earned value scheduling with evengine 6.6
DESCRIPTION
Earned Value Scheduling with EVengine 6.6. Mark E. Read Principal Sequence Advisors, Inc. Objectives. Earned Value Scheduling Background Key Terms What is Earned Value Scheduling? What is EVengine ? Demonstration Ask questions. Sequence Advisors, Inc. Founded in 2003 - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/1.jpg)
Earned Value Schedulingwith EVengine 6.6Mark E. ReadPrincipalSequence Advisors, Inc.
![Page 2: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/2.jpg)
ObjectivesEarned Value Scheduling BackgroundKey TermsWhat is Earned Value Scheduling?What is EVengine?DemonstrationAsk questions
![Page 3: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/3.jpg)
Sequence Advisors, Inc.Founded in 2003Bringing database best practices to Project Management on the Microsoft platformReporting, Development, Integration ServicesTraining, Training, TrainingContact: Mark Read 510 406-4645 [email protected]
![Page 4: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/4.jpg)
EV(t) BackgroundMilitary generally only interested in costDoesn’t matter how much…They want the plane to fly.IT and Pharma, however, are VERY interested in schedulingWalter Lipke developed while working for the US military in OKUse of earned value data to predict the schedule dates… early or late
![Page 5: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/5.jpg)
PMI Practice Standard for EV Management
Is currently being revised. Major revisions will likely include Earned SchedulingWalter Lipke credits Kim Henderson…One of the co-chairman of EV Management Forum is… Kim HendersonEVengine is the only commercial product.
![Page 6: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/6.jpg)
Preparing to use Project for EVMWork Breakdown Structure
Optional Cost Account or OBS codesUnique ResourcesCost DataBaseline DataUpdated Schedule
![Page 7: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/7.jpg)
What is Earned Value Scheduling?
“Earned Schedule (ES) is a breakthrough analytical technique that resolves the EVM dilemma. It is derived from and is an extension to EVM. No additional data is needed for acquiring the ES measures; only the data from EVM is needed. In contrast to the cost-based indicators from EVM, the ES schedule performance indicators are time-based, making them easier to comprehend. The ES indicators provide a status and predictive ability for schedule, analogous to the facility for cost using EVM. “
![Page 8: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/8.jpg)
EVM Terms
![Page 9: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/9.jpg)
Typical Earned Value Metrics
![Page 10: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/10.jpg)
Earned Value Schedule answers:
![Page 11: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/11.jpg)
What is EVengine?Scheduling and other data from Project, extracted into Excel, combined with tools to generate a full suite of Earned Value Analysis
![Page 12: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/12.jpg)
Workflow ImplicationsDo you need or want separation of duties?Work in Project, Extract to ExcelPut rates only in Excel for confidentiality purposesUse terms to more accurately model cashflow
![Page 13: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/13.jpg)
Earned Value Data FieldsOBS – Organizational Breakdown Structure, defines organization to the applicationCA – Control Account: Defines the accounting structure to the applicationSP – Selling Price: Defines the selling price to generate profitabityTerms – Define Payment terms to better model cashflowMUST HAVE UNIQUE RESOURCES
![Page 14: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/14.jpg)
Interpreting Results
![Page 15: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/15.jpg)
Table and ChartsAdd-in to Excel with menus for configurationAll the power of ExcelCan use chart types to add the table.
![Page 16: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/16.jpg)
I am truly excited by Supertech’s release of their newest project control software, EVENGINE 6.6. This new product has incorporated the capability provided by the Earned Schedule extension to EVM. The addition, in my opinion, significantly enhances the already unique capability and utility of EVENGINE for controlling project cost and financial performance. Now with Earned Schedule, EVENGINE 6.6 provides the much needed suite of measures, indicators, and predictors for the management of schedule. This product is possibly the most complete project management control software available.
Walt LipkeCreator of Earned Schedule
For details on Earned Schedule www.earnedschedule.com
![Page 17: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/17.jpg)
Resourceswww.earnedschedule.comSupertech Project Management
James Bulmer
![Page 18: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/18.jpg)
ConclusionEarned Value Scheduling answers the should have beenEVengine is a very handy tool which leverages Excel power and makes it easierYou will be hearing more about this in the future
![Page 19: Earned Value Scheduling with EVengine 6.6](https://reader035.vdocument.in/reader035/viewer/2022062410/56816435550346895dd5fcf7/html5/thumbnails/19.jpg)
Questions? Comments?Thank you!