efficacy of water spray protection against butane jet ... · efficacy of water spray protection...
TRANSCRIPT
-
Efficacy of water spray protection against butane jet fires impinging on Liquefied
Petroleum Gas (LPG) storage tanks
Prepared by Shell Global Solutions (UK)
for the Health and Safety Executive
CONTRACT RESEARCH REPORT 298/2000
-
Efficacy of Water Spray Protection Against Butane Jet FiresImpinging on LPG Storage Tanks
LC Shirvill and JF BennettHSE Consultancy
Shell Global Solutions (UK)Cheshire Innovation Park
PO Box 1CHESTER
CH1 3SH
Liquefied Petroleum Gas (LPG) storage tanks are often provided with water sprays to protectthem in the event of a fire. In 1996 a project (Contract No. 3383/R75.009) was undertaken tostudy, at full-scale, the performance of a water spray system on an empty 13 tonne LPG vesselunder conditions of jet fire impingement from a nearby release of liquid propane. The results,reported in HSE report CRR 137/1997, showed that a typical water deluge system found on anLPG storage vessel cannot be relied upon to maintain a water film over the whole vesselsurface in an impinging propane jet fire scenario.
The objective of the work described in this report (Contract No. 3985/R75.041) was to extendthe understanding to include butane jet fires. These were known to have somewhat differentcharacteristics and may result in different conclusions to those drawn from the earlier workwith propane.
A total of twenty butane tests are reported and these provide a direct comparison with thepropane study. The results were in fact similar in that the water deluge did not always preventdry patches appearing along the top of the vessel, although these were generally smaller thanwith the propane jet fires. The deluge also had a similar significant effect on the fire itself,reducing the luminosity and smoke, and resulting in a lower rate of wall temperature rise at thedry patches, when compared with the un-deluged case. One of the tests was repeated and runfor a longer duration, 10 minutes, at which time the maximum temperature of the small drypatch had stabilised at 360oC. In the final test this was repeated again for more than twice thistime, but with one of the spray nozzles blocked to produce a larger dry patch. The maximumtemperature of this larger patch stabilised at 580oC. At this temperature the steel wall will beseverely weakened but may not necessarily fail.
The results of this study will be used by the HSE in assessing the risk of accidental fires onLPG installations leading to BLEVE incidents.
This report and the work it describes were funded by the Health and Safety Executive. Itscontents, including any opinions and/or conclusions expressed, are those of the author(s) aloneand do not necessarily reflect HSE policy.
-
Crown copyright 2000 Applications for reproduction should be made in writing to: Copyright Unit, Her Majestys Stationery Office, St Clements House, 2-16 Colegate, Norwich NR3 1BQ First published 2000 ISBN 0 7176 1856 0 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the prior written permission of the copyright owner.
ii
-
iii
CONTENTS
1. INTRODUCTION............................................................................................................1
2. EXPERIMENTAL PLAN ................................................................................................1
3. DESCRIPTION OF EQUIPMENT..................................................................................2
3.1 BUTANE SUPPLY AND DISCHARGE SYSTEM ....................................................2
3.2 BUTANE FLOW MEASUREMENT..........................................................................2
3.3 BUTANE PRESSURES AND TEMPERATURES .....................................................4
3.4 TARGET VESSEL AND TEMPERATURE MEASUREMENTS ..............................4
3.5 DELUGE WATER SUPPLY AND DELIVERY SYSTEM.........................................6
3.6 AMBIENT WEATHER MONITORING ....................................................................8
3.7 DATA LOGGING ......................................................................................................8
3.8 PHOTOGRAPHY AND VIDEO.................................................................................9
4. RESULTS AND DISCUSSION .......................................................................................9
4.1 TESTS DEL0401 TO DEL0423 .................................................................................9
4.2 TESTS DEL0424 AND DEL0425 ............................................................................14
5. CONCLUSIONS ............................................................................................................17
6. REFERENCES...............................................................................................................17
7. APPENDICIES A-T .......................................................................................................18
-
iv
-
1
1. INTRODUCTION
Liquefied Petroleum Gas (LPG) storage tanks are often provided with water sprays, referred toas water deluge, to protect them in the event of a fire. This protection has been shown to beeffective in a pool fire(1) but uncertainties remained regarding the degree of protection affordedin a jet fire resulting from a liquid or two-phase release of LPG. The essential differencebetween a pool fire and a jet fire is that the latter can result in higher velocities and in theextreme case of a high-pressure natural gas jet fire water deluge has been shown to be totallyineffective(2).
In 1996 a project (Contract No. 3383/R75.009) was undertaken to study, at full-scale, theperformance of a water spray system on an empty 13 tonne LPG vessel under conditions of jetfire impingement from a nearby release of liquid propane. The results, reported in HSE reportCRR 137/1997(3), showed that a typical water deluge system found on an LPG storage vesselcannot be relied upon to maintain a water film over the whole vessel surface in an impingingpropane jet fire scenario. The results of this study have been used by the HSE in assessing therisk of accidental fires on LPG installations leading to BLEVE incidents, but they are specificto propane fires only.
The objective of the work described in this report was to extend the understanding to includebutane jet fires, using the same equipment and a similar experimental plan to provide a directcomparison with the propane study. Butane jet fires were known to have somewhat differentcharacteristics and it was felt that this may result in different conclusions to those drawn fromthe earlier work with propane.
Section 2. of this report describes the experimental plan, developed in consultation with theHSE sponsor, and Section 3. describes the equipment used. Selected results are presented anddiscussed in Section 4. The complete sets of results for each of the twenty valid tests arecontained in Appendices A-T. Section 5. presents the conclusions drawn from the work,however it should be noted that the data gathered has only been analysed to the extent that itcould be accurately presented. A more detailed analysis may reveal additional features.
2. EXPERIMENTAL PLAN
The plan was to repeat the earlier propane study using butane to provide a direct comparison.The same hole sizes and distances, based on credible accident scenarios considered in the HSEmodel ALIBI (Assessment of LPG Installations leading to Bleve Incidents)(4), were used.
The butane jet fires, from 12.5, 25 and 50 mm holes, were to impinge on a target vessel (anempty 13 tonne LPG tank) from distances of 1, 3 and 5 m. The parametric study was basedon this 3x3 test matrix and each set of conditions were to be carried out both with the waterdeluge on before the fire, and with a 30 s delay in initiating the deluge. It was decided that theshort duration tests without any water deluge, carried out in the propane study, would not berepeated as sufficient data on heat transfer without water could be obtained during the first 30 sof the delayed deluged tests.
-
2
Our aim was to release butane under conditions closely similar to those that would occur if apipe were punctured or severed on an LPG installation. The 12.5 and 25 mm holes were to besharp-edged orifice plates on the end of a 50 mm pipe to achieve liquid releases ofapproximately 1 and 4 kg/s, respectively. The 50 mm release would be full-bore from the pipe,resulting in a liquid release of approximately 9 kg/s.
The tests were to be of longer duration than typically used in the earlier propane study, and iftime permitted one test would be repeated and run for at least 10 minutes.
3. DESCRIPTION OF EQUIPMENT
The equipment used was the same as in the earlier propane tests, but with some modificationsto more precisely control the discharge conditions, and more thermocouples on the target vesselto achieve better spatial resolution.
3.1 BUTANE SUPPLY AND DISCHARGE SYSTEM
A schematic diagram of the butane supply, control and measurement system is shown inFigure 1. The LPG storage tank, containing commercial grade butane, was elevated to achievea positive liquid head at the discharge orifice. The objective was to maintain the liquid butaneat just above its vapour pressure at the point of discharge and to achieve this in a controlledmanner it was necessary to over-pressure the storage with nitrogen. During the tests, thenitrogen pressure was maintained using an Alfa Laval ECA-40 controller and Valtek pressurecontrol valve. Using this arrangement some nitrogen becomes dissolved in the butane. Sampleswere taken after two of the tests and analysed, the results are given in Section 4.
