economic 6

Upload: ali-hussien

Post on 02-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Economic 6

    1/34

    ECONOMIC OPERATION

    OF POWER SYSTEMS

    Faculty ofEngineering

    Tanta University

    Dr. Ahmed Mohamed AzmyDepartment of Electrical Power and Machine Engineering

    Tanta University - Egypt

  • 8/10/2019 Economic 6

    2/34

    Economic load dispatch

    The unit commitment studyIt optimally defines the required generators tomeet the expected load and to provide aspecified margin of operating reserve over a

    specified period of timeThe economic dispatchIt determines the output power of each plantthat would minimize the overall fuel cost. Thisrepresents a coordination process betweenthe unit productions in an economic manner.

  • 8/10/2019 Economic 6

    3/34

    System Constraints

    The technical limitations that have not to be violatedunder any conditionThe violation of these constraints affects the powerquality and the general operation of the powersystem and causesstabilityproblems

    The constraints can be divided into two groups:equality constraintsandinequality constraintsInequality constraints can have a hard nature,where the variables are definite and specific like the

    tap-changing transformer, or a soft nature, wherethe variables are smoothly varied within a specificrange like the nodal voltages

  • 8/10/2019 Economic 6

    4/34

    System Constraints

    Constraints

    Equality constraints Inequality constraints

    hard nature soft nature

    The variables are

    definite and specificlike the tap-changing

    transformer

    The variables are

    smoothly varied withina specific range like

    the nodal voltages

  • 8/10/2019 Economic 6

    5/34

    System Constraints

    Equality ConstraintsThe main equality constraints are the basic load flowequations that establish the flow balance equationsFor example, the equality constrains according to

    Newton-Raphson Method are

    )--sin(yVVQ

    )--cos(yVVP

    ijji

    n

    1jijjii

    ijji

    n

    1jijjii

  • 8/10/2019 Economic 6

    6/34

    System ConstraintsInequality Constraints

    Generator constraints

    The thermal stability of generators requires that thetotal VA "Sg" loading of any generator has not to

    exceed a certain maximum value Sg-max:

    max,g2g

    2gg SQPS

    where: Pgand Qgare the active and reactivegenerated power respectively

  • 8/10/2019 Economic 6

    7/34

    System ConstraintsInequality Constraints

    Generator constraints

    The upper limit of the active power Pmax isconstrained by the thermal consideration

    The lower limit Pmin is constrained by the flameinstability of the boiler

    Consequently, the generated power from any unit"Pg" has to be kept within the limits:

    maxgmin PPP

  • 8/10/2019 Economic 6

    8/34

  • 8/10/2019 Economic 6

    9/34

    System ConstraintsInequality Constraints

    Voltage constraints

    Both the magnitudes and angles of node voltageshave to be controlled in order to keep them within

    acceptable limitsThe power quality necessitates that the voltagemagnitudes at load terminals are kept withinspecific limits or else the equipments will notoperate satisfactorily

    The regulation of the voltage starts from thegenerators (exciters) to reduce the cost of extravoltage regulating devices

  • 8/10/2019 Economic 6

    10/34

    System ConstraintsInequality Constraints

    Voltage constraints

    The upper limit of phase angles is definedregarding the transient stability of power systems

    On the other hand, the lower limit of the angles isdefined taking into account achieving an efficientutilization of transmission facility

    Typical operating angle of transmission line liesbetween 30 - 45

  • 8/10/2019 Economic 6

    11/34

    System ConstraintsInequality Constraints

    Voltage constraints

    where: is the magnitude of node angle with anangle ofdnat node n

    VVV

    maxnmin

    maxnmin

  • 8/10/2019 Economic 6

    12/34

    System ConstraintsInequality Constraints

    Running spare capacity constraints

    To ensure the existence of enough spinning reserveto overcome any emergency situation

    The generation should guarantee a minimum sparecapacity in addition to load demand and power losses

    Pg> PLoad+ Ploss

    This difference, i.e. spare capacity, is definedaccording to economic issues and technical aspectslike the ramping rates of the generators

  • 8/10/2019 Economic 6

    13/34

  • 8/10/2019 Economic 6

    14/34

    System ConstraintsInequality Constraints

    Network security constraints

    Violation of constrains can take place subsequent toabnormal conditions like a line outage, eitherscheduled or forced, which affects the security of thenetwork

    Sometimes a so called (x-1 study) is performed toexamine the reliability and security of the system

    Thex-1studymeans that the network is studied withoutage of one branch at a time

  • 8/10/2019 Economic 6

    15/34

    System ConstraintsInequality Constraints

    Transformer tap settings

    For auto-transformers, tmaxcan be unity

    Sometimes, there is a possibility to change thevoltage in steps, i.e. to chose between different

    values rather than varying the voltage smoothly

    maxtt0

  • 8/10/2019 Economic 6

    16/34

    System ConstraintsInequality Constraints

    Transformer tap settings

    Phase shift-ing transformers have phase shift limits

    maxmin

  • 8/10/2019 Economic 6

    17/34

    Economic Dispatch Problem

    Economic load dispatch concerns with theoperatingcostrather than the fixed costOnly fuel cost is considered in the study where allother costs that are depend on the generated powerwill be included in the expression of the fuel costObviously, the cost of fuel is concerned since thermalplants are assumed

    An early approach of power dispatch was to supply

    power from the most efficient plant till the point ofmaximum efficiency and then from the next mostefficient plant and so on

