`economic analysis of adding capacitor banks … thesis.pdf · `economic analysis of adding...

39
`ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree of Master of Science Department of Electrical Engineering University of Moratuwa Sri Lanka September 2012

Upload: lydang

Post on 25-Aug-2018

232 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

`ECONOMIC ANALYSIS OF ADDING CAPACITOR

BANKS TO THE SRI LANKAN TRANSMISSION

NETWORK

S.A.D. Tharanga

(08/8314)

Degree of Master of Science

Department of Electrical Engineering

University of Moratuwa

Sri Lanka

September 2012

Page 2: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

ECONOMIC ANALYSIS OF ADDING CAPACITOR

BANKS TO THE SRI LANKAN TRANSMISSION

NETWORK

Suraweera Arachchige Damith Tharanga

(08/8314)

Dissertation submitted in partial fulfillment of the requirement for the degree Master

of Science in Electrical Installation

Department of Electrical Engineering

University of Moratuwa

Sri Lanka

September 2012

Page 3: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

i

Declaration

“I declare that this is my own work and this dissertation does not incorporate without

acknowledgement any material previously submitted for a Degree or Diploma in any

other University or institute of higher learning and to the best of my knowledge and

belief it does not contain any material previously published or written by another

person except where the acknowledgement is made in the text.

Also, I hereby grant to University of Moratuwa the non-exclusive right to reproduce

and distribute my dissertation, in whole or in part in print, electronic or other

medium. I retain the right to use this content in whole or part in future works (such as

articles or books)”.

……………………….

Signature of the candidate Date:

(S.A.D.Tharanga)

The above candidate has carried out research for the Masters Dissertation under my

supervision.

…………………………….

Signature of the supervisor Date:

(Dr. K.T.M. Udayanga Hemapala)

Page 4: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

ii

Abstract

At present, there are significant reactive power flows in the Sri Lankan power system, giving

rise to excessive network losses, creating under voltage conditions and limiting the

utilization of transmission line and transformer capacities. This undesirable flow of reactive

power through the network can be reduced by generating reactive power as close as possible

to the loads; at least at grid substation level. Capacitor banks can be used for reactive power

compensation and voltage support in grid substations as it is a comparatively inexpensive

source of reactive power.

Ceylon Electricity Board (CEB) has some amount of breaker switched capacitor banks

installed at several grid substations. In most of the cases the capacitors have been selected

only with the aim of mitigating under voltage situation and very little attention is given for

loss reduction in the power system by installing capacitor banks. But still there are grid

substations which experience under voltages during some periods of the day. Therefore, the

objective of this research is to propose new additions of capacitors to the CEB network for

network loss reduction and mitigating under voltage levels.

Whole CEB power system is modeled in Power System Simulator for Engineering (PSS®E)

software. Load flow network simulations were run for different scenarios and identified the

grid substations showing the under voltages and key locations for reactive power demand.

First the required sizes of capacitor banks were selected for grid substations considering only

under voltage mitigation. Then the capacitor banks were selected for grid substations

considering both voltage support and loss reduction. The new selection of capacitors was

justified by examining its economic feasibility.

Proposed new additions of capacitors to the CEB network can contribute for reducing the

network losses, delaying the investment on generators and improving the voltage level in the

power system.

Key words: Reactive Power, Breaker Switched Capacitor, Network Loss Reduction

Page 5: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

iii

Acknowledgement

First, I would like to express my sincere gratitude to Dr. K.T.M. Udayanga

Hemapala for his guidance and supervision during conducting this research and

preparation of final dissertation.

I extend my sincere gratitude to Prof. J.P. Karunadasa, Head of the Department of

Electrical Engineering and to the staff of the Department of Electrical Engineering

for the support extended during the study period.

I am also most grateful to Mr. Jayasiri Karunanayake for his advice in making this

study practical and meaningful. I also specially thank Mr. Eranga Kudahewa for his

instructions during the simulations and the study.

I would like to take this opportunity to extend my sincere thanks to Mr. Janaka

Manohara, Electrical Engineer (Transmission O&Ms Branch – Galle Region), Mr.

Rohana Ekanayake, Chief Engineer (Transmission O&Ms Branch – Kandy Region),

Mr. Sajith Paulas, Electrical Engineer (Transmission O&Ms Branch – Kandy

Region), Mr. Anuradha Mudannayake, Electrical Engineer (Generation Planning

Branch), Mr. Anjana Subasinghe, Electrical Engineer (New Galle Transmission

Project) and all the Office Staff of Transmission Project(AGSAREP) of Ceylon

Electricity Board who gave their co-operation to make my investigation work a

success.

It is with great pleasure that I remember the encouragement and support extended by

the colleagues in the post graduate programme, friends and specially my parents and

my wife. May be I could not have completed this research without their valuable

support.

