ee353 notes no. 2 - lole&loee
DESCRIPTION
LOLE AND LOEE reliabilitiesTRANSCRIPT
-
Department of Electrical and Electronics Engineering University of the Philippines - Diliman
EE 353 - Power System Reliability
Reliability of Generation SystemGenerating Capacity LOLE & LOEE
Prof. Rowaldo R. del Mundo
-
University of the Philippines
Department of Electrical and Electronics Engineering 2Prof. Rowaldo R. del Mundo
Conceptual Task & Generation System Representation
G LTotal System Generation Total System Load
Generation Model
Load Model
Risk Model
-
University of the Philippines
Department of Electrical and Electronics Engineering 3Prof. Rowaldo R. del Mundo
Generating UnitForced Outage Rate
If the hazard rate of a generating unit is constant
The failure density function is exponential
( ) =th
( ) ( ) ( )= t
0dh
ethtf
=
t
0d
e
( ) tetf =
-
University of the Philippines
Department of Electrical and Electronics Engineering 4Prof. Rowaldo R. del Mundo
Generating Unit Forced Outage Rate
The cumulative failure distribution function is
Then, the reliability function is
( ) ( ) == t0t
0dedftF
[ ]0tt0
eee
==
( ) = e1tF
( ) ( )tF1tR =[ ]te11 =
( ) tetR =
-
University of the Philippines
Department of Electrical and Electronics Engineering 5Prof. Rowaldo R. del Mundo
Generating Unit Forced Outage Rate
The mean-time-to-failure is
( )= 0 dttRMTTF
[ ]=0
te
1
m1MTTF == (mean up time)
=0
tdte
[ ]0ee1 =
-
University of the Philippines
Department of Electrical and Electronics Engineering 6Prof. Rowaldo R. del Mundo
Generating Unit Forced Outage Rate
Also, if the repair rate function is constant
the mean-time-to-repair is
The mean-time-between-failures
and the cycle frequency is
( ) =tr
rMTTR ==1 (mean repair time)
timerepairmeanuptimemeanMTBF +=MTTRMTTF +=
TrmMTBF =+=
T1f =
-
University of the Philippines
Department of Electrical and Electronics Engineering 7Prof. Rowaldo R. del Mundo
Generating Unit Forced Outage Rate
The Availability is the steady-state or long term probability that the generating unit is in operating condition (UP state)
time cycletime up meanA =
f
Tm
==A
+
=
+=
rm
mA
[ ][ ] [ ]
+
=
time uptime downtime up
A
time repair mean time up meantime up meanA
+=
-
University of the Philippines
Department of Electrical and Electronics Engineering 8Prof. Rowaldo R. del Mundo
Generating Unit Forced Outage Rate
The Unavailability of a generating unit is the probability of finding a unit on forced outage at some future time. This is technically termed as Forced Outage Rate or FOR.
f
TrU ==
+
=
+=
rm
rU
[ ][ ] [ ]
+=
time uptime downtime down
U
tyAvailabili1U =
-
University of the Philippines
Department of Electrical and Electronics Engineering 9Prof. Rowaldo R. del Mundo
Markov Modelsof Generation System
Up
Down
Single Generating Unit
State Generator Rate ofDepartureRate ofEntry
1 UP 2 DOWN
-
University of the Philippines
Department of Electrical and Electronics Engineering 10Prof. Rowaldo R. del Mundo
Markov Models of Generation System
Two Generating Units
2
4
3
1
State Gen 1 Gen 2 Rate ofDepartureRate ofEntry
1 UP UP 1 + 2 1 + 22 DOWN UP 1 + 2 1 + 23 UP DOWN 1 + 2 1 + 24 DOWN DOWN 1 + 2 1 + 2
-
University of the Philippines
Department of Electrical and Electronics Engineering 11Prof. Rowaldo R. del Mundo
Generating Capacity Model
(Capacity Outage Probability Table)
A. IDENTICAL UNITSFor identical units, binomial distribution is applicable. The probability of exactly r successes in n trials is
( ) ( )rnr
r p1p!rn!r!nP
=
-
University of the Philippines
Department of Electrical and Electronics Engineering 12Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE 1:2 10 MW units each with 0.03 forced outage rate
0.970.03-1p 2n ===
( ) ( ) ( ) 0009.097.0197.0!02!0!2P 0200 =
=
( ) ( ) ( ) 0582.097.0197.0!12!1!2P 1211 =
=
( ) ( ) ( ) 9409.097.0197.0!22!2!2P 2222 =
=
(probability that exactly two generating unit are available)
(probability that no generating unit is available)
(probability that exactly one generating unit is available)
-
University of the Philippines
Department of Electrical and Electronics Engineering 13Prof. Rowaldo R. del Mundo
Generating Capacity Model
The capacity outage table is summarized as follows:Units Out Capacity Out Capacity Available Probability
0 0 MW 20 MW 0.94091 10 MW 10 MW 0.05822 20 MW 0 MW 0.0009
1.0000
Note: The probability of all possible cases must sum to unity
-
University of the Philippines
Department of Electrical and Electronics Engineering 14Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE 2:3 5 MW units each with 0.03 forced outage rate
0.970.03-1p 3n ===
( ) ( ) ( ) 000027.097.0197.0!03!0!3P 0300 =
=
( ) ( ) ( ) 002619.097.0197.0!13!1!3P 1311 =
=
( ) ( ) ( ) 084681.097.0197.0!23!2!3P 2322 =
=
( ) ( ) ( ) 912673.097.0197.0!33!3!3P 3333 =
=
-
University of the Philippines
Department of Electrical and Electronics Engineering 15Prof. Rowaldo R. del Mundo
Generating Capacity Model
The capacity outage table is summarized as follows:Units Out Capacity Out Capacity Available Probability
0 0 MW 15 MW 0.9126731 5 MW 10 MW 0.0846812 10 MW 5 MW 0.0026193 15 MW 0 MW 0.000027
1.000000
-
University of the Philippines
Department of Electrical and Electronics Engineering 16Prof. Rowaldo R. del Mundo
Generating Capacity Model
For units with 0.03 forced outage rate313 - 4
Units Out Capacity Out Capacity Available Probability0 0.00 MW 13.33 MW 0.885292811 3.33 MW 10.00 MW 0.109520762 6.66 MW 6.66 MW 0.005080863 10.00 MW 3.33 MW 0.000104764 13.33 MW 0.00 MW 0.00000081
1.000000
-
University of the Philippines
Department of Electrical and Electronics Engineering 17Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE:A system consist of two 3 MW units and one 5 MWunit each with forced outage rate of 0.02.
