dt schedule a - epcor · 2017. 4. 4. · note: the local access fee (laf) is a surcharge imposed by...

25
Schedule 2017 SAS DT – Schedule A Transmission Access Service Tariff Effective January 1, 2017

Upload: others

Post on 25-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

Schedule 2017 SAS

DT – Schedule A

Transmission Access Service Tariff Effective January 1, 2017

Page 2: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

Schedule 2017 SAS

Table of Contents

RESIDENTIAL SERVICE ......................................................................................................................................... 1

COMMERCIAL/INDUSTRIAL <50 KVA ............................................................................................................... 2

COMMERCIAL/INDUSTRIAL 50 KVA TO <150 KVA........................................................................................ 3

COMMERCIAL/INDUSTRIAL 150 KVA TO <5,000 KVA ................................................................................... 5

PRIMARY COMMERCIAL/INDUSTRIAL 150 KVA TO <5,000 KVA .............................................................. 7

COMMERCIAL/INDUSTRIAL GREATER THAN 5,000 KVA ........................................................................... 9

COMMERCIAL/INDUSTRIAL GREATER THAN 5,000 KVA TOTALIZED ................................................. 11

DIRECT TRANSMISSION-CONNECTED ........................................................................................................... 13

GENERATOR INTERCONNECTION .................................................................................................................. 14

STREET LIGHTING SERVICE ............................................................................................................................. 15

TRAFFIC CONTROL .............................................................................................................................................. 16

SECURITY LIGHTING SERVICE ........................................................................................................................ 17

LANE LIGHTING SERVICE .................................................................................................................................. 18

TEMPORARY ADJUSTMENT ............................................................................................................................... 19

INTERIM ADJUSTMENT ....................................................................................................................................... 20

SHORT-TERM ADJUSTMENT.............................................................................................................................. 21

TABLE 3: EDTI’S 2017 SYSTEM ACCESS SERVICE RATE SCHEDULES .................................................. 22

TABLE 4: EDTI’S 2017 CUSTOMER SPECIFIC LOSS FACTOR AND OPERATING RESERVE

PERCENTAGE ......................................................................................................................................................... 23

Page 3: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 1 of 23 Effective: January 1, 2017

Schedule 2017 SAS

RESIDENTIAL SERVICE (2017 RATE)

Price Schedule SAS-R Effective: January 1, 2017

For System Access Service for all Points of Service throughout the territory served by the Company.

For single-phase service at secondary voltage through a single meter.

For normal use by a single and separate household.

Not applicable to any commercial or industrial use.

Price

The charge for service in any one billing day is the Energy Charge, determined for each individual

Point of Service.

Energy Charge

(per kWh)

Transmission SAS-R1* $0.03080

The minimum daily charge is the Energy Charge.

Application

1) Price Adjustments - the following price adjustments (riders) may apply:

Local Access Fees (Rider LAF) – See Note Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K) Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 4: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 2 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial <50 kVA (2017 RATE)

Price Schedule SAS- SC Effective: January 1, 2017

For System Access Service for all Points of Service that have a normal maximum demand of less than 50 kVA with single or three-phase electric service at secondary voltage, throughout the territory served by the Company. These services will have energy meters or will have energy consumption on an estimated basis. This rate is also applicable to all sites for which no other rate is applicable

Price

Charges for service in any one billing day shall be the Energy Charge, determined for each individual Point of Service:

Energy Charge

(per kWh)

Transmission SAS-SC1* $0.03276

The minimum daily charge is the Energy Charge.

Application

1) Power Factor Correction - where a Customer’s power factor is found to be less than 90%, the Company may require the Customer to install corrective equipment

2) Price Adjustments - the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J)

Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton.

* Refer to the values associated with the Cell References in the Attached Table 3.