The butane was discharge from the tank through three independent valves into a common50 mm i.d. pipe into an existing supply line. This line was constructed from 149 mm i.d.stainless steel pipe and extended for about 25 metres between the storage tank and thedischarge platform. Several manual and remotely operated valves were located in the line,together with thermal pressure relief valves. At the discharge platform the line reduced to50 mm i.d. stainless steel and terminated in the final, remotely operated, valve used to initiatethe release. Spool pieces, also 50 mm internal diameter, were used beyond the final valve toachieve the three discharge distances of 1, 3 and 5 metres. Details of the discharge distancesare shown in Figure 2. The 12.5, 25.0 mm releases were through sharp-edged orifice plates andthe 50 mm release was full-bore.
3.2 BUTANE FLOW MEASUREMENT
The mass flow rate of the butane was measured using a Coriolis-force mass flow meter,mounted in the butane delivery line, approximately 8 m upstream of the final valve. This flowmeter comprised a Micro Motion flow sensor and a mass flow transmitter. The sensor wascalibrated by the manufacturer and is accurate to within 0.5% of the mass flow rate. The massflow transmitter relayed the output of the flow sensor to the data logging system, described inSection 3.7. The butane mass flow rate achieved was not controlled but governed by thediameter of the release orifice and the exit conditions.
-
3
2 inch LPG discharge line
N
LPG storage tank
Water storage tanks
Water pump
Water recirculation
Buffer tank
6 inch LPG discharge line
Target vessel
Water supply
Nitrogen source
LPG:- mass flow rate, kg/s.
Water:- flow rate, l/min. pressure, barg.
Exit conditions:- pressure, barg., temperature, deg C.
Vapour pressure make-up
Tank liquid head conditions:- pressure, barg. temperature, deg C.
Tank vapour head conditions:- pressure, barg.
Figure 1Schematic diagram of fuel / water storage and release systems
10003000
5000
Figure 2Fuel discharge point locations
-
4
3.3 BUTANE PRESSURES AND TEMPERATURES
The static pressure and temperature of the butane was measured at a number of locations.Pressure and temperature at the exit of the storage tank, together with pressure and temperatureclose to the release point.
The storage tank liquid head pressure was measured using an Ellison Sensors Intl Ltd.PR3100 pressure transmitter located in the liquid discharge from the tank. The range of thisinstrument was 0-20 bar, with a typical accuracy of 1.0% full scale, and a calibration wasperformed prior to installation. This instrument also served the Alfa Laval ECA-40 controllerto maintain the nitrogen pressure blanket on the storage tank.
A further Ellison Sensors Intl Ltd. PR3100 pressure transmitter, with a measuring range of 0-6 bar, with a typical accuracy of 1.0% full scale, was used to measure the pressure at the exitmeasurement position, 0.2 m upstream of the release point. The transmitter was calibrated onsite, before and after the test series, using a Druck DPI 600 series digital pressure calibrator.
The butane temperature was measured in the supply line and at the exit measurement position,using stainless steel sheathed mineral insulated type T thermocouples protruding inside thepipe. The thermocouple has an accuracy of 0.5C, and was connected via suitablecompensating cable to the data logger.
Data from the pressure transducers and temperature transmitters were recorded on the loggingsystem described in Section 3.7 and converted to engineering units by applying the relevantcalibration coefficients for each instrument.
3.4 TARGET VESSEL AND TEMPERATURE MEASUREMENTS
The target vessel was a redundant 13 tonne LPG storage bullet which had been modified forthese experiments. The cylindrical shell was 2.17 m dia. x 7.5 m long, and fitted withtorispherical end caps. The total surface area of the vessel was estimated to be 61.3 m2 (basedon the simplifying assumption of spherically dished end caps), 51.15 m2 over the developedcylindrical surface. To measure the temperature of the 12 mm thick wall of the shell, 85thermocouples were attached to the internal surface. These comprised the original locations, 1to 56 for tests prior to this series plus an extra 29 thermocouples, 57 to 85. These were placedin an area that could be subjected to hot spots and could therefore provide increasedresolution of the surface temperatures. The locations of these thermocouples are indicated anddefined in Figures 3 to 5.
At all locations the thermocouples were attached directly to the steel by capacitance dischargewelder. The welder, type TAU, was supplied by Cooperheat Ltd. Solid conductor, 0.7 mmdia., type 'K' thermocouple wire supplied by Omega was used. Each leg of the thermocouplewas welded separately to the steel, approximately 5 mm apart. Thus the steel becomes part ofthe thermocouple junction and the thermocouple accurately and unambiguously measures thesteel temperature. The thermocouple cable was extended out of and beyond the vessel into ajunction box. In this box type 'K' connector blocks were used to transfer the thermocoupleoutput signals into multicored type 'V' compensating cables and hence to the data collectionpoint.
-
5
A B C D E F G H I
Centre line of vessel
CA DADB
EAEB
FA
1000.0
2000.0
2375.0
2750.0
3125.0
3312.5
3500.0 to Centre Line
3687.5
3875.0
4250.0
4625.0
5000.0
6000.0
7000.0
Figure 3Thermocouple ring locations
3
2
1
4
7
6
5
8
13
12
11
10
9
16
15
14
6870
29
28
27
26
25
32
31
30
45
44
43
42
41
48
47
46
51
50
49
52
55
54
53
56
Ring A Ring B Ring C
Ring DB Ring E Ring EA
Ring G Ring H Ring I
FlameDirection
59
576160
63
66
Ring CA
Ring DA Ring EB
Ring F Ring FA
58
21
20
19
18
17
24
23
22
Ring D
62
65
67 64 6971 7274
7375
78
77
79 76
37
36
35
34
33
40
39
38
80
83
818584
82
Figure 4Thermocouple locations on the various rings
The type 'K' thermocouple wire used to measure the vessel temperatures was supplied totolerance class 2 (International Thermocouple Reference Tables: IEC 584-2:1882 and BS 4937Part 20:1983), giving a tolerance value of +/- 2.5C or 0.0075 x T, which ever is the greatest,
-
6
within the limits of -40C to +1200C. Although suitable for lower temperatures, thesethermocouples may not meet the tolerance value below -40C.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 62
63
64
65
66
67
68
69
7071
72
73
7475
76
77
78
79 80
81
82
83
84
85
3 7 13 21 29 37 45 51 55
A B C D E F G H I
Rear
Top of vessel
Front
Bottom
O Water spraynozzleThermocouple+
Bottom
Bottom rear
Top rear
Top front
Bottom front
Figure 5Development of thermocouple locations
3.5 DELUGE WATER SUPPLY AND DELIVERY SYSTEM
The deluge system was designed by Wormald Fire Systems to achieve a minimum applicationrate of 10.2 litres/min./m2 over the whole exposed surface of the vessel, in accordance withNFPA 15(5). This design was originally used in an investigation of the efficacy of water delugesystems used on offshore facilities(2) but it is identical to that commonly used to protect LPGstorage bullets, the design application rate being just above the minimum of 9.8 litres/min./m2specified in HSG 34(6).