State Gen. 1 Gen. 2 Gen. 3 Capacity In Capacity Out1 UP UP UP 3+3+5 = 11 MW 0 MW2 DOWN UP UP 0+3+5 = 8 MW 3 MW3 UP DOWN UP 3+0+5 = 8 MW 3 MW4 UP UP DOWN 3+3+0 = 6 MW 5 MW5 DOWN DOWN UP 0+0+5 = 5 MW 6 MW6 UP DOWN DOWN 3+0+0 = 3 MW 8 MW7 DOWN UP DOWN 0+3+0 = 3 MW 8 MW8 DOWN DOWN DOWN 0+0+0 = 0 MW 11 MW
Markov Transition States (23 = 8)`
B. NON-IDENTICAL UNITS Binomial distribution is not applicable Basic probability concepts can be applied
-
University of the Philippines
Department of Electrical and Electronics Engineering 18Prof. Rowaldo R. del Mundo
Generating Capacity Model
Note: The probability of exactly 3 MW is out of service is the sum of the probabilities of states 2 and 3. Similarly, the probability of exactly 8 MW is out of service is the sum of the probabilities of states 6and 7. Therefore states 2 and 3 can be combined and states 6 and 7 can be combined to come up with the reduced states capacity probability table.
New State Capacity In Capacity Out Probability1 11 MW 0 P12 8 MW 3 P2 + P33 6 MW 5 P44 5 MW 6 P55 3 MW 8 P6 + P76 0 MW 11 P8
-
University of the Philippines
Department of Electrical and Electronics Engineering 19Prof. Rowaldo R. del Mundo
Generating Capacity Model
Step 1: Combine the two identical units(binomial distribution may be applied)
Step 2: Add the 5 MW units considering that it can exist in two state (in service or out of service)
Capacity Out Capacity In Probability0 MW 6 MW 0.96043 MW 3 MW 0.03926 MW 0 MW 0.0004
1.0000
02.0P98.0 P
serviceof out
servicein
=
=
-
University of the Philippines
Department of Electrical and Electronics Engineering 20Prof. Rowaldo R. del Mundo
Generating Capacity Model
Step 2a: 5 MW unit in service
Step 2b: 5 MW unit out of service
0 + 0 = 0 MW 6 + 5 = 11 MW ( 0.9604 ) ( 0.98 ) = 0.9411923 + 0 = 3 MW 3 + 5 = 8 MW ( 0.0392 ) ( 0.98 ) = 0.0384166 + 0 = 6 MW 0 + 5 = 5 MW ( 0.0004 ) ( 0.98 ) = 0.000392
0.980000
Capacity Out Capacity In Probability
0 + 5 = 5 MW 6 + 0 = 6 MW ( 0.9604 ) ( 0.02 ) = 0.0192083 + 5 = 8 MW 3 + 0 = 3 MW ( 0.0392 ) ( 0.02 ) = 0.0007846 + 5 = 11 MW 0 + 0 = 0 MW ( 0.0004 ) ( 0.02 ) = 0.000008
0.020000
Capacity Out Capacity In Probability
-
University of the Philippines
Department of Electrical and Electronics Engineering 21Prof. Rowaldo R. del Mundo
Generating Capacity Model
Step 2c: Combine probability tables in steps 2a and 2bCapacity Out Capacity In Probability
0 MW 11 MW 0.9411923 MW 8 MW 0.0384165 MW 6 MW 0.0192086 MW 5 MW 0.0003928 MW 3 MW 0.00078411 MW 0 MW 0.000008
1.000000
-
University of the Philippines
Department of Electrical and Electronics Engineering 22Prof. Rowaldo R. del Mundo
Generating Capacity Model
Cumulative Probability TableAn additional column can be added to the capacity outage probability table which gives the cumulative probability. This is the probability of finding a quantity of capacity on outage equal or greater than the indicated amount.
Capacity Out of Service Individual Probability Cumulative Probability0 MW 0.941192 1.0000003 MW 0.038416 0.0588085 MW 0.019208 0.0203926 MW 0.000392 0.0011848 MW 0.000784 0.00079211 MW 0.000008 0.000008
1.000000( ) 118653 PPPPP3 out capP ++++=( ) 11865 PPPP5 out capP +++=
-
University of the Philippines
Department of Electrical and Electronics Engineering 23Prof. Rowaldo R. del Mundo
Generating Capacity Model
Truncating the Probability Table
Theoretically, the capacity outage probability table incorporates all the system capacity. The table, however, can be truncated by omitting all capacity outages for which the cumulative probability is less than a specified amount, e.g., 10-8.
-
University of the Philippines
Department of Electrical and Electronics Engineering 24Prof. Rowaldo R. del Mundo
Generating Capacity Model
Capacity Rounding Probability TableIn a system containing a large number of units of different capacities, the table will contain several hundred positive discrete capacity outage levels. This number can be greatly reduced by grouping the units into identical capacity groups prior to combining or by rounding the table to discrete levels after combining.
The rounding process is done by calculating
For all states i falling between the required rounding states j and k.
( ) ( )ijk
ikj CPCC
CCCP
= ( ) ( )ijk
jik CPCC
CCCP
=
-
University of the Philippines
Department of Electrical and Electronics Engineering 25Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE:Obtain the rounded probability table of the generation system in the previous example rounded in 5 MWincrements.
