effective utility coordination practices using alternative ... · using alternative contract...
TRANSCRIPT
Effective Utility Coordination Practices
Using Alternative Contract Methods
Douglas D. Gransberg, PhD, PE, DBIA
Gransberg & Associates, Inc.
Norman, OK 73070-2395
NCHRP 20-07, Task 373
• The objectives of NCHRP Project 20-07/Task 373: Utility Coordination Using Alternative Contracting Methods are as follows:• Identify, analyze, and understand the current models for
successful utility coordination risk management on projects delivered by alternative contracting methods (ACM).
• Compare the advantages and disadvantages and identify successful approaches to managing utility coordination in each ACM.
• Prepare a set of Guidelines for managing utility coordination on projects delivered using alternative methods for implementation on highway construction projects by public agencies.
Research Team Members• Dr. Dominique Pittenger: Arbor Services, Inc.
• 10+ years paving contracting experience
• Research experience:• Asset management
• 3-D design/CIM
• Mr. Gary Chambers: Chambers Engr, LLC.• 20+ years mechanical/utility design-build contracting experience
• Research experience:• Airport utility operational planning
• Mr. Micheal Loulakis, DBIA: Capital Project Strategies, LLC• 30+ years design-build/construction law experience
• Co-PI on NCHRP 24-44: Geotechnical Risk Management Guide for Design-build Projects.
The Salient Issue
• DOTs use alternative contracting methods (ACM) to accelerate project delivery.
• The design and construction of subsurface features of work is generally the earliest package in the sequence of work.
• Utility issues must typically be resolved before construction can commence.
• Therefore, the risk of delay due to utility coordination problems is always high on ACM projects.
The Opportunity
• ACM projects furnish the ability to gain high levels of integration between the designer, construction contractor, and affected third parties.
• As a result, DOTS are afforded a number of opportunities:• Utility coordination responsibilities can be assigned to
the CMGC contractor/design-builder/P3 developer.
• If the DOT chooses to retain these, ACMs can be used to obtain early contractor involvement in the design details to increase overall constructability.
• During procurement, the DOT is able to consider competing design alternatives for the utility work.
The Research Details
• Literature review• SHRP2 utility products
• DOT utility coordination documents
• Content analysis of ACM procurement documents• 73 RFQ/RFPs
• $15.2 billion worth of projects in 27 states
• DOT survey • 29 DOTs +DC – 58% response rate
• 7 case study projects
Survey, Content Analysis and Case Study Map
Case Study Project SynopsisState/Agency
ProjectDelivery Method
Value Project Type Rationale for Inclusion
Georgia/GDOT
I-285/Ga. 400 Improvements Project
DBF (P3) $1.06billion
Interchangebridges,&roadway
Project only includes private finance with no post-construction maintenance. Schedule is highly aggressive.
Kentucky/IndianaKYTC/INDOT
Ohio River Bridges DB (Downtown Crossing)P3 (East End Crossing)
$2.8billion
Bridges Urban setting with utilities that span two states and two different delivery methods.
Minnesota/MnDOT
Hastings Bridge DB/ATCs $120million
Bridge Project had large ATC that included utility aspects.
Missouri/MoDOT
Stan Musial Veterans Memorial Bridge
DBB/ATC $230million
Bridge Urban setting with utilities that span two states and had an ATC that included utility aspects.
Pennsylvania/PennDOT
Rapid Bridge Replacement Project
DBFM (P3) $1.7billion
557 rural bridges
Massive number of small bridges with a variety of utility issues.
Texas/TxDOT
Horseshoe Interchange Project
DB $818million
Interchange bridges & roadway
Multiple jurisdictions with both overhead and underground utility issues.
Washington/WSDOT
Colman Dock CMGC $320million
Ferry Terminal
Multimodal facility utility coordination with 2 other active projects that abut the ROW.
Benchmark of the Practice
• Causes of inefficiency in the project development and delivery process. • Delays due to utility coordination and location failures.
• Delays due to untimely actions by third party stakeholders and utility companies.
• Inefficiencies in the project delivery process due to failure to include salient utility issues in the procurement process.
• Lost opportunities to avoid utility conflicts.