Twenty four spray nozzles were used in sets of four around the vessel at an axial spacing of1475 mm, Figure 6. This Wormald design called for a total water flow rate into the system of1064 litres/min. delivered at 2.4 barg, and this was the nominal flow rate used in all of thetests. The vessel is 2.17 m dia. thus each set of four nozzles is spraying on an area of 10.06 m2.It is interesting to note that this results in an actual application rate of 17.6 litres/min./m2 onthe cylindrical shell of the vessel, some 73% excess over the design value. This large excess isapparently an inevitable consequence of incremental spray nozzle sizes, the minimum spacing
-
7
required to ensure complete coverage and the hydraulic gradient required to achieve a minimumpressure of 1.4 barg at the most hydraulically remote nozzle, in this particular case.
Centre line of vessel
1475 147514751480 1480 2460
2460
Figure 6The target vessel indicating deluge nozzles
The spray nozzles were Wormald type MV21-110, manufactured from leaded-gunmetal withbrass diffuser plates.
Figure 7, shows a photograph of the deluge operating and it can be seen that a water film wasobtained over the whole surface of the vessel.
Figure 7The target vessel with deluge nozzles operating
The layout of the water supply system is included in Figure 1. Water for the deluge was storedin two large tanks in which the levels were balanced. A single outlet supplied water to a skidmounted water pump driven by a diesel engine. The speed of the pump could be varied
-
8
manually. Water was discharged into a 150 mm nominal bore pipe leading to the delugesystem. Remotely operated valves enabled the water to be recirculated to the storage tanks.This arrangement permitted the pump engine to be brought up to operating temperature underworking conditions and also enabled water at the required rate to flow into the deluge system atthe desired instant during delayed deluge experiments.
Deluge water pressure was measured with a Druck series PTX500 static pressure transducer.This instrument operated within the range of 0 to 10 barg with a typical accuracy of +/-1.0% offull scale and was calibrated on site using a Druck TPI 600 series digital pressure calibrator.The water flow rate was measured using a Krohne IFM1080 flow meter uprated to operatebetween 0 and 3000 litres/min. This instrument was supplied with a calibration produced bythe Dutch Office of Measures and Weights. An uncertainty of +/-1.0% is quoted by thesupplier.
3.6 AMBIENT WEATHER MONITORING
Equipment was deployed to monitor the ambient weather conditions in the vicinity of the testfacility. The wind speed was monitored using four Vector Instruments A100 cup typeanemometers, located at heights of 1.2, 2.9, 6.0 and 6.4 m above the discharge axis on weathermast located to the west of the facility. The wind conditions were also measured using a GillInstruments, Solent logging ultrasonic anemometer, located at a height of 10.0 m above theground, equating to 8.2 m above the discharge axis. This instrument provided horizontal andvertical wind speed components together with the wind direction.
The cup type anemometers can measure wind speed in the range 0 to 25 m/s and the accuracyis quoted by the manufactures as 1%. The ultrasonic anemometer is capable of measuringhorizontal wind speeds in the range 0 to 60 m/s. The wind speed accuracy is 2.5% between 0and 30 m/s. The accuracy of the vertical component is within 5% of the horizontalcomponent. Wind direction is measured in meteorological format i.e. as the direction the windis coming from, measured clockwise from north, with an accuracy of 2% for wind speedsbetween 0 and 30 m/s.
The ambient temperature and relative humidity were measured using a Vaisala HMD 30YBtransmitter. This instrument was mounted on the control cabin roof. The atmospheric pressurewas also monitored using a Vaisala PTA427 transmitter. The accuracy of the measurements,quoted by the manufacturers, are 0.2C for the temperature, 2% for the relative humiditybetween 0 and 90% and 3% between 90 and 100%, and 0.2 mbar for the atmosphericpressure.
Data from all the ambient weather monitoring equipment was recorded on the logging systemdescribed in Section 3.7 and converted to engineering units applying the relevant calibrationcoefficients for each instrument.
3.7 DATA LOGGING
Data from all instruments were recorded using a PC based computer logging system. Thissystem is based on multiplexing of signals at remote locations using equipment manufacturedby Computer Instrumentation Limited. The concept of using this approach is based on limitingthe amount of cabling running between the computer and the instrumentation. Individual cablesfrom the instruments are fed into a multiplexer system located close to a group of instrumentsfrom which only one signal cable is returned to the computer. This system also has the addedadvantage that signals can be amplified by the multiplexer close to their source, thus avoidingthe transmission of small signal levels over long distances.
-
9
Each instrument channel was sampled at once per second for the duration of each test.
3.8 PHOTOGRAPHY AND VIDEO
A video and photographic record was made of each test.
4. RESULTS AND DISCUSSION
4.1 Tests DEL0401 to DEL0423
To complete the 3x3x2 test matrix (12.5, 25 and 50 mm holes, from distances of 1, 3 and 5 m,with deluge on before the fire, and with a 30 s delay) a total of 23 tests were carried out toachieve 18 valid tests. Tests DEL0401, DEL0406, DEL0407, DEL04014 and DEL04015 weredeemed invalid, due to sudden changes in the wind or failure to reach steady flow conditions,and are not reported. Table 1 shows hole sizes, stand-off distances, and series test numbers forthe 18 valid tests, together with the time averaging period used in deriving the subsequent datatables. Each test was run for at least 3 minutes and stopped when the vessel temperaturesappeared to have stabilised, or in one case just under 7 minutes was reached.
Table 1Series test numbers and averaging periods
Deluge on Deluge delayed by 30 s.
Hole dia., mm Stand offdistance, m.
Test number Averagingperiod, s.
Test number Averagingperiod, s.
12.5 1 DEL0402 9 to 335 DEL0403 56 to 277
12.5 3 DEL0417 9 to 402 DEL0416 57 to 244
12.5 5 DEL0418 7 to 364 DEL0419 97 to 279
25.0 1 DEL0404 6 to 231 DEL0405 57 to 235
25.0 3 DEL0412 4 to 302 DEL0413 56 to 252
25.0 5 DEL0420 6 to 302 DEL0421 57 to 243
50.0 1 DEL0408 9 to 243 DEL0409 62 to 302
50.0 3 DEL0410 20 to 208 DEL0411 56 to 221
50.0 5 DEL0422 8 to 242 DEL0423 63 to 302
Table 2 shows the time averaged wind speeds and directions for each test. The averaged windspeeds of between 3 and 10 m/s were slightly higher than those encountered in the earlierpropane tests, 1.6-7.8 m/s. A south westerly co-flowing wind would have ensured that the jetfire was central on the target vessel, however, a cross wind generally from the quadrantbetween west and north was deemed acceptable.
-
10
Table 2Series winds speeds and directions
Deluge on Deluge delayed by 30 s.
Hole dia., mm Stand offdistance, m.
Wind speed,m/s
Winddirection,
degs.
Wind speed, m/s Winddirection,
degs.12.5 1 2.98 8 2.49 314
12.5 3 3.87 271 4.27 271
12.5 5 6.40 260 8.64 261
25.0 1 3.09 276 3.11 280
25.0 3 3.78 262 3.60 266
25.0 5 10.06 264 7.70 264
50.0 1 2.83 284 2.86 289
50.0 3 2.92 250 3.03 249
50.0 5 9.23 265 9.23 267
Table 3 shows the butane discharge conditions for each test. The nitrogen used to over-pressurethe butane storage was just sufficient to achieve fully liquid releases. The exit temperature,measured just upstream of the hole, remained close to ambient, confirming that no flashing hadoccurred at that point and that fully liquid releases had been achieved.
Table 3Series discharge conditions
Deluge on Deluge delayed by 30 s.
Hole dia.,mm
Stand offdistance,
m.
Mass flowrate, kg/s
Exittemperature,
deg C
Exitpressure,
barg.