Page 6: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

iv

Table of Contents

Page

Declaration .................................................................................................................... i

Abstract ........................................................................................................................ ii Acknowledgement ...................................................................................................... iii List of Figures ............................................................................................................. vi List of Tables ............................................................................................................. vii List of Abbreviations ................................................................................................ viii

List of Appendices ...................................................................................................... ix

INTRODUCTION ....................................................................................................... 1

1.1 Background ........................................................................................................ 1 1.2 Objectives .......................................................................................................... 3 1.3 Scope of Work ................................................................................................... 3

REACTIVE POWER FLOW AND CAPACITOR BANKS ....................................... 5 2.1 Reactive Power .................................................................................................. 5

2.2 Shunt Capacitors ................................................................................................ 7 2.3 Different Types of Capacitor Banks .................................................................. 8 2.4 Var Control ........................................................................................................ 9 2.5 Voltage Control ................................................................................................ 10

FAMILIARIZATION WITH CEB POWER SYSTEM ............................................ 11

3.1 Capacitor Banks in the CEB System................................................................ 11 3.2 Dispatch Scenarios in the CEB System ........................................................... 12

SYSTEM MODELLING, SIMULATION AND DATA ANALYSIS ...................... 15

4.1 Selecting Capacitor Banks ............................................................................... 16 4.1.1 Under voltage mitigation only ...................................................................... 16

4.1.2 Both under voltage mitigation and loss reduction ........................................ 17 4.2 Reduction of Mvar Generation at Power Stations ........................................... 21 4.2.1 Under voltage mitigation only ...................................................................... 21

4.2.2 Both under voltage mitigation and loss reduction ........................................ 21 4.3 Reduction of I

2R Loss in the Network ............................................................. 22

4.3.1 Under voltage mitigation only ...................................................................... 22

4.3.2 Both under voltage mitigation and loss reduction ........................................ 22 4.4 Economic Analysis: ......................................................................................... 23

4.4.1 Under voltage mitigation only ...................................................................... 24 4.4.2 Both under voltage mitigation and loss reduction ........................................ 24

CONCLUSION AND RECOMMENDATIONS ...................................................... 27 5.1 Conclusion ....................................................................................................... 27 5.2 Recommendations for Future Developments ................................................... 27

Reference List ............................................................................................................ 28 Appendix 1: Hydro maximum Day Peak…………………………………………... 28

Appendix 2: Hydro maximum Night Peak…………………………………………29

Appendix 3: Hydro maximum Off Peak……………………………………............30

Appendix 4: Thermal maximum Day Peak…………………………………………31

Appendix 5: Thermal maximum Night Peak……………………………………......32

Appendix 6: Thermal maximum Off Peak……………………………………….....33

Page 7: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

v

Appendix 7: Typical Dispatch Day Peak………………………………………….34

Appendix 8: Typical Dispatch Night Peak………………………………………...35

Appendix 9: Typical Dispatch Off Peak…………………………………….……..36

Page 8: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

vi

List of Figures

Page

Figure 2.1: Typical metal enclosed capacitor bank...................................................... 8

Figure2.2: Typical pad mounted capacitor bank .......................................................... 8

Figure 2.3: Typical stacked rack capacitor bank.......................................................... 9

Figure 2.4: Typical pole mounted capacitor bank ....................................................... 9

Figure 3.1: Typical load profile of Sri Lanka ............................................................ 12

Figure 3.2: Capability curve of a hydrogen cooled generator ................................... 14

Figure 4.1: Under voltage condition at Galle grid substation .................................... 15

Figure 4.2 Under voltage condition at Ampara grid substation ................................. 16

Page 9: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

vii

List of Tables

Page Table 3.1: Existing capacitor banks in CEB system ................................................. 11 Table 3.2: Permissible voltage deviations as per CEB voltage criteria ..................... 13 Table 4.1: Grid substations having under voltage condition ..................................... 16

Table 4.2: Capacitor requirement for under voltage condition .................................. 17

Page 10: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

viii

List of Abbreviations

Abbreviation Description

AVR Automatic Voltage Regulator

BSC Breaker Switched Capacitor

CEB Ceylon Electricity Board

GT Gas Turbine

NPV Net Present Value

PCB Poly Chlorinated Biphenyl

PSS/E Power System Simulator for Engineering

Page 11: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

ix

List of Appendices

Appendix Description Page

Appendix 1 Hydro maximum Day Peak 27

Appendix 2 Hydro maximum Night Peak 28

Appendix 3 Hydro maximum Off Peak 29

Appendix 4 Thermal maximum Day Peak 30

Appendix 5 Thermal maximum Night Peak 31

Appendix 6 Thermal maximum Off Peak 32

Appendix 7 Typical Dispatch Day Peak 33

Appendix 8 Typical Dispatch Night Peak 34

Appendix 9 Typical Dispatch Off Peak 35

Page 12: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

1

Chapter 1

INTRODUCTION

1.1 Background

Many power system components in a network and particularly the loads are

inherently inductive and hence consume large amounts of reactive power. Reactive

current supports the magnetic fields in motors and transformers [1]. Supporting both

real and reactive power with the system generation requires increased generation and

transmission capacity, because it increases losses in the network. That is why most of

the power utilities around the world are trying to generate its reactive power

requirements as close as possible to the load centers. In general, many utilities

describe this as the concept of reactive power compensation in the technical

vocabulary.

Shunt-connected capacitors or synchronous condensers near the load centers are a

common method to generate reactive power. Shunt capacitors have the advantage of

providing reactive power close to the load centers, minimizing the distance between

power generation and consumption, and do not have the maintenance problems

associated with synchronous condensers. Breaker switched or fixed capacitor banks,

are comparatively economical and installation is also easy. Later additions according

to match load characteristics are comparatively flexible. Controlling capacitance in a

transmission or distribution network could be the simplest and most economical way

of maintaining system voltage, minimizing system losses and maximizing system

capability.

