edinburgh waverley – capacity upgrade€¦ · edinburgh waverley – capacity upgrade as part of...
TRANSCRIPT
Edinburgh Waverley – capacity upgrade
As part of our rail upgrade plan, and in order to facilitate the introduction of longer trains and to prepare for projected future growth in demand for both track and capacity, a series of infrastructure works will be required within and around Edinburgh Waverley.
There are two programmes underway to enable the introduction of these longer trains, the Edinburgh Glasgow Improvement Programme (EGIP) and the Intercity Express Programme (IEP).
EGIP is a comprehensive package of improvements to Scotland’s railway infrastructure. A Scottish Government priority, EGIP is being delivered by Network Rail and includes modernisation and upgrades to key junctions and infrastructure as well as widespread electrification of the Scottish rail network.
IEP is a Department for Transport led initiative to procure new trains to replace the existing rolling stock on the East Coast Mainline and Great Western Mainline.
The EGIP team will deliver both EGIP and IEP’s requirements for Waverley.
We need to extend platforms at Edinburgh Waverley to accommodate longer trains being introduced on both the Edinburgh to Glasgow via Falkirk (E&G) route and the East Coast Main Line (ECML).
April 2017
Preparatory works commence ahead of excavation for
platform 12
May/June 2017
Excavation for platforms 5/6
begins
December 2018
Commissioning of platform 10/11
crossover
July 2018Completion of platforms 5/6
December 2017
Completion of platform 12
May 2017
Excavation for platform 12 extension
begins
Timeline
05
12
06
Way outPrinces Street
Way outWaverley Bridge
Way outWaverley Bridge
Way outCalton Road
Way outMarket Street
13
08
09
10
11
15
14
16
17
19
2018
02
01
03
04
07
0809
Extension of platforms 5 and 6
Escalators repositioned from the south west corner of the concourse
Extension of platform 12
A1
Do not scale
A B C D E F G H I J K L M N
1
2
3
4
5
6
7
8
9
10
O P
Rev Date By Chkd Appd
Client Project Title
© Arup
Scale at A1
Suitability
Name
Arup Job No
Role
Rev
Drawing Title
ARP-01-00-VS-CS-0001
-251762-00
Civil/Structures
Not to Scale
DraftProposed Escalator RelocationVisualisations
Edinburgh Waverley Platform Extensions
Carillion
Scotstoun House, South QueensferryWest Lothian, EH30 9SET +44(0)131 331 1999 F +44(0)131331 3730www.arup.com
\\glo
bal\e
urop
e\E
dinb
urgh
\Job
s\25
0000
\251
000\
2517
62-0
0\04
DE
LIV
ER
AB
LES
\4-0
3 D
raw
ings
\4-0
3-02
Brid
ge\A
RP
-01-
00-V
S-C
S-0
001.
dwg
11 N
ov 2
016
17:1
1:40
View 1 - Outside WH Smiths looking South East
View 3 - South Ramp Looking East View 4 - Platform 10 Looking North East
View 1 - Outside WH Smiths looking towards Platform 10
Created using CADplot http://www.oasys-
software.com/cadplot/
A1
Do not scale
A B C D E F G H I J K L M N
1
2
3
4
5
6
7
8
9
10
O P
Rev Date By Chkd Appd
Client Project Title
© Arup
Scale at A1
Suitability
Name
Arup Job No
Role
Rev
Drawing Title
ARP-01-00-VS-CS-0001
-251762-00
Civil/Structures
Not to Scale
DraftProposed Escalator RelocationVisualisations
Edinburgh Waverley Platform Extensions
Carillion
Scotstoun House, South QueensferryWest Lothian, EH30 9SET +44(0)131 331 1999 F +44(0)131331 3730www.arup.com
\\glo
bal\e
urop
e\E
dinb
urgh
\Job
s\25
0000
\251
000\
2517
62-0
0\04
DE
LIV
ER
AB
LES
\4-0
3 D
raw
ings
\4-0
3-02
Brid
ge\A
RP
-01-
00-V
S-C
S-0
001.
