e-mail : [email protected] · ... water supply and sewage ... (automated fountain) ... arz ice‐cream...

32
    2016-September Palestinian Control & Supervision - PCS Palestinian Authority - Nablus, Yaser Arafat Street, Fattouh building, Ground floor Mobile : +970 599 25 24 49 Tel/Fax : +970 9 2 34 94 22 E-mail : [email protected]

Upload: phammien

Post on 12-Apr-2018

217 views

Category:

Documents


4 download

TRANSCRIPT

 

 

   

2016-September

Palestinian Control & Supervision - PCS

Palestinian Authority - Nablus,

Yaser Arafat Street, Fattouh building, Ground floor

Mobile : +970 599 25 24 49

Tel/Fax : +970 9 2 34 94 22

E-mail : [email protected]

 

 

Page 1 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

CONTENTS 

I.  PCS in brief ..................................................................................................................................................... 2 

II.  Structure ......................................................................................................................................................... 3 

III.  Targeted markets ........................................................................................................................................... 3 

IV.  Products ......................................................................................................................................................... 4 

V.  Services ........................................................................................................................................................... 5 

VI.  Projects implemented in Palestine ................................................................................................................. 7 

1)  Booster station automation / 4 stations – 2016 ........................................................................................ 7 

2)  ARZ Ice‐Cream factory production line – 2016 ........................................................................................ 10 

3)  ARZ Ice‐Cream factory Mixing Process ‐ 2016 ......................................................................................... 11 

4)  Water Supply and Sewage Facilities Improvement for Bethlehem ‐ Beit Jala & Beit Sahour Area– 201613 

5)  Passavant Energy & Environment ‐ Nablus West WWTP– 2015 .............................................................. 14 

6)  JERICHO MUNICIPALITY – 2015 (WATER FLOW MONITORING)............................................................... 15 

7)  Sakka & Khoudary – 2014 (water supply monitoring) ............................................................................. 16 

8)  NEDCO – 2014 (Electrical sub‐stations scada communication) ............................................................... 17 

9)  PROMEC – 2014 (Automated fountain) ................................................................................................... 18 

10)  ARZ Ice‐Cream New Factory – 2013 (Factory automation design) ...................................................... 18 

11)  Among other clients: ........................................................................................................................... 19 

VII.  SCADA international experience .............................................................................................................. 20 

1)  GEA – ARC ................................................................................................................................................ 20 

2)  Balthazard & cotte ................................................................................................................................... 25 

3)  Novasep ................................................................................................................................................... 27 

4)  Arkopharma ............................................................................................................................................. 29 

 

    

 

 

Page 2 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

I. PCS  IN  BRIEF  

PCS brings together all the skills needed to design, install, commissioning and maintenance for variety 

of electrical and automation installations. Our technology know‐how and application experience enables us to supply products and deliver high quality services with the proven performance and reliability that our customers expect.  Our value offer is based on providing the ultimate Quality within Shortest Time at Lowest Price. 

 

We are particularly specialized in Automation and SCADA, which includes the following areas: 

 

Advanced consulting 

Factory discrete automation 

Factory process automation 

SCADA telecontrol systems 

Manufacturing Execution System (MES) 

Human Machine Interface (HMI). 

Drive technology 

Sensor systems 

Identification solutions 

Field buses and industrial networks 

Stock management 

Robotics 

Petri net optimization 

Low‐voltage power distribution (protection, switching, measuring and monitoring and switchboards) 

 

 

 

 

 

 

 

 

 

Palestinian Control & Supervision is a partner for SIEMENS automation. 

Our philosophy is to pay our clients all the attention and listen to their needs. We deploy professionalism and creativity to contribute to the success of their projects and to gain their loyalty in a relationship of mutual trust. Moreover, any system could be adapted to the utmost needs of the client. 

