eastern cape department of sport recreation, arts & culture third quarterly report 2009/10
DESCRIPTION
EASTERN CAPE DEPARTMENT OF SPORT RECREATION, ARTS & CULTURE THIRD QUARTERLY REPORT 2009/10. COMMUNITY LIBRARY CONDITIONAL GRANT 19 MAY 2010. TABLE OF CONTENTS. Trends in allocations Funding and Top Slicing for 2009/2010 Projected Cash-flows and transfers 3 rd Quarter Performance - PowerPoint PPT PresentationTRANSCRIPT
EASTERN CAPEDEPARTMENT OF SPORT RECREATION,
ARTS & CULTURETHIRD QUARTERLY REPORT 2009/10
COMMUNITY LIBRARY CONDITIONAL GRANT
19 MAY 2010
2
TABLE OF CONTENTS
Trends in allocationsFunding and Top Slicing for 2009/2010Projected Cash-flows and transfers3rd Quarter PerformanceAchievementsReason for deviation and Remedial actions Monitoring capacityConstraintsConclusion
TRENDS IN ALLOCATIONS
Economic Classification 2009/10 2010/11 2011/12
Compensation of Employees
R10,505M R11,920M R12,920M
Goods and Services R27,961M R27, 444 R28,471M
Transfers and Subsidies R1M R1M R1M
Building and other fixed structures
R10,213M R32, 211 32,211
Machinery and equipment R5,836M R6, 372 R6,372M
TOTAL R55,515M R77, 240M R80, 974M
3
4
FUNDING AND TOP SLICING 2009/10
ACTIVITIES R '000
Books/Library Material 11,518
Staff/Staff Training 1,098
ICT Infrastructure (Cabling & Data-line) 4,000
New Library Management system 3,680
ICT Operating Expenditure 1,000
Upgrading of Library infrastructure 10,213
Purchase of library containers 2,100
Security for Library Books and Staff 2,000
Literacy (Programme) 1,200
Special services provided (SALIB) 1,000
Maintenance of library facilities 4,000
Stakeholders Consultative Workshop 200
Building of new facility: Mt’ Ayliff-Alfred Nzo District 3,000
Compensation of employees 10,505
Total 55,515
5
PROJECTED CASHFLOWS AND TRANSFERS
Cash flow amount Transfers
April 3,886,050 11,674
May 3,886,050
June 2,775,750
July 2,220,600 13,894
August 4,996,350
September 5,551,500
October 4,441,200 19,999
November 7,216,950
December 7,216,950
January 3,886,050 9, 948
February 4,996,350
March 4,441,200
Total 55,515
55,515
6
3rd Quarter Performance
Outputs Approved Budget
Committed Actual expenditure
Under or over expenditure
Compensation of employees 10,505,000 - 6, 821,000 3, 684,000
Provision of Library materials 11,518,000 870,865 9, 586, 526 542, 609
Upgrading of library infrastructure 10,213,000 2, 239,000 5, 714,000 2, 260,000
Provision of ICT Infrastructure 4,000,000 1,958,000 2,042,000 -
Training of library workers 1,098,000 42,000 412,000 644,000
Installation of security system 2,000,000 37,010 - 1,962,990
Library Management Information System 3,680,000 - 3,680,000 -
Literacy programme 1,200,000 10,889 158, 330.00 1,031,781
Purchase of ICT equipment 1,000,000 2,940 11,045 986,015
Special services provided 1,000,000 1,000,000 - -
Purchase of Library Containers 2,100,000 - - 2,100,000
Stakeholders Consultative Workshop 200,000 - 200,000 -
New Facilities built 3,000,000 - - 3,000,000
Maintenance of library facilities 4,000,000 134,000 1, 200,099 2,665,901
Admin. Costs 518,000 6,230 298,000 213,770
TOTAL 55,515 6,3000,934 30,123,000 19,091,066
7
ACHIEVEMENTS
A server that will link all libraries and the Provincial Office has been purchased and delivered, libraries that have been cabled will be connected to 79 Libraries in order to benefit from internet and e-mail.
