dubbo base hospital redevelopment stage 1 & 2 review of

82
Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of Environmental Factors Dubbo, NSW External Works Project Stormwater Management Plan Prepared for: Health Infrastructure NSW By: Enstruct Group Revision: C July 2012

Upload: others

Post on 03-May-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of Environmental Factors Dubbo, NSW External Works Project Stormwater Management Plan

Prepared for: Health Infrastructure NSW By: Enstruct Group Revision: C

July 2012

Page 2: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

ISSUE AUTHORISATION PROJECT: Dubbo Base Hospital – External Works Project

Project No: 4363 Rev

Date

Purpose of Issue /Nature of Revision

Prepared by

Reviewed by

Issue Authorised by

A

30/05/12

Draft Issue

IH

TBB

IH

B 08/06/12 Issued For Approval IH TBB TBB

C 05/07/12 Issued For Approval IH TBB TBB

Enstruct group P/L Level 4 – 2 Glen St

Milsons Point Sydney NSW 2061

Australia. Telephone (02) 8904-1444 Facsimile (02) 8904-1555

Page 3: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

1

Table of Contents

1.0 Introduction 2 2.0 Development Description & Previous Reports 2 3.0 Site Description 3 4.0 Flood Analysis 4 5.0 Stormwater Drainage 5 5.1 Rainfall Data 5 5.2 Catchments 5 5.3 Existing Infrastructure 5 5.4 Points of Discharge 6 5.5 Stormwater Drainage Assessment 7 5.6 On-Site Detention 9 6.0 Erosion and Sediment Control 12 Appendix Rainfall Table – Dubbo Calculations Existing Catchment Analysis Development Catchment Analysis On-Site Detention Analysis Drawings 4363-CIV-SI-100-01 General Arrangement Plan Sheet 1 of 4 4363-CIV-SI-100-02 General Arrangement Plan Sheet 2 of 4 4363-CIV-SI-100-03 General Arrangement Plan Sheet 3 of 4 4363-CIV-SI-100-04 General Arrangement Plan Sheet 4 of 4 4363-CIV-SI-100-11 Sediment & Erosion Control Plan & Details Sheet 1 of 4 4363-CIV-SI-100-12 Sediment & Erosion Control Plan & Details Sheet 2 of 4 4363-CIV-SI-100-13 Sediment & Erosion Control Plan & Details Sheet 3 of 4 4363-CIV-SI-100-14 Sediment & Erosion Control Plan & Details Sheet 4 of 4 4363-CIV-SI-100-40 Civil Details Sheet 1 of 2 4363-CIV-SI-100-41 Civil Details Sheet 2 of 2

Page 4: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

2

1.0 Introduction Enstruct have been engaged by Health Infrastructure NSW to complete the detailed civil engineering design works for the external works redevelopment of the Dubbo Base Hospital. The works include construction of a new car park, a new link road and associated infrastructure.

This Stormwater Management Plan discusses the proposed stormwater drainage design for the site including the on-site detention requirements and stormwater discharge from the site. The report also discusses sediment and erosion control for the site.

2.0 Development Description & Previous Reports The proposed development discussed in this report is the enabling works required for the redevelopment of the Dubbo Base Hospital In order to progress the development of the hospital in line with the Dubbo Base Hospital master plan there is a requirement to create additional car parking on the site to cater for the additional users associated with the Stage 1and 2 development on the site. The reorganising of the existing car park area to create a more efficient car parking arrangement also lends itself to the redevelopment of the existing car park which is currently in need of repair. The master plan also calls for the development of a circulation route around the site. To formalise this route a new link road will be constructed between the new car park and the existing road to the west of the existing maintenance buildings. The development of the new car parking area and the new link road will also require the redevelopment of the existing stormwater drainage system along the east side of the site. This drainage design will also make allowance for the proposed stage 1 development of the hospital. Previous reports and investigations have been utilised in the preparation of this report and these reports are listed below:

Dubbo Base Hospital Preliminary Schematic Design/Concept Design Report, Revision V2.0 dated 2nd November 2010.

Geotechnical Investigation – Dubbo Base Hospital Redevelopment, Myall Street, Dubbo by Douglas Partners, Project 72811 dated April 2012.

Dubbo Base Hospital Redevelopment Project – Structural & Civil Engineering – Site Engineering Analysis Conditions and Risk Analysis Report by Enstruct, Project 4363, Revision B dated April 2012.

Dubbo Base Hospital Redevelopment Project – Structural & Civil Engineering – Site Massing Option Assessment Report by Enstruct, Project 4363, revision B dated April 2012.

Dubbo Base Hospital survey information by Imrie, Astley & Associates. Job number 11-232, drawing revision 3 dated March 2012.

Page 5: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

3

3.0 Site Description & Catchment Analysis The site discussed in this report is described as Lot 12 in DP 1159243. The site is located to the North of Myall Street in Dubbo, NSW. The site is bound by Myall Street to the South, the Railway corridor to the west, Muller Street and Moran Drive and Fitzhill Parade to the North and residential development to the east. The site has a total area of 13.4Ha and currently contains the existing hospital campus. The current campus consists of a number of buildings ranging in size and position, car parking areas, circulation roads, a helicopter pad and landscaping areas. The current site topography falls from the north east corner of the site to the southern and western boundaries. The fall of the site varies considerably with the eastern side of the site relatively flat and the western side being much steeper, falling towards the rail corridor. Investigation of the current site topography and existing site drainage infrastructure suggests that the site has been divided into two separate catchment areas. The eastern side of the site draining south towards Myall Street and the western side of the site draining towards the existing council drainage channel on the opposite side of the rail corridor. Initial catchment assessment has been summarised below. This assessment has been used as a base line for the stormwater drainage design for the proposed development.

Sub-catchment Name

Catchment Area (ha)

Percentage Impermeable (%)

East 4.3 60 West 9.1 40 Total 13.4 46

Existing Site Catchment Summary

Page 6: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

4

4.0 Flood Analysis During the course of the design of the sites concept stormwater drainage design an assessment into the impact of flooding on the site was undertaken. Reference was made to the Dubbo City Council Flood Prone Areas report G2.2 with the results summarised in the table below.

Location FSRL (1 in 100 Year Flood)

FPL (1 in 100 year flood + 500mm) PMF

Erskine Street R.L. 262.30 262.8 266.0 River Street R.L. 262.0 262.5 265.7

Flood Levels from Council Report The lowest site level obtained from the site survey indicates that at the North West corner of the site the existing site levels are R.L. 265.0. This indicates that this corner of the site will be flood affected during a PMF flood event however the proposed development of the site will occur at a considerably higher level as the site falls considerably to the west of the site. The levels on the site in the areas where development is proposed are in the vicinity of R.L. 278.00 which is fully 12 meters above the PMF levels associated with the site. No works are proposed in the areas of the site which could be potentially affected by the flood plain and as such, provided the discharge flows from the development are not increased, no adverse effects will be caused by the development on the existing flood levels up or down stream of the site.

Page 7: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

5

5.0 Stormwater Drainage

5.1 Rainfall Data

Dubbo City Council has adopted a standard rainfall chart for use within the council area. Copy of this chart is included in the Appendix to this report. This chart was prepared by the Bureau of Meteorology based on accumulated rainfall data for the area. This rainfall data has been used in the design of the stormwater drainage on this project.

5.2 Catchments & Runoff

As discussed in the site description section above the rainfall catchment for the site is subdivided into two separate sub-catchments. The proposed development for the early works will affect both catchments with the proposed car park and allowance for the stage 1 building draining to Myall Street and the new link road draining to the rail corridor.

To ensure that the development does not have a negative impact on the existing downstream drainage post development flows for the site have been attenuated to the 5 year predevelopment flows.

5.3 Existing Infrastructure

5.3.1 Myall Street The downstream drainage system located under Myall Street is owned and maintained by Dubbo City Council. The current council drainage system below Myall Street consists of a 450mm diameter concrete pipe under the southern side of the street. The pipe is then assumed to drain down toward the Macquarie River to the West of the site. During initial discussions with council it was confirmed that the existing drainage infrastructure had a design capacity to cater for the 10 year design storm flows of the total catchment however the current drainage system does not have the capacity to cater for the existing catchment flows and downstream surcharging is a common problem. To assist in the alleviation of pressure on the existing council stormwater drainage system the current site discharge flows have been calculated and the proposed stormwater drainage for the development designed to ensure that the post development discharge flows will be reduced. 5.3.2 Rail Corridor The drainage channel located to the west of the current rail corridor is owned and maintained by Dubbo City Council. The channel currently drains to the north towards wetlands east of Fitzroy Street.

Page 8: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

6

The channel is currently in a state of disrepair and is overgrown with vegetation. The relatively flat grade of the channel, its unsurfaced state and the current state of vegetation has caused drainage issues within the channel which is currently retaining water in a number of locations. The channel section size would suggest that if repaired the channel would have sufficient capacity to cater for the existing flows which are conveyed through it. The proposed development drainage system has been designed so that the new link road will utilise the existing site detention basin to attenuate the post development flows so as not to exceed that of the predevelopment flows.

