamber
• Quenching chamber is provided to quench the flue gas to desirable temperature by adding fresh air. The
air is being fed with quench air blower and flow rate is controlled by controlling the blower speed with
help of VFD.
• Quenching system will be placed at the first stage of an APCS to reduce temperature of flue gas after
secondary chambers immediately from 1200 ºC to 500 ºC. Gas quench system includes use of cooling
blower. Apart from this due to quenching formation of furans and dioxins will be eliminated.
� Flue gas treatment system
Flue gases after getting cooled in quenching chamber and waste heat recovery section; it will be passed
through series of multi cyclones and scrubbed in three stages scrubber.
2.7 HANDLING OF HAZARDOUS WASTE
All hazardous wastes listed under Schedule – I of Hazardous and Other Wastes (Management and
Transboundary Movement) Rules, 2016 and amended thereafter will be received and treated at proposed
project. Hazardous wastes acceptance criteria mentioned in following section should be strictly followed
by member industries and waste will be accept only after confirmation of compliance with criteria. List of
hazardous waste with source of generation from various industries is attached as Annexure – 2 with EIA
report.
2.7.1 Hazardous waste acceptance criteria
Waste generator member industries should have authorization for disposal of hazardous waste. At the time
of obtaining membership, Waste generator industry carry out comprehensive analysis of solid/hazardous
waste and the same waste will be accepted at TSDF after physical/chemical verification. Criteria for
acceptance of hazardous wastes6 for direct disposal to secured landfill are mentioned in Table 2-5
Table 2-5: Hazardous waste acceptance criteria
Leachate Quality Concentration
pH 4-12
Total Phenols <100 mg./l.
Arsenic <1 mg./l.
Lead <2 mg./l.
Cadmium <0.2 mg /l.
Chromium-VI <0.5 mg./l.
Copper <10 mg./l.
Nickel <3 mg./l.
Mercury <0.1 mg./l.
Zinc <10 mg./l.
Fluoride <50 mg./l.
6Table – 6 from Protocoal for performance evoluation HAZWAMS
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-23
Leachate Quality Concentration
Ammonia <1,000 mg./l.
Cyanide <2 mg./l
Nitrate <30 mg./l
Adsorbable organic bound Chlorine <3 mg./l
Water soluble compounds except salts <10 %
Strength
Transversal Strength (Vane Testing) >25 KN/m2
Unconfined Compression Test >50 KN/m2
Axial Deformation <20 %
Degree of Mineralization or Content of Organic Materials (original sample)
Annealing loss of the dry residue at 550o C <20 Wt. % (for non- biodegradable waste) <5
Wt. % (for biodegradable waste)
Extractable Lipophylic contents (Oil & Grease) <4 Wt. % Note:
1) leachate quality is based on water leachate test i.e Leachability tests are conducted by preparing a suspension of waste and water i.e taking
100 gm of waste and filling up to 1 liter with distilled water, stirring or shaking for 24 hrs, filtering the solids and analyzing the filtrate.
2) Calorific value of the land disposable hazardous waste should be less than 2500 K. Cal/Kg
Engineering design of proposed TSDF site has been done considering above criteria as well as following
parameters,
• Moisture ≤ 20%
• Calorific value ≤ 2500 Kcal/Kg.
• Biodegradable organic matter ≤ 5%
• Total organic conternt ≥ 20%
• Waste amenable to stabilization
• High TDS Effluent (for incinetation)
2.7.1.1 Weighing and sampling
Dedicated vehicles with rubber liners for hazardous waste collection will be allowed to enter in project
site. Weighing of vehicles will be done at weigh-bridge and samples from three different locations shall be
taken to prepare composite sample for quick analysis of parameters like color; odour; moisture; pH; TOC;
flammability etc. Waste sample shall be OK on desire results and vehicles allowed for waste disposal.
If any waste consignment is not meeting the waste acceptance criteria, it will be either returned to the
waste generator industries or taken for appropriate pre-treatment like neutralization / stabilization etc. after
obtain consent for waste generator unit.
2.7.2 Pre-treatment of hazardous waste
If landfillable waste does not meeting the waste acceptance criteria than various pre-treatment of waste
shall be applicable on receipt of consent from waste generator. On completion of pre-treatment, waste is
disposed to TSDF site. In case of incinerable hazardous waste not meeting the waste acceptance criteria
than it will be return to waste generator.
2.7.2.1 Stabilization of waste
Stabilization of waste is a process to convert hazardous wastes in the form of non-aqueous liquids, semi-
solids or reactive solids into less leachable solids that can then be deposited directly into the secured
landfill.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-24
Any waste reject after analysis will be transferred to waste stabilization area. For stabilization of hazardous
waste for secured landfilling, a mechanized closed conveyer system to carry the waste up to stabilization
area will be installed. Hazardous waste is mixed with typical reagents like lime, flyash, bentonite (clay),
cement, saw dust, etc., in combination with sodium silicate solution, if required to create additional binding
properties of the wastes at separate mechanized mixing unit having suction duct/hood, scrubber system and
stack. After completion of mixing, waste is allow to cure for appropriate time. After curing again waste is
analysed as per waste acceptance criteria and if sample found OK than it will finally disposed to TSDF.
2.7.2.2 Neutralization of waste
Addition of effective neutralizing agents into waste to achieve desire range of pH, then it will send to
TSDF cell for disposal or temporary waste storage shed.
2.7.2.3 Alternative use of waste
The waste not meeting the waste acceptance criteria either landfill or incineration will be return to waste
generator. Further guidance will be given to waste generator for conducting feasibility study for alternative
use of waste so that it can be utilized in other industries.