• Claims due to utility-related differing site conditions
• Poor quality utility work
Implementing the Strategies
• “Strategies typically address a specific problem and are formulated to address a problem’s root cause…
• The strategy is implemented through a method. A method is a means or manner of procedure, especially a regular and systematic way of accomplishing something…
• A method is then implemented using a tool. A tool is something used in the performance of an operation” (Anderson et al. 2006).
Preview of the Findings
• Six strategies identified• Implement early contractor design involvement as
appropriate for each given ACM project.• Use ACMs to address utility company timeliness by involving
third party stakeholders as early as practical in project development and delivery.
• Raise the visibility of utility-related issues in ACM projects to ensure competing contractor teams understand the level of criticality on each project.
• Promote utility avoidance as the preferred solution to utility conflicts.
• Avoid utility-related claims through enhanced contract mechanisms designed specifically for addressing utility issues.
• Promote an atmosphere of life cycle-based design and construction decision-making on ACM projects.
Methods and Tools
• The ACMs are the methods for implementing the strategies:• DBB w/ATCs
• CMGC
• DB and DB w/ATCs
• P3 and P3 w/ATCs
• 36 tools were identified• Many apply to all methods
• Some are specific to a method
• Organized by strategy and method for implementation in the proposed guide.
Strategy: Contractor design involvement using ACM
Alliancing
Early Contractor Involvement
Design-Build
CMGC
Public Private Partnership
Design-Bid-Build
Design-Bid-Build w/ATCs
Design Construction MaintenancePlanning
Utility Coord. Tasks vs. ACM TimingPre-Letting
Procurement DBB
Post-Award 1 DOT 1 DOT 2 Cont 1 DOT 2 Cont 1 DOT 2 Cont
1. Utility Coordination Initiation Phase.
2. Utility Research Phase.
3. Utility Initial Notice Phase
4. Utility Verification Phase
5. Utility Conflict Analysis Phase
6. Utility Work Plans Phase
7. Utility Agreement Phase
8. Utility Construction Phase
Stage
IND
OT
UC
Ph
ase
1 DOT responsible for UC
2 CMGC/DB/P3 developer responsible for UC
CMGC DB P3
Project Delivery Method3. Utility Initial Notice Phase DBB CMGC DB P3 Send letter initial notice to each utility Schedule initial coordination workshop meeting with all utility representatives. Determine the
following as a minimum:
DOT participation in obtaining
easements.
Basis for reimbursement for the
utility, if any.
Conceptual estimate for cost to
relocate the utility facilities.
Conceptual schedule to relocate utility if necessary
Where utilities will be relocated if required.
Potential to design to avoid each utility.
Plan for completing the relocation work.
Utility elevations for their facilities, if available.
Need for sub-surface utility engineering (SUE).
Receive written response to initial notice from each utility:
Determine those in the project’s
conceptual limits.
Determine designated
representative.
Conceptual estimate for the cost of relocation.
Determine which are reimbursable and on what
basis.
Consolidate responses to initial notice Develop list of all reimbursable expenses and estimated cost Review project funding for reimbursable relocations Review risk evaluation of utility coordination deliverables Notify appropriate agencies to have utility facilities marked in the field Notify owner of signals to have buried wires marked in the field Measure and record the location of field markings and facilities Designer include utility facility information on plan sheets
Methods and Tools to Implement an Early Contractor Design Involvement Strategy
ACM Tool Source
ATCs Request of utility-related ATCs on DBB projectsUtility-related information interaction during procurement (RFIs/Confidential meetings)Utility-related incentives/disincentives
MoDOT Content
DB Request of utility-related ATCs Responsive utility PAEAssign contractor responsibility for utility coordination Evaluate utility avoidance approach in proposalUtility-related information interaction during procurement (RFIs/Confidential meetings)Utility-related incentives/disincentives
WSDOT MnDOT TxDOT TxDOT Content
ContentCMGC Assign contractor responsibility for utility coordination
Include contractor support to SUE and utility engineering effort in CMGC preconstruction contract
Utility-related information interaction during procurement (RFIs/Confidential meetings)Utility-related incentives/disincentives
WSDOT Lit Content Content Content
P3 Requesting of utility-related ATCs Responsive utility PAE Leverage P3 contractor’s pro forma financial analysis regarding utility riskAssign contractor responsibility for utility coordination Evaluate utility avoidance approach in proposalUtility-related information interaction during procurement (RFIs/Confidential meetings)Utility-related incentives/disincentives
GDOT MnDOT GDOT GDOT GDOT Content Content
