Page 1: DS-16-161 Water Reuse Master Plan

Reuse Master Plan City of Killeen

November 1, 2016

Page 2: DS-16-161 Water Reuse Master Plan

Reuse Master Plan Process

STRATEGIC PLANNING

CUSTOMER EVALUATION

AND DEMAND PROJECTIONS

REUSE SYSTEM CIP

FINANCIAL EVALUATION

REUSE MASTER PLAN

PRESENTATION

2

Page 3: DS-16-161 Water Reuse Master Plan

Strategic Planning

• Identify Implementation Challenges & Solutions

• Document Regulations for Reuse

• Recommended Revisions to City Standards

• Coordination with Bell County WCID #1

• Benchmarking with 11 Local & National Utilities

3

Page 4: DS-16-161 Water Reuse Master Plan

Reuse Master Plan Process

STRATEGIC PLANNING

CUSTOMER EVALUATION

AND DEMAND PROJECTIONS

REUSE SYSTEM CIP

FINANCIAL EVALUATION

REUSE MASTER PLAN

PRESENTATION

4

Page 5: DS-16-161 Water Reuse Master Plan

Customer Evaluation

• Review historical wastewater plant flows for available supply

5

9.93

3.15

8.81

43.80

50.60

36.45

0

5

10

15

20

25

30 0

5

10

15

20

25

30

35

40

45

50

55

60

9/2009 11/2009 2/2010 5/2010 8/2010 11/2010 2/2011 5/2011 8/2011 11/2011 2/2012 5/2012 7/2012 10/2012 1/2013 4/2013 7/2013 10/2013 1/2014 4/2014 7/2014 10/2014 12/2014

Prec

ipita

tion

(in)

Gro

ss E

fflu

ent (

MG

D)

Precipitation South WWTP Monthly Max South WWTP Monthly Average North WWTP Monthly Max North WWTP Monthly Average

Page 6: DS-16-161 Water Reuse Master Plan

Customer Evaluation

• Identify potential reuse customers – Schools, Parks, Golf Courses, Commercial, Industrial

6

Page 7: DS-16-161 Water Reuse Master Plan

Customer Evaluation

7

229.7

11.9 9.0 7.2 6.5 11.9

115.3

7.4 0.5 6.6 5.9 11.4 7.4

155.8

5.8 0.8 4.5 6.5 6.7 5.8 0.0

50.0

100.0

150.0

200.0

250.0

Stonetree Golf Course

Killeen High School

Haynes Elementary

School

Stone Creek Apartments

Independence Place

Apartments

Texas A&M South Campus

Killeen Community

Center

Mill

ion

Gallo

ns (M

G)

2011 2012 2013

Large Irrigation Users

Page 8: DS-16-161 Water Reuse Master Plan

Customer Evaluation

• Demands are highly cyclical, resulting in a small window each year for generating revenue.

• Most utilities with successful reuse systems have a year-round base usage.

8

• Usage for Stonetree Golf Course (current reuse customer) is over 6 times larger than all potential customers combined.

Page 9: DS-16-161 Water Reuse Master Plan

Customer Demand Projections

• Customer demands developed on a weekly basis (example below)

9

Page 10: DS-16-161 Water Reuse Master Plan

Reuse Master Plan Process

STRATEGIC PLANNING

CUSTOMER EVALUATION

AND DEMAND PROJECTIONS

REUSE SYSTEM CIP

FINANCIAL EVALUATION

REUSE MASTER PLAN

PRESENTATION

10

Page 11: DS-16-161 Water Reuse Master Plan

Existing Reuse System – Repurposed existing water line sliplined to 18” diameter line – Pump Station at North WWTP – Currently supplies irrigation for the Stonetree Golf Course to a pond (non-

pressurized) – Not included in the financial analysis

11

Page 12: DS-16-161 Water Reuse Master Plan

Reuse Capital Improvement Plan Development Process • Delineate Service Areas based on ground elevations

• Determine reuse pumping, storage and water line requirements

• Evaluate sizing and phasing with reuse hydraulic model

• Eliminate potential projects with a high cost per million gallons ($/MG)

12

Page 13: DS-16-161 Water Reuse Master Plan

Buildout Reuse CIP

Page 14: DS-16-161 Water Reuse Master Plan

Reuse Capital Improvement Plan Costs

Phase # Reuse Water System Capital Improvement Plan Cost1 New Lower Service Area 3.0 MGD Pump Station and a 2.5 MG Ground Storage Tank 10,166,000$

2 8" and Slip Lined 18" Reuse Water Lines along 28th St. and Veterans Memorial Blvd. 3,154,540$

