    Clause ISO14001 Clause4.1General Requirements 4.1

    4.2Environmental Policy 4.2

    4.3 Planning

    4.3

    4.3.1 Environmental Aspects 4.3.1

    4.3.2 Legal and other requirements 4.3.2

    4.3.3 Objectives, Targets & Programme(s) 4.3.3

    4.4 Implementation And Operation 4.44.4.1 Resources, roles, responsibility and authority 4.4.1

    4.4.2 Competence, Training and Awareness 4.4.2

    4.4.3 Communication 4.4.3

    4.4.3.1

    4.4.3.2

    4.4.4 Documentation 4.4.4

    4.4.5 Control of Documents 4.4.5

    4.4.6 Operational control 4.4.6

    4.4.7 Emergency preparedness and response 4.4.7

    4.5 Checking 4.5

    4.5.1 Monitoring and measurement 4.5.1

    4.5.2 Evaluation Of Compliance 4.5.24.5.3 Nonconformity, corrective action and preventive

    action

    4.5.3

    4.5.3.1

    4.5.3.2

    4.5.4 Control of Records 4.5.4

    4.5.5 Internal Audit 4.5.5

    4.6 Management Review 4.6

  • 7/21/2019 EHS Overview Share

    2/214

    OHSAS18001 ClauseGeneral Requirements 3.1OHS Policy 3.1.1

    Planning

    3.1.2

    Hazard identification, risk assessment and

    determining controls

    3.2

    Legal and other requirements 3.2.1

    Objectives and programs 3.2.2

    3.2.3

    Implementation and operation 3.2.4

    Resources, roles,responsibility,accountability

    and authority

    3.3

    3.3.1

    3.3.2

    Competence, training and awareness 3.3.3

    Communication, participation and consultation 3.3.4

    Communication 3.4

    Participation and consultation

    3.4.1

    3.4.2

    Documentation 3.4.3

    Control of documents 3.4.4

    Operational Control 3.5Emergency preparedness and response 3.5.1

    Checking 3.5.2

    Performance measure and monitoring

    Evaluation of compliance 3.3.4.3Incident investigation, nonconformity, corrective

    action and preventive action

    Incident investigation

    Nonconformity, corrective action and preventive

    action

    Control of record

    Internal audit

    Management Review

  • 7/21/2019 EHS Overview Share

    3/214

    OHSMS 1722

    Policy

    Occupational safety and health policy

    Employee participation

    OrganisingResponsibility and accountability

    Competence and training

    OSH MS documentation

    Communication

    Planning and implementationInitial review

    System planning, development and implementation

    OSH objective

    Hazard prevention

    Evaluation

    Performance monitoring and measure

    Investigation of work related injuries, disabilities, ill

    health, disease and near misses, and their impact on

    safety and health performance

    Audit

    Management review

    Action for improvementPreventive and corrective action

    Continual improvement

    Emergency prevention, preparedness and response

  • 7/21/2019 EHS Overview Share

    4/214

    Eliminate

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Substitute

    Eliminate

    4 S0 F2

    4 S0 F2

    Risk Rating Consequence

    LikelihoodSTATUS DUE PIC

    ontrol Measur

    Risk Assessment

    Dept: C Prepared by: Date: 06.07.1 Rev: 1

  • 7/21/2019 EHS Overview Share

    5/214

    Isolate

    Engineering

    control

    AdminControl

    PPE

    Substitute

    Isolate

    Engineering

    control

    AdminControl

    PPE

    Eliminate

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    6/214

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Eliminate

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    4 S0 F2

    Eliminate

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    7/214

    Substitute

    Isolate

    Engineering

    control

    AdminControl

    PPE

    SubstituteIsolate

    Engineering

    control

    Admin

    Control

    Eliminate

    4 S0 F2

    F2

    Eliminate

    4 S0

  • 7/21/2019 EHS Overview Share

    8/214

    PPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Eliminate4 S0 F2

  • 7/21/2019 EHS Overview Share

    9/214

    Substitute

    Isolate

    Engineering

    controlAdmin

    Control

    PPE

    Substitute

    Isolate

    Engineering

    control

    F2

    Eliminate

    4 S0

    Eliminate4 S0 F2

  • 7/21/2019 EHS Overview Share

    10/214

    Admin

    Control

    PPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Eliminate

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    11/214

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    Eliminate

    4 S0 F2

    Eliminate

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    12/214

    PPE

    Eliminate

    Substitute

    IsolateEngineering

    control

    Admin

    Control

    PPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    S0 F2

    Eliminate

    4 S0 F2

    4

  • 7/21/2019 EHS Overview Share

    13/214

    SubstituteIsolate

    Engineering

    control

    Admin

    Control

    PPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Eliminate

    4 S0 F2

    Eliminate4 S0 F2

  • 7/21/2019 EHS Overview Share

    14/214

    SubstituteIsolate

    Engineering

    control

    Admin

    Control

    PPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Eliminate4 S0 F2

    Eliminate 4 S0 F2

  • 7/21/2019 EHS Overview Share

    15/214

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    4 S0 F2

    Eliminate

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Substitute

    F2

    4 S0 F2

    Eliminate

    4 S0

    Eliminate

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    16/214

    Isolate

    Engineering

    control

    Admin

    ControlPPE

    Substitute

    Isolate

    Engineering

    control

    Admin

    Control

    PPE

    Eliminate

    Eliminate4 S0 F2

  • 7/21/2019 EHS Overview Share

    17/214

    Substitute

    Isolate

    Engineeringcontrol

    Admin

    Control

    PPE

    Substitute

    Isolate

    Engineeringcontrol

    Admin

    Control

    PPE

    Eliminate

    Eliminate

    4 S0 F2

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    18/214

    Substitute

    Isolate

    Engineeringcontrol

    Admin

    Control

    PPE

    4 S0 F2

  • 7/21/2019 EHS Overview Share

    19/214

    Hazard Identification

    Station 1

    - 26P

    Connector

    Riveting &

    Housing

    Assembly

    Circuitbreaker

    Physical

    hazard:

    Moving

    object .

    Station 2

    - Main PCB

    Clinching

    Use 2 hands

    safety

    operation

    switch

    Safety

    interlock

    manual

    handling,

    repetitive

    work (risk:

    injurys to

    fingers and

    hands)

    Existingcontrol

    Hazard &Potential

    Activity/

    Product/

    Services

    HIRADC : Ha

  • 7/21/2019 EHS Overview Share

    20/214

    Circuit

    breaker - As

    above

    Risk: Hand

    injury,

    repetitive

    work,

    electricution

    Station 3

    Safety

    interlock

    manual

    handling,

    repetitive

    work (risk:

    injurys to

    fingers and

    hands)

  • 7/21/2019 EHS Overview Share

    21/214

    Circuit

    breaker - As

    above

    - Housing

    Frame

    Screwing

    Station 4

    Circuit

    breaker - As

    above

    - PCB Visual

    Inspection

    Station 5

    - Flash

    Programmin

    g

    Circuit

    breaker

    Splicing tool

    secure/setup

    station

    expose to

    electrical

    energy

    (Risk=lelectri

    cal

    burn/electroc

    ution)