dwg
11 N
ov 2
016
17:1
1:40
View 1 - Outside WH Smiths looking South East
View 3 - South Ramp Looking East View 4 - Platform 10 Looking North East
View 1 - Outside WH Smiths looking towards Platform 10
Created using CADplot http://www.oasys-
software.com/cadplot/
A1
Do not scale
A B C D E F G H I J K L M N
1
2
3
4
5
6
7
8
9
10
O P
Rev Date By Chkd Appd
Client Project Title
© Arup
Scale at A1
Suitability
Name
Arup Job No
Role
Rev
Drawing Title
ARP-01-00-VS-CS-0001
-251762-00
Civil/Structures
Not to Scale
DraftProposed Escalator RelocationVisualisations
Edinburgh Waverley Platform Extensions
Carillion
Scotstoun House, South QueensferryWest Lothian, EH30 9SET +44(0)131 331 1999 F +44(0)131331 3730www.arup.com
\\glo
bal\e
urop
e\E
dinb
urgh
\Job
s\25
0000
\251
000\
2517
62-0
0\04
DE
LIV
ER
AB
LES
\4-0
3 D
raw
ings
\4-0
3-02
Brid
ge\A
RP
-01-
00-V
S-C
S-0
001.
dwg
11 N
ov 2
016
17:1
1:40
View 1 - Outside WH Smiths looking South East
View 3 - South Ramp Looking East View 4 - Platform 10 Looking North East
View 1 - Outside WH Smiths looking towards Platform 10
Created using CADplot http://www.oasys-
software.com/cadplot/
What’s happening?• A number of existing platforms will
be extended (platforms 5, 6 and 12) creating new long length platforms
• A crossover – a piece of track which enables trains to move from one track to another – will be created to improve flexibility to platforms 10/11
• The extension of platform 12 will require the repositioning of the escalators on the South West corner of the concourse
• The demolition of the buildings on platform 11 to enable the extension of platform 12 and additionally serves to open up a separate area of concourse for pedestrian circulation
What it delivers• This project is about creating platforms
of suitable length to facilitate the safe operation of longer trains, improving the capacity of the route as well as journey times
• Extensions to platforms 5 & 6 are required to accommodate 10-car IEP services on East Coast routes (extended to 275m)
• Extension to platform 12 is required to accommodate 8 car services on Edinburgh to Glasgow line via Falkirk High (extended to 204m)
• In addition to the platform extensions, we will undertake work on the tracks to increase flexibility on approaches to the station from the east
• We are installing a crossover between platforms 10 and 11 which also improves operational flexibility at the station
• Waverley station opened in 1846 and was rebuilt between 1892 and 1902
• Waverley station was originally the site of three railway stations. North Bridge Station, General Station and Canal Street Station were not fully integrated into Waverley Station until 1898
• The station is also located on the former bed of the Nor Loch which was drained in 1763
• Edinburgh Waverley is Scotland’s second busiest railway station with a footfall of 28m
• Waverley has the second largest station footprint in Great Britain (23 acres)
• It has 20 platforms which support circa. 900 train movements per day
• The station’s roof is 34,000m² and is made up of around 28,000 clear glass panels
• There is a 40ft ascent into the station via Waverley Steps
Edinburgh Waverley: fast facts
Q&A
ContactFor the latest information on the platform extensions at Edinburgh Waverley, please visit the Edinburgh Glasgow Improvement Programme website, follow us on Twitter, or contact us via post or email.
Web www.egip.infoEmail [email protected] Tel 03457 11 41 41
Edinburgh Glasgow Improvement Programme (EGIP)Network Rail151 St Vincent StreetGlasgowG2 5NW
Why are the platforms being extended?The platforms are being extended to facilitate the safe operation of eight carriage trains (platform 12) and ten carriage trains (platforms 5/6), improving the capacity of the route.
When will the works be delivered?Advance works commenced in 2016 with main works beginning in April 2017. Platform 12 is due to be completed in December 2017 whilst platforms 5/6 are due to be completed in July 2018. A new crossover at platforms 10/11 will be commissioned by December 2018.
How will this affect the passenger experience at Edinburgh Waverley?The work will be delivered in a way which minimises disruption for station users. Station users with a disability, and who require help around the station, can call 0845 722 5225 for additional assistance.
Why do you work at night?The works at Waverley station will be undertaken 24/7. It is safer for our staff and contractors to deliver work when trains are not running. We are regulated to work in a way that minimises impact on train services.