drainage report-ash disposal area - rev c_sect 3.2
TRANSCRIPT
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
1/10
Drainage Report For Proposed Ash Disposal Area
Originator
HSSIdentification number
MNG/04/P/UEW10D15--/DC/534Rev.
CDate
4-01-2013Lang.
EnSheet
9/10
Use 300mm diameter perforated pipe contained in 20mm to 40mm drainage aggregate wrap
with geotextile is proposed at edge of the ash ponds to evacuate the surface flow faster. The
drainage layout plan for both Ash Pond A and Ash Pond B are presented in Appendix C.
3.2 Detention Ponds
3.2.1 Design Criteria and Standard
Methodology for the detention pond sizing is based on Water Balance Analysis Concept
design which describes the flow of water in and out of a system. Assumptions used in this
report are as follows:
i) Detention pond area allocated in this development layout plan will serve as a dry
detention pond (Pond A & Pond B).
ii) The detention pond will be designed to cater for 1 in 25 year 24 hour storm event and
check for 1 in 100 year 24 hour storm event arising from development discharge from
the ash pond area according to MASMA requirement.
iii) The detention pond sizing is calculated based on the optimal ash deposit in Pond A
and Pond B.
iv) Assumption of 5% void of compacted ash disposal to considered as a storage
capacity.
The water balance calculation for both Ash Ponds has been calculated based on two different
storm events i.e. 25-yr and 100-yr ARI, 24-hrs rainfall. The storage volume is calculated based
from net amount of runoff volume with free board 0.5m at elevation 2.8 mLSD.
Summary of the water balance calculations for Detention Ash Pond A and Ash Pond B are
shown in Table 1 and 2 respectively. The details of the calculations are presented in Appendix
A and B.
3.2.2 Pump
Based from the above calculation, there were no excess volumes for single storm event of 24
hour rainfall. However, it is recommended to provide a 100 m3/hr pump for each ash ponds to
cater excess volume arising from series of storm event which eventually will be accumulated
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
2/10
Drainage Report For Proposed Ash Disposal Area
Originator
HSSIdentification number
MNG/04/P/UEW10D15--/DC/534Rev.
CDate
4-01-2013Lang.
EnSheet
10/10
storm runoff in the ponds which need to be extracted to waste water treatment plant.
Reference to Ash Disposal Management Procedure, section 13.3 stated that any
contaminated surface flow shall be pumped to waste water treatment plant and the
contaminated water also can be used directly on the disposed ash for dust control (section
13.2).
Table 1: Summary of Water Balance Calculation for Pond A
E vapora tion As hPondAAshDet.Pond
AreaPondStorage, S StorageDepth
Pump
Capacity**
(mm/day) (m2) (m2) (m3) (m) (m3/hr)
1. 24hr 25yrARI 7.42 6,482 1.39
2 . 24hr 100yrARI 8.2 8,250 1.77
Note:
1. Rainfalldata(rainfallintensity)isreferredfromERandHP1 Vol.II IDFCurve,2010
2. AssumeDeadWLat0.5mLSDtohavebetterpumpoperation
3. **Recommendedtoprovidepumpforexcessvolumearisingfromseriesofstormeventandfordustsuppression.
1003.0
No. StormD urat ion R ainfal l
94,485 4,656
Table 2: Summary of Water Balance Calculation for Pond B
EvaporationAshPondArea,
FBA
AshDet.Pond
AreaPondStorage, S StorageDepth
Pump
Capacity**
(mm/day) (m2) (m2) (m3) (m) (m3/hr)
1. 24hr 25yrARI 7.42 3,957 0.89
2 . 24hr 100yrARI 8.2 4,983 1.12
Note:
1. Rainfalldata(rainfallintensity)isreferfromHP1 Vol.II IDFCurve,2010
2.Assume
Dead
WL
at
0.5
mLSD
to
have
better
pump
operation
3. **Recommendedtoprovidepumpforexcessvolumearisingfromseriesofstormeventandfordustsuppression.
1003.0
No. StormD urat ion R ainfal l
54,830 4,446
7.0 Conclusion
Based on the above calculations for detention facilities in the ash ponds, the following
recommendations are made:
1. The freeboard of the detention pond is 0.5m (100-yr ARI) @ elevation 2.8 mLSD and
the proposed stage 1 pump cut in level @ elevation 0.5 mLSD.
2. The excess volume arising from series of storm event shall be discharge to water
treatment system assisted by pumps.
3. The detention pond size is 97m (length) x 48m (width) x 2.3m (effective depth) has
been adopted for Pond A and the Pond B detention pond size is 117m (length) x 38m
(width) x 2.3m (effective depth) has been adopted.
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
3/10
APPENDIX A
Water Balance Calculation for Pond A
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
4/10
WaterBalanceCalculation
Evaporation
AshPondA
AshDet.Pond
Area
PondStorage,
SStorageDepth
Pump
Capacity**
(mm/day)
(m2)
(m2)
(m3)
(m)
(m3/hr)
1.
24hr25yrARI
7.42
6,482
1.39
2.
24hr100yrAR
I
8.2
8,250
1.77
Note:
1.
Rainfalldata(rainfallintensity)isreferredfromERandHP1Vol.IIIDFCurve,20
10
2.
AssumeDeadW
Lat0.5mLSDtohavebetterpumpoperation
3.
**Recommendedtoprovidepumpforexcessvolumearisingfromseriesofstorm
eventandfordustsuppression
100
SummaryofWaterBalanceCalculationForDifferentStormEven
tPondA
3.0
No.
