earned value management
DESCRIPTION
Earned Value Management. How do we get started?. What is it?. A planning process An internal policy A contract requirement A way to measure performance A way to identify problems A forecasting tool A way of doing business. What is it?. - PowerPoint PPT PresentationTRANSCRIPT
Earned Value Management
How do we get started?
What is it?
• A planning process
• An internal policy
• A contract requirement
• A way to measure performance
• A way to identify problems
• A forecasting tool
• A way of doing business
What is it?
A way to integrate scope, schedule, and resources all at once!
How is it used?
• A reporting tool– Satisfy the contract reporting requirements– “filling the square”
• As a decision-making tool– To evaluate project planning– To communicate status– To forecast resource needs
Language of EVM
• Budgeted Cost of Work Scheduled (BCWS)– The plan to spend budget
• Actual Cost of Work Performed (ACWP)– The costs of the work that has occurred
• Budgeted Cost of Work Performed (BCWP)– What was performed (what it should have cost)– This is EARNED VALUE
Language of EVM
• Schedule Variance SV = BCWP – BCWS– On/Off plan in dollars (>0 is ahead, 0 is on target, <0 is behind)
• Schedule Performance Index SPI = BCWP/BCWS– On/off plan as a ratio (>1 is ahead, 1 is on target, <1 is behind)
• Cost Variance CV = BCWP – ACWP– Over/under running (>0 is underrun, 0 is on target, <0 is overrun)
• Cost Performance Index CPI = BCWP/ACWP– Return on actual costs (>1 is under, 1 is on target, <1 is over)
Language of EVM
• Budget Authority for unknowns– Management Reserve
• Budget at Complete, BAC– The budget to do the work
• Estimate to Complete, ETC– Estimate of the cost to do the remaining work
• Estimate at Complete– Best guess of cost of entire cost of project
• Latest Revised Estimate– Contractor’s best guess of cost of entire cost of project
In a Picture
Management Reserve
Cost VarianceSchedule Variance
ACWP
BCWP
BCWS
$
EAC
TimeNow
Completion Date
PMB
BAC
time
How do we do this?
• Performance Measurement Baseline– Scope
• Identify the scope of work• WBS• Extend to Work package level
How do we do this?
• Performance Measurement Baseline– Schedule
• Arrange work packages in order• Schedule start and finish• Classify work and choose EV technique
How do we do this?
• Performance Measurement Baseline– Budget
• Identify needed resources (budget)• Spread budget• Calculate Cumulative BCWS
How do we do this?
• Performance measurement baseline
Graph Cumulative BCWS
Example
Task Cost Start End
WP1 9 1 3
WP2 12 3 7
WP3 28 3 4
WP5 8 6 9
WP5 10 1 10
Example
1 42 53 76 98 10
WP3
WP2
WP5
WP4
WP1
Monthly BCWS
Cumulative BCWS
Next time
• New cost spreading techniques– 0/100%– 50/50%– % complete– Balanced Level of Effort– Directed Milestone
Organizational Chart
President & CEOVickery
President & CEOVickery
VP Construction
VP Construction
Senior VPOperationsSenior VPOperations
VPDesign
VPDesign
VPFinance
VPFinance
VP Espionage
VP Espionage
VPEngineering
VPEngineering
VPMaterials
VPMaterials
Vickery’s Egg Delivery Company
Organizational Chart
• Organizational chart glossary– What kind of organization do you have?– What is your decision-making paradigm?
• How do you resolve conflict?
– Who has what responsibilities?• What do they do?• Who do they report to?• What do they cost?
– How will you track it?
Organizational Chart
Rest of Class is part one of your project
• Organizational Chart– Corporation Name– Team Members– Positions– Responsibilities– Charge Track