The application of capacitor banks and its controlling philosophy is different from

location to location. For an end consumer it is used as a power factor corrector that

helps to reduce his demand and avoid penalties from the energy supplier. For a

distribution company, the capacitors installed at intermediate locations on

distribution line reduce line losses hence increases line capacities and improve the

bus bar voltage. For a transmission company, the intention is not only to reduce loses

Page 13: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

2

or increase line capacities but also to give voltage support which is an inherent

system problem under heavily loaded conditions and to further delay investment

costs on augmenting line and substation capacities. Static shunt capacitors are

installed near the load terminals, in factory substations, in the receiving substations,

in switching substations, etc. to provide leading vars and thus to reduce the line

current and total kVA loading of the substation transformer[2]. At generation buses,

capacitor banks also can be used for voltage support though it is rare. Depending on

the location and requirement, the controlling philosophy of the capacitor banks will

differ. Generally, as mentioned earlier, the distribution capacitor banks are controlled

for local requirements. In many cases the control consists of switches that are opened

and closed in a seasonal basis or some other local requirement.

Ceylon Electricity Board (CEB), like many other utilities, has about 130Mvar of

Breaker Switched Capacitor (BSC) banks in operation, installed at various

substations in the system. In most of the cases the capacitors have been selected only

with the aim of mitigating under voltage situation and very little attention is given for

loss reduction in the power system by installing capacitor banks. But still there are

grid substations which experience under voltages during some periods of the day.

Further, some of the installed capacitor banks are currently out of service due to

technical problems. The main intentions of the use of capacitor banks is to give

voltage support at the substation level, reduction of losses in power transformers and

transmission lines, and to release the capacity constraints in transformers and lines.

Increased economic benefits can be achieved by installing more capacitor banks.

Underutilizing an economical reactive power source is a factor to consider.

All the capacitor banks in CEB network are connected to the 33kV load bus in the

relevant grid substation. This philosophy of installing the capacitor banks in grid

substations does not either release the distribution feeder capacity or reduce the

feeder losses. If those were expected then the capacitors could have been closer to

the loads. However, lagging var injection or in other words leading var consumption

at 33kV bus level improves the voltage stability and releases the power transformers

at the substation. If the utility expects latter two cases, the switching of the capacitor

Page 14: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

3

banks shall be based on reactive power or voltage. In case of voltage, the banks

should be switched considering the voltage measurements at the point of

interconnection. If releasing the capacity constraint or minimizing losses are

concerned, then more capacitors shall be utilized to minimize drawing reactive

power from remote generation.

1.2 Objectives

Taking all these into Consideration, the main objective of the research study is to

look in to the possibilities of adding BSC banks to the CEB system with a view of

both under voltage mitigation and reducing network losses.

1.3 Scope of Work

Running load flow simulations of the CEB network in PSS/E software for

different scenarios and identifying the grid substations having under voltage

problem.

Studying the system and identifying key locations with reactive power

demand.

Calculating the network loss without adding new capacitor banks.

Calculating the reactive power generation by generators in the system without

adding new capacitor banks.

Selecting capacitor bank sizes for the selected locations considering under

voltage mitigation only (Method 1).

Calculating the network loss after adding new capacitor banks (Method 1).

Calculating the reactive power generation by generators in the system after

adding new capacitor banks (Method 1).

Selecting capacitor bank sizes for the selected locations considering both

under voltage mitigation and loss reduction (Method 2).

Calculating the network loss after adding new capacitor banks (Method 2).

Page 15: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

4

Calculating the reactive power generation by generators in the system after

adding new capacitor banks (Method 2).

Calculating economic benefits of adding new capacitor banks according to

Method 1 and Method 2.

Reduction of heat(I2R) losses in the network and reduction of reactive power

generation at power station level due to capacitors can be obtained using simulations.

Using those data and investment costs of breaker switched capacitors, economic

feasibility of adding those capacitor banks to the system can be investigated.

Page 16: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

5

Chapter 2

REACTIVE POWER FLOW AND CAPACITOR BANKS

2.1 Reactive Power

Every electric load that works with magnetic fields (motors, chokes, transformers,

inductive heating, arc-welding generators) produces a varying degree of electrical

lag, what is called inductance. This lag of inductive loads maintains the current sense

(eg: positive) for a time even though the negative going voltage tries to reverse it.

This phase shift between current and voltage is maintained, current and voltage

having opposite signs. During this time, negative power or energy is produced and

fed back into the network. When current and voltage have the same sign again, the

same amount of energy is again needed to build up the magnetic fields in inductive

loads[3]. This magnetic reversal energy is called reactive power. In alternating

voltage networks (50/60 Hz) such a process repeats 50 or 60 times a second. So an

obvious solution is to briefly store the magnetic reversal energy in capacitors and

relieve the network (supply line) of this reactive energy. For this reason, automatic

reactive power compensation systems (detuned/conventional) are installed for larger

loads like factory plants. Such systems consist of a group of capacitor units that can

be cut in and cut out and which are driven and switched by a power factor controller

as determined by a current transformer.

As a good approximation many power systems are mainly inductive i.e. have a high

reactance to resistance (X/R) ratio. For such systems difference in voltages causes

reactive power flows and conversely reactive power flows influence terminal

voltage[4].