Massflow
rate, kg/s
Exittemperature,
deg C
Exitpressure,
barg.12.5 1 1.00 10.1 1.3 1.01 8.9 1.3
12.5 3 1.02 7.6 1.4 1.03 7.6 1.4
12.5 5 1.01 7.1 1.4 0.90 6.5 1.4
25.0 1 3.87 6.6 1.2 3.86 6.6 1.2
25.0 3 3.77 8.1 1.5 3.63 8.0 1.6
25.0 5 4.02 8.0 1.4 3.88 8.8 1.4
50.0 1 9.40 5.6 1.0 8.71 4.5 1.0
50.0 3 8.94 5.5 1.2 8.54 T/C failed 1.3
50.0 5 9.61 8.3 1.1 9.10 7.8 1.1
-
11
Liquid butane samples were taken from the storage tank part way through use of the first andsecond deliveries of commercial butane. The results are shown in Table 4. Both samplescontained some propane, which is not uncommon in commercial butane. As expected a smallamount of the nitrogen used to over-pressure the storage had dissolved in the butane
Table 4Analysis of butane samples
Component Sample 1% mole
Sample 2% mole
Propane 11.6 4.0
Isobutane 21.1 21.9
N-butane 65.2 70.7
Trans-2-butene 0.1 0.1
Isopentane 1.4 2.6
N-pentane 0.2 0.5
Nitrogen 0.3 0.2
The full results from each of the 18 tests are contained in Appendices A to R. Each appendixcontains:
a summary of the test conditions
Figure x1 showing the fuel conditions during the test
Figure x2 showing the water deluge conditions during the test
Figures x3-x17, for each ring of thermocouples, showing the target vessel temperaturesduring the test
Figures x18 and x19, development of the vessel surface with temperature contours, at 30 safter ignition on the delayed deluge tests only, and for all at the end of the test .
Table 5 summarises the results, showing the different vessel wall temperature regimes found ineach test. The 120oC criterion, also used in the earlier propane study, was chosen based on thework of Lev and Strachan(7) which showed that this temperature may be taken as "indicative ofhaving achieved critical conditions for failure of the water film".
Table 5 shows that when starting with the deluge on, only the larger releases result in drypatches. The largest dry patch being in test DEL0422 (50 mm hole, 5 m distance) where 4thermocouples exceeded 120oC, also see Appendix Q, Figure Q18.
With the deluge delayed by 30 seconds dry patches are more readily formed but for the smallesthole size these do not persist. Again the largest dry patch occurred with the largest hole and thegreatest distance, test DEL0423, also see Appendix R, Figure R19.
-
12
Table 5Series temperature regimes
Deluge on Deluge delayed by 30 s.
Hole dia.,mm
Stand offdistance,
m.
Maximumtemp., deg
C
Numberof T/Csexceeding120 deg C
Numberof T/Csstaying inexcess of120 deg C
Maximumtemp., deg
C
Numberof T/Cs
exceeding120 deg C
Number ofT/Cs
staying inexcess of120 deg C
12.5 1 93 0 0 137 10 0
12.5 3 95 0 0 137 10 0
12.5 5 98 0 0 98 0 0
25.0 1 103 0 0 185 19 1
25.0 3 101 0 0 239 30 7
25.0 5 174 1 1 283 18 6
50.0 1 140 1 1 229 28 3
50.0 3 107 0 0 292 26 4
50.0 5 233 4 4 332 20 8
Figure 8 shows an example of some target vessel wall temperatures during test DEL0409(50 mm hole, 1 m distance, delayed deluge). The thermocouple responses plotted were chosento illustrate the different types of behaviour found in all of the tests. The last two digits of theidentifier give the thermocouple location, see Figure 5 in Section 3.4, thus TK-40925 isthermocouple 25 located at the top of the vessel in the centre.
0
50
100
150
200
250
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
pera
ture
, deg
C. TK-40925
TK-40963
TK-40964
TK-40966
TK-40969
120 degs
Figure 8Example of wall temperatures during test DEL0409
-
13
The water deluge was initiated 30 seconds after ignition and the flow fully established by50 seconds. At some thermocouples locations, e.g. 63 and 64, a water film was quicklyestablished and the wall temperature never exceeded the 120oC criterion. At location 66 a waterfilm was established at 50 seconds even though the wall had initially exceeded 120oC. Atlocations 69 and 25 it is clear that once the water flow is fully established the rate oftemperature rise is reduced. After 90 seconds a water film is established at location 69 and thetemperature drops 120oC. At location 25, the temperature continues to rise at the reduced rate.
This reduced rate of temperature rise of dry patches was also seen in the earlier propane studyand results from the combustion process being affected by the water sprays. Less soot isformed in the flame resulting in less luminosity and a reduction in the heat transfer by radiationto the vessel surface. This is most clearly illustrated by reference to Figures 9 and 10. Thesephotographs were taken during test DEL0413, before and after establishment of the deluge.
Figure 9Test DEL0413 before deluge
Figure 10Test DEL0413 with deluge
-
14
In all of the tests where this behaviour was observed (DEL0409, DEL0411, DEL0413 andDEL0423) we have estimated the reduction in the rate of temperature rise at dry patches bycomparing the essentially linear temperature rise before the water comes on, with thatimmediately after the deluge has become fully established. The results do not allow specificreductions in rate of temperature rise or heat transfer to be associated with particularconditions, but typically the reduction is a factor of between 2 and 5, similar to that found withpropane (between 1.5 and 5.8) (3).
Some releases from 1 m and 3 m resulted in liquid butane impinging on the target vessel withlocal low temperatures on the vessel wall. Test DEL0409 is a good example, see Appendix F,Figures F18 and F19. In some tests some liquid butane poured onto the ground after hitting thevessel and produced a pool fire under the vessel.
4.2 TESTS DEL0424 AND DEL0425
Test DEL04024 was a repeat of test DEL0413 (25 mm hole, 3 m distance, delayed deluge) runfor 10 minutes to establish the equilibrium temperature reached by a small dry patch. TestDEL04025 was a further repeat of this test, but with one nozzle blocked to induce a larger drypatch, and run for more than 20 minutes to establish the equilibrium temperature reached by alarger dry patch.
Table 6 shows hole sizes, stand-off distances, and series test numbers for these two tests,together with the time averaging period used in deriving the subsequent data tables.
Table 6Long duration test numbers and averaging periods
Deluge on Deluge delayed by 30 s.
Hole dia., mm Stand offdistance, m.
Test number Averagingperiod, s.
Test number Averagingperiod, s.
25.0 3 DEL0424 59 to 611
25.0 3 DEL0425 57 to 1578
Table 7 shows the time averaged wind speeds and directions for each test.
Table 7Long duration tests wind speeds and directions
Deluge on Deluge delayed by 30 s.
Hole dia., mm Stand offdistance, m.
Wind speed,m/s
Winddirection,
degs.
Wind speed, m/s Winddirection,
degs.25.0 3 5.55 259
25.0 3 7.40 261
-
15
Table 8 shows the butane discharge conditions for each test.
Table 8Long duration tests discharge conditions
Deluge on Deluge delayed by 30 s.
Hole dia.,mm
Stand offdistance,
m.
Mass flowrate, kg/s
Exittemperature,
deg C
Exitpressure,
barg.
Massflow
rate, kg/s
Exittemperatur
e, deg C
Exitpressure,
barg.25.0 3 4.31 7.7 1.5
25.0 3 4.57 6.9 1.5
The full results from both of the tests are contained in Appendices S and T. Each appendixcontains:
a summary of the test conditions
Figure x1 showing the fuel conditions during the test
Figure x2 showing the water deluge conditions during the test
Figures x3-x17, for each ring of thermocouples, showing the target vessel temperaturesduring the test
Figures x18 and x19, development of the vessel surface with temperature contours, at 30 safter ignition on the delayed deluge tests only, and for all at the end of the test .Table 9summarises the results, showing the different vessel wall temperature regimes found in eachtest.
