economic 6
TRANSCRIPT
-
8/10/2019 Economic 6
1/34
ECONOMIC OPERATION
OF POWER SYSTEMS
Faculty ofEngineering
Tanta University
Dr. Ahmed Mohamed AzmyDepartment of Electrical Power and Machine Engineering
Tanta University - Egypt
-
8/10/2019 Economic 6
2/34
Economic load dispatch
The unit commitment studyIt optimally defines the required generators tomeet the expected load and to provide aspecified margin of operating reserve over a
specified period of timeThe economic dispatchIt determines the output power of each plantthat would minimize the overall fuel cost. Thisrepresents a coordination process betweenthe unit productions in an economic manner.
-
8/10/2019 Economic 6
3/34
System Constraints
The technical limitations that have not to be violatedunder any conditionThe violation of these constraints affects the powerquality and the general operation of the powersystem and causesstabilityproblems
The constraints can be divided into two groups:equality constraintsandinequality constraintsInequality constraints can have a hard nature,where the variables are definite and specific like the
tap-changing transformer, or a soft nature, wherethe variables are smoothly varied within a specificrange like the nodal voltages
-
8/10/2019 Economic 6
4/34
System Constraints
Constraints
Equality constraints Inequality constraints
hard nature soft nature
The variables are
definite and specificlike the tap-changing
transformer
The variables are
smoothly varied withina specific range like
the nodal voltages
-
8/10/2019 Economic 6
5/34
System Constraints
Equality ConstraintsThe main equality constraints are the basic load flowequations that establish the flow balance equationsFor example, the equality constrains according to
Newton-Raphson Method are
)--sin(yVVQ
)--cos(yVVP
ijji
n
1jijjii
ijji
n
1jijjii
-
8/10/2019 Economic 6
6/34
System ConstraintsInequality Constraints
Generator constraints
The thermal stability of generators requires that thetotal VA "Sg" loading of any generator has not to
exceed a certain maximum value Sg-max:
max,g2g
2gg SQPS
where: Pgand Qgare the active and reactivegenerated power respectively
-
8/10/2019 Economic 6
7/34
System ConstraintsInequality Constraints
Generator constraints
The upper limit of the active power Pmax isconstrained by the thermal consideration
The lower limit Pmin is constrained by the flameinstability of the boiler
Consequently, the generated power from any unit"Pg" has to be kept within the limits:
maxgmin PPP
-
8/10/2019 Economic 6
8/34
-
8/10/2019 Economic 6
9/34
System ConstraintsInequality Constraints
Voltage constraints
Both the magnitudes and angles of node voltageshave to be controlled in order to keep them within
acceptable limitsThe power quality necessitates that the voltagemagnitudes at load terminals are kept withinspecific limits or else the equipments will notoperate satisfactorily
The regulation of the voltage starts from thegenerators (exciters) to reduce the cost of extravoltage regulating devices
-
8/10/2019 Economic 6
10/34
System ConstraintsInequality Constraints
Voltage constraints
The upper limit of phase angles is definedregarding the transient stability of power systems
On the other hand, the lower limit of the angles isdefined taking into account achieving an efficientutilization of transmission facility
Typical operating angle of transmission line liesbetween 30 - 45
-
8/10/2019 Economic 6
11/34
System ConstraintsInequality Constraints
Voltage constraints
where: is the magnitude of node angle with anangle ofdnat node n
VVV
maxnmin
maxnmin
-
8/10/2019 Economic 6
12/34
System ConstraintsInequality Constraints
Running spare capacity constraints
To ensure the existence of enough spinning reserveto overcome any emergency situation
The generation should guarantee a minimum sparecapacity in addition to load demand and power losses
Pg> PLoad+ Ploss
This difference, i.e. spare capacity, is definedaccording to economic issues and technical aspectslike the ramping rates of the generators
-
8/10/2019 Economic 6
13/34
-
8/10/2019 Economic 6
14/34
System ConstraintsInequality Constraints
Network security constraints
Violation of constrains can take place subsequent toabnormal conditions like a line outage, eitherscheduled or forced, which affects the security of thenetwork
Sometimes a so called (x-1 study) is performed toexamine the reliability and security of the system
Thex-1studymeans that the network is studied withoutage of one branch at a time
-
8/10/2019 Economic 6
15/34
System ConstraintsInequality Constraints
Transformer tap settings
For auto-transformers, tmaxcan be unity
Sometimes, there is a possibility to change thevoltage in steps, i.e. to chose between different
values rather than varying the voltage smoothly