StormDuration
Rainfall
94,485
4,656
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
5/10
WATERBALANCECALCULATION
ASHPOND PONDA(24hrRainfall 25yrARI)
Data:
1. AnnualRainfall,Rf24
I25yr = 7.42 mm/hr
2. Evaporation,Ev = 3 mm/day
3. PFAarea = 94,485 m2
4. AssumeDeadWaterLevel,DWL = 0.5 mLSD
5. AshDetentionPondArea = 97mx48m = 4,656 m2
6. FreeBoard = 0.5 m (RefertoDesignChecklistforSWM,JPS,2010)
@Level = 2.8 mLSD
DesignCalculation
Runoffvolume = [7.42mm/hr x 24hrx 94,485m2]
= 16,826 m3
Evaporationvolume = [ 3.0mm/day x 4656m2
]
= 13.97 m3
StoragevolumefromAshPond = 5%x(PFAarea DetentionPondArea)xLivestorage
(Allowed5%voidofAsh) = 10,330 m3
DepthinADP = SPondArea
= 6,481.59
4,656
= 1.39 m
Livestorageavailabe = 2.3 m (freeboard0.5m)
Hence,noexcessrunoff
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
6/10
WATERBALANCECALCULATION
ASHPOND PONDA(24hrRainfall 100yrARI)
Data:
1. AnnualRainfall,
Rf
24
I100yr = 8.2 mm/hr
2. Evaporation,Ev = 3 mm/day
3. PFAarea = 94,485 m2
4. AssumeDeadWaterLevel,DWL = 0.5 mLSD
5. AshDetentionPondArea = 97mx48m = 4,656 m2
6. FreeBoard = 0.5 m (RefertoDesignChecklistforSWM,JPS,2010)
@Level = 2.8 mLSD
DesignCalculation
2 = . ,
= 18,595 m3
Evaporationvolume = [3.0mm/day x 4656m2
]
= 13.97 m3
StoragevolumefromAshPond = 5%x(PFAarea DetentionPondArea)xLivestorage
(Allowed5%voidofAsh) = 10,330 m3
DepthinADP = S
PondArea
= 8,250.35
4,656
= 1.77 m
Livestorageavailabe = 2.3 m (freeboard0.5m)
Hence,noexcessrunoff
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
7/10
APPENDIX B
Water Balance Calculation for Pond B
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
8/10
WaterBalanceCalculation
Evaporation
AshPondArea,
FBA
AshDet.Pond
Area
PondStorage,
SStorageDepth
Pump
Capacity**
(mm/day)
(m2)
(m2)
(m3)
(m)
(m3/hr)
1.
24hr25yrARI
7.42
3,957
0.89
2.
24hr100yrAR
I
8.2
4,983
1.12
Note:
1.
Rainfalldata(rainfallintensity)isreferfromHP1
Vol.IIIDFCurve,2010
2.
AssumeDeadW
Lat0.5mLSDtohavebetterpumpoperation
3.
**Recommendedtoprovidepumpforexcessvolumearisingfromseriesofstorm
eventandfordustsuppression.
100
SummaryofWaterBalanceCalculationForDifferentStormEven
tPondB
3.0
No.
StormDuration
Rainfall
54,830
4,446
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
9/10
WATERBALANCECALCULATION
ASHPOND PONDB(24hrRainfall 25yrARI)
Data:
1. AnnualRainfall,Rf24
I25yr = 7.42 mm/hr
2. Evaporation,Ev = 3 mm/day
3. FBAarea = 54,830 m2
4. AssumeDeadWaterLevel,DWL = 0.5 mLSD
5. AshDetentionPondArea = 117mx38m = 4,446 m2
6. FreeBoard = 0.5 m (RefertoDesignChecklistforSWM,JPS,2010)
@Level = 2.8 mLSD
DesignCalculation
Runoffvolume = [7.42mm/hr x 24hrx 54,830m2]
= 9,764 m3
Evaporationvolume = [3.0mm/day x 4,446m2
]
= 13.34 m3
StoragevolumefromAshPond = 5%x(PFAarea DetentionPondArea)xLivestorage
(Allowed5%voidofAsh) = 5,794 m3
DepthinADP = SPondArea
= 3,956.63
4,446
= 0.89 m
Livestorageavailabe = 2.3 m (freeboard0.5m)
Hence,noexcessrunoff
-
7/29/2019 Drainage Report-Ash Disposal Area - Rev C_sect 3.2
10/10
WATERBALANCECALCULATION
ASHPOND PONDB(24hrRainfall 100yrARI)
Data:
1. AnnualRainfall,Rf24
I100yr = 8.2 mm/hr
2. Evaporation,Ev = 3 mm/day
3. FBAarea = 54,830 m2
4. AssumeDeadWaterLevel,DWL = 0.5 mLSD
5. AshDetentionPondArea = 117mx38m = 4,446 m2
6. FreeBoard = 0.5 m (RefertoDesignChecklistforSWM,JPS,2010)
@Level = 2.8 mLSD
DesignCalculation
Runoffvolume = [8.2mm/hr x 24hrx 54,830m2]
= 10,791 m3
Evaporationvolume = [3.0mm/day x 4,446m2
]
= 13.34 m3
StoragevolumefromAshPond = 5%x(PFAarea DetentionPondArea)xLivestorage
(Allowed5%voidofAsh) = 5,794 m3
DepthinADP = S
PondArea
= 4,983.05
4,446
= 1.12 m
Livestorageavailabe = 2.3 m (freeboard0.5m)
Hence,noexcessrunoff