Page 5: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 3 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial 50 kVA to <150 kVA (2017 RATE)

Price Schedule SAS-MC Effective: January 1, 2017

For System Access Service for all Points of Service that have a normal maximum demand of greater than or equal to 50 kVA and less than 150 kVA, with single or three-phase electric service at secondary voltage, throughout the territory served by the Company. These services will have demand meters

Price

Charges for service in any one billing day shall be the sum of the Demand Charge and Energy Charge, determined for each individual Point of Service:

Demand Charge

(per kVA per Day)

Energy Charge

(per kWh)

Transmission SAS-MC1* $0.23444

SAS-MC2* $0.00435

The billing demand may be estimated or measured and will be the greater of the following:

(a) the highest metered demand during the billing period; (b) 90% of the highest metered demand in the twelve month period including and ending with the

billing period; (c) the estimated demand; (d) the contract demand; (e) 5 kVA.

The minimum daily charge is the sum of the Service Charge and the total Demand Charge.

Page 6: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 4 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial 50 kVA to <150 kVA (2017 RATE)

Price Schedule SAS-MC (Continued) Effective: January 1, 2017

Application

1) Power Factor Correction - where a Customer’s power factor is found to be less than 90%, the

Company may require the Customer to install corrective equipment 2) Price Adjustments - the following price adjustments (riders) may apply:

Local Access Fees (Rider LAF) – See Note Temporary Adjustment (Rider G)

Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 7: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 5 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial 150 kVA to <5,000 kVA Distribution-Connected

(2017 RATE)

Price Schedule SAS-TOU Effective: January 1, 2017

For System Access Services, single or three-phase, that have a normal maximum demand of greater

than or equal to 150 kVA and less than 5,000 kVA, for all Points of Service throughout the territory served by the Company from the Alberta Interconnected System. This rate is applicable to all sites that are served at the secondary voltage of the transformer, normally with a delivery voltage of below 1,000 volts.

The Point of Service must be equipped with interval data metering.

Price

Charges for service in any one billing day shall be the sum of the Energy Charge, Demand Charge,

OSS Charge and Operating Reserve Charges, determined for each individual Point of Service:

Energy Charge (per

kWh)

Demand Charge

(per kW per Day)

OSS Charge

(per kW per Day)

Operating Reserve

(% x kWh delivered during each hour x

Applicable Pool Price during each hour)

Transmission SAS-TOU1* $0.00215

SAS-TOU2* $0.35762

SAS-TOU3* $0.00120

SAS-TOU4* 6.46%

Billing demand for the Transmission charges shall be the higher of:

(a) The highest metered demand during the billing period;

(b) 85% of the highest metered demand in the 12-month period including and ending with the billing

period;

(c) the estimated demand;

(d) the Transmission Contract Demand (TCD);

(e) 50 kilowatts.

Page 8: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 6 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial 150 kVA to <5,000 kVA Distribution Connected

(2017 RATE)

Price Schedule SAS-TOU (Continued) Effective: January 1, 2017

Application

1) Power Factor Correction - where a Customer’s power factor is found to be less than 90%, the Company may require the Customer to install corrective equipment.

2) Price Adjustments - the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 9: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 7 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Primary Commercial/Industrial 150 kVA to <5,000 kVA Distribution Connected

(2017 RATE)

Price Schedule SAS-TOUP Effective: January 1, 2017

For System Access Service, single or three-phase, that have a normal maximum demand of greater

than or equal to 150 kVA and less than 5,000 kVA, for all Points of Service throughout the territory served by the Company from the Alberta Interconnected System. This rate is applicable to all sites that are served at the primary voltage of the transformer, normally with a delivery voltage of over 1,000 volts.

The Point of Service must be equipped with interval data metering.