2.7.3 General Pathway of the waste
Waste received at landfill site can be handled in different ways i.e.,
1. Direct disposal into landfill
2. Pre –treatment (stabilization; neutralization) of wastes and then disposal into landfill
3. Direct incineration
4. Pre-treatment incineration and disposal of incineration ash in landfill
5. Waste processed for fuel/industrial by-products for recycling
6. Others
Depending upon the characteristics of waste and the reactivity of the wastes with each other as well as with
the liner system, the wastes which could be allowed are identified. General pathway of landfill waste from
receives to safe disposal is described below:
• Comprehensive analysis of the wastes – Laboratory facilities
• Decision of waste pathway i.e. Pre-treatment/ storage/disposal
• Collection of wastes from waste generator industries and its transportation to TSDF site
• Waste received at TSDF site.
• Weighing and recording of waste receipt.
• Representative waste sampling and finger print analysis
• Storage at the temporary storage area.
• Waste confirmation w.r.t. waste acceptance criteria
• Secure landfilling of waste.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-25
Figure 2-9: General Pathway of the waste
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-26
2.8 HAZARDOUS WASTE TRANSPORTATION
Transportation of the waste from generator to TSDF site is most important aspect as hazardous waste may
have toxic, flammable, explosive or corrosive characteristics. Hence, transportation of hazardous waste has
to be done in such a way so that it does not cause any risk to health as well as impact on environment
during transportation and handling.
Hazardous waste generators ensure that the packaging and method of transport determines the safety of
hazardous wastes during the transit without any accident or spillage. There is high risk of waste spillage
during waste loading, transportation and unloading.
Dedicated and specially designed vehicles with hydraulic unloading mechanism; linner coated with epoxy
resin and "HAZARDOUS WASTE" will be displayed in bold red letters on a fluorescent yellow
background. The vehicle to be used for the hazardous waste transportation will not be used for any other
purposes. RTO registration numbers of vehicles involved in waste transportation will be shared with
GPCB. Transporters authorized by TSDF shall be allowed to transport waste and he will ensure that at
least two dedicated vehicle shall be maintained/made available to TSDF for emergency situation. Project
authority will also make such provision of spare vehicle to handle emergency.
The transporter and manpower involved for waste transportation shall be trained for awareness about rules,
guidelines, procedure for loading and unloading of waste, safety during waste handling; proper and rapid
identification of emergency and its effective control; emergency response etc. Only after successful
completion of training, transporter will be selected.
Waste to be received at site is expected to be around 200 MTPD on average basis and max. 20 – 25 trucks
will be deploying during operation phase. Packaging, labeling of individual containers and transportation
of hazardous wastes will be done as per provision made in Hazardous and Other Wastes (Management and
Transboundary Movement) Rules, 2016 and amended thereafter.
2.8.1 Packing
Hazardous waste generator will ensure that waste packing containers must be durable to withstand worst
handling practice (jerks and vibrations caused by uneven road surface); leakproof sealing and retain for at
least six month. Mild steel container with suitable corrosion-resistant coating; 200-litre plastic drums;
cardboard cartons, PP and HDPE/LDPE containers, etc., are may be used based on variety of wastes.
2.8.2 Labelling
All hazardous waste containers must be clearly labeled showing all required contents as per Form – 8 of
Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016 and amended
thereafter. Containers storing hazardous waste shall be labeled with the words “HAZARDOUS WASTE”
in vernacular language, Hindi/English. The label shall be of non-washable material, weather proof and
easily visible. The waste generator unit shall provide information in Form 9 [Transport Emergency
(TREM) card] of Haz. waste rule to the transporter. Emergency contact numbers shall be prominently
displayed viz. the phone number of concerned Regional Officer of the SPCB/PCC, Fire Station, Police
Station and other agencies concerned in the label.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-27
2.8.3 Manifest System
Safe transportation of hazardous waste to the TSDF is a collective responsibility of the waste generator,
operator of a facility for treatment and disposal of hazardous waste and the transporter. There is Manifest
system (Movement Document) for hazardous and other waste transportation to be used within the country.
Waste generator unit shall prepare seven colour copies of the manifest (as per Form – 10 of Haz. Rules –
2016) in which each colour code indicated purpose is mentioned in below table. All seven copies shall be
signed by the sender.
Table 2-6: Manifest System
Manifest copy Purpose
Number Colour
1 White To be forwarded by the sender to the State pollution Control Board after signing
all the seven copies.
2 Yellow To be retained by the sender after taking signature on it from the transporter and
the rest of the five signed copies to be carried by the transporter.
3 Pink To be retained by the receiver (actual user or treatment storage and disposal
facility operator) after receiving the waste and the remaining four copies are to
be duly signed by the receiver
4 Orange To be handed over to the transpoter by the receiver after accepting waste.
5 Green To be sent by the receiver to the state Pollution Control Board.
6 Blue To be sent by the receiver to sender
7 Grey To be sent by the receiver to the State Pollution Control Board of the sender in
case the sender is in another state
2.9 PROJECT PHASE
Secure landfill site will be developed phase-wise in cell while incinerator will be installed as per project
scheduled. Activities based on project stages has been identified and described in respective section.
2.9.1 Pre-construction Activity
There is no major cutting at proposed project site as it is located almost on flat terrain. Any clearance of
vegetation is not expected. Existing tree shall not be disturbed during the construction activities as it will
be a part of proposed greenbelt area. Hence, there is no case of tree cutting.
There is no direct accessibility to project site from state or internal road. SH – 7 and SH – 55 is located
1.38 km and 2.36 km from the project site. There is no direct accessibility to project site from SH. It is
observed during site visit that approx. 1.7 km single lane black top bitumen internal road of Zilliyavasan
village is passing nearby (700 mtr.) the project site. It needs to be strengthening to access the project site.
Further, from internal village road approx. two km road shall be developed to access the project site.
2.9.2 Construction Activity
Building a new landfill cell involves various stages of construction and it is meticulously engineered
practice in the ground. The landfill is divided into cells or designated areas where the land will be prepared
for trash disposal. Project site is fall under seismic zone – IV, which is the considered to be the high
seismic zone and engineering design of SLF cell will be done considering seismicity of the area. Following
steps are involved in construction of landfill cell.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-28
• Excavation (digging) down to the bottom of the sub-grade.