But conductors of transmission lines act like plates of a capacitor also. The

conductors are charged, and there is a potential difference between the conductors

and between the conductors and the ground. Therefore there is capacitance between

the conductors and between the conductors and the ground. This also adds capacitive

reactive power to the system. The basic equation for calculation of the capacitance is

Page 17: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

6

the definition of the capacitance as the ratio of the charge and the potential difference

between the charged plates:

CQ

VF

where Q is the total charge on the conductors (plates)

V is the potential difference between the conductors or a conductor and

ground (i.e. plates)

For transmission lines, we usually want the capacitance per unit length

Cq

VF m /

where q is the charge per unit length in C/m

V is the potential difference between the conductors or a conductor and

ground (i.e. plates)

Capacitance of Balanced Three Phase Line between a phase conductor and neutral is

given by

CD

D

F mn

o

eq

b

2

ln

/

where D D D Deq ab bc ca 3

and Dab, Dbc, and Dca are the distances between the

centers of the phase conductors, and Db is the geometric mean radius for the bundled

conductors. (in the expression for Db the outside radius of the conductor is used,

rather than the GMR from the tables.)

The capacitive reactance to neutral than becomes

Xf

D

Dmilecn

eq

b

1779 106.

ln .

Page 18: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

7

2.2 Shunt Capacitors

Capacitor Banks consist of individual capacitor units where such a unit is a

combination of shunt or series set of capacitor elements. Depending on the bank size,

those units are again connected in series or parallel to give the required size. In

medium and high voltage levels, sizing of the capacitors in parallel combinations in

banks generally has to consider the discharge energy through a shorted parallel

capacitor in the same group.

Earlier generation capacitor units were manufactured using very refined kraft paper

with a PCB (Poly Chlorinated Biphenyl) impregnant. The kraft paper had many non-

uniformities or flaws. Several layers of paper were used between the foil layers to

avoid weak spots in the design. With this design, the stress levels were low but the

dielectric losses were higher than that of today’s capacitor can designs. High

dielectric losses resulted in high hot spot temperatures. High temperatures accelerate

deterioration of the capacitor dielectric strength. Failure of the dielectric material

resulted in continued arcing, charring, and gas generation that swelled the capacitor

cans and eventually ruptured the cases.

Today’s capacitor units are built with polypropylene film (instead of kraft paper) and

dielectric fluids with electrical characteristics superior to those of PCB. The

polypropylene film is very thin, pure, and uniform, with exceptionally few design

flaws. This latest design only requires two to three layers of film. While this

increases the stress levels, it reduces the dielectric losses which results in low hot

spot temperatures. As a result of these changes, today’s capacitor units do not age

quickly. Swelling or case rupture is now very rare. Because film layers are thin and

of high quality, element failures do not cause arcing and charring. Instead, the foil

welds together. Capacitor units for power system applications are built with

dielectric polypropylene film, aluminum foil and impregnant. Thin layers of

dielectric film are wound between the aluminum foils, which act as the electrode.

Page 19: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

8

2.3 Different Types of Capacitor Banks

Different types of capacitor banks are available in the present market. Metal enclosed

type, pad mounted type, stack-rack banks and pole top mounted types are the most

common type in utility applications. Metal enclosed type banks specifically made tor

indoor installations. Pad mounted capacitor banks are also enclosed in a metal

enclosure and commonly used for areas where accessible to public.

Figure 2.1: Typical metal enclosed capacitor bank

Normally, metal enclosed and pad mounted units come with factory assembled and

tested hence the installation is very easy. Those banks significantly reduce

unnecessary human interference such as trespassing and tampering. They do not need

a fence around it. However their initial cost is high compared to other types and only

available up to a certain voltage level.

Figure2.2: Typical pad mounted capacitor bank

Stack rack capacitor banks are commonly used in the utility sub stations. The initial

cost of these is comparatively low and all components are visible. The components

are easily replaceable and also easily expandable.

Page 20: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

9

The pole top mounted banks are commonly used in distribution networks for

improving the voltage profile in distribution lines. Those are available as smaller

banks and eliminate the need for space. The maintenance and component

replacement is little difficult.

Figure 2.3: Typical stacked rack capacitor bank

Figure 2.4: Typical pole mounted capacitor bank

2.4 Var Control

Var control is the natural means to control capacitors because the latter adds a fixed

amount of leading var to the system regardless of other conditions, and loss reduction

depends only on reactive current. Since reactive current at any point along a feeder is

affected by downstream capacitor banks, this kind of control is susceptible to

Page 21: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

10

interaction with downstream banks. In a system like CEB, there are no switchable

capacitor banks along the distribution feeder so that this problem will not arise.

However, in multiple capacitor feeders, the furthest downstream banks should go on-

line first and off-line last. Var controls require current sensors and typically costly.

2.5 Voltage Control

Voltage control is used to regulate voltage profiles on the bus on which the

capacitors are connected to. However, while doing this it may not consider the

reduction of system losses since lagging or leading low power factors always

increase the currents through its components. Voltage control requires no current

sensors.

Considering above parameters for switching the capacitor banks, we can define two

concepts of control philosophies. First is single variable switching that considers

only one measuring parameter. Second concept is multi variable and Boolean

switching. In the latter case multiple parameters are measured and the decision for

switching is done depending on the optimal situation considering both parameters.

The fact we have to consider is the cost of the controllers.

Page 22: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

11

Chapter 3

FAMILIARIZATION WITH CEB POWER SYSTEM

3.1 Capacitor Banks in the CEB System

Capacitor banks are installed in several grid substations in the existing CEB system.

