dwall production analysis-based on stec dwg d 920 new cs 4581 rev 0 25012010
TRANSCRIPT
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
1/23
Normal Normal
Project Dwall Dwall G.Total
Work 0.8 1.2 0.8 1.2 0.8 1.2 0.8 1.2
Thk 1.0 1.2
Length 112 666 779
Exc.Area 2,781 29,128 31,909
Exc.Vol. 2,225 34,953 37,179
Mob #REF!
Work Duration #REF!
No.of Panel 20 119 14 55 6 21 0 43 139
Length of Panel 5.62 5.60 69.00 27 43 80
Total wk (MC) 31.00 31.00 13.00 8 10 31
Panel/wk (Based MCP) 5.31 3.38 4
Prod.rate, m3 1.18
No.of Rigs 4
Grab 2 2 2
1.2 BC Cutter 2 2 2
URS DWALL Soil Profile
104 Fill 326 2,536 163 1,223 163 423 0 889 2,862
557 KF 1,857 15,798 1,498 7,073 359 2,884 0 5,841 17,655
209 GVI 131 3,397 0 1,488 131 673 0 1,235 3,527174 GV 468 4,848 468 1,688 0 934 0 2,226 5,316
52 GIV 0 909 0 741 0 57 0 112 909
35 GIII 0 808 0 332 0 190 0 286 808
0 GII 0 831 0 262 0 0 0 569 831
1132 Total area, m3 2,781 29,128 2,128 12,809 653 5,161 0 11,158 31,909
Increased Qty Diff -2,659
Phase 1 Phase 2 Phase 3
Dwall Dwall
\\vboxsrv\conversion_tmp\scratch_2\201400549.xlsx.ms_office
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
2/23
1.0 m Dwall Panel
Zone A Zone A Zone A Zone A1
Block 1 Block 2 Block 3
N Value
Panel Length
(m) - 65.29 - -
0 Fill (m) 2.00
100 GIV (m) -
RQD 30-80 GIII (m) -
RQD 100 GII (m)
N Value Panel Length - - - -
0 Fill (m)
100 GIV (m)
RQD 30-80 GIII (m)
RQD 100 GII (m)
N Value Panel Length - - - -
0 Fill (m)
100 GIV (m)
RQD 30-80 GIII (m)
RQD 100 GII (m)
1.2m Dwall Panel
Zone A Zone A Zone A
Block 1 Block 2 Block 3
N Value
Panel Length
(m) 49.75 19.95 22.80 19.43 16.06 38.87
0 Fill (m) 3.00 3.00 3.00 3.00 3.00 2.50
100 GIV (m) 4.50 2.50 3.00 2.80 2.50 1.50
RQD 30-80 GIII (m) 1.00 1.00 1.00 1.00 1.50 1.00
RQD 100 GII (m) 2.00 3.00
N Value Panel Length - 33.68 16.58 -
0 Fill (m) 3.00 3.00
100 GIV (m) - -
RQD 30-80 GIII (m) 1.00 1.00
Phase 1
Phase 2
Phase 2
Phase 3
Phase 1
)
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
3/23
RQD 100 GII (m)
N Value Panel Length - - 5.70
0 Fill (m) 3.00
100 GIV (m) -
RQD 30-80 GIII (m) 1.00RQD 100 GII (m)
Phase 3
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
4/23
Zone A2 Zone B Zone C Zone D Zone D1
(m)
- - - 14.51 - 79.80
2.20 4.20
20.00 38.50
- -
3.00 9.50
- - -
- - -
-
- - - 32.65 - 32.65
5.00 5.00
11.00 11.00
4.00 4.00
- -
- -
- -
-
- - - - - - -
- -
- -
- -
- -
- -
- -
-
112.45
Zone A2 Zone B Zone C Zone D
(m)
1/F-E B1-C1
- 39.38 11.14 38.87 29.02 23.32 308.59
3.00 2.00 5.00 3.00 5.00 35.50
20.00 22.00 11.50 16.00 19.00 215.30
2.50 10.00 4.50 6.00 7.00 47.00
13.50 7.00 5.00 48.40
2.00 - 1.50 20.30
- 1.00 3.00 1.00 11.50
- 3.00 8.00
- - - - 47.16 20.21 117.63
3.00 3.00 9.00
20.00 22.50 60.00
2.50 9.50 12.50
13.50 7.00 13.50
1.00 - 1.00
- 1.00 3.00 3.00
Zone D1
Other Area
Other Area
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
5/23
- -
- - - 21.25 16.06 154.43 31.09 11.40 239.93
4.00 3.00 3.00 3.00 3.00 19.00
14.00 21.00 21.75 16.00 22.50 116.25
- 2.00 3.50 9.00 10.00 35.50
1.00 - 10.50 5.00 4.50 22.00
- - 3.00 -
1.00 1.00 2.00 3.0015.00 5.00 15.00
666.15
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
6/23
Nos
(m2) of
5.7 Panels
14
162.50
1,498.07
-
467.92
-
-
-
6
163.25
359.15
130.60
-
-
-
-
0
-
-
-
-
-
-
-
2,781.48 20
Nos
(m2) of
5.7 Panels
55
1,019.58
5,894.51
1,240.33
1,407.00
617.30
276.71
218.69
21
352.89
2,403.13
561.20
778.13
47.16
158.05
Total
Total
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
7/23
-
43
741.04
4,867.25
1,029.14
1,855.22
93.27
238.37474.20
24,273.15 119
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
8/23
1 2
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
9/23
a1
ABB222
a2
DT/2009
103.33mrl
100.00mRL
95.00mRL
90.00mRL
85.00mRL
80.00mRL