• Excess material (mostly clay) hauled to on-site stock pile.
• Cell is smoothed and laying of impervious liners at bottom and side slope of cell
• Pipeline installation for leachate and gas collection
• Ramp/access road to cell for waste disposal
Proposed SLF will be developed in phase-wise means second cell will be developed only after cell is filled
to its full capacity. Excavated soil generated due to construction of cell will be properly stored with in
premises and will be reused in construction of bunds, daily waste cover and final cover of the cell as per
requirement.
In addition to above, following structure will be developed.
• Fencing and/or construction of compound wall around the perimeter of site in the interests of security and
public safety.
• Construction of weigh bridge cabin
• Construction of administrative office, Watchman cabin, laboratory etc.
• Construction of internal roads
• Earth Moving Equipment Shelters
• Temporary waste storage, treatment & disposal sites for special wastes
• Water supply facility (bore well)
• Electricity supply system
• Construction of observatory well (Monitoring wells)
• Construction of surface water drainage system
• Green belt
Construction materials like steel, cement, crushed stones; sand, rubble, etc. will be procured from the local
suppliers.
2.9.3 Technical detail of landfill cell
The depth of excavation and height of embankment construction have been considered based on site
constraints and depth of ground water table. Approximately 49,902 sq.mtr. area are allocated for the
construction of secured landfill cells (4 nos.) having height of approximately 15 m (below ground 10 m
and above ground 5 m) and total 7,82,181 MT landfilling is planned as phase wise manner.
Pre-construction soil testing and geophysical investigation has been conducted and based on that designed
is proposed. However no. of cell, height (below ground & above ground), will be decided considering
actual geohydrological features of the site. Design calculation considering maximum capacity of the
proposed landfill site is given in following table:
Table 2-7: Technical Design of Landfill
Sr.
No. Technical Specifications Value
1 Total waste filling landfill area 49902 m2
2 Volume of waste to be disposed 651352.6 m3
3 Quantity of waste to be disposed 7,82,181 MT
4 Bulk density of compacted solid waste 1.2 MT/m3
5 Height of waste bund above GL 7 meters
6 Depth of Excavation 12 meters
7 Waste application height (total) 15 meters
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-29
Sr.
No. Technical Specifications Value
8 Total height of landfill 19 meters
9 Bottom Slope (Traverse) 3%
10 Leachate drainage slope (Longitudinal) 1.5%
11 Inner side slopes of Embankment 1:2 (V:H)
12 Outer side slopes of Embankment 1:3 (V:H)
13 Total no of cell 4
14 Observatory wells Three
Above landfill has been design considering guideline under criteria for hazardous waste landfill, although
this will be finalized during the detailed engineering phase of the facility considering geological aspects.
2.9.3.1 Liners and Final Cover
1.5 mm thick High Density Polyethylene (HDPE) geomembrane will be used in the construction of secured
landfill site. The membrane will consist of single resin being one hundred (100%) virgin and of a narrow
molecular distribution Carbon black will be added to the resin for ultra violet resistance. The flexible
membrane will be purchase to the following approximate ratio; HDPE 97.5% and carbon black 2.5%.
Different impervious layers at the bottom and side of the cell as well as once cell will reach its full capacity
final cover will be laid down as per guideline. Technical information of liners is mentioned in following
Table 2-8.
Table 2-8: Liner Design
Sr
No.
Description Technical information
1
Bottom liner 1st layer from
bottom
450 mm thick compacted clay layer as secondary composite
liner (Permeability co-efficient, k ≤ 10-7
cm/sec)
2nd
layer ≥ 1.5 mm thick HDPE geomembrane lining
3rd
layer ≥ 300 mm thick sand layer (Secondary Leachate collection)
(Permeability co-efficient, k ≥ 10-3
cm/sec)
4th layer 450 mm thick compacted clay layer as primary composite liner
(Permeability co-efficient, k ≤ 10-7
cm/sec)
5th layer ≥ 1.5 mm thick HDPE geomembrane lining
6th layer ≥ 300 mm thick sand layer (Primary Leachate collection)
(Permeability co-efficient, k ≥ 10-2
cm/sec)
2 Side Liner 1st layer from
bottom
450 mm compacted clay
2nd
layer ≥ 1.5 mm thick HDPE geomembrane lining
3rd
layer 450 mm thick compacted clay layer
(Permeability co-efficient, k ≤ 10-7
cm/sec)
4th layer ≥ 1.5 mm thick HDPE geomembrane lining
5th layer 450 mm compacted clay
3 Top liner 1st layer from
bottom
Regular Soil Layer (300 mm) – optional
2nd
layer 600 mm thick compacted clay layer as single composite barrier
(Permeability co-efficient, k ≤ 10-7
cm/sec)
3rd
layer ≥ 1.5 mm thick HDPE geomembrane lining
4th layer 300 mm thick drainage cover
5th layer 600 mm thick top soil
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-30
2.9.3.2 Final Cover After completion of landfill, a final cover will be laid to minimize infiltration and erosion. A final cover
system is provided at the top of landfill, which will enhance surface drainage, prevents infiltrating water
and support vegetation or installation of solar panel for power generation facility.
Section details of bottom and top liner of cell is shown as Figure 2-10 and Figure 2-11
Figure 2-10: Bottom liner
Figure 2-11: Final cover
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-31
2.9.4 Operation Phase
Proposed project is waste management facility; hence receiving of hazardous waste, its storage and
disposal after treatment is main operational activities. The facility shall operate only during day hours
throughout the year except monsoon season.
Following are routine activities of TSDF site,
• Transportation of hazardous waste from member industries to the landfill site.
• Accepting hazardous wastes like ETP sludge, Gypsum/Lime sludge, Iron Sludge, Incinerator Ash, Brine
Sludge, etc. at TSDF only from the generator authorized by SPCB/PCC.