But some of them are out of service due to technical problems. The existing capacitor

banks in operational condition are detailed in Table 3.1.

Table 3.1: Existing capacitor banks in CEB system

Grid Substation

Capacitor Size

(Mvar)

Kotugoda 30

Galle 20

Kurunegala 10

Habarana 10

Kiribathkumbura 20

Matugama 20

Puttalam 20

Panadura 20

All those capacitor banks are breaker switched shunt capacitors connected in

ungrounded double star connection. In the present system, the typical step size of

each bank is 5Mvar. This may slightly changes with the presence of the reactor.

CEB's general concept in fixing the capacitor banks is such that it uses symmetrical

banks for each bus section in the 33kV bus bar. All the capacitor banks in CEB

network are connected to the 33kV load bus in the relevant grid substation and there

are no capacitor banks at the transmission level. The reason for this is due to lower

costs at low voltage levels than at higher voltage levels.

Page 23: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

12

Generally, the banks are equipped with the inrush limiting reactors as well as

detuning reactors in most cases. However there are banks without those reactors as

well. The banks with detuning reactor are called as the filter banks because they are

meant for eliminating the switching inrush, reduce resonance effects and to filter 5th

harmonics in the system loads. The other banks are sometimes having inrush limiting

reactors and sometimes there are no such reactors.

3.2 Dispatch Scenarios in the CEB System

The daily electricity demand pattern of a country depends on its per capita income,

level of industrialization, climate condition, etc. A typical load profile of Sri Lanka

(load curve of 01.03.2012) is shown in Figure 3.1.

Figure 3.1: Typical load profile of Sri Lanka

The load profile of Sri Lankan power system has distinctly identifiable demand

levels during different periods of the day. Those are;

1. Day peak

2. Night peak

3. Off peak

Page 24: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

13

Both hydro power and thermal power carry considerable portions of Sri Lanka’s

electricity generation. Therefore when the water level in the reservoirs is low,

System Control Center dispatches more thermal generators and minimizes hydro

generation. This is called Thermal Maximum dispatch. When the water level in the

reservoirs is high due to rain, System Control Center dispatches more hydro

generators and minimizes thermal generation. This is called Hydro Maximum

dispatch. The pattern of dispatching generators in the remaining periods of the year is

called Typical Dispatch.

Voltage levels and power flows of the network depend on the demand level of the

loads and the locations and the power injections of the generators connected to the

system. Therefore nine scenarios have to be considered regarding load demand and

generator dispatch. They are:

1. Hydro Maximum- Day peak

2. Hydro Maximum- Night peak

3. Hydro Maximum- Off peak

4. Thermal Maximum- Day peak

5. Thermal Maximum- Night peak

6. Thermal Maximum- Off peak

7. Typical Dispatch- Day peak

8. Typical Dispatch - Night peak

9. Typical Dispatch - Off peak

Table 3.2 shows the allowable voltage deviations as per CEB voltage criteria.

Table 3.2: Permissible voltage deviations as per CEB voltage criteria

Nominal Voltage Allowable Variation

33kV +/-5%

132kV +/-10%

220kV +/-5%

Page 25: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

14

There is some contribution from the leading reactive power of transmission line

capacitances for lagging var compensation of the inductive loads. Further when we

look at the typical capability curve of a generator, it is clear that some amount of

reactive power also is generated during the most economical operation of a

synchronous generator (around 0.85 power factor) [5].

Figure 3.2: Capability curve of a hydrogen cooled generator

Page 26: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

15

Chapter 4

SYSTEM MODELLING, SIMULATION AND DATA ANALYSIS

Whole CEB power system is modeled in Power System Simulator for Engineering

(PSS®E) software. Automatic Voltage Regulators (AVR) of generators and

transformers are set to auto mode during the simulations.

For identifying the under voltage conditions, branches with excessive reactive power

flows, calculating the present network losses and amount of reactive power

generation, load flow simulations of the present transmission network were run for

the all nine scenarios (Refer Appendix 1 to Appendix 9). Under voltage conditions at

Galle and Ampara grid substations are shown in Figure 4.1 and Figure 4.2

For selecting capacitors for only under voltage mitigation as per the current CEB

practice, grid substations with under voltage levels were identified. Capacitors were

added for those locations until voltage improves up to the permissible range. Then

the network losses and amount of reactive power generation were calculated after

adding those capacitors to the system.

Figure 4.1: Under voltage condition at Galle grid substation

Page 27: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

16

Figure 4.2 Under voltage condition at Ampara grid substation

For selecting capacitors for both under voltage mitigation and network loss reduction

as the new proposal, it was investigated whether 100% reactive load compensation

can be done at the grid substations without creating overvoltage conditions.

Capacitors were added to grid substations to the nearest 5Mvar step of the reactive

load of each day peak, night peak and off peak load. Simulations were run to see

whether there are any under voltage or over voltage conditions. No under voltage

conditions were observed and over voltages were observed in some grid substations

during off peak. The amount of capacitors were reduced from those grid substations

until those voltages were reduced to permissible limit.

After adding the selected capacitors to the relevant grid substations, network losses

and amount of reactive power generation were calculated by running load flow

simulations for the nine scenarios.

