duration - the holy grail of ms project?

26
MS Project How MS Project Deals With Duration

Upload: dmdk12

Post on 03-Nov-2014

13 views

Category:

Business


1 download

DESCRIPTION

Duration - The Holy Grail of MS Project?

TRANSCRIPT

Page 1: Duration - The Holy Grail of MS Project?

MS Project

How MS Project Deals With Duration

Page 2: Duration - The Holy Grail of MS Project?

MS Project Perspective on Duration

Duration

Units of Productive Capacity

Is a Function of

Productive Work

Required

Page 3: Duration - The Holy Grail of MS Project?

MS Project Perspective on Duration

• Duration:– How long it will take to complete a task/activity

and thereby contribute to building a deliverable– Given:– The productive work required and the units of

production capacity available– Expressed as time (minutes; hours; days)

Page 4: Duration - The Holy Grail of MS Project?

MS Project Perspective on Duration

• Productive Work:– How long it will take to complete a task/activity

and thereby contribute to building a deliverable– Given:– The productive work required and the units of

production capacity available– Expressed as time (minutes; hours; days)

Page 5: Duration - The Holy Grail of MS Project?

MS Project Perspective on Duration

• Unit of Capacity Available for Work– The availability of productive capacity to conduct

work– Given – The Calendar configuration in MS Project– Expressed as availability (100 = full availability)

Page 6: Duration - The Holy Grail of MS Project?

DURATION = WORK/UNITS

WORK = DURATION *UNITS

UNITS = WORK/DURATION

16 8/.5

8 16 *.5

.5 8/16

Page 7: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

DURATION = WORK/UNITS

Page 8: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

DURATION = 8 HRS/ 1

DURATION = 8 HRS/.5

Page 9: Duration - The Holy Grail of MS Project?

Duration Work Units

Page 10: Duration - The Holy Grail of MS Project?

Duration Work Units

Page 11: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

WORK = DURATION *UNITS

Page 12: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

WORK = 8 *.5

WORK = 16 *.5

Page 13: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

DURATION = WORK/UNITS

Page 14: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

DURATION = 8/1

DURATION = 16/1

Page 15: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

DURATION = WORK/UNITS

Page 16: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

DURATION = 8/ 1

DURATION = 8/.5

Page 17: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

UNITS = WORK/DURATION

Page 18: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

UNITS = 8/8

UNITS = 8/16

Page 19: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

DURATION = WORK/UNITS

Page 20: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

DURATION = 8/1

DURATION = 16/1

Page 21: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

Fixed-duration task Work is recalculated.

Work is recalculated.

Units are recalculated.

WORK = DURATION *UNITS

Page 22: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

Fixed-duration task Work is recalculated.

Work is recalculated.

Units are recalculated.

WORK = 8 *1

WORK = 8 *.5

Page 23: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

Fixed-duration task Work is recalculated.

Work is recalculated.

Units are recalculated.

WORK = DURATION *UNITS

Page 24: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

Fixed-duration task Work is recalculated.

Work is recalculated.

Units are recalculated.

WORK = 8 *1

WORK = 16 *1

Page 25: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

Fixed-duration task Work is recalculated.

Work is recalculated.

Units are recalculated.

UNITS = WORK/DURATION

Page 26: Duration - The Holy Grail of MS Project?

IN A IF YOU REVISE UNITS

IF YOU REVISE DURATION

IF YOU REVISE WORK

Fixed-units task Duration is recalculated.

Work is recalculated.

Duration is recalculated.

Fixed-work task Duration is recalculated

Units are recalculated.

Duration is recalculated.

Fixed-duration task Work is recalculated.

Work is recalculated.

Units are recalculated.

UNITS = 8/8

UNITS = 16/8