Table 9Long duration tests temperature regimes
Deluge on Deluge delayed by 30 s.
Hole dia.,mm
Stand offdistance,
m.
Maximumtemp., deg
C
Numberof T/Csexceeding120 deg C
Numberof T/Csstaying inexcess of120 deg C
Maximumtemp., deg
C
Numberof T/Cs
exceeding120 deg C
Number ofT/Cs
staying inexcess of120 deg C
25.0 3 372 27 6
25.0 3 581 19 13
-
16
Figure 11 shows some of the dry spot wall temperatures during tests DEL0424 and DEL0425.
Dry spot temperatures
0
100
200
300
400
500
6000 60 120
180
240
300
360
420
480
540
600
660
720
780
840
900
960
1020
1080
1140
1200
1260
1320
1380
1440
1500
1560
Time from ignition, s.
Tem
per
atu
re, d
eg, C
.
TK-42517
TK-42560
TK-42561
TK-42562
TK-42566
TK-42567
120 degs
TK-42417
TK-42457
Figure 11Dry spot wall temperatures during tests DEL0424 and DEL0425
The maximum temperature reached by the small dry spot (thermocouple location 17) in testDEL0424 was 360oC after 10 minutes. See also Appendix S, Figure S19, for details of the dryspot.
The maximum temperature reached by the large dry spot (thermocouple location 62) in testDEL0425 was 580oC. It appears that thermocouple location 67 may be on the edge of the drypatch as the temperature was falling during the second half of the test. The gap in the dataaround 23 minutes was caused by the necessity to change disks in the data logging system. Seealso Appendix T, Figure T19, for details of the dry spot. The blocked water spray nozzle wasthe one above thermocouple location 24, see Figure 5 in Section 3.4.
At the maximum temperature of 580oC the steel wall will be severely weakened but may notnecessarily fail, resulting in a BLEVE if the vessel had contained LPG.
Figure 12Test DEL0425
-
17
5. CONCLUSIONS
The following conclusions are based on an analysis of the data sufficient only to allow it to beaccurately reported. A more detailed analysis may reveal additional features.
1. The results from the twenty tests reported show that a typical water deluge systemfound on an LPG storage tank cannot be relied upon to maintain a water film over thewhole tank surface in an impinging butane jet fire scenario.
2. The results are similar to those found in the earlier propane work, although any drypatches were generally smaller with the butane jet fires. The deluge also had a similarsignificant effect on the fire itself, reducing the luminosity and smoke, and resulting ina lower rate of wall temperature rise at the dry patches, when compared with the un-deluged case, typically by a factor between 2 and 5.
3. The equilibrium temperature reached by a small dry patch was about 360oC after 10minutes, in one repeated test, run until an equilibrium temperature had been reached.
4. The equilibrium temperature reached by a larger dry patch, induced by blocking one ofthe spray nozzles, was 580oC after about 20 minutes.
5. Some releases resulted in liquid butane impinging on the target vessel with local lowtemperatures on the vessel wall. In some tests some liquid butane poured onto theground after hitting the vessel and produced a pool fire under the vessel.
6. REFERENCES
1. Billinge, K, Moodie, K and Beckett, H. The use of Water Sprays to Protect Fireengulfed Storage Tanks, 5th International Symposium on Loss Prevention and SafetyPromotion in Process Industries, 1986.
2. Shirvill, LC and White, GC. Effectiveness of Deluge Systems in Protecting Plant andEquipment Impacted by High-Velocity Natural Gas Jet Fires, ICHMT 1994International Symposium on Heat and Mass Transfer in Chemical Process IndustryAccidents, Rome 1994.
3. Bennett, JF, Shirvill, LC and Pritchard, MJ. Efficacy of Water Spray ProtectionAgainst Jet Fires Impinging on LPG Storage Tanks, HSE Contract Research Report137/1997.
4. Goose, MH. Recent Developments with ALIBI, a Model for Site Specific Prediction ofLPG Tank BLEVE Frequency, IChemE Symposium Series No. 139, Major HazardsOnshore and Offshore II, Manchester 1995.
5. NFPA 15, Water Spray Fixed Systems, National Fire Protection Association.
6. HSG 34, The Storage of LPG at fixed Installations, HMSO.
7. Lev, Y and Strachan, DC. A Study of Cooling Water Requirements for the Protectionof Metal Surfaces Against Thermal Radiation, Fire Technology, August 1989.
-
18
7. APPENDICIES A-T
-
19
Appendix A - DEL0402
Averaging period 9 - 335 seconds after ignition
Summary of Release Exit Conditions
Discharge hole diameter: 12.50 mmStand-off Distance: 1.00 mButane mass flow rate: 1.02 kg/sExit static pressure: 1.33 bargExit temperature 10.13 deg. C
Deluge Flow
Water sprays: Deluge onWater pressure 2.35 bargWater flow rate 1069.75 litres/min
Ambient Weather Conditions
Wind speed (cup anemometer 1 at 1.2m) 2.7 m/sWind speed (cup anemometer 2 at 2.9m) 2.8 m/sWind speed (cup anemometer 3 at 6.0m) 3.1 m/sWind speed (cup anemometer 4 at 6.4m) 3.2 m/sHorizontal wind speed (sonic at 8.2m) No data m/sVertical wind speed (sonic at 8.2m) No data m/sWind direction 8.31 degrees clockwise from NorthRelative humidity 87.2 %Ambient temperature 12.2 deg CAtmospheric pressure 961.1 mbar
Thermocouples not operating properly
15, 79
-
20
Fuel flow 0402
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Mas
s fl
ow
, kg
/s&
Pre
ssu
re, b
arg
. Mass flow , kg/s
Vapour pressure,bargLiquid headpressure, bargDischargepressure, barg
Figure A1 - Fuel conditions
Water flow 0402
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Pre
ssu
re, b
arg
& F
low
m^3
/min
Water pressure,barg
Water flow rate,m^3/min
Figure A2 - Water deluge conditions
-
21
Ring A
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40201
TK-40202
TK-40203
TK-40204
120 deg C.
Figure A3 - Temperatures - thermocouples 1 - 4
Ring B
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40205
TK-40206
TK-40207
TK-40208
120 deg C.
Figure A4 - Temperatures - thermocouples 5 - 8
-
22
Ring C
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40209
TK-40210
TK-40211
TK-40212
TK-40213
TK-40214
TK-40215
TK-40216
120 deg C.
Figure A5 - Temperatures - thermocouples 9 - 16
Ring CA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40257
TK-40258
TK-40259
TK-40260
TK-40261
120 deg C.
Figure A6 - Temperatures - thermocouples 57 - 61
-
23
Ring D
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40217
TK-40218
TK-40219
TK-40220
TK-40221
TK-40222
TK-40223
TK-40224
TK-40262
120 deg C.
Figure A7 - Temperatures - thermocouples 17 - 24 plus 62
Ring DA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40263
TK-40264
TK-40265
TK-40266
TK-40267
120 deg C.
Figure A8 - Temperatures - thermocouples 63 - 67
-
24
Ring DB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40268
TK-40269
TK-40270
120 deg C.
Figure A9 - Temperatures - thermocouples 68 - 70
Ring E
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40225
TK-40226
TK-40227
TK-40228
TK-40229
TK-40230
TK-40231
TK-40232
TK-40271
120 deg C.
Figure A10 - Temperatures - thermocouples 25 - 32 plus 71
-
25
Ring EA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40272
TK-40273
TK-40274
120 deg C.