For Capacity Out of Service Ci Cj Ck P(Ci) P(Cj) P(Ck)
0 MW 0 MW 0.941192 0.9411920 0.00000003 MW 3 MW 0 MW 5 MW 0.038416 0.0153665 0.02304975 MW 5 MW 0.019208 0.0192080 0.00000006 MW 6 MW 5 MW 10 MW 0.000392 0.0003136 0.00007848 MW 8 MW 5 MW 10 MW 0.000784 0.0003136 0.0004704
(Exact)
(Exact)
Capacity on Outage (MW)
0 MW 0.941192 + 0.0153664 = 0.95655845 MW 0.0230496 + 0.019208 + 2(0.0003136) = 0.0428848
10 MW 0.0000784 + 0.0004704 + 0.0000064 = 0.000555215 MW 0.0000016 = 0.0000016
1.0000000
Individual Probability
The final Rounded Probability Table is:
-
University of the Philippines
Department of Electrical and Electronics Engineering 26Prof. Rowaldo R. del Mundo
Generating Capacity Model
Recursive Algorithm for Capacity Model Building Addition in Probability Table one generating unit at a
time Suitable for computerized computations Cases
No Derated States Derated States Included Unit Removal
-
University of the Philippines
Department of Electrical and Electronics Engineering 27Prof. Rowaldo R. del Mundo
Generating Capacity Model
Case 1: No Derated StatesThe cumulative probability of a particular capacity outage state of X MW after a unit of capacity C MW and forced outage rate FOR is added is given by:
Where, P (X) - Cumulative Probability of X MWor more on outage of new table
P(X) - Probability of X MW or more on outage of old table
C - Capacity of unit to be addedInitial Setting: P(X) = 1.0 for X 0,
P(X) = 0 otherwise
( ) ( ) ( ) ( ) ( )CX'PFORX'PFOR1XP +=
-
University of the Philippines
Department of Electrical and Electronics Engineering 28Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE 1:
Using the Recursive Algorithm, the system capacity outage probability table is created sequentially as follows:
UNIT RATING (MW) FOR1 3 0.022 3 0.023 5 0.02
STEP 1: Add Unit No.1 C = 3 MW( ) ( ) ( ) ( ) ( )30'PFOR0'PFOR10P +=
( )( ) ( )( )0.102.00.102.01 += 0.1=( ) ( ) ( ) ( ) ( )31'P02.01'P02.011P +=
( )( ) ( )( )0.102.0098.0 += 02.0=( ) ( ) ( ) ( ) ( )32'P02.02'P02.012P +=
( )( ) ( )( )0.102.0098.0 += 02.0=( ) ( ) ( ) ( ) ( )33'P02.03'P02.013P +=
( )( ) ( )( )0.102.0098.0 += 02.0=
-
University of the Philippines
Department of Electrical and Electronics Engineering 29Prof. Rowaldo R. del Mundo
Generating Capacity Model
STEP 2: Add Unit No. 2 C = 3 MW( ) ( ) ( ) ( ) ( )30'P02.00'P02.010P +=
( )( ) ( )( )0.102.00.198.0 += 0.1=( ) ( ) ( ) ( ) ( )31'P02.01'P02.011P +=
( )( ) ( )( )0.102.002.098.0 += 0396.0=( ) ( ) ( ) ( ) ( )32'P02.02'P02.012P +=
( )( ) ( )( )0.102.002.098.0 += 0396.0=( ) ( ) ( ) ( ) ( )33'P02.03'P02.013P +=
( )( ) ( )( )0.102.002.098.0 += 0396.0=( ) ( ) ( ) ( ) ( )34'P02.04'P02.014P +=
( )( ) ( )( )02.002.0098.0 += 0004.0=( ) ( ) ( ) ( ) ( )35'P02.05'P02.015P +=
( )( ) ( )( )02.002.0098.0 += 0004.0=( ) ( ) ( ) ( ) ( )36'P02.06'P02.016P +=
( )( ) ( )( )02.002.0098.0 += 0004.0=
-
University of the Philippines
Department of Electrical and Electronics Engineering 30Prof. Rowaldo R. del Mundo
Generating Capacity Model
STEP 3: Add Unit No. 3 C = 5 MW( ) ( ) ( ) ( ) ( )50'P02.00'P02.010P +=
( )( ) ( )( )0.102.00.198.0 += 0.1=( ) ( ) ( ) ( ) ( )53'P02.03'P02.013P +=
( )( ) ( )( )0.102.00396.098.0 += 058808.0=( ) ( ) ( ) ( ) ( )55'P02.05'P02.015P +=
( )( ) ( )( )0.102.00004.098.0 += 020392.0=( ) ( ) ( ) ( ) ( )56'P02.06'P02.016P +=
( )( ) ( )( )0396.002.00004.098.0 += 001184.0=( ) ( ) ( ) ( ) ( )58'P02.08'P02.018P +=
( )( ) ( )( )0396.002.0098.0 += 000792.0=( ) ( ) ( ) ( ) ( )511'P02.011'P02.0111P +=
( )( ) ( )( )0004.002.0098.0 += 000008.0=
-
University of the Philippines
Department of Electrical and Electronics Engineering 31Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE 2:Using the Recursive Algorithm, prepare the generating capacity outage probability table of the system with three (3) generating units:
No. of states = 23
STEPS1. Initialize Table2. Enter Unit A3. Enter Unit B4. Enter Unit C
UNIT RATING (MW) FORA 100 0.01B 150 0.02C 200 0.03
-
University of the Philippines
Department of Electrical and Electronics Engineering 32Prof. Rowaldo R. del Mundo
Generating Capacity Model
STEP 1: Initialize the outage table
Probability when no unit yet is added intothe generation system
STATE X MW or more on Outage Cumulative Probability1 0 1.0000002 50 0.0000003 100 0.0000004 150 0.0000005 200 0.0000006 250 0.0000007 300 0.0000008 350 0.0000009 400 0.00000010 450 0.000000
-
University of the Philippines
Department of Electrical and Electronics Engineering 33Prof. Rowaldo R. del Mundo
Generating Capacity Model
STEP 2: Add unit A : C = 100, FOR = 0.01, 1-FOR = 0.99 STATE X MW P'(X) (X - C) MW P'(X-C) P(X)
1 0 1.000000 -100 1.000000 1.0000002 50 0.000000 -50 1.000000 0.0100003 100 0.000000 0 1.000000 0.0100004 150 0.000000 50 0.000000 0.0000005 200 0.000000 100 0.000000 0.0000006 250 0.000000 150 0.000000 0.0000007 300 0.000000 200 0.000000 0.0000008 350 0.000000 250 0.000000 0.0000009 400 0.000000 300 0.000000 0.00000010 450 0.000000 350 0.000000 0.000000
-
University of the Philippines
Department of Electrical and Electronics Engineering 34Prof. Rowaldo R. del Mundo
Generating Capacity Model
STEP 3: Add unit B: C = 150, FOR = 0.02, 1-FOR = 0.98 STATE X MW P'(X) (X - C) MW P'(X-C) P(X)
1 0 1.000000 -150 1.000000 1.0000002 50 0.010000 -100 1.000000 0.0298003 100 0.010000 -50 1.000000 0.0298004 150 0.000000 0 1.000000 0.0200005 200 0.000000 50 0.010000 0.0002006 250 0.000000 100 0.010000 0.0002007 300 0.000000 150 0.000000 0.0000008 350 0.000000 200 0.000000 0.0000009 400 0.000000 250 0.000000 0.000000
10 450 0.000000 300 0.000000 0.000000
-
University of the Philippines
Department of Electrical and Electronics Engineering 35Prof. Rowaldo R. del Mundo
Generating Capacity Model
STEP 4: Add unit C : C = 200, FOR = 0.03, 1-FOR = 0.97 STATE X MW P'(X) (X - C) MW P'(X-C) P(X)
1 0 1.000000 -200 1.000000 1.0000002 50 0.029800 -150 1.000000 0.0589063 100 0.029800 -100 1.000000 0.0589064 150 0.020000 -50 1.000000 0.0494005 200 0.000200 0 1.000000 0.0301946 250 0.000200 50 0.029800 0.0010887 300 0.000000 100 0.029800 0.0008948 350 0.000000 150 0.020000 0.0006009 400 0.000000 200 0.000200 0.000006
10 450 0.000000 250 0.000200 0.000006
-
University of the Philippines
