egip - queen street station, single option development

2
Background Queen Street station is a main line rail terminus in Glasgow and the third busiest rail station in Scotland. A revised Single Option Development Process was required as a consequence of the revised track and platform layout proposed as part of the Edinburgh to Glasgow Improvement Programme (EGIP). The study required the integration of the OLE, the new track layout and the station design work already undertaken to resolve the impact on the overall station layout, facilities and pedestrian circulation. Originally there was no overhead line provision on any route serving Queen Street High-Level Station, however there had been significant design development undertaken under the overall EGIP scheme. The proposed solution was based on UK standard classic 25kV electrification and consists of layout plans for the station platform areas, approach to platforms and the dual-track tunnel approach from Cowlairs Junction. CASE STUDY PROJECT: EGIP – Glasgow Queen Street, High Level Station CLIENT: Jacobs DATE: April – September 2013 EGIP - Queen Street Station, Single Option Development

Upload: others

Post on 31-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EGIP - Queen Street Station, Single Option Development

Background

Queen Street station is a main line rail terminus in Glasgow and

the third busiest rail station in Scotland. A revised Single Option

Development Process was required as a consequence of the revised

track and platform layout proposed as part of the Edinburgh to

Glasgow Improvement Programme (EGIP).

The study required the integration of the OLE, the new track layout

and the station design work already undertaken to resolve the impact

on the overall station layout, facilities and pedestrian circulation.

Originally there was no overhead line provision on any route serving

Queen Street High-Level Station, however there had been significant

design development undertaken under the overall EGIP scheme.

The proposed solution was based on UK standard classic 25kV

electrification and consists of layout plans for the station platform

areas, approach to platforms and the dual-track tunnel approach

from Cowlairs Junction.

C A S E S T U D Y

PROJECT: EGIP – Glasgow Queen Street, High Level Station

CLIENT: Jacobs

DATE: April – September 2013

EGIP - Queen Street Station, Single Option Development

Page 2: EGIP - Queen Street Station, Single Option Development

Project Details

The new track alignment posed significant problems in providing a compliant

OLE design. The following being some of the issues that were resolved by

our submission:

• The OLE was not allowed to be supported from the arched station roof

due to structural inadequacies.

• Headspans were preferred to TTC’s in the platforms, but bespoke

structures were required to improve pedestrian flow and aesthetics.

• A full catenary system was required in the platforms and up to the tunnel

mouth at the request of the ORR.

• Fixed tension equipment was required to be anchored in the throat prior

to transition beams for conductor bars in the tunnel.

• Low level platforms, 8 & 9, are underneath the platforms, minimising

thearea for locating OLE structures.

• No anchoring was allowed on the lattice overbridge in the throat or at

Cathedral Street overbridge.

• The track crossover was located right under a reduced height lattice

bridge, which was too low to support an SI.

• The scope required any Wall-mounted structures to be eliminated, or at

least minimised, and the extension of the platforms further reduced the

area for locating OLE structures.

• The PWay alignment moved the Toe openings towards the tunnel, with

one set within the tunnel mouth.

• The design required to be compliant to buffer stop extensions and provision

made for anchoring on future station buildings rather than adopting goal

post anchors.

• As there was insufficient room for sectioning in the throat, the switched

overlap was moved into the tunnel, using a conductor bar air gap, with

switching mounted on the anchor structures at the tunnel entrances.

Above: Queen Street station tunnel.

Wentworth House Rail Systems Ltd, Vale House, Aston Lane North, Preston Brook, Cheshire WA7 3PE.

Telephone: +44 (0)12 7044 8405 e.mail: [email protected] website: www.railelectrification.com

C A S E S T U D Y