• Quick analysis (fingerprinting analysis) of hazardous waste on receipt.
• Stabilization of hazardous waste – as applicable.
• Compaction of hazardous waste as per Central Pollution Control Board (CPCB) specification.
• Installation of intermediate and final covers.
• Leachate collection and Treatment at the site.
• Effluent Treatment Plant (ETP) for treatment of wastewater at the site.
• Ensuring waste treatment and/or disposal as per Hazardous Rules, 2016and as amended.
• Operation of incinerator and APCM
• Undertake cleanup operation in case of contamination resulting from the site.
2.9.4.1 Action Plan during Monsoon
15 days before onset of monsoon, landfill cell will be covered with impervious layer As per CPCB /
MoEFCC guidelines, to avoid contact of rainwater on the waste body. Topography of site is not prone to
any flooding. However guard pond of 500 m3 will be provided for any emergency. The run-on during this
period due to unexpected rain, shall be directed to guard pond and shall be gradually taken to ETP for
treatment and/or evaporated through spray dryer.
Impervious layer will be reopened 15 days after end of monsoon season.
2.9.5 Closure of landfill cell
Once landfill cell reach its full capacity, cell will be closed with final cover as mentioned in Section 2.9.3.1
Following interconnectivities are established.
• The leachate collection system of each cell/phase shall be sequentially connected.
• The surface water drainage system at the cover of each cell/phase shall be sequentially connected.
• The temporary surface water drainage system constructed at the base of each completed phase shall be
dismantled.
• The gas collection system of each phase shall be sequentially connected.
Upon completing of all phases a final check shall be made of the proper functioning of all inter connected
systems. An access road shall be provided on the landfill cover to enable easy approach for routine
inspection of the landfill cover. After completion of the phase long term vegetative stabilization will be
undertaken to return the land to its original and natural vegetative landform.
2.10 GENERAL GUIDELINE FOR DAILY ACTIVITY • The landfill will be staged in cells so that the minimum practical area of waste is exposed and maximum
practical area of waste has the final cap in place i.e., progressive filling and capping of the landfill ensuring
minimization of infiltration of wastes.
• The weigh bridge at the main entrance will record all movements and weights and receive waste tracking
receipt as required by the waste manifest system.
• The stand pipe forming part of the leachate collection system shall be checked regularly for the presence of
leachate. Once leachate is detected it shall be regularly pumped out and transferred to the leachate treatment
facility on-site.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-32
• The level of leachate in the standpipe shall not be allowed to rise above the level of the leachate collection
system.
• Once a waste is received at the site, a sample of waste shall be collected, at the samplingbay/ temporary
storage facility and shall undergo laboratory analysis based on which its pathway of treatment / disposal
shall be determined.
• A waste manifest system shall be developed in accordance with the requirement of the regulatory agencies to
cover the transportation of the waste to TSDF and to provide for record of waste manifestation.
• Each load of waste arriving at the facility shall be located properly and logged to identify its pathway of
treatment/ storage/ disposal.
2.11 RESORCE REQUIREMENT
2.11.1 Capital investment
For establishment of common treatment and disposal facilities for hazardous wastes, capital investment
towards land cost, land development cost, TSDF components, transport, Earthmoving and other
machinery, construction of lab admin. Building, Security, weighbridge, internal roads and drains network,
green belt development etc is estimated around Rs. 38.45 Crores.
Table 2-9: Project cost
Sr. No. Description Cost in Rs. (Crores)
1 Land & site development 2.00
2 Civil work 3.00
3 Land fill site 25.00
4 Incinerator 5.00
5 Utilities & Miscellaneous 0.20
6 EMS 3.25
TOTAL 38.45
2.11.1.1 Financial model
Proposed financial model for the TSDF facility is given in following Table 2-10
Table 2-10: Financial Model
Sr No. Terms Amount in crore
1 State & Central Subsidy 9.61
2 Bank Loan 19.23
3 Promoters Contribution 9.61
TOTAL 38.45
2.11.2 Land
Proposed project will developed on 1,06,432 Sq.m plot area. Land is already in possession with project
proponent. Detailed area breakup is shown in table 2-11 below.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-33
Table 2-11: Area Breakup
Area for Area in m2 % Area
Landfill 49903 46.89%
Temporary landfillable waste storage area 500 0.47%
Incinerator 2350 2.21%
Temporary Incinerable waste storage area 810 0.76%
stabilization area 225 0.21%
Internal road 10792 10.14%
Greenbelt 35123 33.00%
Admin, lab, canteen security 500 0.47%
Parking 5300 4.98%
Open space 379 0.36%
ETP area 500 0.47%
Security office 50 0.05%
Total 106432 100.00%
2.11.2.1 Land Acquisition
During the ToR application project proponent has identified plot no. 2483, 2500, 2501, 2503, 2482, 2484,
2499, 2502, 2504, 2486, 2485, 2487, 2488, 2498, 2497, 2505, 2506, 2490, 2491, 2496, 2509, 2510,
2523,2528/1,2528/2,2524,Village. – Chanasma, Taluka. – Chanasma, District Patan, Gujarat. After TOR
and during the preparation of EIA report, some plots were not available for the project. Details of available
and omitted plots are as follows. Hence total plot area from 1,40,881 sq.mtr. is reduce to 1,06,432 sq.mtr.
Table 2-12: Land Acquisition
Sr no. Land Acquisition Status
Acquired Acquisition in process Omitted
1. 2482/1, 2482/2, 2486, 2483/1,
2483/2, 2500, 2499, 2498,
2496/1, 2496/2, 2497, 2502,
2501, 2503, 2506, 2509, 2510
2523, and 2491/1
2487,2491/2 2504, 2485,
2487, 2488, 2505
2490, 2528/1,2528/2, 2524
Land documents are attached as Annexure – 6 with EIA report.