Methods and Tools to Implement Address Utility Company Timeliness Strategy
ACM Tool Source
ATCs Stakeholder panels led by the CMGC/DB/P3 contractor to facilitate a utility
coordination after award
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Leverage existing contractor-utility relationships
MnDOT
WSDOT
Content
Content/Survey
DB Stakeholder panels led by the CMGC/DB/P3 contractor to facilitate a utility
coordination after award
Contractor authority to pay for utility adjustments
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Leverage existing contractor-utility relationships
MnDOT
Content
Content
Content
Content/Survey
CMGC Stakeholder panels led by the CMGC/DB/P3 contractor to facilitate a utility
coordination after award
Contractor authority to pay for utility adjustments
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Leverage existing contractor-utility relationships
MnDOT
Content
Content
Content
Content/Survey
P3 Stakeholder panels led by the CMGC/DB/P3 contractor to facilitate a utility
coordination after award
Contractor authority to pay for utility adjustments
Corridor-level master utility conflict matrix
Leverage existing contractor-utility relationships
MnDOT
Content
WSDOT
Content/Survey
Content/Survey
Methods and Tools to Implement Raised Visibility of Utility-related Issues Strategy
ACM Tool Source
ATCs Request utility-related ATCs on DBB projects
Corridor-level master utility conflict matrix
Utility-related information interaction during procurement (RFIs/Confidential mtgs)
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
MoDOT
WSDOT
Content
Content
Survey
DB Request utility-related ATCs
Utility-related information interaction during procurement (RFIs/Confidential mtgs)
Responsive utility PAE
Weighted utility-related evaluation criteria
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
Lit/content
Content
MnDOT
Content/KYTC
WSDOT
Content
Survey
CMGC Request utility-related info in interview questions
Weighted utility-related evaluation criteria
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
Assign CMGC contractor responsibility to secure final utility agreements
Lit/content
Content/KYTC
WSDOT
Content
Survey
Survey
P3 Request utility-related ATCs
Utility-related information interaction during procurement (RFIs/Confidential mtgs)
Responsive utility PAE
Weighted utility-related evaluation criteria
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
Lit/content
Content
MnDOT
Content/KYTC
WSDOT
Content
Survey
Methods and Tools to Implement Utility Avoidance Strategy
ACM Tool Source
ATCs Include necessary utility data in ACM solicitation
Utility-related incentives/disincentives
Content/KYTC
Content
DB Weighted utility-related evaluation criteria
Include necessary utility data in ACM solicitation documents
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
Content/KYTC
Content
Content
Survey
CMGC Weighted utility-related evaluation criteria
Include necessary utility data in ACM solicitation
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
Content/KYTC
Content
Content
Survey
P3 Weighted utility-related evaluation criteria
Include necessary utility data in ACM solicitation
Corridor-level master utility conflict matrix
Utility-related incentives/disincentives
Include statement of utility strategy intent in solicitation
Content/KYTC
Content
WSDOT
Content Survey
Survey
Methods and Tools to Implement Utility-Related Claims Avoidance Strategy
ACM Tool Source
ATCs Weighted utility-related evaluation criteria
Use a standard utility information report prepared during planning as a
contract document
Definition of utility-related differing site condition
KYTC
MN, TX, &
WSDOT
Content
DB Use a standard utility information report prepared during planning
as a contract document
Definition of utility-related differing site condition
MN, TX, &
WSDOT
Content
CMGC Weighted utility-related evaluation criteria
Use a standard utility information report prepared during planning as a
contract document
Definition of utility-related differing site condition
Content/KYTC
MN, TX,
&WSDOT
Content
P3 Use a standard utility information report prepared during planning as a
contract document
Definition of utility-related differing site condition
MN, TX,
&WSDOT
Content
Methods and Tools to Implement Life Cycle-based ACM Decision-making Strategy
ACM Tool Source
ATCs Require LCC info on ATCs
Include statement of utility strategy intent in solicitation
MoDOT
Survey
DB Require LCC info on ATCs
Include statement of utility strategy intent in solicitation
Lit/Content
Survey
CMGC Include statement of utility strategy intent in solicitation Survey
P3 Include post-construction maintenance
Require LCC info on ATCs
Include statement of utility strategy intent in solicitation
GDOT
Lit/Content/
TxDOT
Survey
UC Guidelines – Chapter 1Chapter/Section
Title Content
Executive Summary A concise review of the important concepts and the business case Brief reference to previous SHRP2-related products.
