eHealth Records Programme

Therapies EPR Project Service Design Meeting

Gaelle Fertil, Therapies Project Manager

Monday 19th July 2010

Page 2: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Agenda:

1. Project Background

2. Project Objectives

3. Project Scope

4. Stage 1 – Referrals Go-live

5. Stage 2 – Electronic clinical noting

6. Scanning and Upload Solution

7. External Suppliers

8. Hardware Requirements

9. Testing Overview

10. Outstanding issues

11. Current Statement of Revenue Costs

Therapies EPR Project

Service Design

Page 3: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Project Background:

Existing Therapies system (TSS) reached end of life 2006.

Directorate encouraged to replace with solution delivered via “core systems”.

“Therapies Clinical Notes” work stream identified in 2007 “eHealth Project Brief”.

Therapies EPR Project approved at February 2009 CPB as Trust Risk Rating 1.

Clive Mellish took over management of project June 2009, followed by Anthony McCourt in March 2010, followed by Gaelle Fertil in June 2010.

Significant analysis undertaken to identify requirements and enable definition project scope and objectives.

Project split in two:

immediate interim delivery – Phase 1, divided into 2 stages:

Pan Trust Referrals Go-live – 19th July

Therapies Directorate OP electronic noting staged Go-live

long term strategic delivery (via re-invigorated eHealth strategy) - TBC

Project re-start and associated costs signed off by CPB in November 2009.

Therapies EPR Project

Service Design

Page 4: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Project Objectives:

To enable a paper-lite environment across the Central Therapies Directorate.

To deliver solutions in response to Therapies requirements which can be then be reused and applied Trust-wide.

Therapies EPR Project

Service Design

Project Scope:

Phase 1

“Native” iCM functionality

Scanning and Upload solution to capture residual paper

Delivery to outpatient pathways in: Foot Health Nutrition and Dietetics Occupational Therapy Patient Appliances Psychology Physiotherapy Social Work Support and Hospital Discharge Department/Safeguarding Speech and Language Therapy Spiritual Health

Page 5: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Stage 1 – Referrals Go-live 19th July Using native iCM Functionality, referrals are orders in EPR.

14 Referrals going live (x1 Psychology deferred):Physiotherapy OUTPATIENT Referral

Occupational Therapy INPATIENT ReferralOccupational Therapy OUTPATIENT Referral

Hand Therapy OUTPATIENT ReferralPatient Appliances Referral (OP and IP use)Patient Appliances Order (OP and IP use)

Speech & Language Therapy INPATIENT Referral Speech & Language Therapy OUTPATIENT Referral

Foot Health Referral (OP and IP use)Nutrition & Dietetics Referral (OP and IP use)

Chaplaincy Referral Social Services Section 2 ReferralSocial Services Section 5 Referral

Adult Safeguarding Referral

Training has been provided by the project

Security rights have been set up: 2 levels of security rights - Order and Modify. Training tracker has been updated

IT Apps have been provided with briefing about the Go-live

Therapies EPR Project

Service Design

Page 6: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 7: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 8: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 9: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 10: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 11: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 12: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 13: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010
Page 14: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Stage 2 – Electronic clinical noting

Figures show total number of items of each category that need to be configured in iCM (i.e. not volumes).

Results relate to submission via the “Results Submission” solution and require an order item in iCM and an order requisition form to be created.

Reports will be bespoke Crystal reports, where they can be created – requirements for reports are in discussion.

Therapies EPR Project

Service Design

6

11

Page 15: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Stage 2 - Scanning and Upload Solution

Figures show count of document type to be scanned in to iCM (i.e. not volume).

S&U Solution is as per King’s supplied and built solution, on EPR+ framework.

Monthly volume is 16,000 per month.

Therapies EPR Project

Service Design

Page 16: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Stage 2 - Scanning and Upload Solution

Therapies EPR Project

Service Design

LetterMaker

Scanner

Workstation running EPR/EPR Plus

Scan document

Network File Share

Document Polling Service(Windows Services)

LetterMaker PersistantStore

LetterMaker HL7 Integration Message Generator(SQL Job)

Sending Service(Windows Service)

Only doc link is transmitted from this point on

S&U

ICM Database

iCM

Poll

iCM Interfaces

DATAGATE

Page 17: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

External Suppliers:

Scanning and Upload solution – King’s College London

No service agreement in place

EPR+ framework – King’s College London

No service agreement in place

Growth Chart (TBC) – Harlow Printing Ltd

Solution in requirements and design phase

Subject to further discussions at CPB

Therapies EPR Project

Service Design

Page 18: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Hardware Requirements

Therapies EPR Project

Service Design

Figures show approximate count of expected requirement for hardware to enable effective, efficient use of solution but will be confirmed during hardware review later in project.

Number of scanners required dependent on solution adopted. Figures shown are expected minimum required (one per distinct location).

Number of “PCs” denotes number of input devices required, not necessarily desktop computers: could be laptops, tablets, PDAs etc.

Additional technology may also be required e.g. smart pens, magic whiteboards, annotation tablets etc. which will be determined during the hardware review.

Page 19: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Testing Overview:

iCM:

Configuration Testing

User Acceptance Testing

Performance Testing – using Syntel

S&U solution:

System Testing (currently failed) – Development team

Performance Testing – using Syntel

Growth Chart (TBC) – Harlow Printing Ltd

System Testing – Development team

User Acceptance Testing

Therapies EPR Project

Service Design

Page 20: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Outstanding Issues:

Outstanding service level agreements with external supplier

Assume the currently service agreement with EPR is sufficient

Ability for EPR to function on wireless network

ER18 – iCM “crashing issue”

Other outstanding iCM issues identified during initial round of UAT

Scanning and Upload issues

Agreement on scope of performance testing by Syntel

Therapies EPR Project

Service Design

Page 21: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

Current Revenue Costs as signed off in PID:

Therapies EPR Project

Service Design

Description Cost PA

Reactive SupportAssumption for number of calls taken by service desk for project is 30 calls / month.Same amount for referring problems on and problem resolution (2nd and third line).

£4,500£4,500

Proactive SupportRelationships and supplier management.20 days / year for "large project" like this.Every business area meets with Application Support Manager to look at how 'things are going'.Application Support Manager also meets with suppliers on a quarterly basis.For large project = £400 / day = £8000 / year.Handover / training = £400 / day @ 5 days = £2000 / year.Capacity planning: 5 day / year (includes meetings to discuss capacity etc) at £400 / day = £2000 / year.3rd Line Development activities (15 days / year) for Scanning and Upload SolutionDisaster recovery: minimum 20 days for large project - not applicable for Therapies EPR project.

£8,000£2,000£2,000

£6,300

ChangeChanges to configurable items (e.g. changes to flowsheets / knowledge trees, printer reconfiguration etc.)System administration (user management)20 days @£400 / day = £8000 £8,000

TrainingAssuming an estimated attrition rate of 10%0.5xFTE at Band 6 (£16,000 pa) £16,000

Annual Total: £51,300

“IT Operations" costs excluded, as IT&T had no metrics to estimate these costs

Page 22: EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

?

Discussion:

Service Design

Therapies EPR Project