2.11.3 Water
There is no major river flow from the project area; hence water for domestic, construction and industrial
activities of proposed project is sourced from bore well. Application to central ground water authority for
withdrawal of ground water has been made. Application copy is attached as Annexure – 4. During
construction phase it is estimated that approximately 35 KLD water will required for various activities
Construction phase :
• Domestic – 10 KLD,
• Construction & other – 25 KLD
• Total – 35 KLD
There is no major use of water during operation phase in proposed project. Water required for various
activities is mentioned in following table, while the water balance diagram is shown as Figure 2-12
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-34
Table 2-13: Water Consumption
Sr
no. Activity
Water Consumption
(KLD) Remarks
A Domestic 8 Fresh water
B Green belt 15 Fresh water
C Industrial 20 -
Boiler 0
Washing
5
water for floor washing, wheel
washing and dust suppression
Cooling 0
Others
(scrubber-incinerator/spray dryer) 15
Total 43
• Total water requirement for the project: 43 KLD
• Quantity to be recycled: 21 KLD
• Total Fresh water requirement: 22 KLD
Figure 2-12: Water Balance Diagram
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-35
2.11.4 Electricity/Power
Power requirement of proposed project will fulfill by Uttar Gujarat Vij Company Ltd. (UGVCL). Power
requirement is estimated 350 KVA and 400 KVA during construction and operation phase respectively. In
case of power failure one DG set of 1500 KVA will be installed as backup power arrangement.
2.11.5 Machineries
Appropriate earth moving equipment like JCB, compactors and waste transportation trucks/dumpers with
hydraulic jack etc. will be required for waste handling and disposal. Installation of mechanized cover
system having arrangement of waste conveyor system, mixing unit with mechanized mixing arrangement,
suction duct/hood and scrubber system with stack.
2.11.6 Fuel
Indian Coal and Furnace Oil (FO) will be used as main fuel at proposed project. Detail of fuel and its
requirement is mentioned in below Table 2-14.
Table 2-14: Fuel Source
Sr no. Fuel Fuel utilized for Quantity
Construction phase
1 High Speed Diesel (HSD) D.G. Set 100 liter/Hr
Operation phase
1 Furnace Oil Incinerator 1200 kg/day
2 High Speed Diesel (HSD) D.G. set 300 liter/Hr
3 Coal Spray Dryer with Inbuilt HAG 200 kg/Hr
2.11.7 Manpower
It is estimated that approximately 170 nos of skilled and semi skilled workers and 25 nos of technical
persons will required for construction activities and development of secured landfill site. During operation
phase, for waste management activities 100 nos of technical staff will be required. Preference to local
person within study area will be given based on their experience and education.
2.11.8 Chemical
Proposed project is waste management facility, hence no major chemical will required at site. Although
chemicals like lime, alum, polyelectrolyte to be required for effluent treatment plant further in addition to
above, lime, flyash, bentonite (clay), cement, saw dust etc. will be utilized for the stabilization of
hazardous waste. Separate shed for storage of such chemicals will be provided. Provision of seven days
storage of above chemicals near to stabilization area will be made.
2.11.9 Laboratory
A well equipped laboratory shall be established to carry out comprehensive analysis (CA) of hazardous
wastes, finger print analysis (FPA) and treatability studies to decide on the disposal path way as per the
waste acceptance criteria.
Analytical equipment required for CA and FPA as well as for routine environmental monitoring during
operation phase will be installed at in-house laboratory. The list of laboratory equipment to be required is
mentioned in table 2-15.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-36
Table 2-15: Laboratory Equipment required for Environmental Monitoring
No. Name Of The Equipment No of Instruments
1 Respirable Dust samplers 3
2 Fine Dust samplers 3
3 Portable Flue Gas Combustion analyzer 1
4 Portable Noise level meter (Dosimeter) 1
5 Portable Waste water Analysis Kit 1
6 BOD Incubator 1
7 COD Digester with colorimeter 2
8 Electronic Balance 1
9 Spectrophotometer 1
10 Hot Air Oven 1
11 Laboratory Water Distillation and demineralization unit 2
12 General glass ware and laboratory chemicals, etc. As per requirement
2.12 POLLUTION LOAD AND MITIGATION MEASURES
Proposed facility is for waste management, but there is certain pollutant as described in respective section
which required to treat and disposed within plant premises. There will be pollution load due to propose
project in form of wastewater; air emission-flue and process and waste generation.
2.12.1 Wastewater
At the end of industrial activities it is assumed that 35 KLD wastewater will be generated from operational
activities, utility and domestic activities, which will be treated in ETP having capacity of 50 KLD. Sewage
from domestic activities will be mixed with the wastewater for dilution. Treated wastewater from ETP will
be again passess from RO plant. RO permeate will be reuse and RO reject will be evaporated in spray
dryer. Hence unit will be Zero Liquid Discharge (ZLD).
Table 2-16: Wastewater Generation
Sr
no.
Activity Wastewater
Generation
(KLD)
Treatment Method
A Domestic 4 Septic tank/soak pit
B Industrial
Washing 5 Treated in ETP followed by RO and
spray dryer Others- (scrubber- incinerator/spray dryer) 15
leachate from landfill 15*
Total Effluent to ETP 35 Treated water sent to RO plant for
further treatment
D RO Reject 14 Evaporated in spray dryer
*considering worst case scenario like heavy rain on SLF cell which is not covered with sheet which is rare occasion of leachate
generation.
Expected characteristics of combined effluent are given in table 2-17.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-37
Table 2-17: Effluent Characteristic
Sr.
No.