    Safety

    interlock

    manual

    handling,

    repetitive

    work (risk:injurys to

    fingers and

    hands)

  • 7/21/2019 EHS Overview Share

    22/214

    Station 6

    Circuit

    breaker - As

    above

    - Finetune

    alignment

    Station 7

    Safety

    interlocksharp object

    (risk:injury to

    fingers and

    hands),

    physical

    injury

    Splicing tool

    secure/setup

    station

    expose to

    electrical

    energy

    (Risk=lelectri

    cal

    burn/electroc

    ution)

  • 7/21/2019 EHS Overview Share

    23/214

    - Mechanism

    to radio

    assembly

    Circuitbreaker - As

    above

    Station 8

    Circuit

    breaker - Asabove

    - Bracket to

    MechanismScrewing

    Station 9manual

    handling,rep

    etitive work

    (risk: injurys

    to fingers

    and hands)

    manual

    handling,

    repetitive

    work (risk:

    injurys to

    fingers and

    hands)

    Safety

    interlock

  • 7/21/2019 EHS Overview Share

    24/214

    Circuit

    breaker - As

    above

    - Bottom

    Cover

    Screwing

    Station 10Safety

    interlock

    sharp object

    (risk:injury to

    fingers and

    hands),

    physical

    injury

    Safety

    interlock

  • 7/21/2019 EHS Overview Share

    25/214

    - Mechanism

    to radio

    assembly

    andinspection

    Station 11

    Circuit

    breaker - As

    above

    - Mechanism

    to radio

    screwing

    Station 12

    Safety

    interlockrepetitive

    work, manual

    handling,

    electricution

  • 7/21/2019 EHS Overview Share

    26/214

    Circuit

    breaker - As

    above

    - Front Cover

    to radio

    assembly

    Station 13

    Safety

    interlock

    manual

    handling

    manual

    handling,

    repetitive

    work (risk:

    injurys to

    fingers and

    hands)

    Safety

    interlock

  • 7/21/2019 EHS Overview Share

    27/214

    - Top Cover

    assembly

    Station 14

    Circuit

    breaker - As

    above

    - Top Cover

    screwing

    Station 15Splicing tool

    secure/setup

    station

    expose to

    electrical

    energy

    (Risk=lelectri

    cal

    burn/electroc

    ution)

    Use 2 handssafety

    operation

    switch

    Using

    engineering

    board for

    setup

    manual

    handling,

    repetative

    work,

    chemicalsubs material

    (glue)

  • 7/21/2019 EHS Overview Share

    28/214

    Circuit

    breaker - As

    above

    - Holding

    Spring

    screwing

    Station 16

    Circuit

    breaker - As

    above

    - Finetune

    alignment

    Station 17Splicing tool

    secure/setup

    station

    expose to

    electrical

    energy

    (Risk=lelectri

    cal

    burn/electroc

    ution)

    Splicing tool

    secure/setup

    station

    expose to

    electrical

    energy

    (Risk=lelectri

    cal

    burn/electroc

    ution)

  • 7/21/2019 EHS Overview Share

    29/214

    Circuit

    breaker - As

    above

    - Functional

    check

    Station 18

    Circuit

    breaker - As

    above

    - Functional

    check

    Station 19

    manual

    handling

    Splicing tool

    secure/setup

    station

    expose to

    electrical

    energy

    (Risk=lelectri

    cal

    burn/electroc

    ution)

  • 7/21/2019 EHS Overview Share

    30/214

    Circuit

    breaker - As

    above

    - Functional

    check

    Station 20

    Safety

    interlock

    Suspended

    Ear plug

    expose to

    electrical

    energy

    (Risk=lelectri

    calburn/electroc

    ution). Noise

    Sound Room

    Using

    engineering

    board forsetup

  • 7/21/2019 EHS Overview Share

    31/214

    Circuit

    breaker - As

    above

    - Sticker

    Assembly

    Station 21

    - Visual

    check

    Station 22

    repetitive

    Safety

    interlock

    repetitive

    work and

    manual

    handling,fall

    object

  • 7/21/2019 EHS Overview Share

    32/214

    - Default

    setting

    Station 23

    - Frame

    assembly

    Station 24Physical

    hazard:

    ImproperConveyor

    width setting

    . Risk :

    damage

    board

    Safety

    interlock

    repetitive

    work and

    manual

    handling,fall

    manual

    handling,fall

    interlock

  • 7/21/2019 EHS Overview Share

    33/214

    - Packing

    None

  • 7/21/2019 EHS Overview Share

    34/214

    Use of

    natural

    resouces

    (electricity)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of

    naturalresouces

    (electricity)

    Picture

    Input Amount/yr

    ard Identification Risk Assessment and Determine ControlEnvironmental Aspect Impact Register

  • 7/21/2019 EHS Overview Share

    35/214

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    36/214

    Use of rawmaterial

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

    Use of raw

    material

    (Glove)

    Use of rawmaterial

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    37/214

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of raw

    material

    (Glove)

    Use of

    natural

    resouces

    (electricity)

    Use ofnatural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    38/214

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    39/214

    Use of raw

    material

    (plastic

    reel/bag)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of

    naturalresouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    40/214

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (barcode reel

    waste paper)

    Use of raw

    material

    (plasticreel/bag)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    41/214

    Use of raw

    material

    (plastic

    reel/bag)

    Use of rawmaterial

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (plastic

    reel/bag)

    Use of raw

    material

    (Glove)

    Use of

    natural

    resouces

    (electricity)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    42/214

    Use of raw

    material

    (Finger coat)

    Use of raw

    material(Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    Resources

    (electricity)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    43/214

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    Resources

    (electricity)

    Use of

    natural

    Resources

    (electricity)

  • 7/21/2019 EHS Overview Share

    44/214

    Use of raw

    material

    (Glove)

    Use of raw

    material

    (Finger coat)

    Use of raw

    material(Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    45/214

  • 7/21/2019 EHS Overview Share

    46/214

    Use of raw

    material

    (Finger coat)

    Use of raw

    material

    (Glove)

    Use of rawmaterial

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    47/214

    Use of raw

    material

    (Glove)

    Use of raw

    material(Finger coat)

    Use of

    natural

    resouces

    (paper)

    Use of raw

    material(Glove)

    Use of raw

    material

    (Finger coat)

    Use of

    natural

    resouces

    (electricity)

    Use of

    natural

    resouces

    (electricity)

  • 7/21/2019 EHS Overview Share

    48/214

    Use of raw

    material

    (Glove)

    Use of raw

    material(Finger coat)

