economic feasibility of co 2 capture retrofits for the library/events/2013/co2...the energy lab...
TRANSCRIPT
the ENERGY lab
Economic Feasibility of CO2 Capture Retrofits for the U.S. Coal Fleet: Impacts of R&D and CO2 EOR Revenue
2013 CO2 Capture Technology Meeting
July 11th, 2013
Michael Matuszewski
Use Picture of Existing Fleet Map
• Determine Economic Feasibility of today’s Carbon Capture Retrofits in an Enhanced Oil Recovery (EOR) market – Capture CO2 and sell for enhanced oil production
• Determine how 2nd generation capture technologies can
improve retrofit economics – Cost to capture CO2 at plant gate
• Assess economic sensitivity to key market variables
– Economic life, dispatch, oil prices
Objectives
* Image from www.clker.com
In a 2nd Generation CO2 Capture Market (2030) with No Carbon Regulations, Compare BAU to Retrofit for EOR
• Database of design and operational details for existing PC units allows extrapolation of CO2 retrofit cost and performance – ~1,350 units comprising 324 GW of nameplate generation
– Capital, operating cost and performance extrapolations
– This analysis evaluates only CO2 capture - no criteria pollutant costs
• 2nd gen capture technology reduces fleet-wide captured costs by ~25% – 2030 projected oil prices ($138/bbl) may further promote capture
– 2nd gen may increase candidate retrofit GW’s five-fold over SOA
• EOR revenue promotes more competitive dispatch – With EOR revenue, CO2 capture may increase dispatch in power markets
– Reasonable CO2 prices ($10-$30/tonne) can eliminate marginal cost increases due to capture
Executive Summary
• By convention, technology evaluations performed on baseline greenfield plant – Conceptual, 550MW greenfield installation – Includes benefits of A-USC Steam cycle
• 2nd generation CO2 capture performance projections based on greenfield plant capture technology contributing to target of $40/tonne captured
• Apply same capture technology to baseline existing plant – Retain existing limitations such as fixed
steam cycle, current heat rate, etc. – Cost of lost power generation – Often requires additional equipment &
effort – Consequently, existing plant cost of
captured is generally >$40/tonne greenfield target (@ constant CF, no EOR)
2nd Generation Projections Overview
New CCS
Existing CCS
• Data on 1,355 individual PC units (324 GW)
• Key information: – Unit ID, Nameplate Capacity, Heatrate, CO2 Emissions,
Capacity Factor
• CO2 Generation Allows Calculation of: – CO2 Captured, Capital Costs, Fixed O&M*, Variable O&M**
• Heatrate and Nameplate Capacity Allow Calculation of: – Post-Retrofit Output, Lost Power Revenue***
• Capacity Factor Allows Calculation of: – Cost of CO2 Captured, Incremental COE/Marginal Costs
Existing Plant Database
*Proportional to TPC ** Proportional to amount of CO2 Captured
***Assuming a market price of electricity
A baseline existing plant is established for conceptual evaluation of retrofitted CO2 technologies on a consistent basis
– Allows evaluation of system-wide effects on power plant
– Isolates net power generation penalty due to CO2 capture retrofit
Baseline Existing Plant
Baseline Existing Plant is equivalent to a subcritical pulverized coal plant without carbon capture, as defined in NETL report “Cost and Performance
Baseline for Fossil Energ y Plants” (Case 9)
* Image from www.clker.com
Technology Comparison • Baseline PC Plant Retrofit (comparison to 2012)
Technology Vintage
Metric 2005* 2012* Example 2nd Gen.
Net Energy Penalty [kWhnet/lb CO2 Captured]
0.181 (+26%)
0.144 0.143 (-1%)
Reference Capital Cost [$/tpd CO2 Capt. @ full load]
$55,400 (-17%)
$66,400 $48,000 (-28%)
Incremental Fixed O&M [$/tpd CO2 Capt. @ full load]
$1,828 (-5%)
$1,926 $1,872 (-2.8%)
Incremental Variable O&M [$/tpd CO2 Capt. @ full load]
$2.59 (-50%)
$5.13 $4.75 (-7%)
CO2 Capture Basis [tpd] 11,216 11,216 11,216
* Based on amine technology
Basis
Technology Comparison • Baseline PC Plant Retrofit (comparison to 2012)
Technology Vintage
Metric 2005* 2012* Example 2nd Gen.