Particular Washing Others
(Scrubber)
Leachate
from SLF
Composite
Effluent
Flow (KLD) 5 15 15 35
1 pH 8.5 7 8 7.64
2 Total Suspended Solids (mg/L) 150 180 550 334.29
3 Total Dissolved Solids (mg/L) 2000 950 50000 22121.43
4 Chemical Oxygen Demand (mg/L) 70 2500 20000 9652.86
5 Biological Oxygen Demand (mg/L) 50 70 12000 5180.00
6 Phenolic compounds (mg/L) - - 8 3.43
7 Ammonical Nitrogen (NH4-N) (mg/L) - - 52 22.29
8 Manganese (mg/L) - - 2.5 1.07
9 Copper (mg/L) - - 0.25 0.11
10 Iron (mg/L) - - 2.5 1.07
11 Lead (mg/L) - - 2.5 1.07
12 Nickel (mg/L) - - 0.8 0.34
2.12.1.1 Effluent Management in ETP
Collection network will be provided for collection of wastewater generated from land fill as leachate,
vehicle wheel washing, scrubber and from laboratory. After collection of wastewater in collection tank it
will be transferred into neutralization cum settling tank for neutralization. After neutralization effluent will
be transferred into filter press where execs water will be drain and remaining sludge will be transferred to
sludge drying bed. Effluent from filter press will be transfer to spray dryer for the drying and dried mass is
disposed into TSDF site along with dried sludge. Effluent treatment units mentioned in Table 2-19 and
effluent treatment process flow diagram is depicted as figure-2.8.
Table 2-18: Technical detail of ETP
Sr
No. Treatment unit No.
Dimension (L, B, H in meter)
or Capacity (KL/hr. or KLD)
Capacity
(KL)
1. Equalization Tank 1 3.0 x 2.0 x (2.0 + 0.5 F.B.) 12.0 m3
2 Neutralization Tank 1 1.0 x 1.0 x (1.0 + 0.8 H.B.+ 0.3 F.B.) 1.8 m3
3 Primary Settling Tank 1 2.0 x 2.0 x (2.0 + 1.0 H.B. + 0.3 F.B.) 12.0 m3
4 Aeration Tank 1 6.0 x 5.0 x (4.0 + 0.5 F.B.) 120.0 m3
5 Secondary Settling Tank 1 2.0 x 2.0 x (2.0 + 1.0 H.B. + 0.3 F.B.) 12.0 m3
6 Intermediate Sump 1 3.0 x 2.0 x (2.0 + 0.5 F.B.) 12.0 m3
7 Filter foundation 1 1.5 x 1.0 1.5 m2
8 Treated Sump 2 3.0 x 2.0 x (2.0 + 0.5 F.B.) 12.0 m3
9 RO Shed 1 5.0 x 4.0 20 m2
10 RO Permeate tank 1 2.0 x 2.0 x (2.0 + 0.5 F.B.) 8 m3
11 Spray dryer feed tank 1 3.0 x 2.5 x (3.0 + 0.5 F.B.) 22.0 m3
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-38
Figure 2-13: ETP Flow Diagram
Table 2-19: Stage-wise effluent characteristic
Sr.
No. Parameters ETP Inlet
Primary
Outlet
Secondary Outlet/
RO Inlet
RO Permeate
for reuse
RO Reject for
Spray dryer
Flow 35 35 35 21 14
1 pH 7.3 6.5 – 7.5 6.5 – 7.5 6.5-7.5 6.5 – 7.5
2 S.S. (mg/L) 220 < 100 < 100 ≤ 30 80
3 TDS (mg/L) 1150 < 2000 < 2000 ≤ 2000 10000
4 COD (mg/L) 2000 <1600 < 250 ≤ 100 150
5 BOD (mg/L) 150 < 50 < 500 ≤ 50 50
2.12.1.2 Technical specification of RO
i) Ultra Filtration System
• Feed Flow Rate 2400 LPH
• UF product water 2100 LPH
• Reject Flow Rate 300 LPH
• U.F. Module Recovery @ 86-90%
• Operating Pressure 2-3 Kg/Cm²
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-39
ii) RO Module
• Feed Flow Rate 2070 LPH
• R.O. Product Water 1200 LPH
• R.O. Module Recovery @ 55-58%
• Operating Pressure 10.0-15.0 Kg/Cm²
2.12.2 Leachate Management
Moisture content in the hazardous waste to be accepted at proposed TSDF site is restricted ≤ 20 % by
disposal criteria. It is assume that daily 200 TPD hazardous wastes will be disposed at site from which 4
KLD Leachate will be generate considering 2 – 5 % leachate generation rate. 15 KLD of leachate assume
to be generated during operation phase considering worst case scenario like heavy rain on SLF cell which
is not covered with sheet which is rare occasion of leachate generation.Waste disposal activities will be
closed during the monsoon; hence leachate generation is unlikely in monsoon. Further impervious liner
will be laid on waste application area during Monsoon to avoide rain water contact with waste. However,
in rare occasion of leachate generation, guard pond of 250 m3 will be provided for any emergency and
gradually leachate will be directed to ETP for treatment and/or disposed through spray dryer.
Following leachate collection and conveyance facility will be provided.
1. Leachate collection sump/wells: Two primary and two Secondary
2. Leachate collection Pumps:
a. Two (1 working + 1 stand by) Primary submersible 5 m3/hr capacity at 15 m head
b. Two (1 working + 1 stand by) Secondary submersible 5 m3/hr capacity at 15 m head
3. Conveyance of leachate: HDPE pipeline
4. Waste water collection tank: RCC lined / RCC tank with impervious liner.
5. Raw wastewater pumps: 5 m3/hr capacity centrifugal pump, 15 m head
As per guideline, facility will take sludge from various chemical industries contains low organic load for
landfilling. So, the sludge will contains very less VOC as well as Ammonical Nitrogen content. However
Leachate will be collected and send to ETP and will undergo primary, Secondary and advanced RO
treatment. RO rejected will be sent to coal fire spray dryer, where max temperature will be kept at round
600 – 650 0C. spray dryer salt will be collected and disposed to landfill site itself.