 

 

 

 

Page 3 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

II. STRUCTURE 

 

PCS company structure is constituted as the following: 

 

 

 

 

 

 

III. TARGETED  MARKETS 

 

Many markets are targeted by PCS, among which are : 

Water and Wastewater 

Electrical Power Transmission and Distribution 

Mining and Cement 

Pharmaceuticals 

Food and Beverages 

Others… 

 

 

 

 

 

 

Page 4 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

IV. PRODUCTS 

 

PCS  is the source for a wide range of automation and SCADA products; being a partner for SIEMENS, allows us  to provide our clients with  the best Quality products and  software. Moreoever, we have  range of products that will fit all the industries and sectors. 

Please visit our website (www.pcs.com.ps) in order to obtain more information and details about our products. 

In  addition  of  being  a  strong  partner  for  SIEMENS,  PCS  have  the  needed  expertise  to  deal  with automation and SCADA solutions for other manufacturers such as: 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 5 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

V. SERVICES 

 

We do provide our clients with a complete service: 

1) Design 

We listen to your needs 

We choose the most adapted solutions technically and financially 

We help you to establish the tender 

We offer you a price quotation 

2) Project supervision 

We follow the project closesly at on each step 

3) Installation 

We realize the electrical and mechanical installations needed for the work 

We integrate it in the right environment 

4) Commissioning and testing 

We commission and start up a site 

We realize the tests 

We optimize the process 

 

 

Page 6 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

5) Staff training 

We train our clients’ staff for operating and maintaining a site 

We offer advanced training on automation 

6) Maintenance 

We assure a preventive maintenance 

We intervene on sites on demand 

We supply you with spare parts 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 7 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

VI. PROJECTS  IMPLEMENTED  IN  PALESTINE 

1) BOOSTER  STATION  AUTOMATION  /  4  STATIONS  –  2016  

 

 

 

 

SAQQA & KHOUDARY Co. Ltd. has chosen PCS to supply, program and commission the automation part for 4 

booster stations situated in Gaza for Attarah, Nuseirat, Berkah and Ma’an sites. The scope of work includes: 

‐ PLC and HMI and networking 

‐ VFDs for the boosters pumps 

 

Figure 1 Layout of the proposed Automation system 

The solution is based on Simatic S7‐1500 CPU and ET200SP for hot‐swapping and higher availability of the system. 

HMI Comfort panels are distributed on site to allow operator monitoring and control of the system. 

We have also provided the state‐of‐the‐art programming SIEMENS laptops (M5 Field PGs); rugged laptop with 

pre‐installed software to allow easy and fast modification on the system which is completely based on TIA Portal. 

As for the VFDs they are connected via the SCALANCE industrial switch to the control system. 

 

 

Page 8 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

The proposed programming of HMI and PLC features object‐oriented program to allow the easy creation and 

modification  of  faceplates  and  processes,  below  is  an  example  of  a  view  used  in  this  project. 

 

Figure 2 Main Reservoir View 

 

Figure 3 Analog Senor Faceplate 

 

 

Page 9 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Figure 4 Booster pumps view 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 10 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

2) ARZ  ICE‐CREAM  FACTORY  PRODUCTION  LINE  –  2016  

ARZ Ice‐Cream have continued their factory upgrading and development but now with an old production line 

which had to be retrofitted with new Motion Control system; as the old was obsolete and very hard to maintain 

and debug in case of an emergency.  

PCS have offered Motion Control Solution based on SIMOTION D and Sinamics modules along with Simotics 

motors.  In addition to ET200SP as  I/Os and Comfort HMI, PCS was able to  implement the retro‐fitting of the 

machine with limitless possibilities to adjust any parameter required to be able to obtain flexibility and precision 

in production. 

The project have been executed on part of  the machine while having  the other part  in production to obtain 

minimum downtime during the peak season.  

The scope of work included electrical cabinet design and assembly, system and functional analysis, programming, 

commissioning and testing.  