Department of Electrical and Electronics Engineering 36Prof. Rowaldo R. del Mundo
Generating Capacity Model
Case 2: Derated States IncludedTo include the multi-state unit representations, the recursive equation is modified as follows:
Where, n - Number of unit statesCi - Capacity outage of state i for
the unit being addedpi - Probability of existence of the
unit state i
( ) ( )=
=
n
1iii CX'PpXP
-
University of the Philippines
Department of Electrical and Electronics Engineering 37Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE 1:
5 MW unit 3-state representation
Replacing the 2-state 5 MW unit in the previous example by the new 3-state unit,
n = 1; C1 = 0 MW
n = 2; C2 = 2 MW
n = 3; C3 = 5 MW
State Capacity Out State Probability1 0 0.9602 2 0.0333 5 0.007
-
University of the Philippines
Department of Electrical and Electronics Engineering 38Prof. Rowaldo R. del Mundo
Generating Capacity Model
( ) ( ) ( ) ( )50'Pp20'Pp00'Pp0P 321 ++=( )( ) ( )( ) ( )( )0.1007.00.1033.00.1960.0 ++= 0.1=
( ) ( ) ( ) ( ) ( ) ( ) ( )52'P007.022'P033.002'P960.02P ++=( )( ) ( )( ) ( )( )0.1007.00.1033.00396.0960.0 ++= 078016.0=
( ) ( ) ( ) ( ) ( ) ( ) ( )53'P007.023'P033.003'P960.03P ++=( )( ) ( )( ) ( )( )0.1007.00396.0033.00396.0960.0 ++= 0463228.0=
( ) ( ) ( ) ( ) ( ) ( ) ( )55'P007.025'P033.005'P960.05P ++=( )( ) ( )( ) ( )( )0.1007.00396.0033.00004.0960.0 ++= 0086908.0=
( ) ( ) ( ) ( ) ( ) ( ) ( )56'P007.026'P033.006'P960.06P ++=( )( ) ( )( ) ( )( )0396.0007.00004.0033.00004.0960.0 ++= 0006744.0=
( ) ( ) ( ) ( ) ( ) ( ) ( )58'P007.028'P033.008'P960.08P ++=( )( ) ( )( ) ( )( )0396.0007.00001184.0033.00960.0 ++= 000283272.0=
( ) ( ) ( ) ( ) ( ) ( ) ( )511'P007.0211'P033.0011'P960.011P ++=( )( ) ( )( ) ( )( )0004.0007.00033.00960.0 ++= 000002.0=
-
University of the Philippines
Department of Electrical and Electronics Engineering 39Prof. Rowaldo R. del Mundo
Generating Capacity Model
Case 3: Unit RemovalFrom the recursive algorithm for capacity model building,
The modified capacity model after a unit removal can be obtained by working on the algorithm in reverse. Thus,
( ) ( ) ( ) ( )FOR1
CX'PFORXPX'P
=
( ) ( ) ( ) ( ) ( )CX'PFORX'PFOR1XP +=
Where: P(X-C) = 1.0 for X C
-
University of the Philippines
Department of Electrical and Electronics Engineering 40Prof. Rowaldo R. del Mundo
Generating Capacity Model
EXAMPLE:Using the obtained capacity outage probability table for the 100 MW system (2 - 25 MW and 1 - 50 MW). Remove the 50MW Unit with FOR = 0.02
Capacity Out of Service (MW) Cumulative Probability0 1.00000025 0.05880850 0.02039275 0.000792
100 0.000008
-
University of the Philippines
Department of Electrical and Electronics Engineering 41Prof. Rowaldo R. del Mundo
Generating Capacity Model
Removing the unit from the capacity outage probability tables that gives the following modified capacity model:
( ) ( ) ( ) ( )( )02.01500'P02.00P0P
=
( )( )98.0
0.102.00.1 = 0.1=
( ) ( ) ( ) ( )( )02.015025'P02.025P25P
=
( )( )98.0
0.102.0058808.0 = 0396.0=
( ) ( ) ( ) ( )( )02.015050'P02.050P50P
=
( )( )98.0
0.102.0020392.0 = 0004.0=
-
University of the Philippines
Department of Electrical and Electronics Engineering 42Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
Consider the following four systems which are very similar but not identical
SYSTEM 1 - 24 x 10 MW Units each having a FOR of 0.01
SYSTEM 2 12 x 20 MW Units each having a FOR of 0.01
SYSTEM 3 - 12 x 20 MW Units each having a FOR of 0.03
SYSTEM 4 - 22 x 10 MW Units each having a FOR of 0.01
-
University of the Philippines
Department of Electrical and Electronics Engineering 43Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
0.0238550.02212522020
0.0017300.00163921030
0.2143220.19046723010
0.0000040.000004190500.0000910.00008720040
1.0000000.7856782400
Cumulative Probability
Individual Probability
Capacity In (MW)
Capacity Out (MW)
SYSTEM 1: Capacity Outage Probability Table
-
University of the Philippines
Department of Electrical and Electronics Engineering 44Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
0.0061750.00596920040
0.0002060.00020118060
0.1136160.10744122020
0.0000050.00000516080
1.0000000.8863842400
Cumulative Probability
Individual Probability
Capacity In (MW)
Capacity Out (MW)
SYSTEM 2: Capacity Outage Probability Table
-
University of the Philippines
Department of Electrical and Electronics Engineering 45Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
0.0003310.00031416080
0.0486500.04380320040
0.0048470.00451618060
0.3061590.25750922020
0.0000010.0000011201200.0000170.000016140100
1.0000000.6938412400
Cumulative Probability
Individual Probability
Capacity In (MW)
Capacity Out (MW)
SYSTEM 3: Capacity Outage Probability Table
-
University of the Philippines
Department of Electrical and Electronics Engineering 46Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
0.0202290.01889420020
0.1113350.00127219030
0.1983690.17814021010
0.0000020.000002170500.0000630.00006118040
1.0000000.8016312200
Cumulative Probability
Individual Probability
Capacity In (MW)
Capacity Out (MW)
SYSTEM 4: Capacity Outage Probability Table
-
University of the Philippines
Department of Electrical and Electronics Engineering 47Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
20%
20%
20%
20%
% Reserve
0.004847200 MW240 MWSystem 3
0.000063183 1/3 MW220 MWSystem 4
0.000206200 MW240 MWSystem 2
0.000004200 MW240 MWSystem 1
Probabilistic RiskLoadTotal Capacity
System
Percentage Reserve Margin Criteria
Note that the risk in system 3 is more than 1000 times greater than that in system 1Analysis of the four systems shows that the variation in true risk depends upon FOR, number of units and load demand
-
University of the Philippines
Department of Electrical and Electronics Engineering 48Prof. Rowaldo R. del Mundo
Comparison of Deterministic and Probabilistic Criteria
22
12
12
24
Units
10 MW
20 MW
20 MW
10 MW
Reserve
0.048650220 MW20 MWSystem 30.020229210 MW10 MWSystem 4
0.006175220 MW20 MWSystem 20.023855230 MW10 MWSystem 1
Probabilistic RiskLoad
Cap/ Unit
System
Largest Unit Reserve Criteria
It is seen from the above comparison that deterministic approaches in power reserve margin planning are inconsistent, unreliable and subjective.