  • 7/21/2019 EHS Overview Share

    49/214

    x x x

    x x x

    Waste

    plasticreel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    xx x

    Normal Abnormal Emergency

    Depletion Of

    natural

    resourcesOutput Amount/yr **Legal

    Condition

  • 7/21/2019 EHS Overview Share

    50/214

    Waste

    plastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste

    plastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

  • 7/21/2019 EHS Overview Share

    51/214

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    xx x

  • 7/21/2019 EHS Overview Share

    52/214

    x x x

    Waste glove 52 pcs x x

    x x x

    Wasterubber 7300 pcs x x

    x x xWaste

    plastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x x

    xx x

  • 7/21/2019 EHS Overview Share

    53/214

  • 7/21/2019 EHS Overview Share

    54/214

    x x x

    Waste

    plastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    Wasteplastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    xx x

    x x x

  • 7/21/2019 EHS Overview Share

    55/214

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste paper

    ? x x

    x x

    Waste

    plastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x xWaste

    rubber 7300 pcs x x

    x x x

  • 7/21/2019 EHS Overview Share

    56/214

    x x x

    Waste

    plastic

    reel/bag 0 x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste

    plasticreel/bag 0 x x

    x

    x x x

    Waste glove 52 pcs x x

    x x x

    x x x

  • 7/21/2019 EHS Overview Share

    57/214

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    xx x

  • 7/21/2019 EHS Overview Share

    58/214

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x

    x x

    x

    x

  • 7/21/2019 EHS Overview Share

    59/214

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    xx x

  • 7/21/2019 EHS Overview Share

    60/214

    x x x

    Waste

    plastic

    reel/bag 0 x x

    x

    x x x

    Waste glove 52 pcs x x

    x x x

    x x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    x

    x x

    x x x

  • 7/21/2019 EHS Overview Share

    61/214

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x x

    x x x

  • 7/21/2019 EHS Overview Share

    62/214

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x x

    waste paper

    ? x x

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

    x

    x

    x x

    x x

  • 7/21/2019 EHS Overview Share

    63/214

    x x x

    Waste glove 52 pcs x x

    x x x

    Waste

    rubber 7300 pcs x x

  • 7/21/2019 EHS Overview Share

    64/214

    Evaluation

    Significant

    Yes/No

    S0-ADB , F2

    = 4 (NO)

    S0 , F2 = 4

    (NO)

    xS0 , F2 = 4(NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    Air Pollution

    Others (Pls

    mention)Soil Pollution

    Water

    Pollution

    Impact to Environment

  • 7/21/2019 EHS Overview Share

    65/214

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    xS0 , F2 = 4(NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    xS0 , F2 = 4(NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    66/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    67/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x S0 , F2 = 4(NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    68/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    69/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    70/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4(NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    71/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4(NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)x

  • 7/21/2019 EHS Overview Share

    72/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4(NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    73/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    74/214

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4(NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    75/214

    S0 , F2 = 4(NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    76/214

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    x

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

    S0 , F2 = 4

    (NO)

  • 7/21/2019 EHS Overview Share

    77/214

  • 7/21/2019 EHS Overview Share

    78/214

  • 7/21/2019 EHS Overview Share

    79/214

  • 7/21/2019 EHS Overview Share

    80/214

  • 7/21/2019 EHS Overview Share

    81/214

  • 7/21/2019 EHS Overview Share

    82/214

  • 7/21/2019 EHS Overview Share

    83/214

  • 7/21/2019 EHS Overview Share

    84/214

  • 7/21/2019 EHS Overview Share

    85/214

  • 7/21/2019 EHS Overview Share

    86/214

  • 7/21/2019 EHS Overview Share

    87/214

  • 7/21/2019 EHS Overview Share

    88/214

  • 7/21/2019 EHS Overview Share

    89/214

  • 7/21/2019 EHS Overview Share

    90/214

  • 7/21/2019 EHS Overview Share

    91/214

  • 7/21/2019 EHS Overview Share

    92/214

  • 7/21/2019 EHS Overview Share

    93/214

    LEGAL REQUIREMENT BY AREA

    LE

    GAL/DEPT

    HR

    -Training

    Clinic

    Canteen

    MOE

    -PgP1

    MFG

    -PgP2

    Maint.B

    ay

    Se c u r i t

    INDEX OF MALAYSIA EHS LEGISLATION : June 20041 Atomic Energy Licensing Act 1984 Act 304 4.4

    2

    Atomic Energy Licecing (Exemption) (Exemption) (Low Activity Radioactive Material)

    Order 2002 PU(A) 182/2002 4.4

    3 Environmental Qualit Act 1974 Act 127 1 X X X X X

    4

    Environmental Quality (Clean Air) (Amendment) Regulations 2000 PU(A) 309/2000

    2

    5

    Environmental Quality (Compounding of Offences) (Amendment) Rules 1999 PU(A)

    512/1999 2

    6

    Environmental Quality (Control of Emission From Diesel Engines)(Amendment)

    Regulations 2000 PU(A) 488/2000 2

    7 Environmental Qualit Dioxin and Furan Re ulations 2004 PU A 104/2004 2

    8 Environmental Qualit Halon Mana ement Re ulation 1999 PU A 452/1999 2

    9

    Environmental Quality (Delegation of Powers) (Halon Management)Regulation 2000

    PU A 490/2000 2

    10 Environmental Quality (Licensing) Regulations 1977 PU(A) 198/1977 1

    11 Environmental Qualit Motor Vehicle Noise Re ulations 1987 PU A 244/1987 2

    12

    Environmental Quality (Prescribed Activities) (Environmental Impact Assessment)

    Order 1987 PU A 362/1987 6

    13

    Environmental Quality (Prescribed Premises) (Scheduled Wastes Treatment and

    Disposal Facilities) Regulations 1989 PU(A) 141/1989 5 X X

    14

    Environmental Quality (Prohibition on the Use of Chlorofluorocarbons and other

    Gases as Propellants and Blowing Agents) Order 1993 and other Gases as

    Propellants and Blowing Agents) Order 1993 2

    15

    Environmental Quality (Prohibited on the Use of the Controlled Substance in Soap,

    Synthetic Detergent and Other Cleaning Agents) Order 1995 PU(A) 115/1995 3 X

    16

    Environmental Quality (Refrigerant Management) Regulation 1999 PU(A) 451/1999

    2 X

    17 Environmental Quality (Scheduled Wastes) Regulations 1989 PU(A) 139/1989 5 X

    18

    Environmental Quality (Sewage and Industrial Effluents) Regulations 2000 PU(A)

    398/2000 3

    19 Factories and Machinery Act, 1967 Act 139 7.2

    20 Factories and Machiner Exem tion No.3 Order 2004 PU A 185/2004 7.2

    21 Factories and Machinery (Asbestos Process) Regulations 1986 7.2

    22

    Factories and Machinery (Building Operations and Works of Engineering

    Construction) (Safety) Regulations 1986 PU(A) 5/1970 7.2

    23

    Factories and Machinery (Fencing of Machinery and Safety) Regulations 1970

    PU(A) 10/1970 7.2 X X X

    24 Factories and Machiner Lead Re ulations 1984 PU A 60/1984 7.2 X X X X

    25 Factories and Machinery (Mineral Dust) Regulations 1989 PU(A) 2/1989 7.2 X X X26 Factories and Machiner Noise Ex osure Re ulations 1989 PU A 1/1989 7.2 X X X X X

    Factories and Machinery (Notification, Certificate of Fitness and Inspection)

    R l ti 1970 PU(A) 444/1970 7 2

  • 7/21/2019 EHS Overview Share

    94/214

    Environmental Aspect/OHS

    Regulations/topic

    Environmental/OHS Law

    (Act; Section; Regulation; Requirements)

    1)Register entry of Generator set DOE.Ref no

    :AP/E/3S (P 71/2010)