Price

Charges for service in any one billing day shall be the sum of the Energy Charge, Demand Charge, OSS

Charge and Operating Reserve Charges, determined for each individual Point of Service:

Energy Charge (per

kWh)

Demand Charge

(per kW per Day)

OSS Charge

(per kW per Day)

Operating Reserve

(% x kWh delivered during each hour x

Applicable Pool Price during each hour)

Transmission SAS-TOUP1* $0.00213

SAS-TOUP2* $0.35814

SAS-TOUP3* $0.00120

SAS-TOUP4* 6.38%

Billing demand for the System charges shall be the higher of:

a) The highest metered demand during the billing period;

b) 85% of the highest metered demand in the 12-month period including and ending with the billing

period;

c) the estimated demand;

d) the Transmission Contract Demand (TCD);

e) 50 kilowatts.

Page 10: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 8 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Primary Commercial/Industrial 150 kVA to <5,000 kVA Distribution Connected

(2017 RATE)

Price Schedule SAS-TOUP (Continued) Effective: January 1, 2017

Application

1) Power Factor Correction - where a Customer’s power factor is found to be less than 90%, the Company may require the Customer to install corrective equipment

2) Price Adjustments - the following price adjustments (riders) may apply:

Local Access Fees (Rider LAF) - Note Temporary Adjustment (Rider G)

Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 11: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 9 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial Greater than 5,000 kVA Distribution-Connected

(2017 RATE)

Price Schedule SAS-CS Effective: January 1, 2017

For System Access Service, single or three-phase, that have a maximum demand of greater than or

equal to 5,000 kVA in the previous year, for all Points of Service throughout the territory served by the Company from the Alberta Interconnected System. This rate is also applicable to new sites that forecast to have a normal maximum demand of greater than or equal to 5,000 kVA. The Point of Service must be equipped with interval data metering.

Each new site under this rate is required to enter into an Electric Service Agreement with EPCOR SYSTEM.

Price

Charges for service in any one billing day shall be the sum of the Energy Charge, Demand Charge,

OSS Charge and Operating Reserve Charges, determined for each individual Point of Service:

Energy Charge (per

kWh)

Demand Charge

(per kW per Day)

OSS Charge

(per kW per Day)

Operating Reserve

(% x kWh delivered during each hour x

Applicable Pool Price during each hour)

Transmission SAS-CS1* $0.00211

SAS-CS2* $0.34657

SAS-CS3* $0.00116

SAS-CS4* Refer to Table 4 below

Billing demand for the System charges shall be the higher of:

a) The highest metered demand during the billing period;

b) 90% of the highest metered demand in the 24-month period including and ending with the billing

period;

c) the estimated demand;

d) the Transmission Contract Demand (TCD);

e) 50 kilowatts.

Page 12: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 10 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial Greater than 5,000 kVA Distribution-Connected

(2017 RATE)

Price (Continued)

Application

1) Power Factor Correction - where a Customer’s power factor is found to be less than 90%, the Company may require the Customer to install corrective equipment

2) Price Adjustments - the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 13: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 11 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial Greater than 5,000 kVA Totalized Distribution-Connected

(2017 RATE)

Price Schedule SAS-CST Effective: January 1, 2017

For System Access Service, single or three-phase, that have a totalized maximum demand of greater

than or equal to 5,000 kVA in the previous year, for all Points of Service throughout the territory served by the Company from the Alberta Interconnected System. This rate is also applicable to new sites that forecast to have a normal totalized maximum demand of greater than or equal to 5,000 kVA. The Point of Service must be equipped with interval data metering.

Each new site under this rate is required to enter into an Electric Service Agreement with EPCOR SYSTEM.

Price

Charges for service in any one billing day shall be the sum of the Energy Charge, Demand Charge,

OSS Charge and Operating Reserve Charges, determined for each individual Point of Service:

Energy Charge (per

kWh)

Demand Charge

(per kW per Day)

OSS Charge

(per kW per Day)

Operating Reserve

(% x kWh delivered during each hour x

Applicable Pool Price during each hour)

Fixed Point of Delivery Daily

Charge

Transmission SAS-CST4* $0.00210

SAS-CST3* $0.39821

SAS-CST6* $0.00138

SAS-CST5* 6.31%

SAS-CST7* $233.01

Billing demand for the System charges shall be the higher of:

a) The highest metered demand during the billing period;

b) 90% of the highest metered demand in the 24-month period including and ending with the billing

period;

c) the estimated demand;

d) the Transmission Contract Demand (TCD);

e) 50 kilowatts.