Due to high temperature of spray dryer and adequate APC system, most of the VOC components will be
decomposed. So, there will be no chances of emission of VOC compounds and Ammonical into air.
2.12.2.1 Technical specification of Spray dryer
Details of technical specification of spray dryer id as follows.
I-DESIGN BASE
Application : WASTEWATER
CAPACITY
Feed rate : 3500 Ltrs/Hr.
Product Rate : 2000 Ltrs/Hr.
Evaporation Rate : 10000 Ltrs/Hr
FEED PROPERTIES
Solid Content Range : 5-25%
Form : Slurry/Solution
Nature : Settling
Solvent : Water
Temperature : 30º C
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-40
PRODUCT PROPERTIES
Product Moisture : 8-10%
No. of Product Collection Points : 2
OPERATING CONDITION
Mode of Heating : Hot Air Generator
Inlet Air Temperature : 550-600 ºC
Outlet Air Temperature : 110-120 ºC
II- UTILITY SPECIFICATIONS
Power : Voltage : 415 V / 4 Wire / 3 phase
Connected Load : 322 KW
Fuel : COAL :
Normal Consumption 200±20 kg/hr @ 5000
GCV
Space Requirement (Approx.) For SPRAY DRYER – 11 M (W) × 19 M (L) × 18.5 M (H)
For HAG - 7 M (W) × 12 M (L) × 12 M (H)
III- SCOPE OF SUPPLY :
COMPONENET WISE DETAILS ARE AS BELOW
1. FEED SECTION
Feed Tank
A feed tank is provided for storage of feed slurry
Type : Vertical Cylindrical, Self Supported
Capacity : 400 L
Material of Construction : Stainless steel 316 L
2. AIR HEATING SECTION
HOT AIR GENERATOR
The fluidized Bed Combustion fired system consists of a fire chamber, Air pollution control equipment. With
furnace and fans
CAPACITY
Energy Generation : 15,00,000 K cal / Hr
Type : Coal Fired Direct HAG
OPERATING CONDITIONS
Mode of Heating : Steam Coal / Imported Coal / Indian Coal
Air Temperature : 50 ºC – 580 ºC
SPRAY DRYER SECTION
Air Distributor
Hot air distributor is located on the top of the spray chamber for distributing the air uniformly across the spray
dryer inlet in the swirl fashion, which will have an arrangement for the cooling to atomizing zone.
Air distributor and chamber roof is designed to minimize deposition of material on chamber roof by minimizing
dead zones of air.
Spray Chamber
A cylindrical vessel with flat / shallow roof and conical bottom is used as spray drying chamber. The chamber is
with inlet and outlet port for hot air exhaust gases and powder.
Wet Scrubber
A water scrubber is provided before the exhaust blower. Dry powder escaping the cyclone will be further treated
with water spray in a close loop system and collected in the bottom tank.
Type : Direct contact type with water spray
No. of Unit : 1
Material of construction
(Contact Parts)
: Stainless steel 316 L
Support Bracket : Carbon steel
Accessories : Droplet separator and interconnecting piping, spray nozzle, hose and
clamp for recycle water, sight/light glass, support bracket, anti
vortex arrangement on bottom cone for water
Circulating Water Tank
The Scrubber tank is provided and shall be self supporting. Feed inlet, feed outlet, drain, provision for mounting
level gauge is provided.
Type : Vertical Cylindrical
Capacity : 5000 L
Material of construction
(Contact Parts)
Stainless steel 316 L
Accessories : Drain Valve
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-41
2.12.3 Observatory Well Groundwater Monitoring stations
Observatory well is the structure to be developed within plant premise for directly access and test the
groundwater around the landfill cell for presence of leachate chemicals or any other contamination due to
project. Typically a groundwater monitoring system will have a series of wells that are located up-gradient
and down-gradient of the landfill disposal area. The up-gradient wells test the water quality before it
moves under the disposal area in order to get a background analysis of the water. The down-gradient wells
then allow testing of the water after it has passed under the disposal area so it can be compared to the
quality of the up-gradient wells to make sure there has been no impact or contamination of the
groundwater. Layout map (Figure 2-4) shows the location of observatory well in proposed project site.
2.12.4 Air emission
Air emission in form of flue gas and process emission will expected to be release from stack attach to hot
air generator, D.G. set and incinerator. Main source of fugitive emission are hazardous waste handling and
transportation. Air emission from proposed project and control measures to be provided is mentioned in
Table 2-21.
2.12.4.1 Flue gas emission
During construction phase, pollutants like PM, SOx, NOx to be emitted from construction machineries and
due to construction activities like excavation, storage of excavated soil etc. Details of emission during
operation are presented in following table.
Table 2-20: Details of Flue gas emission
Sr.
no
Source of
Air
Emission
Pollutant to be emitted
Stack height
and
Diameter
Air pollution
control Equipment
/Mitigation
Measure
Limiting concentration
1 Hot Air
Generator
PM, SO2, NOx Height :20 m
Dia :1 m
Cyclone Separator,
Bag Filter
PM ≤ 150 mg/Nm3
SO2 ≤ 100 ppm
NOx ≤ 50 ppm 2 D.G. set PM, SO2, NOx Adequate
stack height
Adequate stack
height as D.G. set
will be used as back-
up power source.