Figure A11 - Temperatures - thermocouples 72 - 74
Ring EB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40275
TK-40276
TK-40277
TK-40278
TK-40279
120 deg C.
Figure A12 - Temperatures - thermocouples 75 - 79
-
26
Ring F
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40233
TK-40234
TK-40235
TK-40236
TK-40237
TK-40238
TK-40239
TK-40240
TK-40280
120 deg C.
Figure A13 - Temperatures - thermocouples 33 - 40 plus 80
Ring FA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40281
TK-40282
TK-40283
TK-40284
TK-40285
120 deg C.
Figure A14 - Temperatures - thermocouples 81 - 85
-
27
Ring G
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40241
TK-40242
TK-40243
TK-40244
TK-40245
TK-40246
TK-40247
TK-40248
120 deg C.
Figure A15 - Temperatures - thermocouples 41 - 48
Ring H
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40249
TK-40250
TK-40251
TK-40252
120 deg C.
Figure A16 - Temperatures - thermocouples 49 - 52
-
28
Ring I
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
330
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40253
TK-40254
TK-40255
TK-40256
120 deg C.
Figure A17 - Temperatures - thermocouples 53 - 56
-
29
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
120
240
360
480
Figure A18 Development of vessel with temperature contours at 335s after ignition.
-
30
Appendix B - DEL0403
Averaging period 56 - 277 seconds after ignition
Summary of Release Conditions
Discharge hole diameter: 12.50 mmStand-off Distance: 1.00 mButane mass flow rate: 1.01 kg/sExit static pressure: 1.31 bargExit temperature 8.86 deg. C
Deluge Flow
Water sprays: Delayed by 30 secsWater pressure 2.35 bargWater flow rate 1069.38 litres/min
Ambient Weather Conditions
Wind speed (cup anemometer 1 at 1.2m) 2.0 m/sWind speed (cup anemometer 2 at 2.9m) 2.0 m/sWind speed (cup anemometer 3 at 6.0m) 2.2 m/sWind speed (cup anemometer 4 at 6.4m) 2.3 m/sHorizontal wind speed (sonic at 8.2m) 2.49 m/sVertical wind speed (sonic at 8.2m) 0.9 m/sWind direction 314.29 degrees clockwise from NorthRelative humidity 88.7 %Ambient temperature 12.0 deg CAtmospheric pressure 961.6 mbar
Thermocouples not operating properly
15, 53, 54, 55, 79
-
31
Fuel flow 0403
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Mas
s fl
ow
, kg
/s&
Pre
ssu
re, b
arg
. Mass flow , kg/s
Vapour pressure,bargLiquid headpressure, bargDischargepressure, barg
Figure B1 - Fuel conditions
Water flow 0403
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Pre
ssu
re, b
arg
& F
low
m^3
/min
Water pressure,barg
Water flow rate,m^3/min
Figure B2 - Water deluge conditions
-
32
Ring A
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40301
TK-40302
TK-40303
TK-40304
120 deg C.
Figure B3 - Temperatures - thermocouples 1 - 4
Ring B
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40305
TK-40306
TK-40307
TK-40308
120 deg C.
Figure B4 - Temperatures - thermocouples 5 - 8
-
33
Ring C
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40309
TK-40310
TK-40311
TK-40312
TK-40313
TK-40314
TK-40315
TK-40316
120 deg C.
Figure B5 - Temperatures - thermocouples 9 - 16
Ring CA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40357
TK-40358
TK-40359
TK-40360
TK-40361
120 deg C.
Figure B6 - Temperatures - thermocouples 57 - 61
-
34
Ring D
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40317
TK-40318
TK-40319
TK-40320
TK-40321
TK-40322
TK-40323
TK-40324
TK-40362
120 deg C.
Figure B7 - Temperatures - thermocouples 17 - 24 plus 62
Ring DA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40363
TK-40364
TK-40365
TK-40366
TK-40367
120 deg C.
Figure B8 - Temperatures - thermocouples 63 - 67
-
35
Ring DB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40368
TK-40369
TK-40370
120 deg C.
Figure B9 - Temperatures - thermocouples 68 - 70
Ring E
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40325
TK-40326
TK-40327
TK-40328
TK-40329
TK-40330
TK-40331
TK-40332
TK-40371
120 deg C.
Figure B10 - Temperatures - thermocouples 25 - 32 plus 71
-
36
Ring EA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40372
TK-40373
TK-40374
120 deg C.
Figure B11 - Temperatures - thermocouples 72 - 74
Ring EB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40375
TK-40376
TK-40377
TK-40378
TK-40379
120 deg C.
Figure B12 - Temperatures - thermocouples 75 - 79
-
37
Ring F
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40333
TK-40334
TK-40335
TK-40336
TK-40337
TK-40338
TK-40339
TK-40340
TK-40380
120 deg C.
Figure B13 - Temperatures - thermocouples 33 - 40 plus 80
Ring FA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40381
TK-40382
TK-40383
TK-40384
TK-40385
120 deg C.
Figure B14 - Temperatures - thermocouples 81 - 85
-
38
Ring G
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40341
TK-40342
TK-40343
TK-40344
TK-40345
TK-40346
TK-40347
TK-40348
120 deg C.
Figure B15 - Temperatures - thermocouples 41 - 48
Ring H
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40349
TK-40350
TK-40351
TK-40352
120 deg C.
Figure B16 - Temperatures - thermocouples 49 - 52
-
39
Ring I
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40353
TK-40354
TK-40355
TK-40356
120 deg C.
Figure B17 - Temperatures - thermocouples 53 - 56
-
40
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
40
80
120
Figure B18 Development of vessel with temperature contours at 30s after ignition.
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
120
240
360
480
Figure B19 Development of vessel with temperature contours at 277s after ignition.
-
41
Appendix C - DEL0404
Averaging period 6 - 231 seconds after ignition
Summary of Release Conditions
Discharge hole diameter: 25.0 mmStand-off Distance: 1.00 mButane mass flow rate: 3.87 kg/sExit static pressure: 1.23 bargExit temperature 6.62 deg. C
Deluge Flow
Water sprays: Deluge onWater pressure 2.34 bargWater flow rate 1071.53 litres/min
Ambient Weather Conditions
Wind speed (cup anemometer 1 at 1.2m) 2.3 m/sWind speed (cup anemometer 2 at 2.9m) 2.5 m/sWind speed (cup anemometer 3 at 6.0m) 2.7 m/sWind speed (cup anemometer 4 at 6.4m) 2.8 m/sHorizontal wind speed (sonic at 8.2m) 3.09 m/sVertical wind speed (sonic at 8.2m) 0.9 m/sWind direction 276.20 degrees clockwise from NorthRelative humidity 91.3 %Ambient temperature 11.7 deg CAtmospheric pressure 962.0 mbar
Thermocouples not operating properly
15, 79
-
42
Fuel flow 0404
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
0 30 60 90 120
150
180
210
Time from ignition, s.
Mas
s fl
ow
, kg
/s&
Pre
ssu
re, b
arg
. Mass flow , kg/s
Vapour pressure,bargLiquid headpressure, bargDischargepressure, barg
Figure C1 - Fuel conditions
Water flow 0404
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 30 60 90 120
150
180
210
Time from ignition, s.
Pre
ssu
re, b
arg
& F
low
m^3
/min
Water pressure,barg
Water flow rate,m^3/min
Figure C2 - Water deluge conditions
-
43
Ring A
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40401
TK-40402
TK-40403
TK-40404
120 deg C.
Figure C3 - Temperatures - thermocouples 1 - 4
Ring B
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40405
TK-40406
TK-40407
TK-40408
120 deg C.