75.00mRL
70.00mRL
65.00mRL
1 2
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
10/23
60.00mRL
55.00mRL
50.00mRL
Legend
Fill
Kallang Formation
Granite GVI
Granite GV
Granite GIV
Granite GIII
Granite GII
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
11/23
5 63 4
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
12/23
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
13/23
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
14/23
`
7 8 9
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
15/23
ABH218
ABH214
a4
7 8 9
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
16/23
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
17/23
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
18/23
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
19/23
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
20/23
SECTIONAL ELEVATION ON LOW LEVEL DI APHRAGM WALL FOR SURS AT GRID LI NE d1-b8-a4
103.33mrl
100.00mRL
95.00mRL
90.00mRL
85.00mRL
80.00mRL
75.00mRL
70.00mRL
65.00mRL
DWALL TOEL LEVEL
60.00mRL
6m TOE
BELOW
55.00mRL
50.00mRL
0
m
10
m
20
m
30
m
40
m
Legend
Fill Granite GIII
Kallang Formation Granite GII
Granite GVI Diaphragm Wall Panel
Granite GV
Granite GIV
d1
b8
ABH215
TOP OF DIAPHRAGM WALL
ABH213
ABH214
DT/2008/VST,PZS
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
21/23
SECTIONAL ELEVATION ON LOW LEVEL AND FULL HEI GHT DI APHRAGM WALL F OR SURS AT GRID L INE d2-b9-b10
103.33mrl
100.00mRL
95.00mRL
90.00mRL
85.00mRL
80.00mRL
75.00mRL
70.00mRL
65.00mRL
DWALL TOEL LEVEL
60.00mRL
6m TOE L
BELOW S
55.00mRL
50.00mRL
0m
1
0m
2
0m
3
0m
4
0m
Legend
Fill Granite GIII
Kallang Formation Granite GII
Granite GVI Diaphragm Wall Panel
Granite GV
Granite GIV
ABH214
DT/2008/VST,PZS
d2
b9
TOP OF DIAPHRAGM WALL
ABH2
12
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
22/23
Bill of Quantities
Downtown Line Stage 2 C920 Project, Singapore Option A - SURS with Diaphragm Wall
DIAPHRAGM WALL WORKS
ITEM DESCRIPTION UNIT QTY RATE AMOUNT Remarks
All Quanti t ies are Provisional -
1.0 Mobilisation & Demobilisation & Maintenance L/S 1 -$ $ 2,451,690.00
2,451,690.00$
2.0 Guide Wall Construction
2.1 Constructing 300mmx1200mm Guidewall m 790 280.00$ 221,200.00$ Included Material
2.2 Removal of Guidewall m 790 40.00$ 31,600.00$ Included Disposal
252,800.00$
3.0 Diaphragm Wall (1200mm thick)
3.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing) m3 26,135 405.00$ 10,584,675.00$ Included Disposal
3.2 Extra Over for Rock Excavation (GIII Granite) m3 800 650.00$ 520,000.00$ Included Disposal
3.3 Concreting m3 26,135 25.00$ 653,375.00$ Material by Maincon
3.4 Rebar Fabrication & Installation ton 6,011 250.00$ 1,502,762.50$ Material by Maincon
3.5 Place LSS Type I for Backfilling m3 1.00 70.00$ Rate Only
4.0 Diaphragm Wall (1000mm thick)
4.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing) m3 2,328 455.00$ 1,059,240.00$ Included Disposal
4.2 Extra Over for Rock Excavation (GIII Granite) m3 56 455.00$ 25,480.00$ Included Disposal
4.3 Concreting m3 2,328 40.00$ 93,120.00$ Material by Maincon
4.4 Rebar Fabrication & Installation ton 535 250.00$ 133,860.00$ Material by Maincon
4.5 Place LSS Type I for Backfilling m3 1.00 70.00$ Rate Only Included Material
5.0 Diaphragm (SURS) Wall (1200mm thick )
5.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing) m3 6,105 405.00$ 2,472,525.00$ Included Disposal
5.2 Extra Over for Rock Excavation (GII and GIII Granite) m3 1,263 1,705.00$ 2,153,415.00$ Included Disposal
5.3 Concreting m3 1,060 25.00$ 26,500.00$ Material by Maincon
5.4 Rebar Fabrication & Installation ton 244 250.00$ 60,950.00$ Material by Maincon
5.5 Place LSS Type I for Backfilling m3 6,308 70.00$ 441,560.00$ Included Material
19,727,462.50$