-
University of the Philippines
Department of Electrical and Electronics Engineering 49Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Loss of Load Expectation (LOLE)The expected number of days in the specified period in which the daily peak load will exceed the available capacity.Notes:
LOLE is known in the power industry as the LOLP. LOLP is not a probability index but an expectation.
The expected risk of loss of load is determined by convolving the system capacity outage table and the system load characteristic.
-
University of the Philippines
Department of Electrical and Electronics Engineering 50Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Load Models
Daily Peak DemandJanuary 1
to
December 31Day
0 365D
a
i
l
y
P
e
a
k
,
M
W
Actual Load Curve
-
University of the Philippines
Department of Electrical and Electronics Engineering 51Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Load Models
The load is represented by its daily peak arranged in descendingorder to form a cumulative load model called load variation curve.
Load Variation Curve
Daily Peak DemandArrange in Descending Order
Linearized LVC
-
University of the Philippines
Department of Electrical and Electronics Engineering 52Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Where, Ok - Magnitude of the kth outage in the system capacity outage probability table
tk - Number of time units in the study interval that an outage magnitude Ok would result in a loss of load
pk - Individual probability of the capacity outage Ok.
=
=
n
1kkktpLOLP
( )=
=
n
1kk1kk PttLOLP
=
=
n
1kkk PT
Pk - Cumulative outage probability for capacity state Ok.
-
University of the Philippines
Department of Electrical and Electronics Engineering 53Prof. Rowaldo R. del Mundo
Loss of Load Expectation
EXAMPLE 1:Consider a system containing 5 - 40 MWunits each with a FOR of 0.01. The capacity outage probability table is shown on the right.
The system load model is represented by the daily peak load variation curve in the figure on the right.
Capacity Out of
Service
Individual Probability
Cumulative Probability
0 0.950991 1.00000040 0.048029 0.04900980 0.000971 0.000980120 0.000009 0.000009
Note: Probability values less than10-8 have been deleted.
160
120
8064
0 100Time (%)
D
a
i
l
y
P
e
a
k
L
o
a
d
(
M
W
)
Installed Capacity = 200 MW
Time periods during which loss of load occurs
02 = 40MW 03 = 80MW 04 = 120 MW
T4 = 41.7%t3 = T3 = 41.7%
t4 = 83.4% 64
-
University of the Philippines
Department of Electrical and Electronics Engineering 54Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Capacity Out of Service (MW)
Capacity In Service (MW)
Individual Probability, pk
Total Time, tk (%)
LOLPpktk
0 200 0.950991 0.0 0.000000040 160 0.048029 0.0 0.000000080 120 0.000971 41.7 0.0404907
120 80 0.000009 83.4 0.00075060.0412413
Capacity Out of Service (MW)
Capacity In Service (MW)
Cumulative Probability, Pk
Total Time, Tk (%)
LOLPPkTk
0 200 1.000000 0.0 0.000000040 160 0.049009 0.0 0.000000080 120 0.000980 41.7 0.0408660
120 80 0.000009 41.7 0.00037530.0412413
LOLP using Individual Probabilities
LOLP using the Cumulative Probabilities
If the time considered is 365 days per year then,( ) yeardays LOLP 1505307.01000412413.0365 ==
-
University of the Philippines
Department of Electrical and Electronics Engineering 55Prof. Rowaldo R. del Mundo
Loss of Load Expectation
It should be realized that there is difference between the terms capacity outage and loss of load. The term capacity outage indicates a loss of generation which may or may not result in a loss of load.
( ) ddays/perio LCPLOLP n1i
iii=
=
Where, Ci - Available capacity on day iLi - Forecast peak load on day iPi(Ci Li) - Probability of loss of load on day i. This
value is obtained directly from the capacity outage cumulative probability table.
-
University of the Philippines
Department of Electrical and Electronics Engineering 56Prof. Rowaldo R. del Mundo
Loss of Load Expectation
EXAMPLE 2:What is the LOLP of the 450 MW system in a 5-day period?
Generator and Demand DataUnit Rating (MW) FOR Day MW
A 100 0.01 1 95B 150 0.02 2 120C 200 0.03 3 160
4 1105 90
-
University of the Philippines
Department of Electrical and Electronics Engineering 57Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Generation ModelSTATE G1 G2 G3 CAP IN CAP OUT IND CUMULATIVE
1 100 150 200 450 0 0.941094 1.0000002 0 150 200 350 100 0.009506 0.0589063 100 0 200 300 150 0.019206 0.0494004 100 150 0 250 200 0.029106 0.0301945 0 0 200 200 250 0.000194 0.0010886 0 150 0 150 300 0.000294 0.0008947 100 0 0 100 350 0.000594 0.0006008 0 0 0 0 450 0.000006 0.000006
DAY MW1 952 1203 1604 1105 90
DAY MW1 1602 1203 1104 955 90
Load Model
-
University of the Philippines
Department of Electrical and Electronics Engineering 58Prof. Rowaldo R. del Mundo
Loss of Load Expectation
DAY SYSTEM CAPACITY (MW)PEAK LOAD
(MW)RESERVE
(MW)PROB. OF LOSS-OF-
LOAD1 450 160 290 0.0008942 450 120 330 0.0006003 450 110 340 0.0006004 450 95 355 0.0000065 450 90 360 0.000006
LOLP 0.002106
System Reliability
LOLP = 0.002106 Days/5-Days
Annual LOLP 365 days period
-
University of the Philippines
Department of Electrical and Electronics Engineering 59Prof. Rowaldo R. del Mundo
Loss of Load Expectation
EXAMPLE 3:100 MW system with annual peak load of 57 MW
Unit No. Capacity (MW) FOR1 25 0.022 25 0.023 50 0.02
System Capacity Data
Daily Peak Load 57 52 46 41 34No. of Occurences 12 83 107 116 47 = 365 days
System Load Data
-
University of the Philippines
Department of Electrical and Electronics Engineering 60Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Using the recursive algorithm, the capacity outage cumulative probability table is
Capacity Out of Service (MW) Cumulative Probability0 1.000000
25 0.05880850 0.02039275 0.000792
100 0.000008
( ) ( ) ( )( ) ( )34100P4741100P116
46100P10752100P8357100P12LOLP++
++=
( ) ( ) ( ) ( ) ( )66P4759P11654P10748P8343P12 ++++=( ) ( ) ( )
( ) ( )000792.047000792.0116 000792.0107020392.083020392.012
++
++=
yeardays 15108.2LOLP =
-
University of the Philippines
Department of Electrical and Electronics Engineering 61Prof. Rowaldo R. del Mundo
Loss of Load Expectation
LOLP Vs. Peak Load
-
University of the Philippines
Department of Electrical and Electronics Engineering 62Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Scheduled OutagesThe system capacity evaluation examples previously considered assumed that the load model applied to the entire period and that the capacity model was also applicable for the entire period. This will not be the case if the units are removed from services for periodic inspection and maintenance in accordance with the planned program. During this period, the capacity available is not constant and therefore a single capacity outage probability table is not applicable.