5.4 Point of Discharge

Two points of discharge are proposed for the development. The main area of the car park and the allowance for the Stage 1 and 2 development of the hospital have been designed to discharge stormwater flows to the existing council stormwater drainage system below Myall Street. The top section of the car park and the new link road has been designed to discharge stormwater flows to the existing rail corridor drainage channel. The Myall Street system will connect to the existing site connection point at the entrance to the site. The rail corridor system will discharge from the existing site detention basin as overland flow down the slope, under the rail corridor and into the stormwater channel. Both discharge points will be located downstream of stormwater attenuation devices which will ensure that the post development discharge flows are less than the predevelopment flows and as such assist in the alleviation of pressure on the existing council stormwater drainage assets.

Page 9: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

7

5.5 Stormwater Drainage Assessment

5.5.1 Myall Street System

The current site drainage system discharging to Myall Street drains an approximate catchment area of 4.30Ha. The catchment consists of up to 60% impermeable surface and 40% landscaped area. The impermeable area consists of the main site car parking area, the front of house buildings and the original hospital buildings fronting Myall Street. The system connects to council’s external system at two locations, one at the hospital main entrance and one further west along Myall Street. The proposed early works development will not affect the connection to the west and as such assessment of this system will not be included as part of this report. The area under investigation accounts for 80% of the total catchment area. The system connecting at the hospital main entrance consists of a single main line which runs north below the main hospital entrance road. Building drainage lines are connected to this main line at a number of locations and these connections must be retained during the development of the early works. The development of the car park results in the removal of the existing car park drainage system. This system will be replaced by the new proposed system. This system will also make allowance for the future connection of the Stage 1 and 2 works. This means that the pipe sizes and levels are designed to allow for a direct connection of the proposed development to the system. The current drainage system has capacity to convey the 10 year rainfall event flows however the development system has the capacity to convey the 20 year design flows. The additional underground piped flows are attenuated by a stormwater detention tank adjacent to the pump room near the site entrance. Flows in excess of the design flows will be conveyed within the road corridor as overland flow towards Myall Street. The catchment assessment of the Myall Street drainage system is summarised in the table below. This assessment has been undertaken using Rational Method.

Catchment Type Catchment Area (Ha)

Time of Concentration

(mins)

5 Year Design Flows (m³/s)

100 Year Design Flows

(m³/s) Car Park 0.695 5 0.192 0.695 Buildings 1.520 6 0.390 0.866 Road 0.150 5 0.041 0.092 Landscape 0.965 20 0.047 0.113 Total 3.33 0.670 1.766

Existing Myall Street Catchment Assessment These flows will be adopted as the permissible site discharge values for the new system. All flows in addition to these flows will be attenuated on site.

Page 10: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

8

5.5.2 Rail Corridor System The current site drainage system discharging to Rail Corridor drains an approximate catchment area of 9.10Ha. The catchment consists of up to 40% impermeable surface and 60% vegetated area. The impermeable area consists of the remainder of the site buildings and the rear circulation road.

The system connects to the council’s drainage channel at a number of points. The current drainage systems discharge via headwalls along the embankment on the western side of the site and run as overland flow to the rail corridor. The water is then conveyed below the corridor by a number of culverts which discharge to the drainage channel. The area affected by the early works project is located at the northern end of the site and as such will be the only area discussed in this report. The area under consideration accounts for 25% of the total catchment area. There is an existing detention basin located on site at the foot of the embankment. The proposed system for the early works draining to the rail corridor will discharge into this basin. The basin will be upsized to cater for the additional volume requirements and this sizing will be discussed later in this report. The in ground drainage system will have capacity to convey design flows up to and including the 20 year design flows. Flows in excess of this will be conveyed through the site as overland flow discharging down the embankment towards the drainage corridor. The catchment assessment of the rail corridor drainage system is summarised in the table below. Again this assessment has been undertaken using Rational Method.

Catchment Type Catchment Area (Ha)

Time of Concentration

(mins)

5 Year Design Flows (m³/s)

100 Year Design Flows

(m³/s) Car Park - 5 Buildings 0.228 6 0.0585 0.130 Road 0.682 5 0.1750 0.389 Landscape 1.365 20 0.0540 0.160 Total 2.275 0.2880 0.519

Existing Rail Corridor Catchment Assessment

Page 11: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

9

5.6 On-Site Detention 5.6.1 Myall Street Detention

The on-site detention requirement for the development has been set to ensure that the post development discharge flows from the catchment will be restricted to the discharge flow rate created during a 5 year design storm in the pre development case. This restriction will result in a significant reduction in the discharge flows from the site in the post developed case. The on-site detention will restrict the in ground drainage discharge flows from the site to 0.67m³/s for all event up to and including the 20 year design storm. The in ground storm water drainage system will be designed to cater for design storm runoff up to and including the 20 year design storm. During events greater than this the runoff in excess of the 20 year design flows will run as overland flow within the road corridor to Myall Street.

Catchment Type

Catchment Area (Ha)

5 Year Design Flows (m³/s)

10 Year Design Flows (m³/s)

20 Year Design Flows (m³/s)

50 Year Design Flows (m³/s)

100 Year Design Flows (m³/s)

Car Park 0.710 0.196 0.238 0.296 0.380 0.436 Buildings 1.091 0.280 0.341 0.424 0.546 0.621 Road 0.433 0.119 0.145 0.181 0.232 0.266

Landscape 1.096 0.054 0.065 0.081 0.108 0.128 Total 3.33 0.649 0.789 0.982 1.266 1.451

Proposed Myall Street Catchment Assessment

Design ARI (Years) Discharge Flows (m³/s)

Allowable Actual Flows 5 0.670 0.649 10 0.670 0.789 20 0.670 0.982

Myall Street Post Development Discharge Flows Summary

A mass-curve analysis has been undertaken to derive the required storage volume for the catchment. Calculations showing this analysis are included in the Appendix of this report and the findings are summarised in the table below.

Design ARI (Years) OSD Volume Required

(m³) 5 13.06 10 59.30 20 123.30

Myall Street On Site Detention Requirement Summary

The result of the mass-curve analysis indicates a storage requirement of 125m³ will be required for the catchment. This storage volume will be provided within an underground tank on the lower extent of the catchment. Flows from the tank will be restricted using an orifice plate and overflow system with the orifice restricting the design storm discharge flows to the permissible site

Page 12: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

10

discharge whilst the overflow weir will provide an allowance for the discharge of flows in excess of the design flows. The orifice plate will be sized during the detailed design stage of the project when the tank dimensions are finalised,

5.6.2 Rail Corridor Detention

In a similar manner to the Myall Street catchment the on-site detention requirement for the development has been set to ensure that the post development discharge flows from the catchment will be restricted to the discharge flow rate created during a 5 year design storm in the pre development case. The on-site detention will restrict the in ground drainage discharge flows from the site to 0.29m³/s for all event up to and including the 20 year design storm.

Catchment Type

Catchment Area (Ha)

5 Year Design Flows (m³/s)

10 Year Design Flows (m³/s)

20 Year Design Flows (m³/s)

50 Year Design Flows (m³/s)

100 Year Design Flows (m³/s)

Car Park - - - - - - Buildings 0.228 0.0585 0.0713 0.0886 0.1140 0.1298 Road 0.857 0.2198 0.2678 0.3329 0.4285 0.4880 Landscape 1.190 0.0477 0.0573 0.0709 0.1169 0.1393 Total 2.275 0.3260 0.3964 0.4924 0.6594 0.7571

Proposed Rail Corridor Catchment Assessment

Design ARI (Years) Discharge Flows (m³/s)

Allowable Actual Flows 5 0.288 0.326 10 0.288 0.492 20 0.288 0.660

Rail Corridor Post Development Discharge Flows Summary

As for the Myall catchment analysis a mass-curve analysis has been undertaken to assess the on-site detention requirements for the catchment.

Design ARI (Years) OSD Volume Required

(m³) 5 38.95 10 66.95 20 113.85

Rail Corridor On Site Detention Requirement Summary The result of the mass-curve analysis indicates a storage requirement of 115m³ will be required for the catchment. This storage volume will be provided by extending the extent of the existing detention basin on the embankment of the site. This extension will be created by using earthworks from the car park regrading works. Flows from the basin will be restricted using an orifice plate and overflow system with the orifice restricting the design storm discharge flows to the permissible site discharge whilst the overflow weir will provide an allowance for the discharge of flows in excess of the design flows.

Page 13: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

11

The orifice plate will be sized during the detailed design stage of the project when the basin dimensions are finalised.