    AP/E/3S (P 72/2010)

    EQA1974 Regulations 1978 (Control of Emissions from Diesel

    Engines)

    2) Sewage discharge EQA 1974 (Sewage) Regulation 2009

    Environmental Quality (Refrigerant Management) Regulation 1999

    Environmental Quality (Halon Management) Regulation 1999

    4) Air emission

    DOE.Ref no : AK(CR 140/2007)EQA 1978 (Clean Air)

    LEGAL R

    3) Halon

    5) Disposal of Scheduled Wastes:Environmental Quality

    ( Scheduled Waste Regulations) 2005

  • 7/21/2019 EHS Overview Share

    95/214

    OSHA 1994 (Dec 2002): Act 514 Part IV, Sec.16 Duty to

    Formulate Safety and Health Policy

    Occupational Safety and Health (Employers Safety and Health

    General Policy Statements) (Exception) Regulations 1995

    OSHA 1994 (Dec 2002): Act 514 Part VII, Sec.30 Establishment

    of Safety and Health Committee at Place of Work

    Occupational Safety and Health (Safety and Health Committee)Regulations 1996

    OSHA 1994 (Dec 2002): Act 514 Part VII, Sec.29

    Occupational Safety and Health (Safety and Health Officer) Order

    19975) Safety and Health Officer

    3) Safety and Health Policy

    4) Safety and Health Committee

  • 7/21/2019 EHS Overview Share

    96/214

    OSHA 1994 (Dec 2002): USECHH 2000, Regulation 9

    OSHA 1997 (Classification, Packaging & Labeling of Hazardous

    Chemicals)

    OSHA 1994 (Dec 2002): USECHH 2000, Regulation 16

    FMA 1967 (June 2003): Act 139 - Factories and Machinery

    (Safety, Health and Welfare) Regulations 1970 Regulation 32

    6) Chemical Health Risk Assessment

    (CHRA)

    7) Implementation of PPE

    8) Initial Noise MonitoringFMA 1967 (June 2003): Act 139 Factories and Machinery (Noise

    Exposure) Regulations 1989, Part III Exposure Monitoring

  • 7/21/2019 EHS Overview Share

    97/214

    FMA 1967(June 2003): Act 139 Factories and Machinery

    (Safety, Health & Welfare) Regulations 1970 Regulation 13.

    Code of Practice For Safe Working In A Confined Space 2010

    OSHA 1994 (Dec 2002): Act 514, Section 15 (1)

    FMA 1967 (June 2003): Act 139 - Sec. 25 (1) (c)

    Factories and Machinery (Safety, Health and Welfare) Regulations

    1970 Regulation 38

    12) Certificate of Fitness for Oil Separator,

    Air Compressor, Air Receiver, Good Lifts and

    Passenger Lifts

    Factories and Machinery (Notification, Certificate of Fitness and

    Inspection) Regulation 1970 Part II, Certificate of Fitness.

    13) Building Operations and Works of

    Engineering Construction

    Factories and Machinery (Building Operations and Works of

    Engineering Constructions) ( Safety) Regulation 1986

    11) Occupational Health Clinic / First Aid

    Room and First Aid Box

    10) Working in Confined Space

    9) Lead Exposure MonitoringFMA 1967 (June 2003): Act 139 Factories and Machinery (Lead)

    Regulations 1984, Part III Exposure Monitoring.

  • 7/21/2019 EHS Overview Share

    98/214

    14)Environmental Management Systems MS ISO14001: 1997 (ISO/TC 207)

    15) Occupational Health and Safety Standard& Requirement

    AS/NZS 4801:2001OHSAS 18001:1999

    16) Notification of Accident, Dangerous

    Occurrence, Occupational Poisoning and

    Occupational Disease

    Guidelines on Safety and Health ( Notification of Accident,

    Dangerous Occurrence, Occupational Poisoning and

    Occupational Disease) Regulations 1994

    17) Cooling Water Tower Environmental Quality (Sewage and Industrial Effluent)

    Regulations 1979 Second Schedule

    18) Bomba CertificateFire Act

    19) Radiation

    Radiation Act 1984

    20) Solid and General Wastes (Non-

    Scheduled Wastes

    Environmental Quality Act 1974

    1. Regulation (24) Restriction of pollution of the soil.

    2. Regulation (25) Restrictions on pollution of inland waters.

    21) Diesel Properties

    Environmental Quality ( Control of Petrol and Diesel Properties )

    Regulation 2007

    Document number Title

    N93 A1 N93-Preparation and control

    Bosch-Norm | 4497025164 | N93 A | 2011-03-30

  • 7/21/2019 EHS Overview Share

    99/214

    N93 A1.1 Basic requirements for occupational health and safety, fire and

    environmental protection

    N93 A2 Responsibility for occupational health and safety, fire and

    environmental protection

    (HSE); Transferring contractor obligations

    N93 A3 Representatives for occupational health and safety, fire and

    environmental

    protection; Tasks and responsibilities

  • 7/21/2019 EHS Overview Share

    100/214

    N93 A4 Legal specifications

    N93 A5 Evaluation of environmental aspects

    N93 A5.1 Evaluation of environmental aspects; Classification scheme fordefining priorities

    N93 A5.2 Evaluation of environmental aspects; Overview of "Environmental

    impact"

    N93 A6 Audit management and performance assessment of occupational

    health and safety,

    fire and environmental protection

    N93 A8 Employee instruction and training

    N93 A8.1 Training and Instruction Matrix; Environmental Protection and

    Safety

  • 7/21/2019 EHS Overview Share

    101/214

    N93 A9 Emergency control; Evacuating Buildings

    N93 A11 Hazard assessment International version

    N93 A11.1 Hazard assessment - RBIN93 A12 Supplier audits

  • 7/21/2019 EHS Overview Share

    102/214

    N93 A13 Waste management

    N93 A14 Soil and water conservation

  • 7/21/2019 EHS Overview Share

    103/214

    N93 A18 Chemical working substances

    N93 A19 Performing environmental and occupational safety - due diligence

    (HSE-Duediligence)

    N93 A20 Contractor companies (CC)

  • 7/21/2019 EHS Overview Share

    104/214

    N93 A21 Post-Merger-Integration (HSE-PMI)

    N93 A22 Fire protection

    N93 A23 Procedure for closing of locations focusing on environmental

    issues

    N93 B1 Directive; General rules for employees

    N93 B1.1 Directive; General rules for employees; Safety identification

    N93 B1.2N93 B1.2 Directive; Hazard prevention

    N93 B1.3 Directive; Accident notification; Occupational accident notification

    schemeN93 B1.4 Directive; Hazardous substance identification; Hazardous

    substancesN93 B1.4.1 Directive; Labeling elements acc. to GHS/CLP (Regulation EC

    1272/2008

    Bosch-Norm | 4497039248 | N93 B | 2011-03-30

    Document number Title

  • 7/21/2019 EHS Overview Share

    105/214

    N93 B1.4.2 Directive; Comparison of hazard symbols/pictograms

    N93 B1.5 Directive; Skin protection plan; Example

    N93 B1.6 Directive; Use of personal protective equipment (PPE); Examples

    for de artment /worksho

    N93 B10 Directive; Working on electrical machines and equipment (MAE)

