ecosystem services and peatland restoration · 2018-05-16 · bare peat - ~ 500 ha of 2900 ha...
TRANSCRIPT
![Page 1: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/1.jpg)
Paul Leadbitter, Programme Manager
Paul Leadbitter, Peatland Programme Manager
Ecosystem Services and Peatland Restoration
Pennine PeatLIFELIFE16 NAT/UK/000725
![Page 2: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/2.jpg)
Ecosystem Services
• Aka green services, green infrastructure. etc.• Not a new concept.• Plato referenced ES in 400 BC.• Concept developed momentum from 1950’s
until Millennium Ecosystem and TEEB report.
![Page 3: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/3.jpg)
Ecosystem Services
![Page 4: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/4.jpg)
Evolution of ES and Peatlands in North Pennines AONB
• North Pennines Peatland Programme started in 2006 known as Peatscapes.
• Seed funding was from Environment Agency based on water quality and quantity.
• Was to be a ‘hearts and minds’ project.• It has evolved into a decade long programme
based on peatland ecosystem services.• Why?• How?
![Page 5: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/5.jpg)
![Page 6: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/6.jpg)
• 100,000 ha of peat• 61,000 ha of SSSI• 30% of England’s Blanket Bog• England’s largest Blanket Bog• Average depth 200 cm• 60% in degraded state
North Pennines AONB Peatlands
![Page 7: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/7.jpg)
Where to start?
• Identify the resource.• Identify threats.• What do we know?• What don’t we know?• Map.• Quantify.• Prioritise.• Promote.• Fund.• Restore.
• Repeat.
![Page 8: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/8.jpg)
Why is Peat Important?
BiodiversityFloodingWater ColourSediment LoadingCarbon Store/Sink Historical Record
![Page 9: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/9.jpg)
Threats• Drainage • Burning• Grazing• Tracks• Wind Farms• Climate Change
![Page 10: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/10.jpg)
North Pennines AONB Peatlands
• AONB wide survey completed for drains and damaged peat completed
![Page 11: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/11.jpg)
• 10,000 km of ditches
![Page 12: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/12.jpg)
• 2900 ha of eroding peat
• Overwhelming evidence of significant damage to blanket bog and their ecosystem services
• 10,000 km of ditches
![Page 13: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/13.jpg)
![Page 14: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/14.jpg)
![Page 15: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/15.jpg)
Why is Peat Important?
BiodiversityFloodingWater ColourSediment LoadingCarbon Store/Sink Historical Record
![Page 16: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/16.jpg)
ES - Flooding and Water Colour
![Page 17: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/17.jpg)
Grips and bare peat areas are related to increased flooding and an increase in water colour.
Grip blocking - to date ~ 9000 km of the 10,000 km blocked.1) At some scales grip blocking smooths out flows compared to unblocked grips.2) Blocking slowed the flow out of blocked grips vs unblocked grips.3)There are no significant differences in DOC between blocked and open grips.
Bare Peat - ~ 500 ha of 2900 ha restored1) Overland flow has a significantly faster velocity when passing over bare peat compared to vegetated peat. Sphagnum mosses were found to be the most efficient vegetation type to slow the movement of water by increasing “surface roughness” (Holden et al., 2008). 2) Bare peat restoration can reduce DOC.
Can we derive a £, € or $ value for this? Is this a silver bullet?
Site level ES evaluation is complicated.
Solution = Restoration
![Page 18: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/18.jpg)
![Page 19: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/19.jpg)
![Page 20: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/20.jpg)
ES - Carbon
![Page 21: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/21.jpg)
How much Carbon Is There?
Peat (ha) T/ha Carbon CO2
90,000 500 45,000,000 164,700,000
90,000 1,000 90,000,000 329,400,000
90,000 1,500 135,000,000 494,100,000
We are still not sure yet.
![Page 22: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/22.jpg)
• NPAP lead on a National Peat Carbon project.
• 10,000s of peat depth points from across England.
• Used GIS to develop a model to predict carbon amount.
• Model is being refined.
![Page 23: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/23.jpg)
UK currently emits 3 million tonnes of peat CO2 per year
£282,000,000 of carbon damage/avoided costs per year
Each tonne of CO2 released = £34 of ‘carbon damage’ Each tonne costs £60 to recover
Each tonne kept in peat saves £94
~£100,000,000 has been spent on peat restoration since 2000*
Defra – ‘Peat Restoration is beneficial for Climate Change’
![Page 24: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/24.jpg)
![Page 25: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/25.jpg)
![Page 26: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/26.jpg)
ES - Historic Environment
![Page 27: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/27.jpg)
Pennine PeatLIFELIFE16 NAT/UK/000725
![Page 28: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/28.jpg)
The aim of the Pennine PeatLIFE project is to demonstrate and evaluate Blanket Bog (*7130) restoration techniques suited to northern England and the development and showcasing of a financial payment for ecosystem services (PES) mechanism in the UK Peatland Code.