Page 14: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

12

6.0 Sediment & Erosion Control Erosion and sediment controls will be provided during the construction phase in accordance with Council guidelines. An Erosion and Sedimentation Control Plan has been prepared, and is included in the Appendix to this report. The plan includes measures such as sediment fences at the downstream edges of all disturbed areas, filters at all existing pits collecting stormwater runoff from disturbed areas, and a truck shaker tray at each point of access to the work area. A Sedimentation basin has been provided, sized in accordance with the guidelines in the “Blue Book” - Managing Urban Stormwater - Soils and Construction (NSW Department of Housing 1998). Final details of Erosion and Sediment Control measures will be documented in the drawings to be prepared for the final certification documents. The final drawings will take into account the site works staging including the preferred site access points, site shed locations and temporary stockpile locations. These details will be prepared in conjunction with the selected contractor, to ensure that the selected measures are practical and will be well maintained.

Page 15: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

13

Appendix - Civil Design Information

Page 16: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Dubbo Intensity Frequency Data

DURATION 1 Year 2 years 5 years 10 years 20 years 50 years 100 years5Mins 66.7 87.5 116 134 159 193 2216Mins 62 81.3 108 125 148 180 20510Mins 50.5 66.2 87.6 102 120 146 16620Mins 37 48.4 63.9 73.9 87.3 106 12130Mins 29.9 39.1 51.7 59.7 70.4 85.3 97.41Hr 19.8 25.9 34.1 39.3 46.3 56 63.82Hrs 12.5 16.3 21.3 24.4 28.7 34.6 39.33Hrs 9.41 12.2 15.9 18.2 21.3 25.6 296Hrs 5.74 7.43 9.56 10.9 12.7 15.2 17.212Hrs 3.49 4.51 5.78 6.57 7.65 9.13 10.324Hrs 2.09 2.72 3.51 4.02 4.7 5.63 6.3748Hrs 1.21 1.59 2.09 2.41 2.84 3.44 3.9172Hrs 0.85 1.12 1.48 1.72 2.03 2.47 2.81

To import into excel:

1: Save the file as a .csv (comma separated values) file. (e.g. myifdtable.csv)2: Open excel and import the saved myifdtable.csv file.3: Remove these comments.

Format is: DURATION ARI for 1 Year 2 years 5 years 10 years 20 years 50 years 100 years

Page 17: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Existing Catchment Analysis

Page 18: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 100 years

Design Rainfall Intensity 205 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 1.52 ha

Design Flow Rate = 0.86556 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 100 Year Building

360/.. AICQ

Page 19: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.019 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 100 years

Design Rainfall Intensity 221 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.695 ha

Design Flow Rate = 0.42665 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 100 Year Car Park

360/.. AICQ

Page 20: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 100 years

Design Rainfall Intensity 121 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.35

Design Flow Rate

Catchment Area 0.965 ha

Design Flow Rate = 0.11295 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 100 Year Landscape

360/.. AICQ

Page 21: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 100 years

Design Rainfall Intensity 221 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.15 ha

Design Flow Rate = 0.09208 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 100 Year Road

360/.. AICQ

Page 22: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 10 years

Design Rainfall Intensity 125 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 1.52 ha

Design Flow Rate = 0.475 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 10 Year Building

360/.. AICQ

Page 23: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.019 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 10 years

Design Rainfall Intensity 134 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.695 ha

Design Flow Rate = 0.23283 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 10 Year Car Park

360/.. AICQ

Page 24: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 10 years

Design Rainfall Intensity 73.9 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.29

Design Flow Rate

Catchment Area 1.075 ha

Design Flow Rate = 0.06404 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 10 Year Landscape

360/.. AICQ

Page 25: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 10 years

Design Rainfall Intensity 134 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.15 ha

Design Flow Rate = 0.05025 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 10 Year Road

360/.. AICQ

Page 26: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 5 years

Design Rainfall Intensity 108 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 1.52 ha

Design Flow Rate = 0.38988 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 5 Year Building

360/.. AICQ

Page 27: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.019 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 5 years

Design Rainfall Intensity 116 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.695 ha

Design Flow Rate = 0.19147 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 5 Year Car Park

360/.. AICQ

Page 28: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 5 years

Design Rainfall Intensity 63.9 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.28

Design Flow Rate

Catchment Area 0.965 ha

Design Flow Rate = 0.04722 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 5 Year Landscape

360/.. AICQ

Page 29: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 5 years

Design Rainfall Intensity 116 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.15 ha

Design Flow Rate = 0.04133 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment -5 Year Road

360/.. AICQ

Page 30: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 10 years

Design Rainfall Intensity 125 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.07125 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 10 Year Building

360/.. AICQ

Page 31: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 30 min

Rainfall Intensity

Duration 30 minsDesign Storm 10 years

Design Rainfall Intensity 59.7 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.29

Design Flow Rate

Catchment Area 1.365 ha

Design Flow Rate = 0.06569 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 10 Year Land

360/.. AICQ

Page 32: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 10 years

Design Rainfall Intensity 125 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.682 ha

Design Flow Rate = 0.21313 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 10 Year Road

360/.. AICQ

Page 33: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 100 years

Design Rainfall Intensity 205 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.12983 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 100 Year Building

360/.. AICQ

Page 34: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 100 years

Design Rainfall Intensity 121 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.35

Design Flow Rate

Catchment Area 1.365 ha

Design Flow Rate = 0.15976 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 10 Year Land

360/.. AICQ

Page 35: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 100 years

Design Rainfall Intensity 205 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.682 ha

Design Flow Rate = 0.38836 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 100 Year Road

360/.. AICQ

Page 36: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 5 years

Design Rainfall Intensity 108 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.05848 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 5 Year Building

360/.. AICQ

Page 37: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 30 min

Rainfall Intensity

Duration 30 minsDesign Storm 5 years

Design Rainfall Intensity 51.7 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.28

Design Flow Rate

Catchment Area 1.365 ha

Design Flow Rate = 0.05404 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 5 Year Land

360/.. AICQ

Page 38: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 5 years

Design Rainfall Intensity 108 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.682 ha

Design Flow Rate = 0.17493 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 5 Year Road

360/.. AICQ

Page 39: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Proposed Catchment Analysis

Page 40: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 5 years

Design Rainfall Intensity 108 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 1.091 ha

Design Flow Rate = 0.27984 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 5 Year Building Post Dev

360/.. AICQ

Page 41: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 100 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 5 years

Design Rainfall Intensity 116 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.71 ha

Design Flow Rate = 0.19561 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 5 Year Car Post Dev

360/.. AICQ

Page 42: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 5 years

Design Rainfall Intensity 63.9 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.28

Design Flow Rate

Catchment Area 1.096 ha

Design Flow Rate = 0.05363 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 5 Year Landscape Post Dev

360/.. AICQ

Page 43: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 5 years

Design Rainfall Intensity 116 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.433 ha

Design Flow Rate = 0.11929 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment -5 Year Road Post Dev

360/.. AICQ

Page 44: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 10 years

Design Rainfall Intensity 125 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 1.091 ha

Design Flow Rate = 0.34094 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 10 Year Building Post Dev

360/.. AICQ

Page 45: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 100 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 10 years

Design Rainfall Intensity 134 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.71 ha

Design Flow Rate = 0.23785 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 10 Year Car Park Post Dev

360/.. AICQ

Page 46: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 10 years

Design Rainfall Intensity 73.9 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.29

Design Flow Rate

Catchment Area 1.096 ha

Design Flow Rate = 0.06529 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 10 Year Landscape Post Dev

360/.. AICQ

Page 47: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 10 years

Design Rainfall Intensity 134 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.433 ha

Design Flow Rate = 0.14506 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment -10 Year Road Post Dev

360/.. AICQ

Page 48: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 20 years

Design Rainfall Intensity 148 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.95

Design Flow Rate

Catchment Area 1.091 ha

Design Flow Rate = 0.42385 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 20 Year Building Post Dev

360/.. AICQ

Page 49: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 100 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity \

Duration 5 minsDesign Storm 20 years

Design Rainfall Intensity 159 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.95

Design Flow Rate

Catchment Area 0.71 ha

Design Flow Rate = 0.29634 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 20 Year Car Post Dev

360/.. AICQ

Page 50: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 20 years

Design Rainfall Intensity 87.3 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.30

Design Flow Rate

Catchment Area 1.096 ha

Design Flow Rate = 0.08098 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 20 Year Landscape Post Dev

360/.. AICQ

Page 51: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 20 years

Design Rainfall Intensity 159 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.95

Design Flow Rate

Catchment Area 0.433 ha

Design Flow Rate = 0.18072 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment -20 Year Road Post Dev

360/.. AICQ

Page 52: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 50 years

Design Rainfall Intensity 180 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 1.091 ha

Design Flow Rate = 0.5455 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 50 Year Building Post Dev

360/.. AICQ

Page 53: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 100 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity \

Duration 5 minsDesign Storm 50 years

Design Rainfall Intensity 193 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.71 ha

Design Flow Rate = 0.38064 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 50 Year Car Post Dev