    N93 B11 Directive; Battery charging installations

    N93 B14 Directive; Setting up working equipment (MAE)

    N93 B16 Directive; Centrifuges

    N93 B17 Directive; EDM machines

    N93 B18 Directive; Welding, flame cutting, soldering

    N93 B19 Directive; Material-removing processing machines

    N93 B20 Directive; Grinder tools

    N93 B21 Directive; Electrochemical machining installations (ECM)

    N93 B26 Directive; Dust detrimental to health

    N93 B28 Directive; Ladders and Steps

    N93 B29 Directive; Lifting platforms

    N93 B29.1 Directive; Lending and written assignment of hydraulic platforms

    to contractor companies; sample

    N93 B30 Directive; Handling lifting tools and load carrying devices

    N93 B33 Directive; Compressed-gas cylinders

    N93 B35 Directive; Powered industrial vehicles

    N93 B38 Directive; Working alone

    N93 B39 Directive; Circular saws and band saws

    N93 B43 Directive; Storing and provision

    N93 B44 Directive; Warehouse facilities

    N93 B47 Directive; Work on systems using pressurized media

    N93 B48 Directive; Kitchen / canteen

  • 7/21/2019 EHS Overview Share

    106/214

    N93 B53 Directive; X-ray systems and equipment with stray radiation effect

    N93 B54 Directive; Maintenance / machine cleaning

    N93 B59 Directive; Jet stream machines

    N93 B65 Directive; Scooters, bicycles and similar vehicles

    N93 B69 Directive; Docking stations / loading ramps

    N93 B70 Directive; Shears

    N93 B71 Directive; Press containers

    N93 B72 Directive; Firefighting systems; (Building/room protection systems)

    N93 B73 Directive; Workstations with visual display units

    N93 B74 Directive; Working in rooms / areas subject to explosion hazard

    N93 I1 Safety Marking; Overview

    N93 I1.1 General

    N93 I1.1.1 Preamble

    N93 I1.1.2 Guidelines for safety marking

    N93 I1.2 Safety marking at work place

    N93 I1.2.1 Prohibition signs; Plasticized PVC film; self-adhesive

    N93 I1.2.2 Mandatory signs; Plasticized PVC film; self-adhesive

    N93 I1.2.3 Warning signs; Plasticized PVC film; self-adhesive

    N93 I1.2.4 Fire safety signs

    N93 I1.2.5 Signs for fire brigade services

    N93 I1.2.6 Safe condition signs; Plasticized PVC film; self-adhesive

    N93 I1.2.7 Marking of dangerous substances; Plasticized PVC film; self-

    adhesive

    N93 I1.2.9 Inspection stickers

    N93 I1.2.10 Minisymbols; Plasticized PVC film; self-adhesiveN93 I1.2.11 Environmental protection signs; Plasticized PVC film; self-

    adhesive

    N93 I2 Personal protective equipment; Overview

    N93 I2.1 Personal protective equipment; General

    N93 I2.1.1 Compulsory personal protective equipment

    N93 I2.1.2 List of authorized suppliers

    N93 I2.2.0 Eye and face protection; General

    N93 I2.2.1 Eye and face protection; Mechanical impact

    Bosch-Norm | 4497025215 | N93 I | 2011-03-30

    Document number Title

  • 7/21/2019 EHS Overview Share

    107/214

    N93 I2.2.2 Eye and face protection; Optical impact

    N93 I2.2.3 Eye and face protection; Chemical impact

    N93 I2.2.4 Eye and face protection; Thermal impact

    N93 I2.2.5 Eye and face protection; Combined impact

    N93 I2.3.0 Head protection; General

    N93 I2.3.1 Head protection; Mechanical/thermal impact

    N93 I2.4.0 Respiratory protection; GeneralN93 I2.4.1 Respiratory protection

    N93 I2.5.0 Hand and finger protection; General

    N93 I2.5.1 Hand and finger protection; Mechanical impact

    N93 I2.5.2 Hand and finger protection; Chemical impact

    N93 I2.5.3 Hand and finger protection; Thermal impact

    N93 I2.5.4 Hand and finger protection; Electrical impact

    N93 I2.5.5 Hand and finger protection; General impacts

    N93 I2.6.0 Foot protection; General

    N93 I2.6.1 Foot protection; Mechanical impact

    N93 I2.6.2 Foot protection; Chemical impact

    N93 I2.6.3 Foot protection; Thermal impact

    N93 I2.6.4 Foot protection; Mechanical impact and ESD protectionN93 I2.7.0 Body protection; General

    N93 I2.7.1 Body protection; Mechanical impact

    N93 I2.7.2 Body protection; Chemical impact

    N93 I2.7.3 Body protection; Thermal impact

    N93 I2.8.0 Hearing protection; General

    N93 I2.8.1 Hearing protection

    N93 I2.10.1 Skin protection; General

    N93 I2.10.2 Example for skin protection plan

    N93 I3 Best practice solutions

    N93 I3.1 Environmental management system (not yet available

    N93 I3.2 Health and safety management system

    N93 I3.2.1 Recording and analyzing of occupational accidents

    N93 I3.3 Soil and water protection

    N93 I3.3.1.1 Machinery and equipment or handling substances hazardous to

    water; Sealing of bottom surface

    N93 I3.3.1.2 Machinery and equipment or handling substances hazardous to

    water; Design of retention systemN93 I3.3.1.3 Machinery and equipment or handling substances hazardous to

    water; Example:

    Safety program for MAE w. individual feed

    N93 I3.3.1.4 Machinery and equipment or handling substances hazardous to

    water; Example:

    Safety program f. MAE w. central feed

    N93 I3.4 Waste (not yet available)

    N93 I3.5 Air quality (not yet available)

  • 7/21/2019 EHS Overview Share

    108/214

    N93 I3.6 Hazardous materials and goods (not yet available)

    N93 I3.7 Fire protection and emergency control

    N93 I3.7.1 Maintenance of fire protection systems

    N93 I3.7.1.1 Maintenance of fire protection systems; Maintenance contents and

    intervals

    N93 I3.8 Inspection intervals for working equipment (MAE)

    N93 I3.8.1 Inspection of working equipment (MAE) acc. to Ord. on IndustrialSafety and Health

    N93 I3.8.2 Inspection of working equipment (MAE) and installations that

    require monitoring;

    Recommendations

    N93 I3.9 Machinery and equipment safety

    N93 I3.9.1 Machinery and equipment safety; Safety standard

    N93 I3.9.1.0 Minimum requirements for operating work equipment; Appendix 1

    on Ordinance on

    Industrial Safety and Health

    N93 I3.9.1.1 Machinery and equipment safety; Observance Machine VO

    N93 I3.9.1.2 EU-Machine directive/9th ordinance on the Equipment Safety Act;

    Procedure withdeviations from CE

    N93 I3.9.2 Separating protective installations; Safety standard

    N93 I3.9.3 Two-hand operation units; Safety standard

    N93 I3.9.4 Key-operated adjuster; Safety standard

    N93 I3.9.5 Hydraulic hose assemblies; Safety standard

    N93 I3.9.6 Polycarbonate (PC-) inspection windows on machine tools; Safety

    standard

    N93 I3.9.7 Safety-related planning and inspection of working equipment and

    construction

    projects; Examples

    N93 I3.10 Training and instruction

    N93 I3.10.1 Operator training for powered industrial vehicle

    N93 I3.10.2 Tips and hints for our employees (leaflet)