4.1 Selecting Capacitor Banks

4.1.1 Under voltage mitigation only

Table 4.1: Grid substations having under voltage condition

Grid

Substation

Busbar Volage (kV)

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Galle OK 117.7 OK OK 117.6 OK OK 117.6 OK

Ampara OK 115.3 OK 117.2 114.9 OK 118.7 115 OK

Page 28: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

17

To prevent this under voltage condition, capacitors were selected as shown in Table

4.3.

Table 4.2: Capacitor requirement for under voltage condition

Grid

Substation

Capacitor Requirement (Mvar)

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Ampara 0 20 0 10 20 0 10 20 0

Galle 0 20 0 0 30 0 0 20 0

Table 4.4: Voltage improvement after adding capacitor banks

Grid

Substation

Busbar Volage (kV)

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Galle 126.7 122.3 127.2 125.6 121.5 125.7 126.3 121.5 121.9

Ampara 126.9 124.5 128.8 122.2 124 128.4 123.7 124.3 127.3

4.1.2 Both under voltage mitigation and loss reduction

Capacitors were added to grid substations to the nearest 5Mvar step of the reactive

load of each day peak, night peak and off peak load. Over voltages were observed in

some grid substations during off peak. Simulation diagram of capacitor addition

during off peak are shown in Appendix 10. Capacitor bank values for reactive load

compensation during day peak is shown in Table 4.5. Capacitor bank values for

reactive load compensation during night peak are shown in Table 4.6. Capacitor bank

values for reactive load compensation during off peak are shown in Table 4.7.

Page 29: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

18

Table 4.5: Capacitor bank values for reactive load compensation during day peak

Grid Substation

Reactive

Demand

(Mvar)

Capacitor

Bank

(Mvar) Grid Substation

Reactive

Demand

(Mvar)

Capacitor

Bank

(Mvar)

Wimalasurendra 4 5 Kurunegala 18 20

Ampara 12 10 Habarana 19.8 20

Inginiyagala 0 0 Anuradhapura 4.87 5

Ukuwela 11 10 New Anuradhapura 2.4 0

Vavuniya 4.1 5 Trincomalee 7.71 10

Rantambe 1.8 0 Ratnapura 8 10

Kelanithissa 18 20 Kiribathkumbura 26 25

Beliatta 1.8 0 Valachchenai 11.2 10

Hambanthota 5.2 5 Ratmalana 36 35

Horana 18 20 Matugama 19.8 20

Katunayake 22.8 25 Puttalam 2 0

Kosgama 24 25 Athurugiriya 20.62 20

Seethawaka 12 10 Veyangoda 22.13 20

Nuwaraeliya 14.5 15 Jayawardenapura 15.4 15

Thulhiriya 18.3 20 Panadura 30 30

Oruwala 0 0 Madampa 16.8 15

Kolonnawa 41.03 40 Kelaniya 10.2 10

Pannipitiya 22 20 Ambalangoda 10.4 10

Biyagama 38 40 Dehiwala 20.4 20

Kotugoda 35.8 35 Pannala 16.4 15

Sapugaskanda 23.8 25 Aniyakanda 18 20

Bolawatta 29.73 30 Maradana 16.1 15

Badulla 10 10 Havelock Town 19.2 20

Balangoda 5.4 5 Colombo E 29.1 30

Deniyaya 5.22 5 Colombo F 25.2 25

Galle 20.94 20 Puttalam Coal 20 20

Embilipitiya 8 10 Substation C 7.2 5

Matara 16 15

Page 30: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

19

Table 4.6: Capacitor bank values for reactive load compensation during night peak

Grid Substation

Reactive

Demand

(Mvar)

Capacitor

Bank

(Mvar) Grid Substation

Reactive

Demand

(Mvar)

Capacitor

Bank

(Mvar)

Wimalasurendra 2 0 Kurunegala 11 10

Ampara 9 10 Habarana 15.4 15

Inginiyagala 0 0 Anuradhapura 7.97 10

Ukuwela 11.78 10

New

Anuradhapura 3.6 5

Vavuniya 2.5 5 Trincomalee 9.1 10

Rantambe 1.16 0 Ratnapura 6 5

Kelanithissa 7.51 10 Kiribathkumbura 15 15

Beliatta 1.8 0 Valachchenai 0 0

Hambanthota 4.4 5 Ratmalana 18.6 20

Horana 7.31 5 Matugama 15 15

Katunayake 13.2 15 Puttalam 15 15

Kosgama 20 20 Athurugiriya 11.72 10

Seethawaka 8 10 Veyangoda 23.34 25

Nuwaraeliya 17.31 15 Jayawardenapura 9.3 10

Thulhiriya 16.27 15 Panadura 22 20

Oruwala 0 0 Madampa 17 15

Kolonnawa 17.61 20 Kelaniya 8.05 10

Pannipitiya 20 20 Ambalangoda 10.8 10

Biyagama 30 30 Dehiwala 17.2 15

Kotugoda 27.2 30 Pannala 10 10

Sapugaskanda 23.86 25 Aniyakanda 16 15

Bolawatta 29.15 30 Maradana 9.4 10

Badulla 2 0 Havelock Town 10.9 10

Balangoda 7.8 10 Colombo E 12.5 15

Deniyaya 5.18 5 Colombo F 12.1 10

Galle 20.65 20 Puttalam Coal 20 20

Embilipitiya 4 5 Substation C 11.2 10

Matara 13 15

Page 31: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

20

Table 4.7: Capacitor bank values for reactive load compensation during off peak

Grid

Substation

Reactive

Demand

(Mvar)