360/.. AICQ

Page 54: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 50 years

Design Rainfall Intensity 106 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.33

Design Flow Rate

Catchment Area 1.096 ha

Design Flow Rate = 0.10769 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 50 Year Landscape Post Dev

360/.. AICQ

Page 55: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 50 years

Design Rainfall Intensity 193 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.433 ha

Design Flow Rate = 0.23214 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment -50 Year Road Post Dev

360/.. AICQ

Page 56: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 100 years

Design Rainfall Intensity 205 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 1.091 ha

Design Flow Rate = 0.62126 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 100 Year Building Post Dev

360/.. AICQ

Page 57: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 100 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity \

Duration 5 minsDesign Storm 100 years

Design Rainfall Intensity 221 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.71 ha

Design Flow Rate = 0.43586 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment - 100 Year Car Park Post Dev

360/.. AICQ

Page 58: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 100 years

Design Rainfall Intensity 121 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.35

Design Flow Rate

Catchment Area 1.096 ha

Design Flow Rate = 0.12828 m³/s

Sparse Vegitation

Dubbo Hospital - Myall Catchment - 100 Year Landscape Post Dev

360/.. AICQ

Page 59: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 120 mSlope: 0.01 m/m

Time of Concentration: 5 min

Rainfall Intensity

Duration 5 minsDesign Storm 100 years

Design Rainfall Intensity 221 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.433 ha

Design Flow Rate = 0.26581 m³/s

Concrete or Asphalt

Dubbo Hospital - Myall Catchment -100 Year Road Post Dev

360/.. AICQ

Page 60: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 5 years

Design Rainfall Intensity 108 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.05848 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 5 Year Building Post Dev

360/.. AICQ

Page 61: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 30 min

Rainfall Intensity

Duration 30 minsDesign Storm 5 years

Design Rainfall Intensity 51.7 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.28

Design Flow Rate

Catchment Area 1.19 ha

Design Flow Rate = 0.04711 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 5 Year Land Post Dev

360/.. AICQ

Page 62: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 5 years

Design Rainfall Intensity 108 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.86

Design Flow Rate

Catchment Area 0.857 ha

Design Flow Rate = 0.21982 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 5 Year Road Post Dev

360/.. AICQ

Page 63: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 10 years

Design Rainfall Intensity 125 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.07125 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 10 Year Building Post Dev

360/.. AICQ

Page 64: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 30 min

Rainfall Intensity

Duration 30 minsDesign Storm 10 years

Design Rainfall Intensity 59.7 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.29

Design Flow Rate

Catchment Area 1.19 ha

Design Flow Rate = 0.05727 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 10 Year Land Post Dev

360/.. AICQ

Page 65: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 10 years

Design Rainfall Intensity 125 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.90

Design Flow Rate

Catchment Area 0.857 ha

Design Flow Rate = 0.26781 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 10 Year Road Post Dev

360/.. AICQ

Page 66: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 20 years

Design Rainfall Intensity 148 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.95

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.08858 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 20 Year Building Post Dev

360/.. AICQ

Page 67: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 30 min

Rainfall Intensity

Duration 30 minsDesign Storm 20 years

Design Rainfall Intensity 70.4 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.30

Design Flow Rate

Catchment Area 1.19 ha

Design Flow Rate = 0.07091 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 20 Year Land Post Dev

360/.. AICQ

Page 68: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 20 years

Design Rainfall Intensity 148 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 0.95

Design Flow Rate

Catchment Area 0.857 ha

Design Flow Rate = 0.33294 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 20 Year Road Post Dev

360/.. AICQ

Page 69: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 50 years

Design Rainfall Intensity 180 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.114 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 50 Year Building Post Dev

360/.. AICQ

Page 70: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 50 years

Design Rainfall Intensity 106 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.33

Design Flow Rate

Catchment Area 1.19 ha

Design Flow Rate = 0.11693 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 50 Year Land Post Dev

360/.. AICQ

Page 71: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 50 years

Design Rainfall Intensity 180 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.857 ha

Design Flow Rate = 0.4285 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 50 Year Road Post Dev

360/.. AICQ

Page 72: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 100 years

Design Rainfall Intensity 205 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.228 ha

Design Flow Rate = 0.12983 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 100 Year Building Post Dev

360/.. AICQ

Page 73: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.130Flow Path Length: 220 mSlope: 0.02 m/m

Time of Concentration: 20 min

Rainfall Intensity

Duration 20 minsDesign Storm 100 years

Design Rainfall Intensity 121 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 0 % 1 0.80 0.23

2 0.85 0.25Pervious area runoff coefficient: 0.29019 5 0.95 0.28

10 1.00 0.29C10 = 0.29019 20 1.05 0.30

50 1.15 0.33100 1.20 0.35

Design Coeffiecient: 0.35

Design Flow Rate

Catchment Area 1.19 ha

Design Flow Rate = 0.13928 m³/s

Sparse Vegitation

Dubbo Hospital -Rail Corridor Catchment - 100 Year Land Post Dev

360/.. AICQ

Page 74: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Rainfall Discharge Analysis

Project Number 4363Project TitleDate 28-May-12

Note: Design Calcs undertaken adopting AR&R design process.

Using Rational Method:

where: Q = Design Flowrate (m³/s)C = Dimensionless runoff coefficientI = Rainfall Intensity (mm/hr)A = Catchment Area (ha)

Time of Concentration

Predominant Surface Type:Roughness Coefficient: 0.013Flow Path Length: 220 mSlope: 0.01 m/m

Time of Concentration: 6 min

Rainfall Intensity

Duration 6 minsDesign Storm 100 years

Design Rainfall Intensity 205 mm/hr

Runoff Coefficient

10 Year, 1 Hour Intensity: 39.3 mm/hr ARI (years) Fy CyFraction Impervious: 100 % 1 0.80 0.72

2 0.85 0.77Pervious area runoff coefficient: 0.29019 5 0.95 0.86

10 1.00 0.90C10 = 0.9 20 1.05 0.95

50 1.15 1.00100 1.20 1.00

Design Coeffiecient: 1.00

Design Flow Rate

Catchment Area 0.857 ha

Design Flow Rate = 0.48801 m³/s

Concrete or Asphalt

Dubbo Hospital -Rail Corridor Catchment - 100 Year Road Post Dev

360/.. AICQ

Page 75: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

On Site Detention Analysis

Page 76: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

OSD Calculation

Permisible Discharge

Area 3.33 ha

Permissible Discharge 0.6700 m3/s

OSD Design

Design ARI 20 Years

Time of Concentration Actual Intensity Cy Actual Discharge Discharge Volume Allowable Discharge Allowable Volume OSD Volumemin mm/hr m3/s m3 m3/s m3 m35 159 0.735 1.0810 324.30 0.6700 201.00 123.306 148 0.735 1.0062 362.24 0.6700 241.20 121.0410 120 0.735 0.8159 489.51 0.6700 402.00 87.5120 87.3 0.735 0.5935 712.24 0.6700 804.00 -91.7630 70.4 0.735 0.4786 861.54 0.6700 1206.00 -344.4660 46.3 0.735 0.3148 1133.22 0.6700 2412.00 -1278.78120 28.7 0.735 0.1951 1404.89 0.6700 4824.00 -3419.11180 21.3 0.735 0.1448 1563.98 0.6700 7236.00 -5672.02360 12.7 0.735 0.0863 1865.03 0.6700 14472.00 -12606.97720 7.65 0.735 0.0520 2246.85 0.6700 28944.00 -26697.151440 4.7 0.735 0.0320 2760.84 0.6700 57888.00 -55127.162880 2.84 0.735 0.0193 3336.50 0.6700 115776.00 -112439.504320 2.03 0.735 0.0138 3577.34 0.6700 173664.00 -170086.66

Max Volume 123.30 m3

Page 77: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

OSD Calculation

Permisible Discharge

Area 2.275 ha

Permissible Discharge 0.2880 m3/s

OSD Design

Design ARI 20 Years

Time of Concentration Actual Intensity Cy Actual Discharge Discharge Volume Allowable Discharge Allowable Volume OSD Volumemin mm/hr m3/s m3 m3/s m3 m35 159 0.63 0.6330 189.91 0.2880 86.40 103.516 148 0.63 0.5892 212.12 0.2880 103.68 108.4410 120 0.63 0.4778 286.65 0.2880 172.80 113.8520 87.3 0.63 0.3476 417.08 0.2880 345.60 71.4830 70.4 0.63 0.2803 504.50 0.2880 518.40 -13.9060 46.3 0.63 0.1843 663.59 0.2880 1036.80 -373.21120 28.7 0.63 0.1143 822.69 0.2880 2073.60 -1250.91180 21.3 0.63 0.0848 915.85 0.2880 3110.40 -2194.55360 12.7 0.63 0.0506 1092.14 0.2880 6220.80 -5128.66720 7.65 0.63 0.0305 1315.72 0.2880 12441.60 -11125.881440 4.7 0.63 0.0187 1616.71 0.2880 24883.20 -23266.492880 2.84 0.63 0.0113 1953.81 0.2880 49766.40 -47812.594320 2.03 0.63 0.0081 2094.84 0.2880 74649.60 -72554.76

Max Volume 113.85 m3

Page 78: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Civil Drawings

Page 79: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

Mc

GU

INN

DRIVE

Mc

GU

INN

DR

IVE

( 5

SERVICESPIT

WIND SOCKLP

S.W. PIT

CO

NC

RET

E P

ATH

CONC. PATH

CONC. PATH

HIGH STEEL SECURITY FENCE

HIGH STEEL SECURITY FENCE

HIN

GE

-JO

INT

F

ENC

E

HINGE-JOINT FENCE

SECUTITY GARDEN AREA

AREA UNDER CONSTRUCTION

C.W

. FE

NC

E

LIQUIDOXYGENTANK

TANKOXYGENLIQUID

WASTE COLLECTION

STORAGE AREA

CO

NC

RE

TE P

ATH

CO

NC

RET

E P

ATH

HELI PAD

CONCRETE

CONCRETE PATH

CONCRETE PATHC

ON

CR

ETE

CO

NC

.