6.0 Hacking and Trimming Works -
6.1 Hacking and trimming of Diaphragm Wall to Design COL m 884 350.00$ 309,400.00$ Included Disposal
-
7.0
Acceptance Works in Requirements To LTA's M&W
Specification
7.1 Sonic Coring Works No 1.00 $ 5,000.00 Rate Only
7.2 Sonic Logging Works No 1.00 $ 3,000.00 Rate Only
8.0 Other Works -
8.1 Coupler Installation (Labour Only) No 1.00 5.00$ Rate Only Material by Maincon
8.2
Installation of 150mm dia.black pipe for Inclinometer Works byOthers m 1.00 45.00$ Rate Only Included Material
8.3
Installation of 150mm dia.black pipe for Fissured Grouting Works by
Others No 1.00 45.00$ Rate Only Included Material
8.4 Indstallation of H-Beam into Diaphragm Wall T-Panel (Labour Only) No 1.00 1,000.00$ Rate Only Material by Maincon
$ 309,400.00
-
22,741,352.50$TOTAL
Sub-Total
Sub-Total
Sub-Total
Sub-Total
-
8/13/2019 Dwall Production Analysis-Based on STEC DWG D 920 NEW CS 4581 REV 0 25012010
23/23
Bill of Quantities
Downtown Line Stage 2 C920 Project, Singapore Option B - Pre-Boring Works on SURS
DIAPHRAGM WALL WORKS
ITEM DESCRIPTION UNIT QTY RATE AMOUNT Remarks
All Quant i t ies are Provis ional -
1.0 Mobilisation & Demobilisation & Maintenance L/S 1 -$ $ 2,451,690.00
2,451,690.00$
2.0 Guide Wall Construction
2.1 Constructing 300mmx1200mm Guidewall m 790 280.00$ 221,200.00$ Included Material
2.2 Removal of Guidewall m 790 40.00$ 31,600.00$ Included Disposal
252,800.00$
3.0 Diaphragm Wall (1200mm thick)
3.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing) m3 26,135 405.00$ 10,584,675.00$ Included Disposal
3.2 Extra Over for Rock Excavation (GIII Granite) m3 800 650.00$ 520,000.00$ Included Disposal
3.3 Concreting m3 26,135 25.00$ 653,375.00$ Material by Maincon
3.4 Rebar Fabrication & Installation ton 6,011 250.00$ 1,502,762.50$ Material by Maincon
3.5 Place LSS Type I for Backfilling m3 1.00 70.00$ Rate Only Included Material
4.0 Diaphragm Wall (1000mm thick)
4.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing) m3 2,328 455.00$ 1,059,240.00$ Included Disposal
4.2 Extra Over for Rock Excavation (GIII Granite) m3 56 455.00$ 25,480.00$ Included Disposal
4.3 Concreting m3 2,328 40.00$ 93,120.00$ Material by Maincon
4.4 Rebar Fabrication & Installation ton 535 250.00$ 133,860.00$ Material by Maincon
4.5 Place LSS Type I for Backfilling m3 1.00 70.00$ Rate Only Included Material
5.0 Pre-Boring (SURS) Wall (127m Length)
5.1 Pre-Boring on Soil & Rock (GIII Granite at 1.0m socketing) m3 6,105 405.00$ 2,472,525.00$ Included Disposal
5.2 Extra Over for Rock Pre-Boring (GII GIII Granite) m3 1,263 650.00$ 820,950.00$ Included Disposal
5.3 Concreting m3 1,060 25.00$ 26,500.00$ Material by Maincon
5.4 Rebar Fabrication & Installation ton 244 250.00$ 60,950.00$ Material by Maincon
5.5 Place LSS Type I for Backfilling m3 6,308 70.00$ 441,560.00$ Included Material
18,394,997.50$
6.0 Hacking and Trimming Works -
6.1 Hacking and trimming of Diaphragm Wall to Design COL m 884 350.00$ 309,400.00$ Included Disposal
-
7.0
Acceptance Works in Requirements To LTA's M&W
Specification
7.1 Sonic Coring Works No 1.00 $ 5,000.00 Rate Only Included Material
7.2 Sonic Logging Works No 1.00 $ 3,000.00 Rate Only Included Material
8.0 Other Works -
8.1 Coupler Installation (Labour Only) No 1.00 5.00$ Rate Only Material by Maincon
8.2
Installation of 150mm dia.black pipe for Inclinometer Works byOthers m 1.00 45.00$ Rate Only Included Material
8.3
Installation of 150mm dia.black pipe for Fissured Grouting Works byOthers No 1.00 45.00$ Rate Only Included Material
8.4 Indstallation of H-Beam into Diaphragm Wall T-Panel (Labour Only) No 1.00 1,000.00$ Rate Only Material by Maincon
$ 309,400.00
-
21,408,887.50$
Sub-Total
Sub-Total
Sub-Total
Sub-Total
TOTAL