Capacitor Banks

(Mvar)

Grid Substation

Reactive

Demand

(Mvar)

Capacitor Banks

(Mvar)

Initial

To

prevent

over

voltages Initial

To

prevent

over

voltages

Wimalasurendra 0.76 0 0 Kurunegala 3.04 5 0

Ampara 4.56 5 5 Habarana 5.02 5 5

Inginiyagala 0.00 0 0 Anuradhapura 1.68 0 0

Ukuwela 3.86 5 0

New

Anuradhapura 1.52 0 0

Vavuniya 0.00 0 0 Trincomalee 3.79 5 0

Rantambe 0.37 0 0 Ratnapura 3.04 5 0

Kelanithissa 4.51 5 5 Kiribathkumbura 4.56 5 5

Beliatta 1.37 0 0 Valachchenai 0.00 0 0

Hambanthota 1.14 0 0 Ratmalana 7.38 5 5

Horana 3.49 5 0 Matugama 6.99 5 5

Katunayake 6.38 5 5 Puttalam 6.08 5 5

Kosgama 7.40 5 5 Athurugiriya 3.24 5 0

Seethawaka 4.56 5 5 Veyangoda 4.88 5 0

Nuwaraeliya 2.31 0 0 Jayawardenapura 4.64 5 0

Thulhiriya 4.27 5 5 Panadura 9.12 10 0

Oruwala 0.00 0 0 Madampa 7.45 5 0

Kolonnawa 7.52 10 5 Kelaniya 3.32 5 0

Pannipitiya 9.12 10 0 Ambalangoda 4.71 5 0

Biyagama 22.80 20 10 Dehiwala 7.40 5 0

Kotugoda 16.42 15 0 Pannala 4.56 5 0

Sapugaskanda 16.29 15 15 Aniyakanda 4.56 5 0

Bolawatta 13.04 15 10 Maradana 3.88 5 0

Badulla 3.80 5 0 Havelock Town 3.34 5 0

Balangoda 2.28 0 0 Colombo E 4.56 5 0

Deniyaya 1.47 0 0 Colombo F 4.48 5 0

Galle 21.89 20 5 Puttalam Coal 4.48 5 0

Embilipitiya 0.00 0 0 Substation C 2.40 0 0

Matara 6.08 5 5

Page 32: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

21

4.2 Reduction of Mvar Generation at Power Stations

4.2.1 Under voltage mitigation only

Table 4.8: Reduction of Mvar generation by adding capacitors for under voltage mitigation

Scenario

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Q generated w/o

capacitors

(Mvar)

788.6 631.4 41.7 827.7 644.2 79.7 804.6 625.5 31.3

Q generated

with capacitors

(Mvar)

749.2 599.0 41.7 823.3 603.5 79.7 789.7 595.6 31.3

Reduction in

Mvar Generation 39.4 32.4 0.0 4.4 40.7 0.0 14.8 29.9 0.0

Maximum

Reduction in

Mvar Generation 40.7

4.2.2 Both under voltage mitigation and loss reduction

Table 4.9: Reduction of Mvar generation by adding capacitors according to new method

Scenario

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Q generated

w/o capacitors

(Mvar) 788.6 631.4 41.7 827.7 644.2 79.7 804.6 644.2 31.3

Q generated

with capacitors

(Mvar) 21.8 75.1 2.3 31.6 83.7 5.8 26.4 79.2 4.1

Reduction in

Mvar

Generation 766.8 556.3 44.0 796.1 560.5 73.9 778.2 565.0 27.2

Maximum

Reduction in

Mvar

Generation 796.1

Page 33: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

22

4.3 Reduction of I2R Loss in the Network

4.3.1 Under voltage mitigation only

Table 4.10: Loss reduction by adding capacitors for under voltage mitigation

Scenario

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

I2R Loss

without

Capacitors

(MW)

29.2 46.0 9.2 29.4 46.9 11.9 29.4 43.7 10.0

I2R Loss with

Capacitors

(MW)

28.7 45.1 9.2 28.8 46.0 11.9 28.8 42.9 10.0

Reduction in

I2R Loss (MW)

0.5 0.9 0.0 0.6 0.9 0.0 0.6 0.8 0.0

Period

(hours/day) 12 3 9 12 3 9 12 3 9

Energy Saved

per Day (kWh) 8,341.50 10,119.60 9,246.00

Period

(months/year) 1 6 5

Energy Saved

per Year (kWh) 3,458,673.00

4.3.2 Both under voltage mitigation and loss reduction

Table 4.11: Loss reduction by adding capacitors according to new method

Scenario

Hydro Maximum Thermal Maximum Typical Dispatch

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

Day

Peak

Night

Peak

Off

Peak

I2R Loss without

Capacitors (MW) 29.2 46.0 9.2 29.4 46.9 11.9 29.4 46.9 10.0

I2R Loss with

Capacitors (MW) 24.9 43.7 8.7 26.9 45.3 10.6 26.3 44.8 9.8

Reduction in

I2R Loss (MW) 4.3 2.3 0.5 2.5 1.6 1.3 3.1 2.1 0.2

Period

(hours/day) 12 3 9 12 3 9 12 3 9

Energy Saved

per Day (kWh) 62,608.20 46,967.70 45,267.60

Period

(months/year) 1 6 5

Energy Saved

per Year (kWh) 17,122,572.00

Page 34: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

23

4.4 Economic Analysis:

It is necessary to investigate the economic benefits of the investment on capacitors

selected above. Reduction in I2R Loss in transmission lines and transformers can be

calculated. At present the average unit cost of generation is approximately Rs.18.50.

