earned value method

69
Earned Value

Upload: nasser-asain

Post on 25-Nov-2015

41 views

Category:

Documents


2 download

DESCRIPTION

Earn Value Computation

TRANSCRIPT

  • Earned Value

  • Elements of Project Control

    Creation of a Baseline Schedule

    Measurement of Performance

    Effective Corrective Actions

  • Schedule Updating

    1. Schedule durations and sequences often vary from actual durations and sequences

    Subcontractors might use different methods

    Force Majeure events delay the project

    Etc

    2. Participants would like to know how the project is progressing

    Owners When can I move in? How much should I pay this month? What milestones have been met?

    Designers When do I release drawings

    Subcontractors when do I come on to the site?

  • Usefulness of frequent schedule

    updating

    Current state of the project is always known

    Updates provide a valuable record of project status at a given time

    Can document changes, responsibilities and delays throughout the project

    Useful during claims proceedings

    Schedule is a document that can be followed

  • More on updates

    Schedules should be updated periodically

    Especially if a major event such as a logic change occurs

    Updates should show

    New start and completion dates

    Completed activities

    Percentage progress on activities

  • Percentage Complete

  • Planned Vs. Actual

  • Updating a Precedence Diagram

    0 0

    Start

    0 0 0

    0 4

    F (3)4

    3 3 7

    0 3

    A 3

    0 0 3

    3 9

    B (4)6

    3 0 9

    6 8

    D 2

    7 1 9

    3 6

    E 3

    4 1 7

    9 9

    Finish

    9 0 9

    6 8

    C 2

    7 1 9

  • Earned Value

    We have spent 60% of the time for an activity but have completed 40% of the

    work. We are on schedule since we have

    completed the most time consuming parts

    of the activity

  • Evaluating Progress on an Activity

    Units completed

    Length of pipe laid, length of trench dug

    Effort expended

    Plastering = 50%, Painting = 50% effort

    3 walls plastered, two painted out of 4 walls

    Percentage complete = (3x0.5+2x0.5)/4 = 62.5%

    Expert opinion

    Amount spent

    Time taken (?)

  • Project Monitoring

  • Project Monitoring

    Planning and scheduling play an important role in project management

    But without monitoring the project, chances of completing the project on schedule is difficult

    Two parameters are monitored

    Cost

    Time

    The following graph shows the Time-cost relationship for a project

  • Project Monitoring

    This graph shows Project Progress

    Co

    st

    Time

    Cost over-run with schedule

    Time over-run

    Ideal

    Curve

  • Project Monitoring

    Cost is not proportional to the time/man-hours spent on each activity

    Eg:- Installation of a projector in a classroom Cost of the projector is very high

    Man-hours spent on installation are not significant

    Neither expenditure nor man-hours spent can be used to measure the project progress

    Expenditure and man-hours are inputs

    Progress in terms of input does not indicate progress in terms of output

  • Project Monitoring

    Quantities installed can give information regarding project progress, but is limited to very few activities and

    cannot be applied to the entire project as it involves

    various activities

    Thus with the help of above mentioned parameters, it is difficult to measure the project progress.

    Hence the use of EARNED VALUE of time or cost

  • Concepts of Earned Value

  • Concept of Earned Value

    Consider the following example:

    Wall construction Wall is divided into 4 sections

    For 4-sections - 100 man-hours are required

    Hence if 2-sections are completed,

    (2/4) 100

    = 50 man-hours

    We say that 50 man-hours have been EARNED

    The actual man-hours spent to construct these two sections can be more than or less than the Earned

    Value of man-hours

  • Concept of Earned Value

    Wall construction

    If 4 sections cost Rs. 1000/-

    then the cost of constructing 2 sections = Rs. 500/-

    We say that Rs. 500/- is the EARNED value of money

    The actual cost incurred in constructing these two sections can

    be more than or less than the Earned Value of money

    It is important to note that Earned Value is based on the Actual

    quantities installed or Actual quantity of work done

    Hence output is considered in the Earned Value concept

  • Concept of Earned Value

    Calculation of Earned Value

    Earned Value of man-hours or money for an activity can be calculated as follows:

  • Example 1

  • Example 1

    Determination of planned % complete:

    Consider the following example

    Draw % complete with respect to man-hours and money.

    Activity A

    Activity B

    300

    5000

    700 (man-hours)

    5000 (money)

    500

    10000

    800 (man-hours)

    70000 (money)

  • Example 1

    Determination of planned % complete based on man-hours.