Pennine PeatLIFE objectives:
1. Demonstrating financially viable region-specific and sustainable Sphagnum based restoration techniques for re-activating 1353 ha of blanket bog in northern England.
2. Demonstrating through ‘Concept to Contract’ trials, the UK Peatland Code, as a viable payment for ecosystem services for upland peatlands.
3. Demonstrating new approaches using Unmanned Aerial Vehicles (UAV) to assess vegetation change as a proxy measure for monitoring change in ecosystem services benefits of blanket bog undergoing restoration and as a validation tool for the UK Peatland Code.
4. Disseminating the demonstration activities to policy makers, landowners and managers, government agencies, NGOs, and other key stakeholders in the UK and across the EU.
![Page 29: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/29.jpg)
Expected Results
1. 1353 ha of blanket bog (*7130) restored;2. Avoided losses of 26 000 t/C02, plus 1 327.5 t/C02 sequestered after five years;3. Wider stakeholder awareness as to the importance of peatlands;4. A better methodology for the use of UAVs in restoration monitoring;5. Detailed assessment of a PES mechanism - UK Peatland Code;6. A UK and EU wide increase in the awareness of the UK Peatland Code;7. Development of a legally binding contract for PES;
![Page 30: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/30.jpg)
Conclusions
• Biodiversity is best.• ES are different at different scales.• ES are difficult to monetise.• ES come and go in importance.• Bundling ES is effective.• Look for low hanging fruit• Need to keep pushing the ES agenda.
![Page 31: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/31.jpg)
• ES priorities are different for different sectors agencies, funders and decision makers.
• Quantifying exact benefits is difficult – i.e. €1 spent on restoration gives € 1.50 in benefits.
• Bundling of benefits can work.• Ethics still problematic?• To date most funding (~€ 12 million) has come
from biodiversity and flooding pots with the acknowledgement that other benefits come with these.
Conclusions
![Page 32: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/32.jpg)
The UK Peatland Code
From ‘Concept to Contract’
A reminder: Why are Peatlands Important?
BiodiversityWater ColourWater SupplyFloodingSediment LoadingCarbon Historical RecordEconomy
€1.50 Flooding?
What is Blanket Bog worth?
€4.00 Carbon Store?
€3.20 Biodiversity?
€1.65 Sediment?
€0.65 Water Colour?
![Page 33: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/33.jpg)
Paul Leadbitter, Programme Manager
Paul Leadbitter, Peatland Programme Manager
Pennine PeatLIFELIFE16 NAT/UK/000725
![Page 34: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/34.jpg)
Thank YouLIFE Programme
Yorkshire Water
Northumbrian Water
United Utilities
Environment Agency
![Page 35: Ecosystem Services and Peatland Restoration · 2018-05-16 · Bare Peat - ~ 500 ha of 2900 ha restored 1) Overland flow has a significantly faster velocity when passing over bare](https://reader034.vdocument.in/reader034/viewer/2022042409/5f25aae362ce595a554644ca/html5/thumbnails/35.jpg)
NAME TITLE ORGANISATION E MAIL ADDRESS
Paul Leadbitter Peatland Programme Manager North Pennines AONB Partnership [email protected]
Tim Thom Peatland Programme Manager Yorkshire Wildlife Trust [email protected]
Elliott Lorimer Principal Officer Forest of Bowland AONB [email protected]
Emma Taylor Field Officer North Pennines AONB Partnership [email protected]
Alistair Lockett Field Officer North Pennines AONB Partnership [email protected]
Christopher Miller Peatland Restoration Officer Yorkshire Wildlife Trust [email protected]
Jenny Sharman Peatland Restoration Officer Yorkshire Wildlife Trust [email protected]
Mark Brown GIS & Remote Sensing Officer Yorkshire Wildlife Trust [email protected]
Joanna Richards Communications Manager IUCN UK Peatland Programme [email protected]
Christopher Osborne Earth Observation Officer Yorkshire Peat Partnership [email protected]
Lyndon Marquis Communications Officer Yorkshire Wildlife Trust [email protected]
Sylvia Cleasby Admin. Assistant North Pennines AONB Partnership [email protected]
Christopher Watt Peatland Conservation Trainee North Pennines AONB Partnership [email protected]
Pennine PeatLIFE Team