Leap ahead with Effective monitoring for testing in agile
Tomer Rider, Intel
Leap ahead with effective monitoring in agile 2 Tomer Rider
What to expect?
Focus
Takeaways
Monitoring in an agile environment
Familiarity with common measurements
What to expect?
Audience Agile team leaders / project managers / QA
Leap ahead with effective monitoring in agile 3 Tomer Rider
Introduction
• Increase team productivity
• Ensure product quality
• Enable decision making
• Motivation
• Provide a project status • Real-time
• Retrospective
• Projected
Why do we need to measure?
Leap ahead with effective monitoring in agile 4 Tomer Rider
What's different about Agile?
Leap ahead with effective monitoring in agile 5 Tomer Rider
Short dev cycles
Leap ahead with effective monitoring in agile 6 Tomer Rider
Strong collaboration
Leap ahead with effective monitoring in agile 7 Tomer Rider
Welcome changes
Leap ahead with effective monitoring in agile 8 Tomer Rider
Team ownership
Leap ahead with effective monitoring in agile 9 Tomer Rider Organization name
Constant need of data
Leap ahead with effective monitoring in agile 10 Tomer Rider
Measuring across the development lifecycle
Tracking Execution Planning
Leap ahead with effective monitoring in agile 11 Tomer Rider
Planning
Leap ahead with effective monitoring in agile 12 Tomer Rider
Planning – Velocity
Leap ahead with effective monitoring in agile 13 Tomer Rider
Planning – Bug fixing
Leap ahead with effective monitoring in agile 14 Tomer Rider
Planning – QA coverage and focus
- Based on Risk: what are the areas that are compromised?
- Based on bug spread: what are the most “buggiest” areas?
- Based on new user stories
67 User Stories
30 Bugs
Leap ahead with effective monitoring in agile 15 Tomer Rider
Execution
Leap ahead with effective monitoring in agile 16 Tomer Rider
Execution – Coverage and Progress
67 User Stories
88% Covered
189 Test Cases
65% Executed
43 Bugs Found
27 Bugs verified
Leap ahead with effective monitoring in agile 17 Tomer Rider
Execution – Coverage and Progress
Execution – Opened bugs, current iteration
Leap ahead with effective monitoring in agile 18 Tomer Rider
Tracking
Leap ahead with effective monitoring in agile 19 Tomer Rider
Tracking – Task / User story
Leap ahead with effective monitoring in agile 20 Tomer Rider
Tracking – User stories Acceptance
Acceptance status:
Acceptance rate:
Leap ahead with effective monitoring in agile 21 Tomer Rider
Tracking
- Backlog bugs
- Unassigned / Un prioritized Bugs
- incompleted tasks
- Risks
- Changes in requirements
Leap ahead with effective monitoring in agile 22 Tomer Rider
How to stay effective?
Leap ahead with effective monitoring in agile 23 Tomer Rider
How to stay effective?
- Data consolidation – connect the dots
- Clear definition of the acceptance criteria
- Define clear business metrics
- Define clear diagnostics that will enable metrics improvement
- Continues improvement of the processes
- Give the right context
Leap ahead with effective monitoring in agile 24 Tomer Rider
If you can’t measure it, you can’t improve it!