edinburgh waverley – capacity upgrade€¦ · edinburgh waverley – capacity upgrade as part of...

7
Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains and to prepare for projected future growth in demand for both track and capacity, a series of infrastructure works will be required within and around Edinburgh Waverley.

Upload: others

Post on 26-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

Edinburgh Waverley – capacity upgrade

As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains and to prepare for projected future growth in demand for both track and capacity, a series of infrastructure works will be required within and around Edinburgh Waverley.

Page 2: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

There are two programmes underway to enable the introduction of these longer trains, the Edinburgh Glasgow Improvement Programme (EGIP) and the Intercity Express Programme (IEP).

EGIP is a comprehensive package of improvements to Scotland’s railway infrastructure. A Scottish Government priority, EGIP is being delivered by Network Rail and includes modernisation and upgrades to key junctions and infrastructure as well as widespread electrification of the Scottish rail network.

IEP is a Department for Transport led initiative to procure new trains to replace the existing rolling stock on the East Coast Mainline and Great Western Mainline.

The EGIP team will deliver both EGIP and IEP’s requirements for Waverley.

We need to extend platforms at Edinburgh Waverley to accommodate longer trains being introduced on both the Edinburgh to Glasgow via Falkirk (E&G) route and the East Coast Main Line (ECML).

Page 3: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

April 2017

Preparatory works commence ahead of excavation for

platform 12

May/June 2017

Excavation for platforms 5/6

begins

December 2018

Commissioning of platform 10/11

crossover

July 2018Completion of platforms 5/6

December 2017

Completion of platform 12

May 2017

Excavation for platform 12 extension

begins

Timeline

Page 4: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

05

12

06

Way outPrinces Street

Way outWaverley Bridge

Way outWaverley Bridge

Way outCalton Road

Way outMarket Street

13

08

09

10

11

15

14

16

17

19

2018

02

01

03

04

07

0809

Extension of platforms 5 and 6

Escalators repositioned from the south west corner of the concourse

Extension of platform 12

A1

Do not scale

A B C D E F G H I J K L M N

1

2

3

4

5

6

7

8

9

10

O P

Rev Date By Chkd Appd

Client Project Title

© Arup

Scale at A1

Suitability

Name

Arup Job No

Role

Rev

Drawing Title

ARP-01-00-VS-CS-0001

-251762-00

Civil/Structures

Not to Scale

DraftProposed Escalator RelocationVisualisations

Edinburgh Waverley Platform Extensions

Carillion

Scotstoun House, South QueensferryWest Lothian, EH30 9SET +44(0)131 331 1999 F +44(0)131331 3730www.arup.com

\\glo

bal\e

urop

e\E

dinb

urgh

\Job

s\25

0000

\251

000\

2517

62-0

0\04

DE

LIV

ER

AB

LES

\4-0

3 D

raw

ings

\4-0

3-02

Brid

ge\A

RP

-01-

00-V

S-C

S-0

001.

dwg

11 N

ov 2

016

17:1

1:40

View 1 - Outside WH Smiths looking South East

View 3 - South Ramp Looking East View 4 - Platform 10 Looking North East

View 1 - Outside WH Smiths looking towards Platform 10

Created using CADplot http://www.oasys-

software.com/cadplot/

A1

Do not scale

A B C D E F G H I J K L M N

1

2

3

4

5

6

7

8

9

10

O P

Rev Date By Chkd Appd

Client Project Title

© Arup

Scale at A1

Suitability

Name

Arup Job No

Role

Rev

Drawing Title

ARP-01-00-VS-CS-0001

-251762-00

Civil/Structures

Not to Scale

DraftProposed Escalator RelocationVisualisations

Edinburgh Waverley Platform Extensions

Carillion

Scotstoun House, South QueensferryWest Lothian, EH30 9SET +44(0)131 331 1999 F +44(0)131331 3730www.arup.com

\\glo

bal\e

urop

e\E

dinb

urgh

\Job

s\25

0000

\251

000\

2517

62-0

0\04

DE

LIV

ER

AB

LES

\4-0

3 D

raw

ings

\4-0

3-02

Brid

ge\A

RP

-01-

00-V

S-C

S-0

001.

