durgapur projects limited: vocational training presentation
TRANSCRIPT
Presentation on Vocational Training at DPLSubmitted by:
Inderveer Singh Kamboh
Dipanwita Ghosh
Satyajit Marik
Saumyadip Moitra
Sayantany Ghanty
Sumanta Das
Department of Electrical Engineering, BCREC
1BCREC/EE/7thSem
About DPL-Overview
Thermal Power Station
Alternator Units
Transformers
Transmission & Distribution
Protection Systems
Switch Yard
Load Dispatch centre
Coke Oven
Conclusion &Future prospects
2BCREC/EE/7thSem
About DPL-Overview
•Incorporated on 6th September,1961. Govt. of West Bengal Undertaking•Thermal Power Plant. A total of seven units of different capacities have an aggregate 701-mega watt of installed capacity •Consists of Coke Oven Batteries, Bye-products Plant, Gas Grid Project, Thermal Power Plant and Water Works•. Generation of power and its distribution at 11KV in its licensed area at Durgapur and transmission of surplus power to WBSEB & WBSEDCL
3BCREC/EE/7thSem
Thermal Power Station•A generating station, which converts heat energy of coal combustion into
electrical energy, is known as a steam power station
•A steam power station works on the Rankine cycle. Steam is produced in
the boiler by utilizing the heat of coal combustion that is then expanded in
the prime mover (i.e. steam turbine) and is condensed to be fed into the
boiler again. The steam turbine drives the alternator which converts
mechanically energy of turbine into electrical energy
ADVANTAGES:
The fuel (i.e. coal) used is quite cheap.
Less initial cost as compared to other generating stations
It can be installed at any place irrespective of the existence of coal. The
coal can be transported to the site of the plant by rail or road.
It requires less space as compared to the hydroelectric power stations.
4BCREC/EE/7thSem
Coal and ash handling arrangements.
Steam generating plant.
Steam turbine.
Boiler
Alternator.
Feed water.
Cooling arrangements
Layout of a typical Thermal Power Plant:
5BCREC/EE/7thSem
BOILER:
•The boiler is a rectangular furnace about 50 feet (15 m) on a side and 130 feet (40 m) tall. Its walls are made of a web of high pressure steel tubes about 2.3 inches (58 mm) in diameter.•The accessories include –1.Economizer2. Boiler Drum3. Down comers 4. Water walls5. Water wall plates 6. Primary super heater 7. Platen super heater 8. Final Super heater 9. Reheater 10. Burner 11. Ignitors.•The heat of combustion of coal in the boiler is utilized to convert water into steam at high pressure and temperature.
6BCREC/EE/7thSem
•Generator of the alternator as it is usually called in the electrical end of the turbo-generator set. It is cylindrical pole synchronous generator•converts the mechanical energy of the turbine into electrical energy. The generation of electricity is based on the Faradays law of electromagnetic induction. •STATOR: THE stator is a component that embodies the armature core and armature winding.•ROTOR: The rotor forms the poles and provides the magnetic field. It revolves at a speed of 3000 r.p.m.
7BCREC/EE/7thSem
Description Unit I Unit II Unit III Unit IV Unit V Unit VI Unit VII Total
Capacity(MW) 30 30 77 77 77 110 300 641
Date of
Synchronisation10.6.1960 10.4.1960 23.4.1964 19.6.1964 4.5.1966 3.7.1985 29.12.2007
Date of Commercial
Operation10.8.1960 10.6.1960 23.6.1964 29.6.1964 4.7.1966 1.1.1987 30.4.2008
Present Status Decommissioned Decommissioned In operation In operation In operation In operation In operation
Cross section of an elementarystator and salient-pole rotor
8BCREC/EE/7thSem
Transformer is the static device for rising or lowering voltage level in a.c. electrical circuitsIn DPPS there are 6 generator transformers., 1 auxiliary transformer & 1 reserve transformerThese transformers are cooled by three methods-OFAFONAFONAN BHEL is the provider for majority of these transformers.