3 8" and 12" Reuse Water Line along 38th Street 684,830$

4 8" Reuse Water Line along Rancier Avenue 753,830$

5 8" & 16" Reuse Water Lines and Repurposing 0.25 MG Park St. EST 2,013,870$

6 8" Reuse Water Line along East Rancier Avenue 602,890$

7 8" Reuse Water Line along 60th Street 712,430$

8 6" Reuse Water Line along 48th Street 56,930$ 9 8" Reuse Water Line along Roy Reynolds Drive 587,410$

18,732,730$ 10 Lower Service Area 2.50 MGD Pump Station Expansion to 5.50 MGD at the North WWTP 747,500$

11New Douglas Mtn Service Area 3.50 MGD Pump Station, 1.5 MG Ground Storage Tank and 18" Reuse Water Transmission Line 9,792,550$

12 12", 16" and 24" Reuse Water Lines along Watercrest Road 4,271,970$

13 12" Reuse Water Line along Clear Creek Road 453,680$ 14 8" Reuse Water Line along Robinett Road 243,230$

15,508,930$

15Lower Service Area 2.5 MGD Pump Station Expansion to 8.0 MGD and 1.0 MG Ground Storage Tank 1,868,750$

16Douglas Mtn Service Area 1.5 MGD Pump Station Expansion to 5.0 MGD and 1.0 MG Ground Storage Tank 1,569,750$

17 16" Reuse Water Line and Repurposing Douglas Mountain 0.66 MG GST 7,748,210$

18 8" Reuse Water Line along Clear Creek Road 543,380$

19 8" Reuse Water Line along SH 195 376,050$

20 6" Reuse Water Line along Stan Schlueter Loop 256,170$

21 8" Reuse Water Line along Illinois Avenue 568,390$ 22 6" and 12" Reuse Water Lines along Cody Poe Road 1,411,920$

14,342,620$ 48,584,280$ Grand Total:

10 Y

ear

10 - 20 Year Total:

20 Year - Buildout Total:

20 Y

ear -

Bui

ldou

t10

- 20

Yea

r

10 Year Total:

Page 15: DS-16-161 Water Reuse Master Plan

Reuse Master Plan Process

STRATEGIC PLANNING

CUSTOMER EVALUATION

AND DEMAND PROJECTIONS

REUSE SYSTEM CIP

FINANCIAL EVALUATION

REUSE MASTER PLAN

PRESENTATION

15

Page 16: DS-16-161 Water Reuse Master Plan

Financial Evaluation

16

• Developed Reuse Rate Structure – Break even analysis – Impact to Water and Wastewater CIPs – Potable Water Rate Structure – Local Reuse Rates (Typically Between

$0.50 and $2.00/1,000 gal)

• Developed Revenue & Cost Comparison

• Developed Cost & Rate Model • Reviewed Two Financial Scenarios

– Complete Buildout of Reuse CIP – Construction of 10 year CIP

Page 17: DS-16-161 Water Reuse Master Plan

Financial Evaluation: Scenario 1 (Full CIP)

17

• Funding of entire Reuse CIP over 50 years

• Reuse Rate = $2.46/1,000 gal – High rate compared to other utilities – Study showed rates are typically $0.50-$2.00.

• Positive Cash Flow first 5 years – $100,000 prior to bond issuance – Result of reduced cost of water to serve Stonetree Golf Course

• Deficit in Reuse Fund – Average $3.5 million per year for over 50 years – Approximately 3.1% of current Water/Sewer Fund

Page 18: DS-16-161 Water Reuse Master Plan

Financial Evaluation: Scenario 2 (10-year CIP)

18

• Funding of 10 year Reuse CIP over 40 years

• Reuse Rate = $2.46/1,000 gallons

• Positive Cash Flow first 5 years – $100,000 prior to bond issuance – Result of reduced cost of water to serve Stonetree Golf Course

• Deficit in Reuse Fund next 35 years – Average $1.5 million per year – Approximately 1.8% of current Water/Sewer Fund

• Small positive Cash Flow after 40 years

Page 19: DS-16-161 Water Reuse Master Plan

Reuse Master Plan Process

STRATEGIC PLANNING

CUSTOMER EVALUATION

AND DEMAND PROJECTIONS

REUSE SYSTEM CIP

FINANCIAL EVALUATION

REUSE MASTER PLAN

PRESENTATION

19

Page 20: DS-16-161 Water Reuse Master Plan

Reuse Master Plan Conclusions & Recommendations

20

• A direct nonpotable reuse system would be dependent on transfers from the Water/Sewer Fund, $1.5 – 3.5 million/year.

• Providing reuse water to the Stonetree Golf Course results in a positive cash flow and should be continued.

• Analysis shows that full development of a reuse water system will not result in cost savings to the city until after 35 years.

• Reuse may become more financially attractive over time as alternative sources of supply become more expensive.

• At this time, it is recommended that the City not pursue additional reuse customers, but reuse should be reevaluated in the future for customers with large nonpotable water demands.

Page 21: DS-16-161 Water Reuse Master Plan

Questions

21