Net Energy Penalty [kWhnet/lb CO2 Captured]
0.181 (+26%)
0.144 0.143 (-1%)
Reference Capital Cost [$/tpd CO2 Capt. @ full load]
$55,400 (-17%)
$66,400 $48,000 (-28%)
Incremental Fixed O&M [$/tpd CO2 Capt. @ full load]
$1,828 (-5%)
$1,926 $1,872 (-2.8%)
Incremental Variable O&M [$/tpd CO2 Capt. @ full load]
$2.59 (-50%)
$5.13 $4.75 (-7%)
CO2 Capture Basis [tpd] 11,216 11,216 11,216
* Based on amine technology
Basis
Not used Evaluated in this
work
Equipment Cost Scaling (2011 dollars)
y = 1359.1x0.6374
y = 1747.4x0.6374
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
0 5,000 10,000 15,000 20,000 25,000 30,000
$100
0
TPD Captured CO2 @ Full Load
CO2 Capture TPC
5B.1 TPC (1 train)
5B.1 TPC (2 trains)
y = 416.03x0.6501
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
$350,000
0 5,000 10,000 15,000 20,000 25,000 30,000
$100
0
TPD Captured CO2 @ Full Load
BoP
y = 1908.7x0.2241
$0
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
$16,000
$18,000
$20,000
0 5,000 10,000 15,000 20,000 25,000 30,000
$100
0
TPD Captured CO2 @ Full Load
Letdown Turbine
y = 109.46x0.6093
y = 143.51x0.6093
$0
$10,000
$20,000
$30,000
$40,000
$50,000
$60,000
$70,000
$80,000
0 5,000 10,000 15,000 20,000 25,000 30,000
$100
0
TPD Captured CO2 @ Full Load
CO2 Compression TPC
5B.2 TPC (1 train)
5B.2 TPC (2 trains)
Reference Reference
Reference Reference
0%
5%
10%
15%
20%
25%
30%
35%
40%
7,000 8,000 9,000 10,000 11,000 12,000 13,000
Pow
er P
enal
ty [%
of o
rigi
nal o
utpu
t]
Pre-Retrofit Heat Rate [BTU/kWh HHV]
Net Output Penalties of CCS Retrofits
PC-2005 Amine
PC-2012 Amine
PC-Sorbent Based
PC-Membrane Based
Ideal Power Penalty
Net Derate Projections*
*As evaluated on baseline existing plant. Does not include balance of plant improvements
Includes: •Regeneration Energy •Capture Electrical •Compression Electrical •Off-design ST Operation
Thermodynamic Advancements
0.184 kWh/lb
0.144 kWh/lb
0.143 kWh/lb
0.113 kWh/lb
0.048 kWh/lb
• Where: – Captured Cost [=] $/tonne
– TOC = Total Overnight Cost [=] $
– CCF = Capital Charge Factor [=] yr-1
– LP = Lost Power [=] MW
– PP = Market Power Price [=] $/MWh
– CF = Capacity Factor [=] (fraction)
– FOM = Fixed O&M [=] $/yr
– VOM = Variable O&M [=] $/yr @ 100% load
– Annual CO2 Captured [=] tonnes/yr
CO2 Captured Cost Metric
CapturedAnnualCOCFVOMFOMCFPPLPTOCCCFstCapturedCo
2
**8760*** +++=
Plant-gate cost to capture CO2 defined as key metric for retrofit evaluation in EOR market.
Cost of lost power generation
0
10
20
30
40
50
60
70
80
20 40 60 80 100 120 140 160 180
CO2 E
OR
Pric
e at
Pow
er P
lant
Gat
e CO
2 Cap
ture
Cos
t ($
/ton
ne)
WTI ($/bbl)
2030 Oil Prices May Support EOR CO2 Prices that are Equal to or Above CO2 Capture Costs
From 2008 to mid-2011, the average annual new contract price for CO2 ($/MSCF) at the Denver City, Texas “hub”, varied between 1.8% and 2.5% of the average annual WTI Crude oil price ($/bbl) in the corresponding years. Expressed in $/tonne, this is 34% to 47% (at standard conditions of 60 ⁰F and 14.7 psia). (The non-averaged contract prices ($/MSCF) varied between 1.4 and 3.3% of the oil price between 2008 and mid-2011.) Source: Chaparral Energy “US CO2 & CO2 EOR Developments” Panel Discussion at CO2 Carbon Management Workshop December 06, 2011. Estimated 100 km pipeline transport cost of $3.65/tonne is subtracted to convert the historical “hub” price to an estimated power plant gate price.