CONCRETE

CONCRETE

1 1 K

V

STE

EL &

TIM

BE R

225 mm

225 mm

225 mm

150 m

m

150 mm

200 mm

200 mm

300 mm

300

mm

PIPE NOTLOCATED

250 mmS.W. PIT

TOP

BANK

TOP

BANK

TOP

BAN

K

T OP

BANK

EAR

TH

BUNDS.

W.

RETE

NTIO

N

BASIN

BO

TTO

M B

ANK

BO

TTO

M B

ANK

BOTTOM B

ANK

BOTT

OM B

ANK

BOTT

OM

BAN

K

CO

NC

RE

TE K

. & G

.

CO

NC

RET

E K

. & G

.

CONCR

ETE

K. &

G.CO

NCRET

E K.

& G

.

CONCRETE K. & G.

CONCRETE K. & G.

CONCRETE K. & G.

CO

NC

RET

E K

. & G

.

CONCRETE K. & G.

TOP

277.8

2

INV. 2

75.32SM

H

BITU

MEN

R

OAD

ED

GE

OF

BIT

UM

EN

EDGE OF BITUMEN

ED

GE

OF

CO

NC

RET

E

EDGE OF BITUM

EN

ED

GE

OF

BIT

UM

EN

BITUPAVE ROAD

BITUPAVE ROAD

BITU

PAVE

RO

AD

BITU

PAVE

RO

AD

BITU

PAVE

RO

AD

BIT

UM

EN

R

OA

D

BITU

MEN

RO

AD

BIT

UM

EN R

OAD

BIT

UM

EN R

OAD

BITU

ME N

R

OA D

BIT

UM

EN

R

OA

D

PAVING

PAVING

LAWN

LAWNLAWN

LAWN

LAW

TAP

STEEL PLATEON PIPE

CAR

PA

RK

ING

BA

YS

1

2

3

4

5

6

1

2

3

4

5

6

7

8

9

10

LP

SP

SP

SP

ROW OF SMALL

S.W. P

IT AC

LOCATE

D

AC

AC AC

S.W. P

IT NOT

AC

POLYTANK

SU

B-ST

N

S. I. PIT

S. I. PIT

INV. 277.60TOP 277.91

S. I. PITTOP 277.46INV. 276.66

TOP 2

76.84

INV. S.

W. P

IT

INV. 275.53TOP 276.53

SW PIPE N

OT LO

CATED

G. I. PITTOP 275.88INV. 274.95

TOP 276.58INV. 275.73

INV.TOP 277.36

APPROX. ASSU

MED PO

SITION FRO

M D

ESIGN

PLANS

SW PIPE NOT LOCATEDAPPROX. ASSUMED POSITION

SW PIPE NOT LOCATED

APPROX. ASSUMED POSITION

CONCRETECHIMNEY

WASTE

& STEEL BUILDING

ACUTE PSYCHIATRIC

INPATIENT UNIT

BUILDING

BRICK BUILDING

METAL ROOF

" SO

UL

CO

M. "

C'B

BU

ILD

ING

COLOUR-BOND

BRICK & METAL BUILDINGDIABETES

ONCOLOGY

IRON ROOF

AREA SUPPLY &

STORES BUILDING

METAL ROOFMORGUE

BRICK BUILDING

BRICK

PER

GO

LA

BRICK PAVINGSTEEL & TIMBER

PERGOLA

STEEL &

COLOURBOND

GARAGE

C

STO

RE

CO

NT '

R.

VERANDAH

VER

AN

DA

H

OX

YGEN

PIPE

OXY

GE N

PIP

E

11

10

7

9

8

F.L.

276.7

7

ST

F.L.

277.7

7

F.L.

277.7

7

CW

100

mm

CW

100

mm

ASS

UM

ED 0

.6 m

DE

EP

T WIN

GE N

E RA T

OR

RO

OM

268.

0

269.

027

0.0

270.0

271.

027

2.0

273.

027

4.0

275.0

275.0

276.0

276.

0

276.0

276.

0

277.0

277.0

278.

0

Document Control Status:

Scale:

Drawing Title

Co-ordinated:

Client

Project

ConsultantsConsultants

Drawing Number:

Revision:

Project Engineer:

Project Director:

Date:

North:

enstruct group Pty Ltd ACN 094 570 671

Project No.

PROJECT MANAGEMENT

ADDRESS: LEVEL 16, 207 KENT STREET, NSW 2000TEL: 02 9276 1400

NAME: TSA MANAGEMENT

B1 DRAWING SHEET

ARCHITECT

ADDRESS: LEVEL 2, 204 CLARENCE STREET SYDNEY, NSW 2000TEL/FAX: 02 9267 9599 / 02 9264 5844

NAME: COX RICHARDSON

ELECTRICAL & ICT ENGINEERS

ADDRESS: 100 CHRISTIE STREET ST LEONARDS, NSW 2065TEL/FAX: 02 9928 2100 / 02 9928 2500

NAME: SINCLAIR KNIGHT MERZ

MECHANICAL & LIFT ENGINEERS

ADDRESS: LEVEL 3, 454-456 PACIFIC HIGHWAY ST LEONARDS, NSW 2065TEL/FAX: 03 TEL NO / 03 FAX NO

NAME: WOOD & GRIEVE

HYDRAULICS & FIRE PROTECTION CONSTANTS

ADDRESS: 60 HICKSON ROAD, NSW 2000TEL/FAX: 02 9241 4188 / 02 9241 4334

NAME: NORTHROP

ACOUSTIC ENGINEERS

ADDRESS: LEVEL 1, 60 MILLER STREET, NORTH SYDNEY, NSW 2060TEL/FAX: 02 9928 6800 / 02 9955 6900

NAME: NORMAN, DISNEY & YOUNG

LANDSCAPE DESIGN

ADDRESS: LEVEL 1 / 5 WILSON STREET, NEWTOWN, NSW 2042TEL/FAX: 02 9577 5533 / 9519 8323

NAME: OCULUS

TRAFFIC PLANNING

ADDRESS: LEVEL 9, 203 PACIFIC HIGHWAY, ST LEONARDS, NSW 2065TEL/FAX: 02 94967700 / 02 9439 5120

NAME: CARDNO

4363

DUBBO BASE HOSPITAL

REDEVELOPMENT STAGE 1 / 2

MYALL STREET, DUBBO NSW

NCC & ACCESSIBILITY

ADDRESS: LEVEL 1, 71-73 ARCHER STREET, CHATSWOOD, NSW 2057TEL/FAX: 02 9411 5360 / 02 9411 5420

NAME: BCA LOGIC

Drawn:

enstruct group pty ltdLevel 4, 2 Glen StreetMilsons Point NSW 2061

Telephone (02) 8904 1444Facsimile (02) 8904 1555http: // www.enstruct.com.au enstruct

NOTES

THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE

1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING WITH

THE WORK. ENSTRUCT SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT

CONTRACTS, SPECIFICATIONS, REPORTS AND DRAWINGS.

COPYRIGHT OF THIS DRAWING IS VESTED IN ENSTRUCT PTY LTD

DescriptionRev By Date

FOR GENERAL NOTES REFER TO DRAWING CIV-SI-001-00

CIV-SI-100-01

T.B.B.

I.H.

I.H. 1:200

14/06/2012

04

I.H.