All library materials have been purchased and R5,714M has been paid, the remaining is awaiting delivery.
14 Libraries have been installed with CCTV security systems: 2 libraries per district (Alfred Nzo; Amathole; Cacadu; Chris Hani; Nelson Mandela; O.R. Tambo and Ukhahlamba.
Eastern Cape has been identified to change from PALS library management system to BROCADE. An amount of R3,680m has since been paid to SITA for installation of this new system.
35 Libraries have been cabled and 20 have been installed with data-lines. The payment will be effected in January. These libraries will be able to benefit from internet and e-mail services.
Contractors are working at all sites and there will be a saving which will complement the Mdantsane Library Project which was initiated by National Department.
Tender for library tattle-tapes detection system has been advertised. The budget for the tender is R4M for twenty libraries.
The Department is in partnership with South African Library for the Blind to provide services for partially blind people. A sum of R1M has been committed to assist in this project. The following libraries are going to benefit: Cedarville (Alfred Nzo District); Stutterheim (Amathole District); Mlungisi (Chris Hani District); Graaf Reinet & Humansdorp (Cacadu District); Mthatha Reference (O.R. Tambo District) and Aliwal North (uKhahlamba District).
8
Reasons for deviation and remedial actionsREASONS FOR DEVIATIONS REMEDIAL ACTION
Building of new library in Mt ’Ayliff could not take off. There has been challenges in the capturing of infrastructure budget in the Department and this ended up not entered in the B3Treasury infrastructure document.
This amount has since been re-directed to Mdantsane Library Project. The project was initiated by National Dept. of Arts & Culture but due to compliance issues, it was transferred to our department. This project will continue in the next financial year.
There were delays in the appointment of twelve librarians due to renovations that were still taking place at the libraries where the librarians were going to be placed .
Twelve librarians have since been employed, ten has already assumed their duties in December 2009 and two will start in January 2010.
Delays in the procurement of ICT equipment were due to renovations in the libraries.
The Libraries that have been identified for ICT equipment has since been renovated and equipment will be procured in the next quarter.
The project of container libraries is still on hold because of challenges encountered in the previous financial year’s tender (2008/09). The matter is being addressed through Departmental Legal Advisers.
The budget for Container Libraries has been re-directed to the payment of library security systems. The project will be resuscitated in the next financial year.
Literacy programme delayed to kick start due to challenges in the payment of stipend to trainers.
Trainers have submitted required documentation and the project is going to continue.
The budget for maintenance of ICT library facilities has been earmarked for provision of data-lines at public libraries but there were delays in the implementation of the project by the Premier’s Office and SITA.
The project has since been implemented, data-lines have been installed in twenty libraries and payment will be effected in the fourth quarter.
There is still a lack of credible service providers for training of library workers.
Local institutions have been approached for assistance in the training of proffessionals.
9
Monitoring capacity• The Administration of Conditional Grant is centralized. There is a
project manager and core staff at head office that ensures that the project functions effectively and efficiently.
• The Department gets support from Local Municipalities on staff deployed in community libraries.
The Department has a monitoring and evaluation component that is assisting in ensuring that projects are done according to plans.
For ICT purposes, Conditional Grant has employed three network controllers that work together with SITA in all ICT projects.
User and circulation statistics at community libraries are monitored by both Municipalities and Districts.
Constraints
SITA delays in the implementation of projects. Dept. of Public Works categorizes our projects
as incubators.Constitutional arrangements for delivery of
library services still remains a challenge.
10
Conclusion
On a straight line, the Department was supposed to be at 75%. The actual expenditure is at 54% and commitments and actual expenditure is presently at 66%.It is with pleasure to inform the committee that the Department has managed to reach 91,1% by the closing of the financial year.
11
12
THE END