With the new installed system, ARZ can now focus more on ice cream production and its quality. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 11 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

3) ARZ  ICE‐CREAM  FACTORY  MIXING  PROCESS  ‐ 2016  

ARZ  Ice‐Cream have constructed a new  state‐of‐the‐art  factory  in Nablus/Palestine where  they manufacture 

broad array of  ice‐cream products ranging from  ice  lollies to cones and even big  family size boxes. PCS have 

equipped the factory with automated system for preparation of all ice‐cream types using SIEMENS technology 

from Industry Automation. 

 The installation of the new system and user interface not only simplifies smooth operation but it also permits 

new and complex mixtures to be prepared easily and with precision to assure a constant excellence in quality of 

the Ice‐Cream.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 12 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 13 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

4) WATER  SUPPLY  AND  SEWAGE  FACILITIES   IMPROVEMENT  FOR  BETHLEHEM  ‐ BEIT  JALA  &  

BEIT  SAHOUR  AREA–  2016  

PCS was awarded "Water Supply and Sewage Facilities  Improvement for Bethlehem  ‐ Beit Jala & Beit Sahour 

Area"  area;  the  project  is  financed  by  AFD  (Agence  Française  de  Développement)  and  NRO  (Netherlands 

Representative Office). The main contractor is Madanat Contracting Co.  

The project consists construction of new reservoirs and network lines, and also rehabilitation of old reservoir and 

pump stations. PCS will be in charge of the whole Automation and SCADA connectivity system. 

 

Figure 5 Mutelleh Reservoir in Bethlehem 

 

 

 

 

 

 

 

 

Page 14 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

5) PASSAVANT  ENERGY  &  ENVIRONMENT  ‐  NABLUS  WEST  WWTP–  2015  

Due to unexpected failure of the SCADA system, PCS  intervened to redeploy the SCADA system  in the Nablus 

West WWTP. All software including but not limited to SIMATIC TIA PORTAL Step7 and WinCC have been installed. 

Data  logging,  trending  and  reporting was  carried  out  via  Acron  Software. Morever,  because Waste Water 

Treatment Plant SCADA system availability is crucial for every plant; PCS have deployed redundant solution on 

the server via RAID 1 configuration and scheduled automatic backup of plant data. 

 

Figure 6 SCADA control room Nablus West WWTP, Server and client workstations 

 

 

 

 

 

 

 

 

 

Page 15 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

Figure 7 RTU cabinet with Flowmeter 

transmitter 

 

6) JERICHO  MUNICIPALITY  –  2015  (WATER  FLOW  MONITORING)  

 

 

 

 

 

Jericho municipality had  several  issues with  their old ultrasonic clamp‐on  flowmeter measuring  system, as a 

result, they couldn’t control their water resources. To solve this problem, PCS have installed SIEMENS Electro‐

magnetic flowmeter with an accuracy of 0.2% to meet the application requirement.  

Furthermore, our team have connected the flowmeter via the GSM/GPRS network to make the data available 

not only in Center Control Room, but also via mobile phone for site operators. 

 

     

Figure 8 Electromagnetic 16" Flowmeter 

      

 

 

 

Page 16 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

7) SAKKA  &  KHOUDARY  –  2014  (WATER  SUPPLY  MONITORING)  

 

 

 

 

 

 

 

 

PCS was awarded 2 projects in the Hebron area; the project is financed by USAID and the main contractor SAQQA 

& KHOUDARY Co. Ltd. awarded the automation and SCADA part to PCS. 

 

Works are to be executed  in Al‐Safi reservoir, Ras al Taweel pipeline and Hebron waste‐water access road,  it 

consists of installing flowmeters, pressure transmitters and differential pressure switches to be able to monitor 

reservoirs water flow and status but also underground buried vaults with no electrical power supply. 

 

PCS was able to answer to all project 

requriements with ease due  to our 

strong  partnership  with  SIEMENS 

and  we  offered MAG8000  battery 

powered  flowmeters  with 

GSM/GPRS  connectivity  to  be  able 

to transmit vital data to the SCADA 

Main  Control  Room  located  in 

Ramallah  Water  Department  of 

West Bank. 