TENDER

SHEET 1 OF 4PLANGENERAL ARRANGEMENT

01 ISSUED FOR APPROVAL 08.06.12IH

02 ISSUED FOR TENDER 20.06.12IH

03 ISSUED FOR TENDER 28.06.12IH

04 ISSUED FOR APPROVAL 05.07.12IH

Page 80: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

D

D

190°

0 4 2

0.11

DR

IVE

EASEMENTFOR

WATERSUPPLY

5 WIDE

( 5 )

( 5 )

COVERED CARPARK

CONC. PATH

CONC. PATH

CONC. PATH

CO

NC

. P

AT H

CONCRETE

CO

NC

. P

A TH

CONCRETE

HIN

GE-

JOIN

T

FE

NCE

HINGE-JOINT FENCE

HIGH C.W. FENCE

HIGH C.W. FENCE CE

HIGH C.W. FENCE

WIRE FENCE

WIRE FENCE

CONCRETE

CONCRETE

CONCRETE

PARKING BAY H

PARKING BAY G

PARKING BAY F

PARKING BAY E

O/H

PO

WE

R L

INE S

O/H

PO

WE

R L

INES

CONC. KERB

CONC. KERB

CO

NC

. K

ERB

CO

NC

. K

ER

B

CONC. KERB

150 mm

150 mm150 mm 150 mm

150 mm

150 mm

225

mm

300 mm

150 mm

ED

GE

OF

BIT

UM

EN

TUMEN

ED

GE

OF

CO

NC

RET

E

EDGE OF BITUMEN

BIT

UM

EN

R

OA

D

BITUMEN TRACK

BITUMEN TRACK

T RAC

K

TRAC

K

BITUMEN CARPARK

BITUMEN CARPARK

BITUMEN CARPARK

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACEBITUMEN SURFACE

PAVING

PAVI

NG

PAVING

PAVING

PAVING

PAVING

PAVING

LAWN

LAWN

ROW OF SMALL TREES

CO

NC. KER

B

CON

C . KERB

BLUE METAL

CARPARK

AC

TANK

S. I. PITTOP 279.45INV. 278.56

S. I. PITTOP 279.15INV. 278.30

S. I. PIT

S. I. PITINV. 277.83TOP 278.85

TOP 278.92INV. 278.19

TOP 279.14INV. 278.19

S. I. PIT

S. I. PITTOP 278.92INV. 277.62

TOP

278.8

5

INV. 2

78.36

S. I. P

IT

S. I.

PIT

INV.

278.2

6

TOP 27

8.77S. I .

PIT

INV.

278

. 16

TOP

278.

74

S. I. P

ITTO

P 278.5

8

INV. 2

78.11

S. I. PIT

INV. 277.60TOP 277.91

SOIL

BINS

WASTE

BINS

CONCRETEBLOCK

WALL

METAL & BRICK BUILDING

COLOURBOND STOREDEMOUNT. BUILDING

BRICK BUILDINGMETAL ROOF

METAL ROOF

BRICK BUILDING

CO

LOU

RB

ON

D

STEEL &

COLOURBOND

GARAGE

STEEL &COLOURBOND

WORKSHOP

C. G. I.CARPORT

GARAGE

STEELMESH

G. I.SHEDCOLOURBOND BUILDINGMETAL ROOF

C. BLOCKW.C.

SWIMMING

POOLPERGOLA

FIB

RO

WO

RKS

HO

PC

'BO

ND

RO

OF

COVERED STEEL & IRON CARPORT

BRICK BUILDINGMETAL ROOF

WORKSHOP

WORKSHOP

BOILER HOUSE & LAUNDRY

C'BOND

SHED

WM 150 mm 2 m DEEP

WM 150 mm

WM 150 mm

11

10 9

12

13

F.L.

279.

13

278.0

278.

0

278.0

278.0

278.0

278.0

279.0

279.

0

279.0

279.

0

279.

0

279.

0

279.0

280.0

280.0

281.0

281.0

Document Control Status:

Scale:

Drawing Title

Co-ordinated:

Client

Project

ConsultantsConsultants

Drawing Number:

Revision:

Project Engineer:

Project Director:

Date:

North:

enstruct group Pty Ltd ACN 094 570 671

Project No.

PROJECT MANAGEMENT

ADDRESS: LEVEL 16, 207 KENT STREET, NSW 2000TEL: 02 9276 1400

NAME: TSA MANAGEMENT

B1 DRAWING SHEET

ARCHITECT

ADDRESS: LEVEL 2, 204 CLARENCE STREET SYDNEY, NSW 2000TEL/FAX: 02 9267 9599 / 02 9264 5844

NAME: COX RICHARDSON

ELECTRICAL & ICT ENGINEERS

ADDRESS: 100 CHRISTIE STREET ST LEONARDS, NSW 2065TEL/FAX: 02 9928 2100 / 02 9928 2500

NAME: SINCLAIR KNIGHT MERZ

MECHANICAL & LIFT ENGINEERS

ADDRESS: LEVEL 3, 454-456 PACIFIC HIGHWAY ST LEONARDS, NSW 2065TEL/FAX: 03 TEL NO / 03 FAX NO

NAME: WOOD & GRIEVE

HYDRAULICS & FIRE PROTECTION CONSTANTS

ADDRESS: 60 HICKSON ROAD, NSW 2000TEL/FAX: 02 9241 4188 / 02 9241 4334

NAME: NORTHROP

ACOUSTIC ENGINEERS

ADDRESS: LEVEL 1, 60 MILLER STREET, NORTH SYDNEY, NSW 2060TEL/FAX: 02 9928 6800 / 02 9955 6900

NAME: NORMAN, DISNEY & YOUNG

LANDSCAPE DESIGN

ADDRESS: LEVEL 1 / 5 WILSON STREET, NEWTOWN, NSW 2042TEL/FAX: 02 9577 5533 / 9519 8323

NAME: OCULUS

TRAFFIC PLANNING

ADDRESS: LEVEL 9, 203 PACIFIC HIGHWAY, ST LEONARDS, NSW 2065TEL/FAX: 02 94967700 / 02 9439 5120

NAME: CARDNO

4363

DUBBO BASE HOSPITAL

REDEVELOPMENT STAGE 1 / 2

MYALL STREET, DUBBO NSW

NCC & ACCESSIBILITY

ADDRESS: LEVEL 1, 71-73 ARCHER STREET, CHATSWOOD, NSW 2057TEL/FAX: 02 9411 5360 / 02 9411 5420

NAME: BCA LOGIC

Drawn:

enstruct group pty ltdLevel 4, 2 Glen StreetMilsons Point NSW 2061

Telephone (02) 8904 1444Facsimile (02) 8904 1555http: // www.enstruct.com.au enstruct

NOTES

THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE

1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING WITH

THE WORK. ENSTRUCT SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT

CONTRACTS, SPECIFICATIONS, REPORTS AND DRAWINGS.

COPYRIGHT OF THIS DRAWING IS VESTED IN ENSTRUCT PTY LTD

DescriptionRev By Date

FOR GENERAL NOTES REFER TO DRAWING CIV-SI-001-00

CIV-SI-100-02

T.B.B.

I.H.

I.H. 1:200

14/06/2012

04

I.H.

TENDER

SHEET 2 OF 4PLANGENERAL ARRANGEMENT

01 ISSUED FOR APPROVAL 08.06.12IH

02 ISSUED FOR TENDER 20.06.12IH

03 ISSUED FOR TENDER 28.06.12IH

04 ISSUED FOR APPROVAL 05.07.12IH

Page 81: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

2

26

D.P. 291

D.P. 2

D.P

D.P

D

D

190°

04'

00"

267

.4

Mc

GU

INN

DR

IVE

Mc

GU

INN

DIL

UTI

ON

PIT

COVERED CARPARK

CONCRETE PATH CONCRETE PATH

CO

NC

RET

E P

A TH

CO

NC

RE

TE P

ATH

CO

NC

RET

E

PATH

CO

NC

RET

E P

A TH

PA

TH

CO

NC

. P

ATH

SECURITYFENCE

FEN

CE

COM. PIT

COM. PIT

COM. PIT

COM. PITC

OM

. PIT

CO

M. &

PO

WER

PIT

COM. & POWER PIT

0.8

DE

EP

0.7 DEEP

COM. PIT

CONCRETE PED.

CROSSING

HOTWATERUNITS

CONCRETE K. & G.

CONCRETE K. & G.

BITUMEN PED.

CROSSING

CONCRETE K. & G.

CONCRETE KERB

CONCRETE KERB

CONCRETE

PARKING BAY E

PARKING BAY D

PARKING BAY D

PARKING BAY C

PARKING BAY C

PARKING BAY B

PARKING BAY B

PARKING BAY A

ELE. PIT

ELE. PIT

ELECT. PIT

ELECT. PIT

ELECT. PIT

ELECT. PIT

ELE.

PIT

1.3

DE

EP

11 K

V

11 KV + L V

11 KV + LV

11 KV + LV11 KV + LV

11 KV + LV

11 KV + LV

11 KV

11 K

V

SWITCHBOARD

O/ H

PO

WE

R L

INES

CO

NC

.

CONC. KERB

TOP 276.84INV. 276.30

TOP 276.84INV. 276.13

S. I. PITTOP 277.04INV. 276.00

G.I. PIT

S.W. PITTOP 277.70INV. 276.55

G. I. PIT

TOP 277.65INV. 276.15

S. W. PITTOP 277.68INV 276.63

S. W

. 30 0

mm

S.W

. 300

mm

DIA

.