    Activity A

    Activity B

    300

    5000

    700 (man-hours)

    5000 (money)

    500

    10000

    800 (man-hours)

    7000 (money)

    Daily Cumulative

    Total Cumulative

    % Complete

    300 1200 800

    300 1500 2300

    300 1200 300 2300 2300 2300

    = 1.0 = 0.65 = 0.13

  • Example 1

    Determination of planned % complete based on money.

    Activity A

    Activity B

    300

    5000

    700 (man-hours)

    5000 (money)

    500

    10000

    800 (man-hours)

    27000 (money)

    Daily Cumulative

    Total Cumulative

    % Complete

    5000 15000 7000

    5000 20000 27000

    = 1.0 = 0.741 = 0.185

    5000 20000 90000 27000 27000 27000

  • Example 1 P

    erc

    en

    tag

    e

    Stages

  • Example 1

    BCWS Man-hours

    Stages 1 2 3 Total

    Activity A 300 700 0 1000

    Activity B 0 500 800 1300 2300

    Stage Total 300 1200 800

    Cumulative Total 300 1500 2300

    Project % Complete 0.13 0.65 1.0

  • Example 1

    BCWS Money

    Stages 1 2 3 Total

    Activity A 5000 5000 0 10000

    Activity B 0 10000 7000 17000 27000

    Stage Total 5000 15000 7000

    Cumulative Total 5000 20000 27000

    Project % Complete 0.185 0.741 1.0

  • Determination of Earned Value of Man-hour.

    Consider the previous problem (man-hours)

    Example 1

    500 800

    700 300 Activity A

    Activity B

    % Complete

    0.25 0.95 1.0

    0.6 0.95

    Activity A

    Activity B

    scheduled

  • Example 1

    Determination of Earned Value of Man-hour.

    Stage 1: EMh (A)

    EMh (B)

    Total Man-hours = 2300

    % complete of project: % complete = 250 / 2300

    % complete = 0.11

  • Example 1

    Determination of Earned Value of Man-hour.

    Stage 2: EMh (A)

    EMh (B)

    Total Man-hours = 2300

    % complete of project: % complete = 1730 / 2300

    % complete = 0.752

  • Example 1

    Determination of Earned Value of Man-hour.

    Stage 3: EMh (A)

    EMh (B)

    Total Man-hours = 2300

    % complete of project: % complete = 2235 / 2300

    % complete = 0.97

  • Determination of Earned Value of Man-hour:

    Earned Value (man-hours)

    500 800

    700 300 Activity A

    Activity B

    % Complete

    0.25 0.95 1.0

    0.6 0.95

    Activity A

    Activity B

    scheduled

    250 700 50 Man-hours

    780 455 Man-hours

    0.108 0.752 0.971 Project - % Complete

    Example 1

  • Example 1

    Determination of Earned Value of Man-hour.

    BCWP

    Stages 1 2 3

    % complete

    Activity A

    Activity B

    0.25

    0

    0.95

    0.6

    1.0

    0.95

    Earned Value (man-hours)

    Activity A

    Activity B

    Stage total

    250

    0

    250

    700

    780

    1480

    50

    455

    505

    Activity A (cum)

    Activity B (cum)

    250

    0

    950

    780

    1000

    1235

    Total cumulative 250 1730 2235

    Project % complete 0.109 0.752 0.972

  • Example 1

    Determination of Earned Value of Man-hour: ACTUAL MAN-HOURS

    Actual (man-hours)

    500 800

    700 300 Activity A

    Activity B scheduled

    400 500 100 Man-hours

    450 1000 Man-hours

  • Example 1

    Determination of Earned Value of Man-hour:

    ACWP

    Stages 1 2 3

    Activity A

    Activity B

    400

    0

    500

    450

    100

    1000

    Stage Total 400 950 1100

    Cumulative Total 400 1350 2450

  • Example 1

    Determination of Earned Value of Man-hour:

    Stage 1 Stage 2 Stage 3

    BCWS SCHEDULED MAN-HOUR (Cumulative) 300 1500 2300

    BCWP EARNED MAN-HOUR (Cumulative) 250 1730 2235

    ACWP ACTUAL MAN-HOUR (Cumulative) 400 1350 2450

    SV BCWP-BCWS -50 230 -65

    CV BCWP-ACWP -150 380 -215

    SPI BCWP/BCWS 0.83 1.15 0.97

    CPI BCWP/ACWP 0.63 1.28 0.9122

  • Example 1

    Determination of Earned Value of Man-hour: Earned Value

    Ma

    n-h

    ou

    r

    Stages

  • Example 1

    Determination of Earned Value of Money

    Consider the previous problem (money)

    10000 7000

    5000 5000 Activity A

    Activity B

    % Complete

    0.25 0.95 1.0

    0.6 0.95

    Activity A

    Activity B

    scheduled

  • Determination of Earned Value of Money.