 

The added is integrated in the Main 

SCADA Control in order to be able to 

get valuable data from the installed 

field instrumentation. Next stages of 

this project  is to be able to achieve 

not only monitoring but also control 

of pumping stations and reservoirs. 

 Figure 9 Al Safi reservoir 

 

 

Page 17 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Figure 10 Bani Naim underground chamber with Electromagnetic Flowmeters equiped with GSM/GPRS transmitting capabilities 

 

8) NEDCO  –  2014  (ELECTRICAL  SUB‐STATIONS  SCADA  COMMUNICATION)  

 

 

 

 

 

PCS was  in charge of supplying SIEMENS SCADA hardware and software and providing SCADA support for 

NEDCO. These equipment will help the company to start planning and executing the SCADA network for all the 

station the company has in Palestine.  

 

We did not stop there, a 2 day training was also arranged free of charge for NEDCO at SIEMENS offices in 

order to be able to go further and discuss some critical questions for NEDCO’s network and Telecontrol solution. 

  

NEDCO is a newly established utility services company is specializing in the electricity distribution sector in the 

northern area of Palestine, and PCS feels honored to be able to help to  improve the electricity quality  in our 

country. 

 

 

 

 

 

Page 18 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

9) PROMEC  –  2014  (AUTOMATED  FOUNTAIN)  

 

 

 

 

PCS was  in  charge  of  debugging    a  light‐music  fountain  that  is  equipped with Delta  PLC.  This  fountain 

contained  colored  LED  lights,  solenoid  valves  and  control  equipment which  allows  the  fountain  to  play  in 

synchronized way with the music. 

 

 

 

 

 

 

 

 

 

 

 

 

 

10) ARZ  ICE‐CREAM  NEW  FACTORY  –  2013  (FACTORY  AUTOMATION  DESIGN)  

 

PCS was in charge along with LIGHT EMCO Ltd. of design of a new state‐of‐the‐art factory for ARZ Ice‐Cream. 

The design includes the following: 

SCADA system and PLCs (SIEMENS) 

Electrical distribution (around 5000 Amps) 

Multi‐site Management system that brings together: 

o Access Control 

o Intrusion Alarm 

o Fire Alarm 

o CCTV  

o Elevator Control 

o Parking gates 

o BMS 

 

 

 

 

 

 

Page 19 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

11) AMONG  OTHER  CLIENTS:  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 20 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

VII. SCADA  INTERNATIONAL EXPERIENCE  

 

1) GEA  –  ARC  

 

 

 

 

‐A project of 216 Input/Output and of value:  200 000 Euros. 

ARC International factory (France), entrusted GEA Process Engineering (Bischoff) a turnkey project for automatic 

system for the smoke treatment of a glass production facility in its factory, this smoke treatment was carried out 

for 2 ovens (Oven H and L). The work included the installation of electrical equipment and the implementation 

of an automated process. Technord (where I worked in France) was the subcontractor of GEA for this project. 

A reagent is injected into the gas stream to dilute corrosive dust particles and mix it with material that will allow 

the gas to be easily transported. This will also allow us to absorb the acid gas components (SOx, HCl, HF). The 

reagent reacts with the SOx hence allowing  it to be effortlessly collected as dust within the ESP (electrostatic 

filter) and then evacuated from the system by a conveyor system. 

The facility includes the following equipment: 

• A gas circuit comprising ducts, exhaust fan (drive). 

• An electrostatic filter (Electro‐ION BLAST 1). 

• A dust removal system that consists of a conveyor and a screw valve. 

• A Big‐Bag System. 

• A lime Ca(OH)2  Silo injection and storage station. 