S.W

. 300

mm

S. I. PITTOP 277.11

150 mm

S.W

. 300

mm

375

mm

100

mm

S. I. PIT S. I. PIT

300 mmm

225

mm

225 mm

EDGE OF BANK EDGE OF BANK

BANK BASEBANK BASE

CO

NC.

K.

& G

.

CO

NC

. K E

RB

CO

NC

. KE

RB

SEWER JUN. SMH

TOP 277.65INV. 276.94

SMH

TOP 277.62INV. 276.49

SMH

INV. 275.54TOP 277.54

SMH

TOP 276.60

INV. 274.43

150 mm150 mm

150 mm225 mm225 mm

TOP 2

77.10

277.0

2

TOP

277.7

7

SMH

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN CARPARK

BITUMEN CARPARK

BITUMEN CARPARK

BITUMEN CARPARK

B ITU

MEN

SU

RF A

CE

BITU

MEN

SU

RFA

CE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN CARPARKBITUMEN SURFACE

BIT

UM

EN

RO

A DB

ITU

MEN

R

OAD

BITUMEN SURFACEBITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

BITUMEN SURFACE

LAWN

LAWN

LAWN

ROW OF HEDGE SHRUBS

TANK

SU

B-S

T NS

UB-

STN

S. I. PITINV. 277.83TOP 278.92INV. 278.19

TOP 277.67INV. 276.42

INV.

275.

54

TOP

276.1

4IN

V. 275

.76

TOP 27

6.38

76.6075.75

INV. 276.14

INV .

275

.40

TOP

276

.60

INV. 275.69

TOP 276.59

S. I

. PIT

S. I. PITNOT

LOCATED

CONCRETECHIMNEY

BRICK BUILDING

METAL ROOF

BRICK BUILDING

METAL ROOF

BRICK BUILDING

METAL ROOF

THREE STOREY BRICK BUILDINGTILE ROOF

METAL & BRICK BUILDINGMETAL ROOF

COLOURBOND STOREDEMOUNT. BUILDING

COVERED STEEL & IRON CARPORT

BRICK BUILDING

METAL ROOF

BRICK BUILDING

METAL ROOF

BRICK BUILDING

AMBULANCEBAY

STEEL & METALCARPORT

BRIC

K B

UILD

ING

MET

AL R

OO

F

VERANDAH VERANDAH

VERANDAH

VERANDAH

VER

AND

AH

BOILER HOUSE & LAUNDRY

NURSES ACCOMMODATION

ADMISSIONS & OUTPATIENTS

PAEDIATRICS

"NGAMUUNG"MAMOGRAPHY

METAL ROOF

ADMISSIONS & EMERGENCY

BUILDING No. 68

C'BOND

SHED

SPRINKLER

VALVES

WM

150

mm

100m

m D

IA.

150 mm

W. M

. 15 0

mm

BI A

. 0.3

DEE

PSV

SV

SV

WM

15 0

mm

0.9

m D

EEP

WM

150

mm

1.2

m D

EE P

WM 150 mm 0.6 m DEEP

12

14

13

15

F.L.

277.

77

F.L.

277.

77

F.L.

276.

76

F.L. 277.88

GND F.L

. 278

.31

1ST

F.L.

281.4

4

2ND

F .L. 28

4.54

DEEPEEP

FH 150 mm 0.5 m DEEPCW 100 mm 0.5m DEEP

FH 150 mm 0.5 m DEEPCW 100 mm 0.5m DEEPIRR 100 mm 0.5m DEEP

m DEEPm DEEPm DEEP

ENCH

COMMON TRENCH

m DEEPPE

T WIN

GE N

E RA T

OR

RO

OM

MAI

N S

WI T

CH

AN

D J

UN

CT I

ON

RO

OM

OLD

S

UB

MAI

NS(P

LAN

967

20-E

0101

)

OLD SUBMAINS

(PLAN 96720-E0101)

OLD

S

UBM

AIN

S(P

LAN

967

20-E

0101

)

(PLAN 96720-E0102)

(PLA

N 9

6720

-E01

02)

SU

BM

AIN

S N

OT

LO

CA

TED

SUBMAINS NOT LOCATED

( PL A

N 9 672 0-E

0 102 )

CA

B LE N

OT L O

CA

T ED

277.

0

277.0

277.0

277.

0

277.0277.0

277.

0

277.

0

277.0

277.0

277.0

277.0

278.0

278.0

278.0

278 .

0

278.0

278.0

278.0

279.0

Document Control Status:

Scale:

Drawing Title

Co-ordinated:

Client

Project

ConsultantsConsultants

Drawing Number:

Revision:

Project Engineer:

Project Director:

Date:

North:

enstruct group Pty Ltd ACN 094 570 671

Project No.

PROJECT MANAGEMENT

ADDRESS: LEVEL 16, 207 KENT STREET, NSW 2000TEL: 02 9276 1400

NAME: TSA MANAGEMENT

B1 DRAWING SHEET

ARCHITECT

ADDRESS: LEVEL 2, 204 CLARENCE STREET SYDNEY, NSW 2000TEL/FAX: 02 9267 9599 / 02 9264 5844

NAME: COX RICHARDSON

ELECTRICAL & ICT ENGINEERS

ADDRESS: 100 CHRISTIE STREET ST LEONARDS, NSW 2065TEL/FAX: 02 9928 2100 / 02 9928 2500

NAME: SINCLAIR KNIGHT MERZ

MECHANICAL & LIFT ENGINEERS

ADDRESS: LEVEL 3, 454-456 PACIFIC HIGHWAY ST LEONARDS, NSW 2065TEL/FAX: 03 TEL NO / 03 FAX NO

NAME: WOOD & GRIEVE

HYDRAULICS & FIRE PROTECTION CONSTANTS

ADDRESS: 60 HICKSON ROAD, NSW 2000TEL/FAX: 02 9241 4188 / 02 9241 4334

NAME: NORTHROP

ACOUSTIC ENGINEERS

ADDRESS: LEVEL 1, 60 MILLER STREET, NORTH SYDNEY, NSW 2060TEL/FAX: 02 9928 6800 / 02 9955 6900

NAME: NORMAN, DISNEY & YOUNG

LANDSCAPE DESIGN

ADDRESS: LEVEL 1 / 5 WILSON STREET, NEWTOWN, NSW 2042TEL/FAX: 02 9577 5533 / 9519 8323

NAME: OCULUS

TRAFFIC PLANNING

ADDRESS: LEVEL 9, 203 PACIFIC HIGHWAY, ST LEONARDS, NSW 2065TEL/FAX: 02 94967700 / 02 9439 5120

NAME: CARDNO

4363

DUBBO BASE HOSPITAL

REDEVELOPMENT STAGE 1 / 2

MYALL STREET, DUBBO NSW

NCC & ACCESSIBILITY

ADDRESS: LEVEL 1, 71-73 ARCHER STREET, CHATSWOOD, NSW 2057TEL/FAX: 02 9411 5360 / 02 9411 5420

NAME: BCA LOGIC

Drawn:

enstruct group pty ltdLevel 4, 2 Glen StreetMilsons Point NSW 2061

Telephone (02) 8904 1444Facsimile (02) 8904 1555http: // www.enstruct.com.au enstruct

NOTES

THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE

1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING WITH

THE WORK. ENSTRUCT SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT

CONTRACTS, SPECIFICATIONS, REPORTS AND DRAWINGS.

COPYRIGHT OF THIS DRAWING IS VESTED IN ENSTRUCT PTY LTD

DescriptionRev By Date

FOR GENERAL NOTES REFER TO DRAWING CIV-SI-001-00

CIV-SI-100-03

T.B.B.

I.H.

I.H. 1:200

14/06/2012

04

I.H.

TENDER

SHEET 3 OF 4PLANGENERAL ARRANGEMENT

01 ISSUED FOR APPROVAL 08.06.12IH

02 ISSUED FOR TENDER 20.06.12IH

03 ISSUED FOR TENDER 28.06.12IH

04 ISSUED FOR APPROVAL 05.07.12IH

Page 82: Dubbo Base Hospital Redevelopment Stage 1 & 2 Review of

2

A

D.P. 3

D.P. 2

D.P.

BBORA

ROAD

Mc

GU

INN

DR

I VE

DIL

UTI

ON

PIT

CONCRETE

RAMP

CONC. PATH

CO

NC

. P

ATH

CONC. PATH

CONC. PATH

CO

NC

. P

AT H

CO

NC

. P

AT H

PLAY GROUND

SECURITYFENCE

SEC

UR

ITY

FEN

C E

CO

NC

RE

TE

PATH

11 K

V

1 1 K

V

1 1 K

V

11 KV

S.W

. 300

mm

S.W

. 300

mm

S. W

. 300

mm

S. W

. 450

mm

S.W. 450 m

m

375 mm

375 mm

SW 375 mm

SW 375 mm

SW 375 m

m

375

mm

375

mm

INV.