Figure C4 - Temperatures - thermocouples 5 - 8
-
44
Ring C
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40409
TK-40410
TK-40411
TK-40412
TK-40413
TK-40414
TK-40415
TK-40416
120 deg C.
Figure C5 - Temperatures - thermocouples 9 - 16
Ring CA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40457
TK-40458
TK-40459
TK-40460
TK-40461
120 deg C.
Figure C6 - Temperature - thermocouples 57 - 61
-
45
Ring D
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40417
TK-40418
TK-40419
TK-40420
TK-40421
TK-40422
TK-40423
TK-40424
TK-40462
120 deg C.
Figure C7 - Temperatures - thermocouples 17 - 24 plus 62
Ring DA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40463
TK-40464
TK-40465
TK-40466
TK-40467
120 deg C.
Figure C8 - Temperature - thermocouples 63 - 67
-
46
Ring DB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40468
TK-40469
TK-40470
120 deg C.
Figure C9 - Temperature - thermocouples 68 - 70
Ring E
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40425
TK-40426
TK-40427
TK-40428
TK-40429
TK-40430
TK-40431
TK-40432
TK-40471
120 deg C.
Figure C10 - Temperature - thermocouples 25 - 32 plus 71
-
47
Ring EA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40472
TK-40473
TK-40474
120 deg C.
Figure C11 - Temperature - thermocouples 72 - 74
Ring EB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40475
TK-40476
TK-40477
TK-40478
TK-40479
120 deg C.
Figure C12 - Temperature - thermocouples 75 - 79
-
48
Ring F
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40433
TK-40434
TK-40435
TK-40436
TK-40437
TK-40438
TK-40439
TK-40440
TK-40480
120 deg C.
Figure C13 - Temperatures - thermocouples 33 - 40 plus 80
Ring FA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40481
TK-40482
TK-40483
TK-40484
TK-40485
120 deg C.
Figure C14 - Temperatures - thermocouples 81 - 85
-
49
Ring G
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40441
TK-40442
TK-40443
TK-40444
TK-40445
TK-40446
TK-40447
TK-40448
120 deg C.
Figure C15 - Temperatures - thermocouples 41 - 48
Ring H
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40449
TK-40450
TK-40451
TK-40452
120 deg C.
Figure C16 - Temperatures - thermocouples 49 - 52
-
50
Ring I
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40453
TK-40454
TK-40455
TK-40456
120 deg C.
Figure C17 - Temperatures - thermocouples 53 - 56
-
51
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
120
240
360
480
Figure C18 Development of vessel with temperature contours at 231s after ignition.
-
52
Appendix D - DEL0405
Averaging period 57 - 235 seconds after ignition
Summary of Release Conditions
Discharge hole diameter: 25.0 mmStand-off Distance: 1.00 mButane mass flow rate: 3.86 kg/sExit static pressure: 1.23 bargExit temperature 6.62 deg. C
Deluge Flow
Water sprays: Delayed by 30 secsWater pressure 2.36 bargWater flow rate 1069.69 litres/min
Ambient Weather Conditions
Wind speed (cup anemometer 1 at 1.2m) 2.1 m/sWind speed (cup anemometer 2 at 2.9m) 2.3 m/sWind speed (cup anemometer 3 at 6.0m) 2.5 m/sWind speed (cup anemometer 4 at 6.4m) 2.6 m/sHorizontal wind speed (sonic at 8.2m) 3.11 m/sVertical wind speed (sonic at 8.2m) 0.9 m/sWind direction 279.81 degrees clockwise from NorthRelative humidity 92.1 %Ambient temperature 11.6 deg CAtmospheric pressure 962.4 mbar
Thermocouples not operating properly
15, 79
-
53
Fuel flow 0405
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
0 30 60 90 120
150
180
210
Time from ignition, s.
Mas
s fl
ow
, kg
/s&
Pre
ssu
re, b
arg
. Mass flow , kg/s
Vapour pressure,bargLiquid headpressure, bargDischargepressure, barg
Figure D1 - Fuel conditions
Water flow 0405
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 30 60 90 120
150
180
210
Time from ignition, s.
Pre
ssu
re, b
arg
& F
low
m^3
/min
Water pressure,barg
Water flow rate,m^3/min
Figure D2 - Water deluge conditions
-
54
Ring A
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40501
TK-40502
TK-40503
TK-40504
120 deg C.
Figure D3 - Temperatures - thermocouples 1 - 4
Ring B
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40505
TK-40506
TK-40507
TK-40508
120 deg C.
Figure D4 - Temperatures - thermocouples 5 - 8
-
55
Ring C
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40509
TK-40510
TK-40511
TK-40512
TK-40513
TK-40514
TK-40515
TK-40516
120 deg C.
Figure D5 - Temperature - thermocouples 9 - 16
Ring CA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40557
TK-40558
TK-40559
TK-40560
TK-40561
120 deg C.
Figure D6 - Temperatures - thermocouples 57 - 61
-
56
Ring D
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40517
TK-40518
TK-40519
TK-40520
TK-40521
TK-40522
TK-40523
TK-40524
TK-40562
120 deg C.
Figure D7 - Temperatures - thermocouples 17 - 24 plus 62
Ring DA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40563
TK-40564
TK-40565
TK-40566
TK-40567
120 deg C.
Figure D8 - Temperatures - thermocouples 63 - 67
-
57
Ring DB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40568
TK-40569
TK-40570
120 deg C.
Figure D9 - Temperatures - thermocouples 68 - 70
Ring E
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40525
TK-40526
TK-40527
TK-40528
TK-40529
TK-40530
TK-40531
TK-40532
TK-40571
120 deg C.
Figure D10 - Temperatures - thermocouples 25 - 32 plus 71
-
58
Ring EA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40572
TK-40573
TK-40574
120 deg C.
Figure D11 - Temperatures - thermocouples 72 - 74
Ring EB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40575
TK-40576
TK-40577
TK-40578
TK-40579
120 deg C.
Figure D12 - Temperatures - thermocouples 75 - 79
-
59
Ring F
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40533
TK-40534
TK-40535
TK-40536
TK-40537
TK-40538
TK-40539
TK-40540
TK-40580
120 deg C.
Figure D13 - Temperatures - thermocouples 33 - 40 plus 80
Ring FA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40581
TK-40582
TK-40583
TK-40584
TK-40585
120 deg C.
Figure D14 - Temperatures - thermocouples 81 - 85
-
60
Ring G
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40541
TK-40542
TK-40543
TK-40544
TK-40545
TK-40546
TK-40547
TK-40548
120 deg C.
Figure D15 - Temperatures - thermocouples 41 - 48
Ring H
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40549
TK-40550
TK-40551
TK-40552
120 deg C.
Figure D16 - Temperatures - thermocouples 49 - 52
-
61
Ring I
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40553
TK-40554
TK-40555
TK-40556
120 deg C.
Figure D17 - Temperatures - thermocouples 53 - 56
-
62
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
40
80
120
Figure D18 Development of vessel with temperature contours at 30s after ignition.
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
120
240
360
480
Figure D19 Development of vessel with temperature contours at 235s after ignition.