dwg

11 N

ov 2

016

17:1

1:40

View 1 - Outside WH Smiths looking South East

View 3 - South Ramp Looking East View 4 - Platform 10 Looking North East

View 1 - Outside WH Smiths looking towards Platform 10

Created using CADplot http://www.oasys-

software.com/cadplot/

A1

Do not scale

A B C D E F G H I J K L M N

1

2

3

4

5

6

7

8

9

10

O P

Rev Date By Chkd Appd

Client Project Title

© Arup

Scale at A1

Suitability

Name

Arup Job No

Role

Rev

Drawing Title

ARP-01-00-VS-CS-0001

-251762-00

Civil/Structures

Not to Scale

DraftProposed Escalator RelocationVisualisations

Edinburgh Waverley Platform Extensions

Carillion

Scotstoun House, South QueensferryWest Lothian, EH30 9SET +44(0)131 331 1999 F +44(0)131331 3730www.arup.com

\\glo

bal\e

urop

e\E

dinb

urgh

\Job

s\25

0000

\251

000\

2517

62-0

0\04

DE

LIV

ER

AB

LES

\4-0

3 D

raw

ings

\4-0

3-02

Brid

ge\A

RP

-01-

00-V

S-C

S-0

001.

dwg

11 N

ov 2

016

17:1

1:40

View 1 - Outside WH Smiths looking South East

View 3 - South Ramp Looking East View 4 - Platform 10 Looking North East

View 1 - Outside WH Smiths looking towards Platform 10

Created using CADplot http://www.oasys-

software.com/cadplot/

Page 5: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

What’s happening?• A number of existing platforms will

be extended (platforms 5, 6 and 12) creating new long length platforms

• A crossover – a piece of track which enables trains to move from one track to another – will be created to improve flexibility to platforms 10/11

• The extension of platform 12 will require the repositioning of the escalators on the South West corner of the concourse

• The demolition of the buildings on platform 11 to enable the extension of platform 12 and additionally serves to open up a separate area of concourse for pedestrian circulation

What it delivers• This project is about creating platforms

of suitable length to facilitate the safe operation of longer trains, improving the capacity of the route as well as journey times

• Extensions to platforms 5 & 6 are required to accommodate 10-car IEP services on East Coast routes (extended to 275m)

• Extension to platform 12 is required to accommodate 8 car services on Edinburgh to Glasgow line via Falkirk High (extended to 204m)

• In addition to the platform extensions, we will undertake work on the tracks to increase flexibility on approaches to the station from the east

• We are installing a crossover between platforms 10 and 11 which also improves operational flexibility at the station

Page 6: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

• Waverley station opened in 1846 and was rebuilt between 1892 and 1902

• Waverley station was originally the site of three railway stations. North Bridge Station, General Station and Canal Street Station were not fully integrated into Waverley Station until 1898

• The station is also located on the former bed of the Nor Loch which was drained in 1763

• Edinburgh Waverley is Scotland’s second busiest railway station with a footfall of 28m

• Waverley has the second largest station footprint in Great Britain (23 acres)

• It has 20 platforms which support circa. 900 train movements per day

• The station’s roof is 34,000m² and is made up of around 28,000 clear glass panels

• There is a 40ft ascent into the station via Waverley Steps

Edinburgh Waverley: fast facts

Page 7: Edinburgh Waverley – capacity upgrade€¦ · Edinburgh Waverley – capacity upgrade As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains

Q&A

ContactFor the latest information on the platform extensions at Edinburgh Waverley, please visit the Edinburgh Glasgow Improvement Programme website, follow us on Twitter, or contact us via post or email.

Web www.egip.infoEmail [email protected] Tel 03457 11 41 41

Edinburgh Glasgow Improvement Programme (EGIP)Network Rail151 St Vincent StreetGlasgowG2 5NW

Why are the platforms being extended?The platforms are being extended to facilitate the safe operation of eight carriage trains (platform 12) and ten carriage trains (platforms 5/6), improving the capacity of the route.

When will the works be delivered?Advance works commenced in 2016 with main works beginning in April 2017. Platform 12 is due to be completed in December 2017 whilst platforms 5/6 are due to be completed in July 2018. A new crossover at platforms 10/11 will be commissioned by December 2018.

How will this affect the passenger experience at Edinburgh Waverley?The work will be delivered in a way which minimises disruption for station users. Station users with a disability, and who require help around the station, can call 0845 722 5225 for additional assistance.

Why do you work at night?The works at Waverley station will be undertaken 24/7. It is safer for our staff and contractors to deliver work when trains are not running. We are regulated to work in a way that minimises impact on train services.