dubai lng terminal dusup
DESCRIPTION
Presentation of Dubai's DUSUP LNG terminalTRANSCRIPT
1
Dubai LNG Terminal
Author: Abdi R. Nayak – DUSUP
Co-Author: Maaike van der Werf - Shell
Dubai Supply Authority
2
Who Are We?
• Dubai Supply Authority (DUSUP) was created by decree
in 1992, owned 100% by the Dubai government
• It is the sole authority for supply of gas and the operation
of all natural gas pipeline systems in the Emirate of Dubai
• It is one of the Emirate’s strategic energy infrastructure
assets providing economic, clean and reliable energy for
power generation and economic development of Dubai
• It employs approximately 180 professional and technical
staff to develop, operate and maintain the gas
infrastructure in Dubai
3
Our Assets
Collectively creating flexibility for DUSUP to optimise based on market opportunities & seasonality
~460 Km of
transmission
pipeline
Gas storage field
Gas Control Operations Center
LNG TerminalCustomers – Power generation &
Industrials
Pipeline
Supplies
4
Why LNG?
jan-01 jan-02 jan-03 jan-04 jan-05 jan-06 jan-07 jan-08 jan-09 jan-10
Dubai Electricity Load Growth
Load Growth Limited Pipeline SuppliesPeak Demand
Cleaner FuelFlexibility
LNG FSRU FID
5
Why an FSRU?
Quick to implement
Waterfront access is at a premium
Lower life cycle cost than conventional terminal for short
operational period of 10-15 years
New application but based on existing technologies
6
Marine facilities Shell contracted for concept selection and the initial design
Halcrow performed detailed engineering
Archirodon Construction (Overseas) Company constructed the marine facilities
Breakwater, Jetty and sub-sea pipeline construction October 6th 2010
FSRU Golar was contracted to deliver the FSRU and to undertake the detailed design
through Moss Maritime, based on DNV Regas notation.
Conversion at Keppel Shipyard Singapore completed in April 2010
Commissioning at the jetty and first gas October 30th 2010
Shell performed overall technical and safety assurance on the whole project on
behalf of DUSUP
Project Background:
7
LOA: 288 m Beam 44 m Draft 11.5 m
FSRU – Golar Freeze
Conversion of Golar Freeze into an Floating Storage Regasification Unit
126,000 m3 storage capacity
Open loop vaporizers for regasification utilizing favorable seawater conditions
Send out capacity:
– base 400 MMSCFD
– peak 480 MMSCFD
Moored all year round at jetty
Traditional unloading arms as with shore terminals
NO “flex hoses” for LNG transfer
2 x 240 plus one installed spare
8
Technology Overview
• Proven technologies packaged to address DUSUP’s
requirements.
• Key systems:
− Modular Regasification skids by Hamworthy Gas System
− Additional power generation and seawater supply systems
− First application of traditional LNG Arms on a FSRU
− Integrated mooring system between jetty, FSRU & LNGC allows
the LNGC mooring to FSRU & jetty via quick release hooks
− Minimum Sendout Compressor - reciprocating compressor to
send excess BOG onshore, Minimum Sendout Compressor
− Integrated safety systems between FSRU & Jetty
9
REGASIFICATION
SKIDS
Process Overview
SUCTION
DRUM
1
2
3
METERING
SEA WATER SYSTEM
MSO
COMPRESOR
Auxiliaries
(Fuel)
LNG
Vapor
10
LNG GAS
LNG/Propane Ex
SW/Propane Ex
HP Pumps
Propane Drum
Propane
Pump
Trim Heaters
Seawater In
Regasification Skids
Seawater Out Seawater Out
11
Regas Skids
HP Pumps
Trim Heater
Skid’s Outlet
SW/Propane Ex
LNG/Prop. Ex
& Propane
drum
12
Forward Machinery Space
Condensers
Turbo Generators
5.5 MW each
Seawater lift pumps
Vaporizers
13
Terminal Layout Design
Island jetty , capable to convert into conventional LNG terminal jetty
30m by 30m jetty platform
Permanent mooring facilities for FSRU
– Able to receive LNGC size up to Q-flex
Breasting and Mooring Dolphins
High pressure gas line to shore and tie in to Dubai gas grid (~1.4 km)
Security surveillance & gas detection systems
14
Jetty & Mooring Dolphins
Mooring
Dolphins
Gas Arms to
FSRU
Pipeline Riser Power and Controls “Umbilical cords”
Isolation Valve
15
LNG Transfer Arms
• First application of traditional arms. No “hoses”. Same cargo transfer
procedures as shore based terminals
• 16 inch
• 2 Liquid
• 1 Vapor
• QC/DC
• PERC
• ESD 1
• ESD 2
16
LNGC - Terminal Interface
Integrated controls between Jetty &
FSRU, so systems operate as one unit.
QR hooks on jetty and FSRU allow
release of LNGC (FSRU permanently
moored)
Mooring load monitoring information to
LNGC via fiber optic
Speed of approach monitoring & vessel
movement recording during approach &
berthing
Operations similar to berthing at a
shore based terminal
17
Commissioning & Startup
• Challenges:
• Safety & Environmental considerations
• Geographic locations
• Different approaches (marine vs. shore practices)
• Solutions:
• Close coordination of interfaces during design & construction
• Enforcing cleanliness, tightness & Integrity protocols
• Rethinking typical terminal commissioning sequences/timings
• Segregation of commissioning activities to reduce
interdependencies
18
Questions?
Author:Abdi NayakAssets Manager –LNGDubai Supply AuthorityMobile: +971 50 628 [email protected]
Co-Author:Maaike van der WerfSenior Process Engineer LNG & Gas ProcessingShell Global Solutions International BVMobile: +31 6 5236 [email protected]