  • 8/10/2019 Economic 6

    18/34

    Another approach was to load the machines so thatall units have the same incremental cost ofproductionHowever, the locations of power plants and thetrans-mission losses are not consideredGenerating power in far plants requires supplying thetransmission losses in addition to the load demandEconomic distribution of load demand amonggenerating units necessitates expressing thecostas

    a function of thegenerated powerThe performance curve ofboiler-turbine-generatorset is required, which is called input-output curve

    Economic Dispatch Problem

  • 8/10/2019 Economic 6

    19/34

    input-output curve

    Input fuel (Btu/h)

    Output power (MW)

    PmaxPmin

  • 8/10/2019 Economic 6

    20/34

  • 8/10/2019 Economic 6

    21/34

    The incremental fuel rate is given as

    Incremental fuel rate =(P)d

    (F)d

    (output)

    (input)

    With Fis the input fuel and Pis the output powerThe reciprocal of the incremental heat rate is knownasthe incremental efficiencyTo operate at the maximum fuel efficiency, the point

    of the minimum heat rate has to be definedMultiplying the incremental fuel rate by the fuel cost,the incremental fuel cost is obtained in($/MWh)

    (Btu/MWh)

    Economic Dispatch Problem

  • 8/10/2019 Economic 6

    22/34

  • 8/10/2019 Economic 6

    23/34

    The fuel is given as:

    F=(40+4*P + 0.012*P2)*106

    Also, the heat rate can be calculated from equation

    (MW)poweroutput

    (Btu/h)fuelinputrateHeat

    The fuel cost as a function of the output power is:C=0.12*10-6 *F= 4.8 + 0.48*P + 0.0014*P2 ($/h)

    The incremental fuel cost is:

    Ifr= 0.48 + 0.0028*P ($/MWh)

  • 8/10/2019 Economic 6

    24/34

    P (MW) 10 20 30 70 80 90 100

    F*10-6 (Btu/h) 81.2 124.8 170.8 378.8 436.8 497.2 560

    Heat rate *10-6

    (Btu/MWh)8.12 6.24 5.69 5.41 5.46 5.52 5.6

    IFR ($/MWh) 0.5 0.53 0.56 0.67 0.7 0.73 0.76

  • 8/10/2019 Economic 6

    25/34

    10 40 70 1000

    2

    4

    6 Input fuel (Btu/h) * 108

    Output power (MW)

    Input output curve

  • 8/10/2019 Economic 6

    26/34

    Heat rate curve

    10 40 70 1005

    6

    7

    8

    Output power (MW)

    Heat rate(Btu/MWh) * 105

  • 8/10/2019 Economic 6

    27/34

    Incremental fuel cost

    10 40 70 100

    0.5

    0.6

    0.7

    0.8 Incremental fuel cost ($/MWh)

    Output power (MW)

  • 8/10/2019 Economic 6

    28/34

    Operating cost of thermal plants

    According to the input-output curve of thermalpower plant, the cost function is simplified in aquadrate form:

    C = a+ b*P + *P2

    This relation gives a good approximation to theactual variation of the cost with the variation of

    the output power

  • 8/10/2019 Economic 6

    29/34

    Economic Dispatch Neglecting Losses

    It is assumed that allgenerators are connectedat the same bus withoutlosses in transmission linesThe economic dispatch

    problem neglecting alllosses in the transmissionsystem is defined as:

    1

    2

    n

    .

    .

    .

    F1

    F2

    Fn

    P1

    P2

    Pn

    PD

    Min FT=

    n

    1iiF Subject to

    imax,iimin,

    1D

    PPP

    P

    n

    i

    iP

  • 8/10/2019 Economic 6

    30/34

    Economic Dispatch Neglecting Losses

    Min FT=

    n

    1iiF Subject to

    imax,iimin,

    1D

    PPP

    P

    n

    i

    iP

    With FTis the total input fuel to the generators, Fiis

    the input fuel to ith unit, PDis the total load demand,Piis the output power of the i

    th unit and Pmin,iandPmax,iare the lower and upper limits of unit i

    For simplicity, assume only two units connected atthe same bus

    PD= P1+ P2 FT= F1+ F2

  • 8/10/2019 Economic 6

    31/34

    Economic Dispatch Neglecting Losses

    For minimum total fuel consumption and selectingthe power of the first unit as a variable

    PD

    = P1

    + P2

    FT

    = F1

    + F2

    000 1P2P

    2dP2dF

    1dP1dF

    1P2F

    1dP1dF

    1PTF

    Differentiating the load demand equation withrespect to the power of generating 1 we get:

    1011P2P

    1P2P

    PD= P1+ P2

  • 8/10/2019 Economic 6

    32/34

    Economic Dispatch Neglecting Losses

    012

    2

    2

    1

    1

    P

    P

    dP

    dF

    dP

    dF

    101 1P2P

    1P2P

    ndPndF

    2dP2dF

    1dP1dF ... Condition of

    optimal operation

    iPdiFdThe term represents the incremental production

    cost of the ith plant in $/MWh

    All generators have to operate at the sameincremental cost of production to achieve aneconomic operation

    where: is the Lagrange multiplier

  • 8/10/2019 Economic 6

    33/34

  • 8/10/2019 Economic 6

    34/34

    Economic Dispatch Neglecting Losses

    n

    nDP

    2...22 22

    11

    b

    b

    b

    n

    n

    2

    2

    1

    1

    n21

    D

    2222

    1

    2

    1

    2

    1P ......

    b

    n

    1i i

    n

    1i i

    iD

    2

    1

    2P