273.8

9

TOP

274.3

8

TOP 275.99INV. 275.08

TOP 27

4.47

INV. 2

73.37

W. 4

50 m

m

CONC. K. & G.

CO

NC

. K.

& G

.

CONC. K. & G.CONC. K. & G.

CO

NC.

K.

& G

.

CONC. K. & G.

CO

NC

. KE

RB

CO

NC

. KE

D. I. C. L. SEWER PIPE

HO

S PIT

AL

INV.

274. 4

6

TOP

275.0

0

SMH

SMH

SMH

TOP 27

5.64

INV. 2

74.6

5

TOP 276.76TO

P 27

6.87

TOP 276.92

SMH

SMHINV. 275.71

INV. 2

76.2

2

SMH

INV. 275.67

TOP

275.

68

SMH

0.3 m DEEP

INV. 2

74.8

4

TOP 2

75.08

RE

CO

RD

S

OLDSMH

BITUMEN SURFACE

BITUMEN SURFACE

BIT

UM

E N S

UR

FAC

E

BI T

UM

EN

SU

RFAC

E

BITUMEN SURFACE

BITUMEN SURFACE BITUMEN SURFACE

BITUMEN CARPARK

BITUMEN ROAD

BITUMEN ROAD

BITUMEN ROAD

BITUMEN FOOTPATH

BITUMEN CARPARK

NG

AVING

PAVING

PAVING

PAVING PAVING

LAWN

LAWN

LAWN

LAWN

LAWN

LAWN

LAWN

LAWN

LAWN

LAWN

ROSE

GARDEN

ROSE GARDEN

CONC.

B- B

-Q

CO

NC

RE

TE

STA

IRS

CO

NC

RET

E

STA

IRS

STE

EL S

T AIR

S

STEPS

AC

AC

AC

AC

G. I. PITTOP 276.00INV. 274.91

S. I . PI T

TOP 275.65

I NV. 274.90

TOP 275.34INV. 273.76

G. I. PIT

INV. 273.49TOP 274.78G. I. PIT

INV. 273.95TOP 275.91G. I. PIT

G. I. P

ITIN

V. 274

.17

TOP

276.3

2

G. I. P

ITTOP 27

6.26

INV. 2

74.67

INV. 2

74.7

4

TOP 27

6.33

G. I. P

IT

P 275.93

V. 275.28

INV. 2

75.54

TOP 27

6.14

G. I. P

IT

S. W. PIT

S. W. P

IT

TWO STOREY BRICK BUILDING

TILE ROOF

BRICK BUILDING

METAL ROOF

BRICK BUILDINGMETAL ROOF

BRICK BUILDING

METAL ROOF

BRICK BUILDING

METAL ROOF

BRICK BUILDING

BRICK BUILDINGMETAL ROOF

DO

M.

WA

TER

PR

ES

SU

RE

PU

MPS

FIR

E H

YDR

ANT

BO

OS

TER

PU

MP

AMBULANCEBAY

STEEL & METALCARPORT

BRIC

K B

UILD

ING

MET

AL R

OOF

VERANDAH

VERANDAH

GEORGE HATCH BUILDINGCHILD MINDING CENTRE

METAL ROOF

DOCTORS

ACCOMODATION

ADMISSIONS & EMERGENCY

BUILDING No. 68

FH 1

50 m

m 0

.6 m

DEE

P

FH 150 mm 0.45 DEEP

FH 1

50 m

m 1

m D

EEP

FH 150 mm 0.9m DEEP

FH 150 mm 1 m DEEP

FH 150 mm 0.65 m DEEP

FH 1

50 m

m

WM

15 0

mm

0.8

m D

EEP

WM

15 0

mm

0.9

m D

EE

P

CW

150

mm

0.8

m D

EEP

CW 150 mm 0.8 m DEEP

WM

10 0

mm

16

17

18

F.L. 277.88

FH 150 mm 0.5 m DEEPCW 100 mm 0.5m DEEPIRR 100 mm 0.5m DEEP

COMMON TRENCH

IRR

IGAT

ION

100

mm

IRRIGATION 100 mm

CW 150 mm 0.8 m DEEP

TEAM PIPE SUSPENDEDH BETWEEN BUILDINGS

PIPE CAPPED

(PLA

N 9

6720

-E

SU

BM

AIN

S N

OT

(PL AN 9 67 20 -E

0 10 2)

CA

B LE N

OT LO

CA

TED

(PLA

N 96 720- E

0 102)C

ABLE N O

T LOCA

T ED

74.0

274.0

275.0

275.0

276.0

276.0

276.0

276.0

276.0

276 .

0

276.0

277.0

277.0

277.

0

277.

0

277.0

277.0

278.

0

Document Control Status:

Scale:

Drawing Title

Co-ordinated:

Client

Project

ConsultantsConsultants

Drawing Number:

Revision:

Project Engineer:

Project Director:

Date:

North:

enstruct group Pty Ltd ACN 094 570 671

Project No.

PROJECT MANAGEMENT

ADDRESS: LEVEL 16, 207 KENT STREET, NSW 2000TEL: 02 9276 1400

NAME: TSA MANAGEMENT

B1 DRAWING SHEET

ARCHITECT

ADDRESS: LEVEL 2, 204 CLARENCE STREET SYDNEY, NSW 2000TEL/FAX: 02 9267 9599 / 02 9264 5844

NAME: COX RICHARDSON

ELECTRICAL & ICT ENGINEERS

ADDRESS: 100 CHRISTIE STREET ST LEONARDS, NSW 2065TEL/FAX: 02 9928 2100 / 02 9928 2500

NAME: SINCLAIR KNIGHT MERZ

MECHANICAL & LIFT ENGINEERS

ADDRESS: LEVEL 3, 454-456 PACIFIC HIGHWAY ST LEONARDS, NSW 2065TEL/FAX: 03 TEL NO / 03 FAX NO

NAME: WOOD & GRIEVE

HYDRAULICS & FIRE PROTECTION CONSTANTS

ADDRESS: 60 HICKSON ROAD, NSW 2000TEL/FAX: 02 9241 4188 / 02 9241 4334

NAME: NORTHROP

ACOUSTIC ENGINEERS

ADDRESS: LEVEL 1, 60 MILLER STREET, NORTH SYDNEY, NSW 2060TEL/FAX: 02 9928 6800 / 02 9955 6900

NAME: NORMAN, DISNEY & YOUNG

LANDSCAPE DESIGN

ADDRESS: LEVEL 1 / 5 WILSON STREET, NEWTOWN, NSW 2042TEL/FAX: 02 9577 5533 / 9519 8323

NAME: OCULUS

TRAFFIC PLANNING

ADDRESS: LEVEL 9, 203 PACIFIC HIGHWAY, ST LEONARDS, NSW 2065TEL/FAX: 02 94967700 / 02 9439 5120

NAME: CARDNO

4363

DUBBO BASE HOSPITAL

REDEVELOPMENT STAGE 1 / 2

MYALL STREET, DUBBO NSW

NCC & ACCESSIBILITY

ADDRESS: LEVEL 1, 71-73 ARCHER STREET, CHATSWOOD, NSW 2057TEL/FAX: 02 9411 5360 / 02 9411 5420

NAME: BCA LOGIC

Drawn:

enstruct group pty ltdLevel 4, 2 Glen StreetMilsons Point NSW 2061

Telephone (02) 8904 1444Facsimile (02) 8904 1555http: // www.enstruct.com.au enstruct

NOTES

THIS DRAWING IS AN UNCONTROLLED COPY. UNLESS NOTED OTHERWISE

1. DO NOT SCALE DRAWINGS. WRITTEN DIMENSIONS GOVERN.2. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED OTHERWISE.3. ALL DIMENSIONS SHALL BE VERIFIED ON SITE BEFORE PROCEEDING WITH

THE WORK. ENSTRUCT SHALL BE NOTIFIED IN WRITING OF ANY DISCREPANCIES.4. THIS DRAWING MUST BE READ IN CONJUNCTION WITH ALL RELEVANT

CONTRACTS, SPECIFICATIONS, REPORTS AND DRAWINGS.

COPYRIGHT OF THIS DRAWING IS VESTED IN ENSTRUCT PTY LTD

DescriptionRev By Date

FOR GENERAL NOTES REFER TO DRAWING CIV-SI-001-00

CIV-SI-100-04

T.B.B.

I.H.

I.H. 1:200

14/06/2012

04

I.H.

TENDER

SHEET 4 OF 4PLANGENERAL ARRANGEMENT

01 ISSUED FOR APPROVAL 08.06.12IH

02 ISSUED FOR TENDER 20.06.12IH

03 ISSUED FOR TENDER 28.06.12IH

04 ISSUED FOR APPROVAL 05.07.12IH