Typical Annual Load& Capacity Model
Total Installed Capacity
January 1 December 31
S
y
s
t
e
m
D
a
i
l
y
P
e
a
k
L
o
a
d
Reserve
Units onmaintenance
-
University of the Philippines
Department of Electrical and Electronics Engineering 63Prof. Rowaldo R. del Mundo
Loss of Load ExpectationConsidering scheduled maintenance, the annual LOLPa can be obtained by dividing the year into periods and calculating the period LOLPP values using the modified capacity model and the appropriate period load model.The annual risk index is given by
Subdivision of Period
=
=
n
1ppa LOLPLOLP
Total Installed Capacity
P1 P2 P3
S
y
s
t
e
m
D
a
i
l
y
P
e
a
k
L
o
a
d
R1
R2R3
-
University of the Philippines
Department of Electrical and Electronics Engineering 64Prof. Rowaldo R. del Mundo
Loss of Load Expectation
Approximate methods may also be used to take into account scheduled maintenance while using the original capacity outage probability table such as shown in the following figures:
Installed Capacity
Time load exceeded the indicated value
L
o
a
d
0
Reserve CapacityPeak Load
Capacity onMaintenance
Modified LoadCharacteristicOriginal LoadCharacteristic
Installed Capacity
Time load exceeded the indicated value
L
o
a
d
0
Reserve CapacityCapacity on Maintenance Peak Load
-
University of the Philippines
Department of Electrical and Electronics Engineering 65Prof. Rowaldo R. del Mundo
LOLE with Load Forecast Uncertainty
The calculation of reliability indices presented so far assumes that the actual peak load will differ from the forecast value with zero probability. But some uncertainties exists in load forecasting arising from the historical data considered, the methodology used and the assumptions made. There is, therefore, a need to improve the risks calculation by including these uncertainties in building the system load model.
Studies made in the past had shown that the uncertainty in the load forecasts can be reasonably described by a normal distribution with the peak load value as the distribution mean parameter. The distribution can be divided into a discrete number of class intervals. The load representing the class interval midpoint is assigned the probability for that class interval. A seven-step distribution is considered reasonable in the subdivision.
-
University of the Philippines
Department of Electrical and Electronics Engineering 66Prof. Rowaldo R. del Mundo
Load Forecast Uncertainty
-3 -2 -1 0 +1 +2 +3
0.006
0.061 0.2420.382
0.006
0.0610.242
Probability given by indicated area
No. of standard deviations from the mean
Mean = forecast load (MW)
-
University of the Philippines
Department of Electrical and Electronics Engineering 67Prof. Rowaldo R. del Mundo
0.00020562150.0000046420
0.0061745410
0.0000000725
0.1136151351.000000000
Cumulative Probability
Capacity Outage (MW)
(probability values less than 10-B are neglected)
Example:The capacity model of a system consisting of twelve 5 MW units,
each with forced outage rate of 0.01 is shown below.
Load Forecast Uncertainty
-
University of the Philippines
Department of Electrical and Electronics Engineering 68Prof. Rowaldo R. del Mundo
0.0095630500.156771320.06152+2
0.0025418510.010503520.24249-10.0048877280.012795100.382500
0.22468462
0.08619473
0.008116450.00562781
LOLP (days/year) (4)
0.0208591250.24251+1
0.0013481070.00653+3
0.0004951030.06148-20.0000337660.00647-3
(3) x (4)Probability of the Load (3)
Load (MW)
(2)
Number of S. D. (1)
Using a seven-step normal distribution approximation of the load forecast with peak load of 50MW, 2% S.D., 70% load factor and straightline load variation curve, calculate the annual LOLP of the system in days/year.Standard Deviation = (0.02)(50) = 1 MW Mean = 50 MW
Annual LOLP = 0.03972873 days/year
Load Forecast Uncertainty
-
University of the Philippines
Department of Electrical and Electronics Engineering 69Prof. Rowaldo R. del Mundo
Peak megawattdemand
Alternative 2
Alternative 1
0 2 4 6 8 Years
MW0
M
e
g
a
w
a
t
t
s
Note: MW0 = capacity of existing generating plant
Application in Generation System Expansion Analysis
-
University of the Philippines
Department of Electrical and Electronics Engineering 70Prof. Rowaldo R. del Mundo
Application in Generation System Expansion Analysis
Percentage of days the daily peak load
exceeded the indicated value
Daily peak load variation curve Year Number Forecast Peak Load (MW)1 160.02 176.03 193.64 213.05 234.36 257.57 283.18 311.4
Load Growth at 10% p.a.
-
University of the Philippines
Department of Electrical and Electronics Engineering 71Prof. Rowaldo R. del Mundo
Consider a system containing five 40 MW units each with a forced outage rate of 0.01.
Capacity outof service
IndividualProbability
CumulativeProbability
0 MW 0.950991 1.00000040 MW 0.048029 0.04900980 MW 0.000971 0.000980
120 MW 0.000009 0.0000091.000000
Sytem installed capacity = 200 MW
Generation model for thefive-unit system.