Due to the reduction of Mvar generation in the generators of the system, generation

capacity is relieved for active power (MW) generation. According to the Capability

Curve of a typical generator in Figure 3.2, power (MW) generation can be increased

by approximately 0.5 times the reduction of Mvar generation in the generators.

Typical life time of a capacitor bank can be taken as 20 years. Therefore addition of

respectively 20MW Gas Turbine (GT) power plant and 400MW coal plant can be

postponed by 20 years for each case as summarized below.

Typical cost is USD700/kW for a 20MW GT power plant and USD150/kW for a

400MW coal power plant. Typical cost of capacitor bank addition is 4Mn Rs/Mvar

including capacitor, switchgear and control equipment. Exchange rate is taken as

Rs.130/USD.

Table 4.12: Cash flow data for economic analysis

Capacitor Bank

Selection Method

UV Mitigation

Only

UV Mitigation and

Loss Reduction

Size of New Cap Banks Installed

(Mvar) 30 225

Cost of New Cap Banks ( Mn Rs.) 120 3260

Reduction in Mvar Generation in

Power Plants 40.75 796.10

Size of Postponed Power Plant

(MW) 20 400

Postponed Investment on Power

Plant (Mn Rs.) 1820 7800

Energy Saved per Year by Loss

Reduction (kWh) 3,458,673 17,122,572

Cost of Energy Saved per Year

(Mn Rs.) 63.9 316.7

Page 35: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

24

4.4.1 Under voltage mitigation only

Net Present Value (NPV) of capacitor banks installed according to the above criteria

is calculated in Table 4.13 .

4.4.2 Both under voltage mitigation and loss reduction

Net Present Value (NPV) of capacitor banks installed according to the above criteria

is calculated in Table 4.14.

Page 36: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

25

Table 4.13: NPV of capacitor banks installed under voltage mitigation only

Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Cost of New Cap Banks (Mn Rs.)

(-) 120

Postponed Investment on

Generators (Mn

Rs.)

1820

(-)

1820

Cost of Energy

Saved per Year (Mn Rs.)

63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9

Net Cash Flow of

Project (Mn Rs.) 1700 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9 63.9

(-)

1756.1

NPV (Mn Rs.) 1,535.0

Page 37: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

26

Table 4.14: NPV of capacitor banks installed according to new method

Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Cost of New Cap

Banks (Mn Rs.) -3260

Postponed

Investment on Generators (Mn

Rs.)

7800 -7800

Cost of Energy Saved per Year

(Mn Rs.)

316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7

Net Flow of

Project (Mn Rs.) 4540 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7 316.7

-

7483.3

NPV (Mn Rs.) 4,524.2

Page 38: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

27

Chapter 5

CONCLUSION AND RECOMMENDATIONS

5.1 Conclusion

1. Despite capacitor banks are installed at several grid substations, still there are

grid substations in the CEB system having under voltage situation during

different periods of the day.

2. 100% reactive load compensation at rgrid substations can be done during day

peak and night peak without creating over voltage conditions.

3. 100% reactive load compensation during off peak creates over voltages in

several grid substations.

4. Adding capacitor banks considering both under voltage situation and amount

of reactive power flow can reduce network losses significantly compared to

adding capacitor banks considering only the under voltage situation, and

hence gives more economic benefits compared to the latter.

5. Addition of a power plant can be delayed by the life time of proposed

capacitors.

6. If release the capacity constraint or minimize losses are concerned, then the

capacitors shall be fully utilized to minimize drawing reactive power from

remote generation. Therefore it is required to consider capacitor bank

controllers with multi- parameter or Boolean switching. Reactive power and

voltage shall be the parameters to consider in the switching decisions.

5.2 Recommendations for Future Developments

Adding capacitors at grid substations helps to release capacity and reduce losses of

the transmission network but does not release capacity or reduce losses of the

distribution feeders. If capacitors are added with optimal sizes at optimal locations

for individual feeders of each grid substation, network losses can be further reduced.

Page 39: `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS … Thesis.pdf · `ECONOMIC ANALYSIS OF ADDING CAPACITOR BANKS TO THE SRI LANKAN TRANSMISSION NETWORK S.A.D. Tharanga (08/8314) Degree

28

Reference List

[ 1] Dhillon M.S. , Tziouvaras D. A. , Protection of fuseless capacitor banks using

digital relays

[2] Gupta J.B. (2004), Switchgear and Protection (2nd

edition), S.K. Kataria & Sons

Publishers and Distributors, Chapter 16 pp 510

[ 3] Web site: http://www.aet.com.sg/technical_notes/technical_notes.html

[4] Arulampalam A. , Barnes M. , Englers A. , Goodwin A. , Jenkins N. , Control of

power electronic interfaces in distributed generation Microgrids

[5] Prabha Kundur : “Power System Stability and control” , The EPRI

Power System Engineering Series, McGraw-Hill, Inc., 1994.

[7] Maxwell M., “Distribution System”, Electric Utility Engineering Reference

Book, Westinghouse Electric Corporation. (for general reading reference)