Draft Framework Guidelines on System Operation - Process Presentation Workshop, Ljubljana, 24 August 2011 Uroš Gabrijel (ACER)

Upload: brandon-hopper

Post on 31-Dec-2015

25 views

Category:

Documents


0 download

DESCRIPTION

Draft Framework Guidelines on System Operation - Process. Presentation Workshop, Ljubljana, 24 August 2011. Uroš Gabrijel (ACER). Content. Introduction Process description State of play Details on public consultation Next steps. Introduction (1). - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Draft  Framework Guidelines  on System Operation - Process

Draft Framework Guidelines on System Operation

-Process

Presentation Workshop, Ljubljana, 24 August 2011

Uroš Gabrijel (ACER)

Page 2: Draft  Framework Guidelines  on System Operation - Process

2

Content

.Introduction

.Process description

.State of play

.Details on public consultation

.Next steps

Page 3: Draft  Framework Guidelines  on System Operation - Process

3

Introduction (1)

. During the “interim period”, ERGEG assumed the role

assigned to ACER by the 3rd package and worked on

“pilot” Framework Guidelines (FG)

. ERGEG has been working on three FG:

» Electricity Grid Connection

» Capacity Allocation and Congestion Management

» System Operation

Page 4: Draft  Framework Guidelines  on System Operation - Process

4

Introduction (2)

. Work on drafting the FG on System Operation was

concluded under ACER

. ACER was invited to submit to the Commission, by 31

December 2011, a framework guideline on electricity

system operation

Page 5: Draft  Framework Guidelines  on System Operation - Process

5

Process description (1)

. General timeline as set out in Reg. (EC) 714/2009

EC defines priorities

for network codes

6 Months

EC requests

Agency to submit

framework guidelines

Agency prepares Framework Guidelines

ENTSO prepares network codes

12 Months

EC requests ENTSO to

submit network code

3 Months

Agency reviews network codes

CO

MIT

OL

OG

Y

ENTSO submits

network code to Agency

Agency submits

network code to EC when satisfied,

recommending approval via Comitology

Page 6: Draft  Framework Guidelines  on System Operation - Process

6

Process description (2)

.Annual priority list − Commission

. Consultation with ACER, ENTSO-E, other relevant

stakeholders

. Areas for the development of FG/NC

. Initial Impact assessment − ACER

. To support the development of the FG

. Expert group representing wide industry perspective

. Identification of problems / objectives / policy options

Page 7: Draft  Framework Guidelines  on System Operation - Process

7

Process description (3)

. Framework Guidelines (FG) − ACER

. Invitation from the Commission to draft FG

. Public consultation

. Adoption of the FG / Submission to the Commission (6

months)

.Network Codes (NC) − ENTSO-E

. Commission request

. ENTSO-E prepare the NC in line with the FG (12 months)

. ACER reasoned opinion on NC (3 months)

Page 8: Draft  Framework Guidelines  on System Operation - Process

8

State of play

.ACER deliverables on FG (2011 Work Programme)

. Electricity Grid Connection (finished)

. Capacity Allocation and Congestion Management (finished)

. System Operation (on-going)

. Balancing (to be delivered in mid 2012)

Page 9: Draft  Framework Guidelines  on System Operation - Process

9

Details on public consultation (1)

.Public consultation on Draft Framework Guidelines on

System Operation

» Run from 15 July to 15 September 2011

.Email-based consultation

» Submission of comments to:

[email protected]

» Personal details should be enclosed

.Constructive and comprehensive responses

» Large companies invited to coordinate their answers

internally

Page 10: Draft  Framework Guidelines  on System Operation - Process

10

Details on public consultation (2)

.Questionnaire to steer the structure of responses

» 8 general issues, 4 specific issues

. Transparency

» Responses will be published on the ACER

website

» Comments marked confidential will be considered

but not disclosed

Page 11: Draft  Framework Guidelines  on System Operation - Process

11

Next steps

.Public consultation

» On-going

» Ending on 15 September 2011

.Evaluation of responses

» Within approximately two months

. Finalization of the FG

» Submission to EC by 31 December 2011