160
120
8064
0 100Time (%)
D
a
i
l
y
P
e
a
k
L
o
a
d
(
M
W
)
Installed Capacity = 200 MW
Time periods during which loss of load occurs
02 = 40MW 03 = 40MW 04 = 40 MW
T4 = 41.7%t3 = T3 = 41.7%
t4 = 83.4% 64
Loss of Load Expectation
-
University of the Philippines
Department of Electrical and Electronics Engineering 72Prof. Rowaldo R. del Mundo
Capacity Outof Service (MW)
Capacity InService (MW)
IndividualProbability
Total Timetk (%)
LOLE(%)
0 200 0.950991 0.0 -40 160 0.048029 0.0 -80 120 0.000971 41.7 0.0404907120 80 0.000009 83.4 0.0007506
1.000000 0.0412413
Capacity Outof Service (MW)
Capacity InService (MW)
CumulativeProbability
Total Timetk (%)
LOLE(%)
0 200 1.000000 0.0 -40 160 0.049009 0.0 -80 120 0.000980 41.7 0.040866120 80 0.000009 41.7 0.0003753
0.0412413
LOLE using individual probabilities
LOLE using cumulative probabilities
Loss of Load Expectation
-
University of the Philippines
Department of Electrical and Electronics Engineering 73Prof. Rowaldo R. del Mundo
LOLE (days/year)System Peak
Load (MW)200 MWCapacity
100 0.001210120 0.002005140 0.086860160 0.150600180 3.447000200 6.083000220 -240 -250 -260 -280 -300 -320 -340 -350 -
Loss of Load Expectation
-
University of the Philippines
Department of Electrical and Electronics Engineering 74Prof. Rowaldo R. del Mundo
System PeakLoad (MW)
200 MWCapacity
250 MWCapacity
100 0.001210 -120 0.002005 -140 0.086860 0.001301160 0.150600 0.002625180 3.447000 0.068650200 6.083000 0.150500220 - 2.058000240 - 4.853000250 - 6.083000260 - -280 - -300 - -320 - -340 - -350 - -
LOLE (days/year)
Loss of Load Expectation
-
University of the Philippines
Department of Electrical and Electronics Engineering 75Prof. Rowaldo R. del Mundo
System PeakLoad (MW)
200 MWCapacity
250 MWCapacity
300 MWCapacity
100 0.001210 - -120 0.002005 - -140 0.086860 0.001301 -160 0.150600 0.002625 -180 3.447000 0.068650 -200 6.083000 0.150500 0.002996220 - 2.058000 0.036100240 - 4.853000 0.180000250 - 6.083000 0.661000260 - - 3.566000280 - - 6.082000300 - - -320 - - -340 - - -350 - - -
LOLE (days/year)
Loss of Load Expectation
-
University of the Philippines
Department of Electrical and Electronics Engineering 76Prof. Rowaldo R. del Mundo
200 MWCapacity
250 MWCapacity
300 MWCapacity
350 MWCapacity
100 0.001210 - - -120 0.002005 - - -140 0.086860 0.001301 - -160 0.150600 0.002625 - -180 3.447000 0.068650 - -200 6.083000 0.150500 0.002996 -220 - 2.058000 0.036100 -240 - 4.853000 0.180000 0.002980250 - 6.083000 0.661000 0.004034260 - - 3.566000 0.011750280 - - 6.082000 0.107500300 - - - 0.290400320 - - - 2.248000340 - - - 4.880000350 - - - 6.083000
LOLE (days/year)System Peak
Load (MW)
Loss of Load Expectation
-
University of the Philippines
Department of Electrical and Electronics Engineering 77Prof. Rowaldo R. del Mundo
Loss of Energy Indices
Load Model: Load Duration Curve (LDC) Individual hourly load values arranged in
decreasing orders The area under the curve represents the energy
required in the given period
Let, Ok - Magnitude of the capacity outage
Pk - Probability of the capacity outage equal to Ok
Ek - Energy curtailed by capacity outage equal to Ok.
-
University of the Philippines
Department of Electrical and Electronics Engineering 78Prof. Rowaldo R. del Mundo
Loss of Energy Expectation
Load Models
Hourly Load Curve(Luzon Grid)
HOUR LOAD P.U. LOAD1 1452 0.712 1422 0.693 1446 0.714 1405 0.695 1440 0.706 1464 0.717 1417 0.698 1455 0.719 1547 0.7510 1498 0.7311 1574 0.7712 1535 0.7513 1501 0.7314 1499 0.7315 1504 0.7316 1487 0.7317 1504 0.7318 1659 0.8119 2051 1.0020 1960 0.9621 1830 0.8922 1718 0.8423 1598 0.7824 1661 0.81
-
University of the Philippines
Department of Electrical and Electronics Engineering 79Prof. Rowaldo R. del Mundo
Loss of Energy Expectation
Load Models
Load Duration Curve(Hourly Peak arrange in descending order)
HOUR P.U. LOAD1 1.002 0.963 0.894 0.845 0.816 0.817 0.788 0.779 0.7510 0.7511 0.7312 0.7313 0.7314 0.7315 0.7316 0.7317 0.7118 0.7119 0.7120 0.7121 0.7022 0.6923 0.6924 0.69
-
University of the Philippines
Department of Electrical and Electronics Engineering 80Prof. Rowaldo R. del Mundo
Loss of Energy Indices
The probability energy curtailed by a capacity outage equal to Ok is Ekpk.Loss of Energy Expectation is the total energy curtailment because of capacity outages.
The per unit LOEE value represents the ratio between the probable load energy curtailed due to deficiencies in available generating capacity and the total energy required to served the system demand.