1Introduction to ACM Utility Coordination
Purpose of the guidelines; Target audience; Definitions of key terminology; Brief description of each ACM
1.1 The Business Case Brief summary of utility coordination issues in the ACM context; Proactive utility coordination strategies found in the research One or two examples of benefits realized on case study project
1.2Generic Project Development Process
Brief overview of a typical federal-aid project’s development process Utility issues that influence design decision at each stage in the project development
process. Graphic of project life cycle timeline showing utility milestones
1.3ACM Selection Decision
Utility issues that influence the decision to not use traditional DBB ACM selection rationale referencing Colorado ACM decision tool Utility issues that must be included in the ACM decision. Utility red flags that indicate reconsidering or dropping ACM delivery
1.4 Utility ACM Strategies Discussion of the development of utility strategies in ACM projects Review of the 6 strategies found in the research Explanation of relating ACMs and related tools to a given strategy
1.5The ACM Utility Coordination Strategy Workshop
Explanation of the workshop’s purpose Reference to workshop template in Appendix D General instructions for planning and executing the workshop Reference to specific instruction is each ACM chapter
1.6How to use the Guidelines
List and short explanation of the various components of the guidelines Instructions on how to access supporting SHRP2 products
UC Guidelines
• One chapter for each specific ACM
• Chapter on ACM contract administration• ACM Utility Identification,
Location, and Coordination Contract Components
• ACM Design Phase Contract Components
• ACM Construction Phase Contract Components
• ACM P3 Maintenance Phase Contract Components
• ACM Dispute Avoidance and Resolution
Design-Build Utility Coordination Flow Chart
Design-Build Utility Coordination Flow Chart (continued)
Pro
cure
me
nt
Stag
eP
re-L
ett
ing
Stag
eP
ost
-Aw
ard
Sta
ge
Pre-Award Activities
Design-Build Project Closeout
Preliminary Engineering Final Engineering Construction
Project RFQ
Utility Coordination Qualifications
Utility Coordination
Technical Req’ts
Develop the DB RFQ/RFP
Select Design-builder
Award DB Contract
Short-List? Project RFP
Utility ATCs Evaluate Utility ATCs
YESApproved ATCs
Evaluate Proposals
Project ProposalsATCs? NO
Assess Utility ATC Impact on
Proposed Strategy
Utility Coordination
Plan
Construction Utility Tasks
Project Complete
Proceed to Post- Award Stage
Pre-Work Conferences
From Procurement
Stage
Conduct Post-award Utility Coordination
Workshop
Updated Utility Risks w/Design-
Builder
SUE QL-B Validation
Final Project Utility
Strategy
Updated Project Risk Register w/Design-builder
Input
Post-Award Risk
Management Conference
Initial Post-Award Design
Conference
Develop SUE/Utility Impact Assessment
SUE/Utility Impact Analysis
SUE QL-A Test Holes, as req’d
Utility Relocation
Plans
Request Utility
Permits
Design-Builder Coordination Meetings w/
Utility Owners as req’d
ID Eligible Reimburse-
ments
Eligible Utility Reimbursements
Reimburse Eligible Utility
Owners
Project As-Builts
This line blurs in DB if work is packaged
Complete Project
Construction
Complete Project Design
Effort
Utility-Related Administrative
Documents
Assign Utility Coord to Design-
builder?
Proposed DB Project Utility
Strategy
Select DB Project Delivery
Develop Utility Coordination
Scope
Project Scope of Work
Utilities High Risk?
Develop Utility Input to
Procurement Documents
YES
NO
Project Risk Register
Identified Utility Risks
SUE QL-B Overlay on Conceptual
Plans
Utilities Risk a
Driver?
NO
YES
Conduct Initial Utility Coordination
Workshop with Utility Owners
Draft Utility MOUs
Pre-Let Utility Risk Mitigation
Plan
Pre-Procurement
Administrative Tasks
YESNO
YES
Update SUE/
Utility Inventory
Proposal Validation;Partnering; Etc.
Questions???