    N93 I3.11 Safety standards informative

    N93 I3.11.2 Presses; Safety standard

    N93 I3.11.3 Noise; Safety standard

    N93 I3.11.3.1 Acoustic, machine acceptance; Safety standard

    N93 I3.11.4 Industrial robots; Safety standard

    N93 I3.11.5 Laser installations; Safety standard

    N93 I3.11.6 Storing of hazardous substances; Safety standard

    N93 I3.11.9 Setting up and operating electroplating shops; Safety standard

    N93 I3.11.10 Machines with stock removal using mineral oil as metal workingfluid (KSS); Safety

    standard

    N93 I3.11.10.1 Checklist; Machinery with stock removal using cooling lubricants

    oil; Safety

    standard

    N93 I3.11.10.2 Switch off matrix; Machinery and equipment MAE using cooling

    lubricants oil CL; Safety standard

    N93 I3.11.11 Electromagnetic fields; Safety standard

  • 7/21/2019 EHS Overview Share

    109/214

    N93 I3.11.11.1 Electromagnetic fields; Identification of workshops

    N93 I3.11.12.1 Traffic and escape routes; Safety standard

    N93 I3.11.13 Inspection/assembly installations with combustible liquids; Safety

    standard

    N93 I3.11.13.1 Inspection and supply rooms with combustible liquids; Safety

    standard

    N93 I3.11.13.2 Inspection and assembly installations with combustible liquids(minimum

    requirements); Safety standard

    N93 I3.11.16 Handling biological working materials; Safety standard

    N93 I3.11.16.1 Handling biological working materials, hazard assessment; Safety

    standard

    N93 I3.11.18 Remote maintenance of machine controls; Safety standard

    N93 I3.11.18.1 Remote maintenance of machine data; Protocol

    N93 I3.11.19 Working alone; Safety standard

    N93 I3.11.20 Design and equipment of storage facilities for compressed-gas

    cylinders (gascylinder storage)

    N93 I3.12 Explosion protection

    N93 I3.12.1 Hazardous explosive atmosphere; General

    N93 I3.12.1.1 Explosion protection document acc. to Ordin. on Ind. Safety and

    health (BetrSichV)

    N93 I3.12.1.1.1 Explosion protection document; Assessment of explosion hazard

    from gases,

    fumes or mist

    N93 I3.12.1.1.2 Explosion protection document acc. to Ordin. on Ind. Safety and

    health

    (BetrSichV); Installations relevant for ex. Protection (samples)

    N93 I3.13 HSE-relevant specifications

    N93 I3.13.1 Identification, evaluation and documentation of HSE specifications

    N93 I3.14 Environment-related product data

    N93 I3.14.1 Environment-related product data; Data format and process

  • 7/21/2019 EHS Overview Share

    110/214

    N93 S1 Safety-related planning and inspection of working equipment andconstruction

    projects

    N93 S14 Machinery and equipment (MAE) for handling substances

    hazardous to the

    environment

    N93 S17 Work subject to prior authorization; Safety standard

    N93 S21 Battery installations for electro-powered industrial vehicles; Safetystandards

    N93 S22.1 Fire protection - constructional; Safety standards

    Bosch-Norm | 4497017384 | N93 S | 2011-03-30

    Document number Title

  • 7/21/2019 EHS Overview Share

    111/214

    N93 S22.2 Fire protection - operational; Safety standards

  • 7/21/2019 EHS Overview Share

    112/214

    N93 S22.3 Fire protection - organizational; Safety standards

  • 7/21/2019 EHS Overview Share

    113/214

    Bosch -Norm N93 CN93 C 1 Check Lists for Superiors

    N93 C 1.1 Check Duties

    N93 C2 Check Lists for Safety Representatives (SHB)

    N93 C2.1 Personal Protection Equipment (PPE)/Skin Protection

    N93 C2.2 Traffic, Escape and Rescue Routes

    N93 C2.3 Hazardous Substances

    N93 C2..4 Safety of Machines/Equipment

    N93 C2.5 Electrical Installations and Tooling

    N93 C2.6 Ladders and Steps

    N93 C2.7 Lifting Tools, Loading and Stop Equipment

    N93 C2.8 Fire and Explosion Protection

    N93 C2.9 Transporting and Storing

    N93 C3 Check Lists for Safety specialists and planners

    N93 C3.1 Assessing floor/installation plans

  • 7/21/2019 EHS Overview Share

    114/214

    Registration

    Number

    Bosch

    Compliance

    Compliance

    related

    Monitoring or action

    required

    Area

    Responsibility

    Yes Refer comment Baseline monitoring: Done Facilities

    Yes Refer comment Monthly monitoring: Facilities

    Yes

    -

    Facilities

    Yes

    Refer comment -

    Yes Quarterly

    Facilities, Wave

    soldering, lacquering

    , oven re-flow.

    standby generators

    EGISTER AND EVALUATION OF COMPLIANCE (Legal and other r

    Yes Refer comment

    Monthly sent Waste to KA

    Monthly Scheduled waste

    inventory report to

    Department of Environment

    Waste Generator

    Waste Management

    Center

  • 7/21/2019 EHS Overview Share

    115/214

    Yes

    To have a safety

    policy for a

    Penang in both

    English and

    Bahasa

    Policy formulated and

    published plant wide.

    Revision will be done when

    there are changes in process

    and activities within the plant.

    HSE

    Yes - None HSE

    Yes

    Yes

    Yes

    Monthly report to MD

    Assist Quarterly Audit bySafety Committee

    Yes

    Yearly Safety training

    HSE

    Monthly meetingMeeting minute sent to

    management for reference.

    HSE

  • 7/21/2019 EHS Overview Share

    116/214

    Yes

    IH Monitoring

    Hygiene TechHSE

    Yes

    Labeling Maintenance

    Yes

    PPE HSE

    Yes

    Yes

    Initial noise monitoring &

    Additional noise monitoringHSE

    Yes

    1All operation

    processes,standby generators

  • 7/21/2019 EHS Overview Share

    117/214

    HSE

    ENG, PUR

    Confined Space SOP

    Yes

    Yes

    Yes

    Yes PMA/PMT yearly permit Facilities

    Yes None Facilities

    Nurse

    Yes Facilities

    Yes

  • 7/21/2019 EHS Overview Share

    118/214

    Yes

    Yearly Management Review

    Yearly Internal audit

    Yearly Surveillance audit

    3 yearly Re-assessment audit

    HSE-MS Area rep

    YesYearly Management Review

    Yearly Internal audit

    Yearly Surveillance audit

    3 yearly Re-assessment audit

    HSE-MS Area rep

    Yes Yearly Report to DOSH

    Headquarter

    24 hours notification of any

    incident of accident occurred

    in the workplace

    HSE

    Yes Legionella analysis Facilities, sewage

    treatment plant

    Yes Yearly Renewal Facility

    Yearly renewal

    RPO

    QA

    Yes All

    Refer comment 6 months Facilities

    Yes None HSE-PT,C/PS

  • 7/21/2019 EHS Overview Share

    119/214

    Evaluation

    process

    In their area of responsibility

    executives have to ensure

    that there are no deviations

    from legal

    requirements or from Bosch

    requirements that might be

    avoided or prevented byadequate monitoring.