=
=
n
kkk pELOEE
1
-
University of the Philippines
Department of Electrical and Electronics Engineering 81Prof. Rowaldo R. del Mundo
Loss of Energy Indices
STATE CAP IN CAP OUT INDIVIDUAL CUMULATIVE1 450 0 0.941094 1.0000002 350 100 0.009506 0.0589063 300 150 0.019206 0.0494004 250 200 0.029106 0.0301945 200 250 0.000194 0.0010886 150 300 0.000294 0.0008947 100 350 0.000594 0.0006008 0 450 0.000006 0.000006
Generating Capacity Model
Example:
-
University of the Philippines
Department of Electrical and Electronics Engineering 82Prof. Rowaldo R. del Mundo
Loss of Energy Indices
Hourly Load
1 160.002 152.903 142.764 134.025 129.586 129.427 124.668 122.799 120.6810 119.7511 117.3312 117.33
13 117.0914 116.9415 116.8616 116.0017 114.2118 113.5119 113.2720 112.8021 112.3422 110.9323 110.5424 109.61
-
University of the Philippines
Department of Electrical and Electronics Engineering 83Prof. Rowaldo R. del Mundo
Loss of Energy Indices
Loss of Energy Expectation (LOEE)CAP IN = 150 PROB = 0.000294
HOUR LOAD CURTAILED EXPECTATION1 160.00 10.00 0.0029402 152.90 2.90 0.0008533 142.76 0.00 0.0000004 134.02 0.00 0.0000005 129.58 0.00 0.0000006 129.42 0.00 0.0000007 124.66 0.00 0.0000008 122.79 0.00 0.0000009 120.68 0.00 0.00000010 119.75 0.00 0.00000011 117.33 0.00 0.00000012 117.33 0.00 0.00000013 117.09 0.00 0.00000014 116.94 0.00 0.00000015 116.86 0.00 0.00000016 116.00 0.00 0.00000017 114.21 0.00 0.00000018 113.51 0.00 0.00000019 113.27 0.00 0.00000020 112.80 0.00 0.00000021 112.34 0.00 0.00000022 110.93 0.00 0.00000023 110.54 0.00 0.00000024 109.61 0.00 0.000000
12.901024 0.003793SUBTOTAL
-
University of the Philippines
Department of Electrical and Electronics Engineering 84Prof. Rowaldo R. del Mundo
Loss of Energy Indices
CAP IN = 100 PROB = 0.000594HOUR LOAD CURTAILED EXPECTATION
1 160.00 60.00 0.0356402 152.90 52.90 0.0314233 142.76 42.76 0.0253994 134.02 34.02 0.0202095 129.58 29.58 0.0175686 129.42 29.42 0.0174757 124.66 24.66 0.0146498 122.79 22.79 0.0135379 120.68 20.68 0.01228510 119.75 19.75 0.01172911 117.33 17.33 0.01029312 117.33 17.33 0.01029313 117.09 17.09 0.01015414 116.94 16.94 0.01006115 116.86 16.86 0.01001516 116.00 16.00 0.00950517 114.21 14.21 0.00843918 113.51 13.51 0.00802219 113.27 13.27 0.00788320 112.80 12.80 0.00760521 112.34 12.34 0.00732722 110.93 10.93 0.00649323 110.54 10.54 0.00626124 109.61 9.61 0.005705
535.309605 0.317974SUBTOTAL
Loss of Energy Expectation (LOEE)
-
University of the Philippines
Department of Electrical and Electronics Engineering 85Prof. Rowaldo R. del Mundo
Loss of Energy Indices
CAP IN = 0 PROB = 0.000006HOUR LOAD CURTAILED EXPECTATION
1 160.00 160.00 0.0009602 152.90 152.90 0.0009173 142.76 142.76 0.0008574 134.02 134.02 0.0008045 129.58 129.58 0.0007776 129.42 129.42 0.0007777 124.66 124.66 0.0007488 122.79 122.79 0.0007379 120.68 120.68 0.00072410 119.75 119.75 0.00071811 117.33 117.33 0.00070412 117.33 117.33 0.00070413 117.09 117.09 0.00070314 116.94 116.94 0.00070215 116.86 116.86 0.00070116 116.00 116.00 0.00069617 114.21 114.21 0.00068518 113.51 113.51 0.00068119 113.27 113.27 0.00068020 112.80 112.80 0.00067721 112.34 112.34 0.00067422 110.93 110.93 0.00066623 110.54 110.54 0.00066324 109.61 109.61 0.000658
2935.309605 0.017612SUBTOTAL
Loss of Energy Expectation (LOEE)
-
University of the Philippines
Department of Electrical and Electronics Engineering 86Prof. Rowaldo R. del Mundo
Loss of Energy Indices
STATE CAP IN CAP OUT PROB CURTAILED EXPECTATION1 450 0 0.941094 0.00 0.000002 350 100 0.009506 0.00 0.000003 300 150 0.019206 0.00 0.000004 250 200 0.029106 0.00 0.000005 200 250 0.000194 0.00 0.000006 150 300 0.000294 12.90 0.003797 100 350 0.000594 535.31 0.317978 0 450 0.000006 2935.31 0.01761
0.33938LOEE (MWH)
Loss of Energy Expectation (LOEE)
-
University of the Philippines
Department of Electrical and Electronics Engineering 87Prof. Rowaldo R. del Mundo
Loss of Energy Indices
Applications in Probabilistic Production Simulations
Consider the LDC below
75.0
52.5
30.0
0 20 100
Duration (hours)
L
o
a
d
(
M
W
)
-
University of the Philippines
Department of Electrical and Electronics Engineering 88Prof. Rowaldo R. del Mundo
Loss of Energy Indices
and the generating units capacity data
Assume that the economic loading order is units 1, 2 & 3.
If there were no units in the system, the expected energy not supplied would be
MWh4575.0 Energy Required Total = (area under the curve)
MWh0.4575EENS0 =
Unit No. Capacity (MW) Probability1 0 0.05
15 0.3025 0.65
2 0 0.0330 0.97
3 0 0.0420 0.96
-
University of the Philippines
Department of Electrical and Electronics Engineering 89Prof. Rowaldo R. del Mundo
Loss of Energy Indices
If the system contained only Unit 1, the EENS can be calculated as follows:
The expected energy produced by Unit 1= EENS0 - EENS1= 4575.0 - 2500.0
= 2075.0 MWh
Capacity Out ofService (MW)
Capacity inService (MW) Probability
Energy Curtailed(MWh)
Expectation(MWh)
0 25 0.65 2075.0 1348.7510 15 0.30 3075.0 922.5025 0 0.05 4575.0 228.75
EENS1 2500.00
-
University of the Philippines
Department of Electrical and Electronics Engineering 90Prof. Rowaldo R. del Mundo
Loss of Energy Indices
EENS with Units 1 and 2
The expected energy produced by Unit 2= EENS1 - EENS2= 2500.0 - 401.7
= 2098.3 MWh
Capacity Out ofService (MW)
Capacity inService (MW) Probability
Energy Curtailed(MWh)
Expectation(MWh)
0 55 0.6305 177.8 112.0910 45 0.2910 475.0 138.2325 30 0.0485 1575.0 76.3930 25 0.0195 2075.0 40.4640 15 0.0090 3075.0 27.6855 0 0.0015 4575.0 6.86
EENS 2 401.70
-
University of the Philippines
Department of Electrical and Electronics Engineering 91Prof. Rowaldo R. del Mundo
Loss of Energy IndicesEENS with Units 1, 2 and 3
The expected energy produced by Unit 3= EENS2 - EENS3= 401.7 - 64.08 = 337.6 MWh
Capacity Out ofService (MW)
Capacity inService (MW) Probability
Energy Curtailed(MWh)
Expectation(MWh)
0 75 0.60528 0.0 0.0010 65 0.27936 44.4 12.4220 55 0.02522 177.8 4.4825 50 0.04656 286.1 13.3230 45 0.03036 475.0 14.4240 35 0.00864 1119.4 9.6745 30 0.00194 1575.0 3.0650 25 0.00078 2075.0 1.6255 20 0.00144 2575.0 3.7160 15 0.00036 3075.0 1.1175 0 0.00006 4575.0 0.27
EENS 3 64.08