Greenfield 2nd Gen CC
Today’s Coal with CC
Favorable CO2 Prices
Prohibitive CO2 Prices
$138/bbl*
$61
$42
*NEMS Projection
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
$10/tonne CO2
Incremental Marginal Cost Trends Retrofitting SOA CO2 Capture
Retrofit: Increased O&M, lost power revenue
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
0
50
100
150
200
250
300
350
-60 -40 -20 0 20 40 60 80 100
Cum
ulat
ive
Ret
rofit
s (G
W p
re-re
trofit
)
Marginal Costs w/CO2 Revenue [$/MWh]
Pre-Retrofit
Post-Retrofit - no EOR Revenue
Post Retrofit w/CO2 Revenue ($10/tonne)
Post Retrofit w/CO2 Revenue ($30/tonne)
$10/tonne CO2
Incremental Marginal Cost Trends Retrofitting SOA CO2 Capture
Retrofit: Increased O&M, lost power revenue
$30/tonne CO2
Reasonable CO2 revenue supports higher dispatch
But to what level?
-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
Existing CFIncrease to 75% CFIncrease to 85% CF
UnlikelyCO2 Prices
abovehistorical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
Existing CF
Increase to 75% CF
Increase to 85% CF
UnlikelyCO2 Prices
abovehistorical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range
Effect of Dispatch - 2030 Capacity Factor Parameter Sensitivity
*NEMS Projections. Capital costs reflect ~15% premium due to increase in oil prices.
State of the Art
• 30yr CCF • $75/MWh*
power price • $138/bl oil* State
of the Art
32.4GW (top decile)
-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
Existing CF
Increase to 75% CF
Increase to 85% CF
UnlikelyCO2 Prices
abovehistorical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
Existing CFIncrease to 75% CFIncrease to 85% CF
UnlikelyCO2 Prices
abovehistorical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range
Effect of Dispatch - 2030 Capacity Factor Parameter Sensitivity
*NEMS Projections. Capital costs reflect ~15% premium due to increase in oil prices.
State of the Art
• 30yr CCF • $75/MWh*
power price • $138/bbl oil* State
of the Art
2nd
Gen
~24% decrease in top decile CO2 price
2nd Generation
Unlikely
CO2 Pricesabove
historical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range
Note shift from EOR revenues @ $100/bbl
In 2030, 2nd gen capture could saturate EOR market
32.4GW (top decile)
-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
30yr
20yr
10yrUnlikely
CO2 Pricesabove
historical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
30yr
20yr
10yr
UnlikelyCO2 Prices
abovehistorical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range
Effect of Capital Recovery Period - 2030 Capital Charge Factor Parameter Sensitivity
State of the Art
• 85% CF • $75/MWh
power price • $138/bbl oil
State of the Art
32.4GW (top decile)
-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
30yr
20yr
10yr
UnlikelyCO2 Prices
abovehistorical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range-50
0
50
100
150
200
250
300
350
0 10 20 30 40 50 60 70 80 90
Cum
ulat
ive
Ret
rofit
s In
cent
iviz
ed (G
W p
re-re
trofit
)
Minimum Plant Gate CO2 EOR Revenue Required to Incentivize CCS ($/tonne)
30yr
20yr
10yrUnlikely
CO2 Pricesabove
historical range
PossibleCO2 Prices
withinhistorical range
ProbableCO2 Prices
belowhistorical range
Effect of Capital Recovery Period - 2030 Capital Charge Factor Parameter Sensitivity
State of the Art
• 85% CF • $75/MWh
power price • $138/bbl oil
State of the Art
~27% decrease in top decile CO2 price
2nd Generation
2nd Gen
32.4GW (top decile)
Short-term (10yr) investment viewpoints reduce viability by ~90%!
• In 2030, SOA technology promotes 0-45GW of economic retrofits*
• 2nd gen improvements increase potential up to five-fold (25-215GW)* – CO2 contract price relationship to price of WTI crude
• EOR market while limited in size, is an excellent transition step for proving out carbon capture and reducing risk for future installations
• Still need help for “slam dunk” EOR scenario – Need CO2 capture R&D success!
– Dispatch is essential – and likely achievable
– Regulatory drivers encouraging CO2 capture should also support a long-term (30yr) investment viewpoint
• EOR revenue will offset lost power revenue, reducing marginal costs – $10/tonne nearly offsets marginal cost increases for entire fleet
– $30/tonne eliminates marginal costs (≤$0/MWh) for ~150GW
Conclusions Compared cost of CO2 retrofits to minimum CO2 price in EOR market
Bounding scenario: Calculations indicate best case for BAU vs. retrofit
*Range dictated by capital recovery period range (10-30yrs) assuming fleet-wide CF increase to 85%
• NETL – John Wimer – Project Guidance
– Kristin Gerdes – Sensitivity Analyses
– Robert Stevens – 2nd Gen Technology Projections
• Booz Allen Hamilton – Vince Chou – Cost and Performance Extrapolation
• Leonardo Technologies Inc. – Massood Ramezan – Project Guidance
– Connie Zaremsky – Database Management
– Eric Lopert – Data Generation
Acknowledgements