3 Incinerator PM, HCl, SO2, CO, TOC,
HF, NOx, Total Dioxin &
Furan, Cd+Th+Their
compounds,
HG and its compounds
(Sb+As+Pb+Cr+CO+Cu+
Mn+Ni+V+their
compounds
Height : 30
m
Dia : 1.2 m
Quencher, Carbon
Column, Droplet
Separator, Cyclone
Separator, Bag
Filter, Ventury
Scrubber, Alkali
Scrubber
PM ≤ 50 mg/Nm3
HCl ≤ 50 mg/Nm3
Sulphur Dioxide ≤ 200 mg/Nm3
CO ≤ 50 mg/Nm3 (24 hr)
TOC ≤ 20 mg/Nm3
HF ≤ 4 mg/Nm3
NOx ≤ 400 mg/Nm3
Total Dioxin & Furan, ≤ 0.1
ngTEQ/Nm3
Cd+Th+Their compounds ≤
0.05 mg/Nm3
HG and its compounds ≤ 0.05
mg/Nm3
(Sb+As+Pb+Cr+CO+Cu+Mn+
Ni+V+their compounds ≤ 0.05
mg/Nm3
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-42
2.12.4.2 Fugitive emission
It is assumed that during construction phase, mainly fugitive dust generated by earth moving activities,
hauling of soil, construction materials, and base course surfacing and moving of construction vehicles.
Continuous water sprinkling around the construction area for dust suppression will take place. Greenbelt
around the boundary of project site consisting air pollution capturing species will acts as natural barrier to
stop carrying of dust along with the wind current.
Fugitive emissions in the form of dust, PM and VOCs will mainly generated due hazardous waste
transportation and handling activities at SLF and incineration during operation phase. There will be
possibility of VOC generation from temporary waste storage area also.
2.12.4.3 Odour control
There will be odour due to handling of hazardous waste at landfill cell as well as incinerator. Following
measures will be adopted by project proponent to control the odour.
• Daily waste covering with soil will help to reduce odours from newly deposited wastes.
• Odour suppression chemicals like foaming, spraying of deodorant chemicals at odour generating
area like around a landfill site, temporary waste storage/handling area, ETP area etc.
• Ventilation at odorous chemical storage area will be provided in such a way so that it will be
disperse properly.
• Greenbelt containing odour capturing species will be developed along the boundary of project site
2.12.5 Waste generation
As a waste management facility, hazardous waste to be collected from waste generating industries will be
handling and manage as per Hazardous and Other Wastes (Management and Transboundary Movement)
Amendment Rules, 2016. All the hazardous waste generated from the project itself will also be managed as
per the rule within plant premises. List of hazardous waste to be generated from proposed project is
mentioned in Table 2-21
Table 2-21: List of Hazardous waste
Sr.
no.
Name of
Waste
Source of
Waste
Generation
Category
of Waste
Quantity to
be generated
(MTPA)
Waste management method
1 ETP Sludge ETP 35.3 180 Collection & disposed at
proposed landfill site within
premises
2. Incineration
Ash
Incinerator 37.2 360 Collection & disposed at
proposed landfill site within
premises
3. Spray Dryer
Sludge
Spray Dryer 37.1 220 Collection & disposed at
proposed landfill site within
premises
4. Used Oil Utility
/machineries
5.1 200 LPA Sell to approved/registered
recycler
5. Discarded
containers &
bags
Storage area 33.1 72 Sell to approved/registered
recycler
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-43
2.13 ECOLOGY AND BIO DIVERCITY
There is no tree cutting is envisaged for the development of the project. However around 33% are of total
project will be developed as green belt and will be will be started along with construction phase as per
greenbelt development plan.
2.13.1 Green belt
Green belt not only provides habitat for faunal species but also acts as a sink for pollutants, attenuation of
noise levels and improvement in aesthetic quality of the plant. This not only mitigate the ecological
problem but also enhance the beauty of project area that will attract avifauna, small mammals & insect
species, and by this way ecological balance can be maintained to great extent. Greenbelt with varieties of
species is preferred to maintain species diversity, rational utilization and for maintaining health of the
trees. 35123 m2
area consisting of air, odor and noise pollution capturing species (10415 nos.) will be
developed as Greenbelt as per CPCB guideline of 1000 trees per acre as well as considering 80% survival
rate of tree.
2.14 NOISE POLLUTION
Main source of noise in proposed project are vehicular movement involved in waste transportation,
machineries involved in waste handling and operation of utilities. To mitigate noise within project
premises, following measures will be taken:
• Greenbelt around the project boundary consisting of noise and air pollution capturing species and acts
as natural barrier to stop carrying of noise propagate.
• To reduce the noise generation during the transportation activities; the vehicle will be kept periodically
serviced and maintain as per the requirement. Only those vehicles with PUC’s will be allowed for the
transportation.
• Noise monitoring will be carried out regularly at prominent places in the plant as per guideline.
2.15 PROJECT IMPLEMENTATION
Implementation of project within a pre-determined time frame is an important factor for the success of
project. Timely implementation may save on various costs like interest, administrative overheads and helps
to realize the goals as per pre-determined objectives. The implementation of the project will involve major
activities like preparation of specification / drawings, receipt of quotations, scrutiny of quotations, placing
of orders, civil & structural construction, delivery & erection of equipment, test trial runs of various items
of equipment and commissioning of equipment.
All project activities will be started only after obtaining EC from MoEFCC and CTE/CTO from GPCB. A
tentative project schedule presented in Table 2-22 is prepared considering day one from the obtaining all
mandatory approvals from the statutory authority as mentioned above and other.
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-44
Table 2-22: Project Implementation Schedule
Project Activities Period in Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Strengthening of kuchcha road and construction of
bore well
Preconstruction activity- contour survey, Site
grading, site preparation, Boundary wall etc.
Creation of storm water drain
Development of cell including excavation, layers,
liners etc. and installation of incinerator
Fabrication, painting and installation of hardware
Civil building construction, weigh bridge,
laboratory, admin, internal road, leachate treatment
etc
Final inspection of SLF and Incinerator
en-vιsι�n
NORTH GUJARAT ENVIRO PROJECTS, CHANSMA, GUJARAT 2-45
2.15.1 Organization Structure The Chief Executive Officer of the proposed facility is responsible for all the project activities i.e. landfill
and incineration. Based on the project requirement following organizational structure has been decided by
project proponent. Role and responsibilities of each persons involved in activates is defined in following
figure. Organizational structure shall be made available on-site to regulatory officials.
Figure 2-14: Organizational Structure