 

 

Page 21 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Figure 11: A global gas treatment view 

Our work consisted of the following 

Functional analysis 

PLC programming 

SCADA Supervision programming 

Designing and verification of electrical diagrams 

Tests 

Commissioning 

 

 

 

Page 22 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

The  PLC programming was  the  longest part of  this project.  The  PLC program  should  completely match  the 

previously designed functional analysis. The work was done on SIEMENS – Step7 programming software.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The architecture of the project consisted of 1 new PLC that is connected to an old existing PLC for furnace control 

room. The new PLC is connected to a deported Input Output unit and also to a VFD SINAMIC G150. The main PLC 

is then connected to a SCADA supervisory computer with an optional workstation for monitoring and control. 

Figure 12: SCADA and VFD architecture 

 

 

Page 23 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Figure 13: Existing Networks 

In this installation there exists 2 networks, the first one is Profinet through Ethernet In order to connect the PLC 

with the SCADA software, and the other one is Profibus for connecting the deported module and the VFD with 

the PLC.

 

 

 

Page 24 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Figure 14: The electro‐static filter 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 25 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

2) BALTHAZARD  &  COTTE  

 

‐A project of value:  80 000 Euros. 

Balthazard & Cotte  is  a  company of  Lhoist  group, world  leader  in  lime production. We have developed  an 

automated  system  for  logistics  and  weighing management  of  trucks  through  an  interactive  terminal.  This 

terminal allows the drivers to identify themselves when entering a site and the weighting scale saves the weight 

of the truck. 

The truck goes into the site and fills the truck with the finished product. Before exiting the site, the truck goes 

into another weighing station where his weight difference is taken and a bill of delivery is printed automatically. 

This system  interfaces with the ERP system (SAP  in this case), to allow a complete automation of the process 

including financial transactions. This technology was installed in all site of Balthazard &  Cotte. 

 

 

 

Page 26 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

Figure 15: View of the site 

The system that was installed by us is the following: 

 

  Ethernet standard RJ45 

  Series connection RS485  

M12, 5 cables, that returns an input signal of 4…20 mA 

 

 

 

 

 

 

 

 

 

Page 27 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

3) NOVASEP  

 

 

 

‐A project of 720 Input/Output and of value:  110 000 Euros only for programming. 

This project is about a CIP (Clean In Place) automated system which includes reservoirs, pumps, pipes, and control 

equipment  in  order  to  prepare  a  specific  step  by  step  cleaning  procedure  of  the  factory.  This  Project was 

implemented for a Chinese factory through Novasep. 

This project have used an existing standards for the PLC programming, it was done through Step7 SIEMENS PLC 

programming software. However, the for the SCADA supervision we have implemented Wonderware solution; 

ArchestrA System Platform (ASP). 

 

Figure 16: An example of supervision screen 

 

 

Page 28 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Moreover, we have participated  in the design of the electrical diagrams for (motors, valves,  I/O card of PLCs, 

pneumatic modules, sensors and instrumentations…etc). 

 

Figure 17: Electrical diagram 

 

 

 

 

 

 

 

 

Page 29 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

4) ARKOPHARMA  

 

 

 

‐A project of value:  303 000 Euros. 

This project was focused on improving the pharmaceutical industry by tracking all the weighing processes; this 

can also be called MES (Manufacturing Execution System) and it is connected to the ERP (Enterprise Resource 

Planning)  in order to have the clearest possible view on the enterprise and  its manufacturing part. The work 

consisted of analyzing a proper pharmaceutical industrial project and to create which elements in it has to be 

tracked and saved in a historical database in order to retrieve this information when needed. After that, we have 

created a model of the tracking program and integrated a Gantt chart so that it would organize all the weighting 

orders optimally. 

 

 

Page 30 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

 

Figure 18: General view showing the state of all the weighing stations 

 

Figure 19: Calibrating of a scale 

 

 

Page 31 of 31 

Palestine, Nablus, Yaser Arafat Street, Fattouh Building – GF 

Tel/Fax: +970 9 23‐494‐22 Mob: +970 599 25‐24‐49 

E‐mail:   [email protected] Website: www.pcs.com.ps  

The project was implemented through Wonderware ASP (ArchestrA System Platform).

 

Figure 20: The status of all scales