    EHS-basic requirements

    which have to be observed by

    all locations are listed in

    attachment B

    HSE

    Yes The subordinate managers

    have to provide adequate

    operational facilities conform

    to HSE requirements, to

    check and monitor their

    proper functioning and to

    allocatefunds tailored to the

    requirements for a hazard

    minimized, environmental

    sound and proper operation .

    HSE have to ensure that

    associates are appropriately

    qualified and trained as well

    as prescribed medical

    examinations

    of associates are provided.

    Ensure that legal

    requirements and Bosch

    regulations on occupational,

    health and safety, fire and

    environmental protection. are

    observed. Ensure,

    that company doctors and

    first-aid personnel as

    required by local law are

    appointed

    HSE,Subordinate

    manager

    Yes BOSH-Norm to be implented

    within a period of a 6 months.

    Deviationsrequire coordination with

    C/PS and have to be

    documented.

    2 Terms

    HSE

  • 7/21/2019 EHS Overview Share

    120/214

    Yes Identify clear requirements

    for MAE or processes.

    Prepare an information sheet

    containing the actual

    specifications for

    the operator and to update as

    required.Process and detail in N93 A5

    no 4

    Facility

    operator,HSE

    Yes Identify the environmental

    aspects related of its

    activities, products and

    services, that it can control

    and influence.

    Determine those which have,

    or can have significant

    impacts on the environment

    HSE, All

    Yes Establishing environment allobjective HSE

    None

    Yes With regard to minor and

    major non-conformities the

    audited area will have to

    generate an action plan.

    Auditors have to be

    knowledgeable and trained in

    the relevant techniques and

    management systems and

    the audit principles of ISO

    19011. All the topics

    relevant for the location have

    to be evaluated.

    HSE-Question catalog.

    HSE, Auditor, All

    Yes Employee instruction and

    training shall be organized on

    location. Supervisor on site

    responsible for conducting

    the instruction

    Instruction and training to be

    carried out are listed in N93

    A8.1. Performance ofinstruction and training must

    be documented

    Document form 1: Example

    "List of Signatures"

    HSE,PUR

    Yes It depend on the group to

    conducting the training.

    All

  • 7/21/2019 EHS Overview Share

    121/214

    Yes Escape and rescue plans

    shall be made and

    evacuation drills have to take

    place if one of the following

    criteria

    applies:

    Conduct every 2 year

    All

    Yes For new MAE and building

    investments, an overall final

    acceptance process at the

    plant level has to be set

    up, carried out and

    documented.

    Document form 1: Sample

    hazard assessment .

    doc

    Documentation form 2:

    Hazard characteristics .

    HSE,All

    Yes The questionnaire Supplier

    Audits (attachment 1)

    provides the minimum

    standard. Refer

    4.3 the process and detail in

    N93 A12 supplier audits

    Documentation :

    Questionnaire

    HSE

  • 7/21/2019 EHS Overview Share

    122/214

    Measures for the protection

    of ground and waters for the

    case of leakages have to be

    taken With dangerous

    goods transports the

    corresponding national

    regulations have to beobserved. Material samples

    of pharmaceuticals,

    cosmetics, food and

    stimulants that manufacturers

    and customers make

    available for testing have to

    be returned to the

    manufacturer or disposed of

    properly.

    All waste disposal contractors

    that are to be contracted by

    Bosch for the first time haveto undergo a review

    Those responsible must have

    undergone sufficient training

    as required.

    Document form

    1: Sample info-

    questionnaire.

    Document form

    2: Hazard characteristics.

    HSE and FCM

    Yes The requirements to the

    properties of surfaces and

    retention volume for escaping

    substances that are

    hazardous

    to the environment, including

    performance examples, are

    specified in BoschNorm

    N93S14 in 4.2.1 Machinery

    and equipment (MAE) and

    4.2.2 Wastewater discharge

    HSE

  • 7/21/2019 EHS Overview Share

    123/214

  • 7/21/2019 EHS Overview Share

    124/214

    Yes The implementation of all

    Bosch-internal requirements

    (GF-guidelines, central

    directives, Bosch-Norms)

    must have been concluded

    18 months after

    acquisition.N93 DocumentA21 Form 1 HSE-PMI-check

    list (

    N93 A21 Form 1 HSE-PMI-

    check list

    PDF Example:

    Implementation Timeline

    (RBNA)

    Yes Stricter insurers

    requirements have to be

    assessed by the plant.Requirements from location-

    specific regulations (building /

    operating permit) have to be

    harmonized accordingly

    in the fire protection concept

    FCN,PUR,HSE,All

    Yes Process Scheme GE,HSE

    Yes Protective measures/rules of

    conduct

    HSE and All

    Yes None HSE and All

    Yes None HSE and All

    Yes None HSE, Clinic

    Yes None HSE

    Yes None HSE

  • 7/21/2019 EHS Overview Share

    125/214

    Yes None HSE

    Yes None HSE

    Yes None HSE

    Yes Protective measure code/behavior HSE

    Yes Protective measure code/

    behavior

    HSE and LOG

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE

    Yes Protective measure code/behavior

    HSE,FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and LOG/PUR

    Yes None

    Yes Protective measure code/

    behavior

    HSE and LOG/PUR

    Yes Protective measure code/

    behavior

    HSE

    Yes Protective measure code/

    behavior

    Yes Protective measure code/

    behavior

    HSE and All

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE, LOG/PUR

    Yes Protective measure code/

    behavior

    HSE, LOG/PUR

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

  • 7/21/2019 EHS Overview Share

    126/214

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE

    ,FCM,LOG/PUR

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure code/

    behavior

    HSE and FCM

    Yes Protective measure/ code

    beviour

    HSE and FCM

    Yes Protective measure/ code

    beviour

    HSE and LOG/PUR

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, AllNone ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

  • 7/21/2019 EHS Overview Share

    127/214

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, AllNone ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, AllNone ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    None ; information HSE, All

    National requirements for

    responsibilities, deadlines,

    content and documentation of

    accident causes have to be

    observed. There are process

    sequence for the record and

    analysis of accident in N93

    I3.2.1 no 4

    HSE

    None HSE and FCM

    None HSE and FCM

    None HSE and FCM

    None HSE and FCM

  • 7/21/2019 EHS Overview Share

    128/214

    None HSE

    None HSE

    None HSE

    None HSE, FCM

    None HSE

    None HSE , FCM

    None; information All

    None HSE , FCM

    None; information HSE

    None; information HSE

    None; information All

    None; information ESH

    None; information ESH

    fire department emergency

    control forces must have

    access to working equipment

    internal spaces.