Page 14: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 12 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Commercial/Industrial Greater than 5,000 kVA Totalized Distribution-Connected

(2017 RATE)

Price (Continued)

Application

1) Power Factor Correction - where a Customer’s power factor is found to be less than 90%, the Company may require the Customer to install corrective equipment

2) Price Adjustments - the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 15: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 13 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Direct Transmission-Connected (2017 RATE)

Price Schedule SAS-DC Effective: January 1, 2017

For System Access Service, single or three-phase, for all Points of Service throughout the territory served by the Company from the Alberta Interconnected System, that are directly connected to a transmission substation, and do not make any use of System facilities owned by EPCOR System.

The Point of Service must be equipped with interval data metering.

Price

Charges for service in any one billing day shall be the sum of the Energy Charge, Demand Charge,

OSS Charge and Operating Reserve Charges, determined for each individual Point of Service:

Transmission The applicable rate(s) of the Alberta Electric System Operator Tariff

Total charges from the AESO for each Point of Delivery applicable to sites on this rate will be flowed through to such sites.

Application

1) Price Adjustments - the following price adjustments (riders) may apply:

Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 16: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 14 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

GENERATOR INTERCONNECTION Distribution-Connected

(2017 RATE)

Price Schedule SAS-DGEN Effective: January 1, 2017

For Points of Service served by the Company from the Alberta Interconnected System, with on-site

generating equipment connected to the System, which may be used to supply load at the same site.

For interconnection of the generator to the Distribution System

To charge Generators if the Point of Delivery attracts STS charges from the AESO

The Point of Service must be equipped with bi-directional interval data metering, for both supply and demand, the cost of which will be in addition to the charges under this rate.

Price

Charges for service in any one billing day shall be the sum of the STS charges from the AESO: Capital Recovery Charges:

The cost of the Incremental Interconnection Facilities will be determined as set out in Section 9.4 of the Terms and Conditions for System Service Connections. The total amount will be collected from the customer in accordance with Section 9.5 of the Terms and Conditions for System Service Connections. A contract will be arranged between the customer and the Company, specifying the contract term and the monthly amount, which will be calculated using the Company’s Rate of Return and Depreciation in effect at the commencement of the contract term.

The Generating customer will be required to pay all replacement costs for incremental facilities as per Section 9.4 of the Terms and Conditions for System Service Connections.

Application

1) Price Adjustments - the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton.

Page 17: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 15 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

STREET LIGHTING SERVICE (2017 RATE)

Price Schedule SAS-SL Effective: January 1, 2017

To the Retailer for services owned by the City of Edmonton for Street Lighting Service

Price

Charges for service in any one billing month are the sum of the Demand Charges.

Demand Charge

(per kW per Day)

Transmission SAS-SL1* $0.18117

Billing demand for the Transmission charges shall be 90% of the highest metered demand in the 12-

month period including and ending with the billing period.

Application

1) Price Adjustments – the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 18: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 16 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Traffic Control (2017 RATE)

Price Schedule SAS-TL Effective: January 1, 2017

For services owned by the City of Edmonton for Traffic Lights and other Traffic Control Service

Price

Charges for service in any one billing month are the sum of the Demand Charges.

Demand Charge

(per kW per Day)

Transmission SAS-TL1* $0.73937

Billing demand for the Transmission charges shall be 90% of the highest metered demand in the 12-

month period including and ending with the billing period.