    Stage 1: EMh (A)

    EMh (B)

    Total Man-hours = 27000

    Example 1

    % complete of project: % complete = 2500 / 27000

    % complete = 0.093

  • Example 1

    Determination of Earned Value of Money.

    Stage 2: EMh (A)

    EMh (B)

    Total Man-hours = 27000

    % complete of project: % complete = 19700 / 27000

    % complete = 0.730

  • Example 1

    Determination of Earned Value of Money.

    Stage 3: EMh (A)

    EMh (B)

    Total Man-hours = 27000

    % complete of project: % complete = 26150 / 27000

    % complete = 0.969

  • Example 1

    Determination of Earned Value of Money.

    Earned Value (money)

    10000 7000

    5000 5000 Activity A

    Activity B

    % Complete

    0.25 0.95 1.0

    0.6 0.95

    Activity A

    Activity B

    scheduled

    2500 7000 500 Money

    10200 5950 Money

    0.093 0.730 0.969 Project - % Complete

  • Example 1

    Determination of Earned Value of Money.

    BCWP

    Stages 1 2 3

    % complete

    Activity A

    Activity B

    0.25

    0

    0.95

    0.6

    1.0

    0.95

    Earned Value (money)

    Activity A

    Activity B

    Stage total

    2500

    0

    2500

    7000

    10200

    17200

    500

    5950

    6450

    Activity A (cum)

    Activity B (cum)

    2500

    0

    9500

    10200

    10000

    16150

    Total cumulative 2500 19700 26150

    Project % complete 0.093 0.730 0.969

  • Example 1

    Determination of Earned Value of Money. ACTUAL MONEY

    Actual (money)

    10000 7000

    5000 5000 Activity A

    Activity B scheduled

    4500 6000 5000 Money

    8500 7500 Money

  • Example 1

    Determination of Earned Value of Money.

    ACWP

    Stages 1 2 3

    Activity A

    Activity B

    4500

    0

    6000

    8500

    5000

    7500

    Stage Total 4500 14500 12500

    Cumulative Total 4500 19000 31500

  • Example 1

    Determination of Earned Value of Money.

    Stage 1 Stage 2 Stage 3

    BCWS SCHEDULED MONEY (Cumulative) 5000 20000 27000

    BCWP EARNED MONEY (Cumulative) 2500 19700 26150

    ACWP ACTUAL MONEY (Cumulative) 4500 19000 31500

    SV BCWP-BCWS -2500 -300 -850

    CV BCWP-ACWP -2500 700 -5350

    SPI BCWP/BCWS 0.5 0.99 0.97

    CPI BCWP/ACWP 0.56 1.04 0.83

  • Example 1

    Determination of Earned Value of Money. Earned Value

    Mo

    ne

    y

    Stages

  • Example 2

  • Example 2

    Determination of planned % complete:

    Draw % complete with respect to Man-hours and Money.

    MAN-HOURS

    20 20 20 20 20

    12.5 12.5 12.5 12.5

    10 10

    MONEY

    8000 8000 8000 8000 8000

    10000 10000 10000 10000

    75000 75000

    Sch. Qty. Sch. Mhrs

    Flooring 400 100

    Electrical 100 50

    AV systems 20 20

    Sch. Money

    40000

    40000

    150000

  • Example 2

    Determination of planned % complete based on Man-hours:

    Sch. Mhrs.

    Flooring 100

    Electrical 50

    AV systems 20

    170

    20 20 20 20 20

    12.5 12.5 12.5 12.5

    10 10

    20 20 32.5 32.5 32.5 32.5 10 10

    20 40 72.5 105 137.5 150 160 170

    20

    170

    40

    170

    72.5

    170

    105

    170

    137.5

    170

    150

    170

    160

    170

    170

    170

    0.118 0.235 0.426 0.618 0.809 0.882 0.941 1.0

    Total Mhrs.

    Cuml. Mhrs.

    % complete

    Stage 1 Stage 2 Stage 3 Stage 4

  • Example 2

    Determination of planned % complete based on money:

    Sch. Money

    Flooring 40000

    Electrical 40000

    AV systems 150000

    230000

    8000 8000 8000 8000 8000

    10000 10000 10000 10000

    75000 75000

    8000 8000 18000 18000 18000 10000 75000 75000

    8000 16000 34000 52000 70000 80000 155000 230000

    8000

    230000

    16000

    230000

    34000

    230000

    52000

    230000

    70000

    230000

    80000

    230000

    155000

    230000

    230000

    230000

    0.034 0.069 0.147 0.226 0.304 0.347 0.673 1.0

    Total Money

    Cuml. Money

    % complete

    Stage 1 Stage 2 Stage 3 Stage 4

  • Example 2

    Scheduled-percentage complete

    Pe

    rce

    nta

    ge

    Days

  • Example 2

    Determination of Earned Value of Man-hour UPDATE 1

    Quantity Installed

    50 70

    12.5 17.5 0 0 0 0 0 0

    12.5 30 30 30 30 30 30 30

    0.074 0.176 0.176 0.176 0.176 0.176 0.176 0.176

    Sch. Mhrs Inst. Qty.