9BCREC/EE/7thSem
Transformer Protection & Accessories:
There are many protection devices used to protect a power transformer. The factors governing the protection scheme are its size, importance and location of the transformer.CONSERVATORBREATHERBUCHHOLZ RELAYVENT PIPEAIR NATURAL COOLING FAN
10BCREC/EE/7thSem
TRANSMISSION & DISTRIBUTION
The Power that is generated from power plant must be transmitted to different places through substations Every substations has one or more than one transformer & circuit breakers.132 KV Incomers Lightning arrester Isolator CT Circuit breaker Isolator Lightning arrester Step - transformer (132KV /11KV) 11 KV incomer Bus Bar Feeders Outgoing line Underground cable Distributor
11BCREC/EE/7thSem
Circuit Breakers:A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit. Its basic function is to detect a fault condition and interrupt current flow.Type of circuit breaker:1)Low-voltage circuit breakers 2)Magnetic circuit breakers 3)Medium-voltage 4)High-voltage circuit breakers 5) (SF6) high-voltage circuit breakers6)Carbon dioxide (CO2) high-voltage CB 7)Vacuum circuit breakerRelayA relay is an electrically operated switch. Many relays use an electromagnet to mechanically operate a switch, but other operating principles are also used, such as solid-state relays
12BCREC/EE/7thSem
Isolator
ISOLATOR:•Isolator is basically a no load switch designed to operate under no load condition•Isolators used in power system are generally three pole isolators having identical supports•The isolators are “Horizontal Breaker Type”.LIGHTNING ARRESTER:
•Lightning Arrester are usually connected between phase and ground of the power plant to protect the equipment from sudden over voltages caused by lightning or some other reasons •Lightning arrester consists of low resistor and gap elements. Resistor elements consist of nonlinear resistors
13BCREC/EE/7thSem
In DPL there are three different KV bus bars present33KV132 KV220KV 33kv feeders go to two substation:-One is near Barrage at Bankura & another is near coal belt region.132kv feeders go to four substations of DPL. The substations are:-A-Substations(FCI)B-Substations(near MAMC)C-Substations(Durgapur Chemicals)C-1 Substations(near Raturia) 220kv feeders go to Bidhannagar substations
14BCREC/EE/7thSem
The Load Despatch Department is the nerve centre for the operation , planning , monitoring and control of the power system . Electricity cannot be stored and has to be produced when it is needed. It is therefore essential that power system is planned and operated optimally & economically.
DPLThere are 4 tie lines : 2 nos. of 132 KV line(temporarily OFF now) and 2 nos. of 220
KV line. These tie lines are used for import or export of power. Since now 132 KV lines are OFF hence at present the 2 nos. 220kV lines are used for this purpose.If there is excess power generation above demand then those excess are exported and if demand is more than generation then power has to be imported. These import and export of power is done from/ to WBSETCL and IEX(Indian energy Exchange).All consumers are of 132 KV, but power is generated or received at 220 KV. So to distribute power to the consumers there are 3 nos. auto transformer, 2 nos. 160 MVA 220Kv/ 132Kv transformers and 1 nos. 100 MVA transformer. These instruments step down power to 132 KV from 220 KV for distribution to consumers.It is also mandatory to buy some small amount of solar energy namely 2, 3, 4 MW.A 15 mins recording procedure is used for recording of power generation ,demand and frequency.
15BCREC/EE/7thSem
DPL's Coke Oven Complex is India's one of the largest Merchant Cokery producing Coke of global quality. The current installed capacity of the Coke Oven Complex is 0.5 million tonnes of Gross Coke per annum, 20,000 tonnes of Crude Coal Tar per annum and 90 million NM3 of Coke Oven gas per annum.
Description #1 #2 #3 #4 #5 Total
Nos of Ovens 30 30 - - 40 100
Status Operational Hot Blank Future
Rebuilding
Future
Rebuilding
Operational
Height (Mtrs) 4.5 4.5 - - 4.5
Width (mm) 400 400 - - 400
Length (mm) 13400 13400 - - 13430
Eff. Volume M3 21.74 21.74 - - 21.76
Type Twin flue Side jet gas gun
system
Twin flue Side jet gas gun
System
- - Twin flue underjet
heat regenerative
Oven Availability 100% 100% - - 100%
COKE OVEN
16BCREC/EE/7thSem
Conclusion & Future Prospects:
•8th Unit 250 MW capacity is being built in association with BHEL•Units I &II decommissioned , sold as scrap.•In order to boost its financial position, DPL has forayed into Real Estate Sector.•Coal Bed Methane (CBM ) technology is being implemented for future power generation
17BCREC/EE/7thSem
18BCREC/EE/7thSem