Application

1) Price Adjustments – the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 19: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 17 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Security Lighting Service (2017 RATE)

Price Schedule SAS-SEL Effective: January 1, 2017

For existing unmetered Security Light Service. This rate is not available to new services.

Price

Charges for service in any one billing month are the sum of the Demand Charges, determined for

each individual Point of Service.

Demand Charge

(per kW per Day)

Transmission SAS-SEL1* $0.18907

Billing demand for the Transmission charges shall be 90% of the highest metered demand in the 12-

month period including and ending with the billing period.

Application

1) Price Adjustments – the following price adjustments (riders) may apply: Local Access Fees (Rider LAF) – See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 20: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 18 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Lane Lighting Service (2017 RATE)

Price Schedule SAS-LL Effective: January 1, 2017

For the services owned by the City of Edmonton for Lane Lights

Price

Charges for service in any one billing month are the sum of the Demand Charges.

Demand Charge

(per kW per Day)

Transmission SAS-LL1* $0.18986

Billing demand for the Transmission charges shall be 90% of the highest metered demand in the 12-

month period including and ending with the billing period.

Application

1) Price Adjustments – the following price adjustments (riders) may apply: Local Access Fees (Rider LAF)- See Note

Temporary Adjustment (Rider G) Interim Adjustment (Rider J) Short Term Adjustment (Rider K)

Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The LAF applies to all sites within the City of Edmonton. * Refer to the values associated with the Cell References in the Attached Table 3.

Page 21: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 19 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

TEMPORARY ADJUSTMENT Rider G - Balancing Pool Rider Effective: January 1, 2017

Applicable to all customers, at points of service, throughout the territory served by the Company for

energy consumption.

Current Rider G rates are available on EPCOR’s website:

https://www.epcor.com/products-services/power/rates-tariffs-fees/Pages/power-tariffs-terms-and-

conditions-edmonton.aspx

Rate Schedule Energy Charge Demand

Charge per KW or KVA per Day

OSS Charge Operating Reserve

SAS-R - N/A N/A N/A

SAS-SC - N/A N/A N/A

SAS-MC - N/A N/A N/A

SAS-TOU - N/A N/A N/A

SAS-TOUP - N/A N/A N/A

SAS-CS - N/A N/A N/A

SAS CST - N/A N/A N/A

SAS-DC - N/A N/A N/A

SAS-DGEN - N/A N/A N/A

SAS-SL - N/A N/A N/A

SAS-TL - N/A N/A N/A

SAS-LL - N/A N/A N/A

SAS-SEL - N/A N/A N/A

Note: Rider G does not apply to Rider LAF and Rider J.

Page 22: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 20 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

INTERIM ADJUSTMENT Rider J - SAS True-Up Rider Effective: January 1, 2017

Applies to all electric service throughout the territory served by the Company when a charge or refund

is approved by the AUC.

Current Rider J rates are available on EPCOR’s website:

https://www.epcor.com/products-services/power/rates-tariffs-fees/Pages/power-tariffs-terms-and-

conditions-edmonton.aspx

Rate Schedule

Energy Charge Demand Charge per KW or KVA per Day

OSS Charge Operating Reserve

SAS-R N/A N/A N/A N/A

SAS-SC N/A N/A N/A N/A

SAS-MC N/A N/A N/A N/A

SAS-TOU N/A N/A N/A N/A

SAS-TOUP N/A N/A N/A N/A

SAS-CS N/A N/A N/A N/A

SAS-CST N/A N/A N/A N/A

SAS-DC N/A N/A N/A N/A

SAS-DGEN N/A N/A N/A N/A

SAS-SL N/A N/A N/A N/A

SAS-TL N/A N/A N/A N/A

SAS-LL N/A N/A N/A N/A

SAS-SEL N/A N/A N/A N/A

Page 23: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 21 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

SHORT-TERM ADJUSTMENT Rider K - Transmission Charge Deferral Account True-Up Rider Effective: January 1, 2017

Applies to all electric service throughout the territory served by the Company when a charge or refund

is approved by the AUC.