maxtt0
-
8/10/2019 Economic 6
16/34
System ConstraintsInequality Constraints
Transformer tap settings
Phase shift-ing transformers have phase shift limits
maxmin
-
8/10/2019 Economic 6
17/34
Economic Dispatch Problem
Economic load dispatch concerns with theoperatingcostrather than the fixed costOnly fuel cost is considered in the study where allother costs that are depend on the generated powerwill be included in the expression of the fuel costObviously, the cost of fuel is concerned since thermalplants are assumed
An early approach of power dispatch was to supply
power from the most efficient plant till the point ofmaximum efficiency and then from the next mostefficient plant and so on
-
8/10/2019 Economic 6
18/34
Another approach was to load the machines so thatall units have the same incremental cost ofproductionHowever, the locations of power plants and thetrans-mission losses are not consideredGenerating power in far plants requires supplying thetransmission losses in addition to the load demandEconomic distribution of load demand amonggenerating units necessitates expressing thecostas
a function of thegenerated powerThe performance curve ofboiler-turbine-generatorset is required, which is called input-output curve
Economic Dispatch Problem
-
8/10/2019 Economic 6
19/34
input-output curve
Input fuel (Btu/h)
Output power (MW)
PmaxPmin
-
8/10/2019 Economic 6
20/34
-
8/10/2019 Economic 6
21/34
The incremental fuel rate is given as
Incremental fuel rate =(P)d
(F)d
(output)
(input)
With Fis the input fuel and Pis the output powerThe reciprocal of the incremental heat rate is knownasthe incremental efficiencyTo operate at the maximum fuel efficiency, the point
of the minimum heat rate has to be definedMultiplying the incremental fuel rate by the fuel cost,the incremental fuel cost is obtained in($/MWh)
(Btu/MWh)
Economic Dispatch Problem
-
8/10/2019 Economic 6
22/34
-
8/10/2019 Economic 6
23/34
The fuel is given as:
F=(40+4*P + 0.012*P2)*106
Also, the heat rate can be calculated from equation
(MW)poweroutput
(Btu/h)fuelinputrateHeat
The fuel cost as a function of the output power is:C=0.12*10-6 *F= 4.8 + 0.48*P + 0.0014*P2 ($/h)
The incremental fuel cost is:
Ifr= 0.48 + 0.0028*P ($/MWh)
-
8/10/2019 Economic 6
24/34
P (MW) 10 20 30 70 80 90 100
F*10-6 (Btu/h) 81.2 124.8 170.8 378.8 436.8 497.2 560
Heat rate *10-6
(Btu/MWh)8.12 6.24 5.69 5.41 5.46 5.52 5.6
IFR ($/MWh) 0.5 0.53 0.56 0.67 0.7 0.73 0.76
-
8/10/2019 Economic 6
25/34
10 40 70 1000
2
4
6 Input fuel (Btu/h) * 108
Output power (MW)
Input output curve
-
8/10/2019 Economic 6
26/34
Heat rate curve
10 40 70 1005
6
7
8
Output power (MW)
Heat rate(Btu/MWh) * 105
-
8/10/2019 Economic 6
27/34
Incremental fuel cost
10 40 70 100
0.5
0.6
0.7
0.8 Incremental fuel cost ($/MWh)
Output power (MW)
-
8/10/2019 Economic 6
28/34
Operating cost of thermal plants
According to the input-output curve of thermalpower plant, the cost function is simplified in aquadrate form:
C = a+ b*P + *P2
This relation gives a good approximation to theactual variation of the cost with the variation of
the output power
-
8/10/2019 Economic 6
29/34
Economic Dispatch Neglecting Losses
It is assumed that allgenerators are connectedat the same bus withoutlosses in transmission linesThe economic dispatch
problem neglecting alllosses in the transmissionsystem is defined as:
1
2
n
.
.
.
F1
F2
Fn
P1
P2
Pn
PD
Min FT=
n
1iiF Subject to
imax,iimin,
1D
PPP
P
n
i
iP
-
8/10/2019 Economic 6
30/34
Economic Dispatch Neglecting Losses
Min FT=
n
1iiF Subject to
imax,iimin,
1D
PPP
P
n
i
iP
With FTis the total input fuel to the generators, Fiis
the input fuel to ith unit, PDis the total load demand,Piis the output power of the i
th unit and Pmin,iandPmax,iare the lower and upper limits of unit i
For simplicity, assume only two units connected atthe same bus
PD= P1+ P2 FT= F1+ F2
-
8/10/2019 Economic 6
31/34
Economic Dispatch Neglecting Losses
For minimum total fuel consumption and selectingthe power of the first unit as a variable
PD
= P1
+ P2
FT
= F1
+ F2
000 1P2P
2dP2dF
1dP1dF
1P2F
1dP1dF
1PTF
Differentiating the load demand equation withrespect to the power of generating 1 we get:
1011P2P
1P2P
PD= P1+ P2
-
8/10/2019 Economic 6
32/34
Economic Dispatch Neglecting Losses
012
2
2
1
1
P
P
dP
dF
dP
dF
101 1P2P
1P2P
ndPndF
2dP2dF
1dP1dF ... Condition of
optimal operation
iPdiFdThe term represents the incremental production
cost of the ith plant in $/MWh
All generators have to operate at the sameincremental cost of production to achieve aneconomic operation
where: is the Lagrange multiplier
-
8/10/2019 Economic 6
33/34
-
8/10/2019 Economic 6
34/34
Economic Dispatch Neglecting Losses
n
nDP
2...22 22
11
b
b
b
n
n
2
2
1
1
n21
D
2222
1
2
1
2
1P ......
b
n
1i i
n
1i i
iD
2
1
2P