    Flooring 100 120

    Electrical 50

    AV Systems 20

    170

    Actual Man-hours

    20 20

    20 20 0 0 0 0 0 0

    20 40 40 40 40 40 40 40

    Earned Mhrs.

    Cuml. Earned Mhrs.

    % complete

    Total Mhrs.

    Cuml. Mhrs.

  • Update 1

    Example 2 M

    an

    -ho

    urs

    Stages

  • Example 2

    Determination of Earned Value of Man-hour UPDATE 2

    Quantity Installed

    50 70 80 80

    25 30

    12.5 17.5 32.5 35 0 0 0 0

    12.5 30 62.5 97.5 97.5 97.5 97.5 97.5

    0.074 0.176 0.368 0.574 0.574 0.574 0.574 0.574

    Sch. Qty. Sch. Mhrs Inst. Qty.

    Flooring 400 100 280

    Electrical 100 50 55

    AV Systems 20 20

    170

    Actual Man-hours

    20 20 30 30

    15 15

    20 20 45 45 0 0 0 0

    20 40 85 130 130 130 130 130

    Earned Mhrs.

    Cuml. Earned Mhrs.

    % complete

    Total Mhrs.

    Cuml. Mhrs.

  • Example 2

    Update 2

    Ma

    n-h

    ou

    rs

    Days

  • Example 2

    Determination of Earned Value of Man-hour UPDATE 3

    Quantity Installed

    50 70 80 80 90 30

    25 30 35 10

    12.5 17.5 32.5 35 0 0 0 0

    12.5 30 62.5 97.5 137.5 150 150 150

    0.074 0.176 0.368 0.574 0.809 0.882 0.882 0.882

    Sch. Qty. Sch. Mhrs Inst. Qty.

    Flooring 400 100 400

    Electrical 100 50 100

    AV Systems 20 20 0

    170

    Actual Man-hours

    20 20 30 30 30 15

    15 15 15 15

    20 20 45 45 45 30 0 0

    20 40 85 130 175 205 205 205

    Earned Mhrs.

    Cuml. Earned Mhrs.

    % complete

    Total Mhrs.

    Cuml. Mhrs.

  • Example 2

    Update 3

    Ma

    n-h

    ou

    rs

    Days

  • Components of Earned Value

  • Components of Earned value Analysis

    Budgeted Cost of Work Scheduled (BCWS)

    It is the budgeted cost of work scheduled to be performed

    It is also called the Planned Value (PV)

    It tells how much work have been completed

  • Components of Earned value Analysis

    Budgeted Cost of Work Performed (BCWP)

    It is the budgeted cost of work actually performed

    The Earned Value for the work actually completed

    It tells how much work is actually completed

  • Components of Earned value Analysis

    Actual Cost of Work Performed (ACWP)

    It is the amount actually spent on the work completed

    This could be more or less than the Earned Value

  • Components of Earned value Analysis

    Scheduled Variance (SC)

    It compares work completed vs work planned

    It helps to identify whether the project is ahead or behind schedule

    Negative value indicated that the project is behind schedule

  • Components of Earned value Analysis

    Scheduled Performance Index (SPI)

    It helps to identify whether the project is ahead or behind schedule

    Less than 1 indicates that the project is behind schedule

    It can be used to forecast how long it will take for the project to complete

  • Components of Earned value Analysis

    Cost Varience (CV)

    It compares what was planned to be spent on the work completed vs. what was actually spent

    It helps to identify whether the project is ahead or behind schedule

    Negative value indicates that the project is over budget

  • Components of Earned value Analysis

    Cost Performance Index (CPI)

    It helps to identify weather the project is above or below budget

    Less than 1 means the project is over budget

    It can be utilised to forecast how much amount will be required to complete the project

  • Components of Earned value Analysis

    Budget at Completion (BAC)

    It is the amount that was originally budgeted to complete the project

  • Components of Earned value Analysis

    Estimate at Completion (EAC)

    It is the estimated amount required to complete the project

  • Components of Earned value Analysis

    http://www.iceincusa.com/16CSP/content/4_ev/gifs/image1.gif (17.01.2007)