Current Rider K rates are available on EPCOR’s website:

https://www.epcor.com/products-services/power/rates-tariffs-fees/Pages/power-tariffs-terms-and-

conditions-edmonton.aspx

Rate Schedule

Energy Charge Demand Charge per KW or KVA per Day

OSS Charge Operating Reserve

SAS-R - N/A N/A N/A

SAS-SC - N/A N/A N/A

SAS-MC - N/A N/A N/A

SAS-TOU - N/A N/A N/A

SAS-TOUP - N/A N/A N/A

SAS-CS - N/A N/A N/A

SAS-CST - N/A N/A N/A

SAS-DC - N/A N/A N/A

SAS-DGEN - N/A N/A N/A

SAS-SL - N/A N/A N/A

SAS-TL - N/A N/A N/A

SAS-SEL - N/A N/A N/A

SAS-LL - N/A N/A N/A

Page 24: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 22 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Table 3: EDTI’s 2017 System Access Service Rate Schedules (2017 RATE)

Rate Class Cell

Reference Value Description

Residential SAS-R1 $0.03080 / kWh of Energy Charge

Commercial/ Industrial Service <50 kVA

SAS-SC1 $0.03276

/ kWh of Energy Charge

Commercial/ Industrial Service 50 kVA to Less Than 150 kVA

SAS-MC1 $0.23444

/kVA/day of Demand Charge

Commercial/ Industrial Service 50 kVA to Less Than 150 kVA

SAS-MC2 $0.00435

/ kWh of Energy Charge

150 to 5000 kVA (Secondary) SAS- TOU1 $0.00215 / kWh of Energy Charge

150 to 5000 kVA (Secondary) SAS-TOU2 $0.35762 /kW/day of Demand Charge

150 to 5000 kVA (Secondary) SAS-TOU3 $0.00120 /kW/day of Other System Support Charge

150 to 5000 kVA (Secondary) SAS-TOU4 6.46% Operating Reserve Charge (Total Energy x

OR% x Pool Price)

150 to 5000 kVA (Primary) SAS-TOUP1 $0.00213 / kWh of Energy Charge

150 to 5000 kVA (Primary) SAS-TOUP2 $0.35814 /kW/day of Demand Charge

150 to 5000 kVA (Primary) SAS-TOUP3 $0.00120 /kW/day of Other System Support Charge

150 to 5000 kVA (Primary) SAS-TOUP4 6.38% Operating Reserve Charge (Total Energy x

OR% x Pool Price)

> 5000 kVA SAS-CS1 $0.00211 / kWh of Energy Charge

> 5000 kVA SAS-CS2 $0.34657 /kW/day of Demand Charge

> 5000 kVA SAS-CS3 $0.00116 /kW/day of Other System Support Charge

> 5000 kVA SAS-CS4 See Table 4 for individual OR%

Operating Reserve Charge (Total Energy x OR% x Pool Price)

CST SAS-CST4 $0.00210 / kWh of Energy Charge

CST SAS-CST3 $0.39821 /kW/day of Demand Charge

CST SAS-CST6 $0.00138 /kW/day of Other System Support Charge

CST SAS-CST5 6.31% Operating Reserve Charge (Total Energy x

OR% x Pool Price)

CST SAS-CST7 $233.01 Fixed Point of Delivery Daily Charge

Direct Connects to AESO SAS-DC1 Flowthrough / kWh of Energy Charge

Direct Connects to AESO SAS-DC2 Flowthrough /kW/day of Demand Charge

Direct Connects to AESO SAS-DC3 Flowthrough /kW/day of Other System Support Charge

Direct Connects to AESO SAS-DC4 Flowthrough Pool Price Charge (Total Energy)