-
63
Appendix E - DEL0408
Averaging period 9 - 243 seconds after ignition
Summary of Release Conditions
Discharge hole diameter: 50.0 mmStand-off Distance: 1.00 mButane mass flow rate: 9.40 kg/sExit static pressure: 1.04 bargExit temperature 5.63 deg. C
Deluge Flow
Water sprays: Deluge onWater pressure 2.40 bargWater flow rate 1067.29 litres/min
Ambient Weather Conditions
Wind speed (cup anemometer 1 at 1.2m) 1.8 m/sWind speed (cup anemometer 2 at 2.9m) 1.9 m/sWind speed (cup anemometer 3 at 6.0m) 2.2 m/sWind speed (cup anemometer 4 at 6.4m) 2.3 m/sHorizontal wind speed (sonic at 8.2m) 2.83 m/sVertical wind speed (sonic at 8.2m) 0.9 m/sWind direction 284.31 degrees clockwise from NorthRelative humidity 93.1 %Ambient temperature 11.2 deg CAtmospheric pressure 963.2 mbar
Thermocouples not operating properly
15, 79
-
64
Fuel flow 0408
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Mas
s fl
ow
, kg
/s&
Pre
ssu
re, b
arg
. Mass flow , kg/s
Vapour pressure,bargLiquid headpressure, bargDischargepressure, barg
Figure E1 - Fuel conditions
Water flow 0408
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Pre
ssu
re, b
arg
& F
low
m^3
/min
Water pressure,barg
Water flow rate,m^3/min
Figure E2 - Water deluge conditions
-
65
Ring A
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40801
TK-40802
TK-40803
TK-40804
120 deg C.
Figure E3 - Temperatures - thermocouples 1 - 4
Ring B
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40805
TK-40806
TK-40807
TK-40808
120 deg C.
Figure E4 - Temperatures - thermocouples 5 - 8
-
66
Ring C
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40809
TK-40810
TK-40811
TK-40812
TK-40813
TK-40814
TK-40815
TK-40816
120 deg C.
Figure E5 - Temperatures - thermocouples 9 - 16
Ring CA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40857
TK-40858
TK-40859
TK-40860
TK-40861
120 deg C.
Figure E6 - Temperatures - thermocouples 57 - 61
-
67
Ring D
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40817
TK-40818
TK-40819
TK-40820
TK-40821
TK-40822
TK-40823
TK-40824
TK-40862
120 deg C.
Figure E7 - Temperatures - thermocouples 17 - 24 plus 62
Ring DA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40863
TK-40864
TK-40865
TK-40866
TK-40867
120 deg C.
Figure E8 - Temperatures - thermocouples 63 - 67
-
68
Ring DB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40868
TK-40869
TK-40870
120 deg C.
Figure E9 - Temperatures - thermocouples 68 - 70
Ring E
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40825
TK-40826
TK-40827
TK-40828
TK-40829
TK-40830
TK-40831
TK-40832
TK-40871
120 deg C.
Figure E10 - Temperatures - thermocouples 25 - 32 plus 71
-
69
Ring EA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40872
TK-40873
TK-40874
120 deg C.
Figure E11 - Temperatures - thermocouples 72 - 74
Ring EB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40875
TK-40876
TK-40877
TK-40878
TK-40879
120 deg C.
Figure E12 - Temperatures - thermocouples 75 - 79
-
70
Ring F
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40833
TK-40834
TK-40835
TK-40836
TK-40837
TK-40838
TK-40839
TK-40840
TK-40880
120 deg C.
Figure E13 - Temperatures - thermocouples 33 - 40 plus 80
Ring FA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40881
TK-40882
TK-40883
TK-40884
TK-40885
120 deg C.
Figure E14 - Temperatures - thermocouples 81 - 85
-
71
Ring G
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40841
TK-40842
TK-40843
TK-40844
TK-40845
TK-40846
TK-40847
TK-40848
120 deg C.
Figure E15 - Temperatures - thermocouples 41 - 48
Ring H
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40849
TK-40850
TK-40851
TK-40852
120 deg C.
Figure E16 - Temperatures - thermocouples 49 - 52
-
72
Ring I
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40853
TK-40854
TK-40855
TK-40856
120 deg C.
Figure E17 - Temperatures - thermocouples 53 - 56
-
73
A B C D E F G H I
REAR
TOP
FRONT
BOTTOM
O Water spraynozzleThermocouple+
BOTTOM
Temperature scale
-20
0
120
240
360
480
Figure E18 Development of vessel with temperature contours at 243s after ignition.
-
74
Appendix F - DEL0409
Averaging period 62 - 302 seconds after ignition
Summary of Release Conditions
Discharge hole diameter: 50.0 mmStand-off Distance: 1.00 mButane mass flow rate: 8.71 kg/sExit static pressure 1.05 bargExit temperature 4.51 deg. C
Deluge Flow
Water sprays: Delayed by 30 secsWater pressure 2.37 bargWater flow rate 1064.02 litres/min
Ambient Weather Conditions
Wind speed (cup anemometer 1 at 1.2m) 2.1 m/sWind speed (cup anemometer 2 at 2.9m) 2.2 m/sWind speed (cup anemometer 3 at 6.0m) 2.4 m/sWind speed (cup anemometer 4 at 6.4m) 2.5 m/sHorizontal wind speed (sonic at 8.2m) 2.86 m/sVertical wind speed (sonic at 8.2m) 0.9 m/sWind direction 289.47 degrees clockwise from NorthRelative humidity 93.2 %Ambient temperature 11.1 deg CAtmospheric pressure 963.5 mbar
Thermocouples not operating properly
15, 79
-
75
Fuel flow 0409
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Mas
s fl
ow
, kg
/s&
Pre
ssu
re, b
arg
. Mass flow , kg/s
Vapour pressure,bargLiquid headpressure, bargDischargepressure, barg
Figure F1 - Fuel conditions
Water flow 0409
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Pre
ssu
re, b
arg
& F
low
m^3
/min
Water pressure,barg
Water flow rate,l/min
Figure F2 - Water deluge conditions
-
76
Ring A
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40901
TK-40902
TK-40903
TK-40904
120 deg C.
Figure F3 - Temperatures - thermocouples 1 - 4
Ring B
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40905
TK-40906
TK-40907
TK-40908
120 deg C.
Figure F4 - Temperatures - thermocouples 5 - 8
-
77
Ring C
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40909
TK-40910
TK-40911
TK-40912
TK-40913
TK-40914
TK-40915
TK-40916
120 deg C.
Figure F5 - Temperatures - thermocouples 9 - 16
Ring CA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40957
TK-40958
TK-40959
TK-40960
TK-40961
120 deg C.
Figure F6 - Temperatures - thermocouples 57 - 61
-
78
Ring D
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40917
TK-40918
TK-40919
TK-40920
TK-40921
TK-40922
TK-40923
TK-40924
TK-40962
120 deg C.
Figure F7 - Temperatures - thermocouples 17 - 24 plus 62
Ring DA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40963
TK-40964
TK-40965
TK-40966
TK-40967
120 deg C.
Figure F8 - Temperatures - thermocouples 63 - 67
-
79
Ring DB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40968
TK-40969
TK-40970
120 deg C.
Figure F9 - Temperatures - thermocouples 68 - 70
Ring E
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40925
TK-40926
TK-40927
TK-40928
TK-40929
TK-40930
TK-40931
TK-40932
TK-40971
120 deg C.
Figure F10 - Temperature - thermocouples 25 - 32 plus 71
-
80
Ring EA
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40972
TK-40973
TK-40974
120 deg C.
Figure F 11 - Temperature - thermocouples 72 - 74
Ring EB
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
. TK-40975
TK-40976
TK-40977
TK-40978
TK-40979
120 deg C.
Figure F12 - Temperature - thermocouples 75 - 79
-
81
Ring F
0
50
100
150
200
250
300
350
400
0 30 60 90 120
150
180
210
240
270
300
Time from ignition, s.
Tem
per
atu
re, d
eg C
.
TK-40933
TK-40934
TK-40935
TK-40936
TK-40937
TK-40938
TK-40939
TK-40940
TK-40980