Direct Connects to AESO SAS-DC5 Flowthrough Fixed Point of Delivery Daily Charge Multiplied

by applicable Substation Fraction

Photo Eye (Street Lights) SAS-SL1 $0.18117 /kW/day of Demand Charge

Continuous Operating Load SAS-TL1 $0.73937 /kW/day of Demand Charge

Photo Eye (Security Lights) SAS-SEL1 $0.18907 /kW/day of Demand Charge

Photo Eye (Lane Lights) SAS-LL1 $0.18986 /kW/day of Demand Charge

Page 25: DT Schedule A - EPCOR · 2017. 4. 4. · Note: The Local Access Fee (LAF) is a surcharge imposed by the City of Edmonton and is not approved by the Alberta Utilities Commission. The

EPCOR Distribution & Transmission Inc.

Page 23 of 23 Effective: January 1, 2017

EPCOR Distribution & Transmission Inc.'s Terms and Conditions for Distribution Access Service and Terms and Conditions for Distribution Service Connections apply to all retailers and customers provided with Distribution Access Services and/or System Access Service by EPCOR Distribution & Transmission Inc. Both sets of Terms and Conditions are available at EPCOR System offices during normal working hours or on the website www.epcor.ca.

Schedule 2017 SAS

Table 4: EDTI’s 2017 Customer Specific Loss Factor and Operating Reserve Percentage

Rate Class Cell

Reference CS Loss Factor

SAS-CS4 Description

> 5000 kW - Primary CS20 0.16% 6.31% Specific Distribution Loss Factor - CS20

> 5000 kW - Primary CS21 0.35% 6.32% Specific Distribution Loss Factor - CS21

> 5000 kW - Primary CS22 1.35% 6.39% Specific Distribution Loss Factor - CS20

> 5000 kW - Primary CS23 0.18% 6.31% Specific Distribution Loss Factor - CS23

> 5000 kW - Primary CS24 0.09% 6.31% Specific Distribution Loss Factor - CS24

> 5000 kW - Primary CS25 0.20% 6.31% Specific Distribution Loss Factor - CS25

> 5000 kW - Primary CS26 1.44% 6.39% Specific Distribution Loss Factor - CS26

> 5000 kW - Primary CS27 0.20% 6.31% Specific Distribution Loss Factor - CS27

> 5000 kW - Primary CS28 0.43% 6.33% Specific Distribution Loss Factor - CS28

> 5000 kW - Primary CS29 0.38% 6.32% Specific Distribution Loss Factor - CS29

> 5000 kW - Primary CS30 0.01% 6.30% Specific Distribution Loss Factor - CS30

> 5000 kW - Primary CS31 0.18% 6.31% Specific Distribution Loss Factor - CS31

> 5000 kW - Primary CS32 0.19% 6.31% Specific Distribution Loss Factor - CS32

> 5000 kW - Primary CS33 1.37% 6.39% Specific Distribution Loss Factor - CS33

> 5000 kW - Primary CS34 0.10% 6.31% Specific Distribution Loss Factor - CS34

> 5000 kW - Primary CS35 0.30% 6.32% Specific Distribution Loss Factor - CS35

> 5000 kW - Primary CS37 0.12% 6.31% Specific Distribution Loss Factor - CS37

> 5000 kW - Primary CS38 0.00% 6.30% Specific Distribution Loss Factor - CS38

> 5000 kW - Primary CS39 0.724% 6.35% Specific Distribution Loss Factor - CS39

> 5000 kW - Primary CS40 1.273% 6.38% Specific Distribution Loss Factor - CS40

> 5000 kW - Primary CS41 0.668% 6.34% Specific Distribution Loss Factor - CS41

> 5000 kW - Primary CS42 0.574% 6.34% Specific Distribution Loss Factor - CS42

> 5000 kW - Primary CS43 0.513% 6.33% Specific Distribution Loss Factor - CS43

> 5000 kW - Primary CS44 0.470% 6.33% Specific Distribution Loss Factor - CS44