    ESH,FCM

    None;Information All

    None;Information All

    None;Information All

    None;Information ESH

    None;Information All

    None;Information ESH

    None;Information All

    Heated baths must have a

    protection against

    overheating

    All

    None;Information All

    None;Information ESH,FCM

    None;Information ESH,FCM

    None;Information All

  • 7/21/2019 EHS Overview Share

    129/214

    None;Information ESH,FCM

    None;Information All

    None HSE

    None;Information ESH

    None HSE

    None HSE and FCM

    None HSE and FCM

    None: Construction /

    equipment / protective

    measures

    None; Information HSE and FCM

    Employers have to identify

    and assess their employees

    hazards due to explosions

    and to decide on the required

    protective measures.

    The required explosion

    protection measures have to

    be selected and evaluated

    within an explosion protection

    concept that is free from

    inherent contradictions

    HSE and All

    None HSE

    None HSE

    None HSE

    None.4 Refer N93 i3.14Process description and

    process responsibilities

    (overview) for more

    information

    HSE

    None HSE

  • 7/21/2019 EHS Overview Share

    130/214

    Yes Planning instructions targetspecification or Internal target

    specification and planning

    and procuring of working

    equipment and building of

    structures. Working

    equipment and buildings

    have to be acquired or built in

    accordance with the safety-

    related requirements,

    Deviations require

    coordination with C/PS and

    have to be documented.Working equipment and

    structures have to comply

    with internal and external

    requirements.

    HSE and All

    Yes None

    Yes See Fire Protective " Best

    Proactive"

    Yes None HSE

    Planning and approval

    requirements are available at

    all times and have to be

    adhered to. Facilities on roof

    areas (mechanical / technical

    equipment) have to be

    accessible at least in two

    places, opposite ones if

    possible. Marked

    emergency exits have to

    open in escape direction

  • 7/21/2019 EHS Overview Share

    131/214

    Yes Location must have a safe

    water supply for firefighting.

    Primarily sprinkler systems

    have to be provided

    according to requirements.

    Sprinkler systems have to be

    maintained.All areas in Bosch buildings

    have to be designed with a

    smoke release system.

    Sprinkler protected buildings

    fire alarm systems have to be

    implemented only in selected

    areas.

    Automatic fire alarm systems

    have to be installed in

    production plants

    FCM, HSE

    Fire fighting systems with

    gaseous agents have tocomply with the requirements

    regarding protection of

    persons

    and the environment strictly.

    Gas detection systems have

    to be carried out as required

    by law Design and

    installation of smoke and

    heat release systems with

    natural action have to comply

    with state-of-the art

    technologyA location must have a safe

    water supply for firefighting

  • 7/21/2019 EHS Overview Share

    132/214

    Yes Emergency plans have to be

    designed and to be

    coordinated with the specific

    emergency response teams.

    Incidents have to be

    categorized, assessed and

    evaluated (extent ofdamage).

    A sufficient number of

    employees will have to be

    trained in behavior during a

    fire and in firefighting with

    firefighting equipment

    All installations and

    equipment for fire protection

    needs to be maintained

    (including reporting) . Fire

    safety audits have to be

    conducted at regular intervalsand preferably in combination

    with health, safety and

    environmental site visits.

    Evaluation requirements

    have to be at state-of-the-art

    level . First response

    activities have to be ensured

    HSE, ERT Team

    Required fire compartments

    (e. g. due to legal

    requirements) have to be

    separated by spatial distance

    (minimum

    distance from neighboring

    building the height of the

    higher of the two structures)

    or by constructional

    measures.

    Fire walls must have a

    minimum fire resistance of 90

    minutes and be continued for

    at least 30 cm

    above the roof; stability of the

    wall must be guaranteed also

    with external loads (e. g.

    collapsing racks, cranesystems).

    New constructions

    separations of required

    stairways have to be at least

    90 minutes fire resistant

  • 7/21/2019 EHS Overview Share

    133/214

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

    None None

  • 7/21/2019 EHS Overview Share

    134/214

  • 7/21/2019 EHS Overview Share

    135/214

    HSE Policy in all dept/area

    HSE

    3 latest SHO report to MD.

    Action taken and closed.

    SHO Report 8th

    July, 8th June and

    5th May 2011

    CEP Training

    HSE

    Management

    Review minutes of

    meeting

    Meeting minutes

    kept by HSE

    3 latest SHC meetingminutes. Corrective action

    taken and closed.

    SHC minutes ofmeeting

    (Q2&Q4)

  • 7/21/2019 EHS Overview Share

    136/214

    HSE

    Latest IH monitoring.

    Latest CHRA report.

    Action taken and closed.

    CHRA Report

    complete as at

    15/4/2011

    IH Monitoring for

    LEV in progress

    New chemicals and

    chemical waste

    containers

    Chemical buy off

    procedure. Latest

    chemical in the database.

    Chemical

    Management

    Storage Area,

    Production Line

    and Waste

    Management

    Area

    N/A

    Latest chemical register

    List of hazardous chemical

    Any action taken to reduce

    the risk.

    Form F under

    CHRA reportDept Work Unit

    First Aid box. Please verify

    the quantity.

    First Aid box

    inventory updated

    by Supervisor

    Supervisor

    Inventory

    Checklist

    HSE

    Latest noise monitoring

    data. Mapping zone done

    using in-house

    meter/external parties

    Noise Monitoring

    Report

    Record:Biochem

    Lab

    HSE

    List of employee expose to

    extreme noise. Latest

    Audiomtric test. Evaluationof result.

    Audiometric

    monitoring

    conducted in 2008

  • 7/21/2019 EHS Overview Share

    137/214

    HSE latest lead monitoring data.

    Mapping zone area

    expose to lead.

    Soldering area mapping

    Monitoring

    conducted 2007

    List of employee expose to

    leadLatest confined space

    activity conducted.

    PTW sampling

    HSE PMT/PMA certificate.

    Latest renew date:

    DOSH Log Book

    n/a Latest excavation work. Monitor Work

    Permit

    ClinicFirst Aid box. Please verify

    the quantity.

    Facilities

    SOP & Confined

    Space procedure

    inprogress

  • 7/21/2019 EHS Overview Share

    138/214

    HSE database Latest Mgt Review. Action

    taken & closed.

    Latest internal audit.

    Action taken & closed

    Latest Surveillance Audit.

    Action taken & closed

    n/a Latest Mgt Review. Actiontaken & closed.

    Latest internal audit.

    Action taken & closed

    Latest Surveillance Audit.

    Action taken & closed

    Accident report and

    investigation

    Accident Statistic.

    NADOOPOD report to

    DOSH. JKKP 8

    Last 3 accident report.

    Action taken & closed.

    Evaluate effectiveness of

    the accident CA/PA

    JKKP 8

    2010 Accident

    Case

    Facilities Latest Legionella test

    result

    Certificate Latest Cert:

    Film Badge

    Entry/exit Medical

    check-up

    Cert: LPTA/A/1170

    Area surveillance:

    Personal surveillance:

    Schedule Waste

    centralized in Waste

    Management Center

  • 7/21/2019 EHS Overview Share

    139/214

    A1.1 Checklist

  • 7/21/2019 EHS Overview Share

    140/214

  • 7/21/2019 EHS Overview Share

    141/214

  • 7/21/2019 EHS Overview Share

    142/214

  • 7/21/2019 EHS Overview Share

    143/214

  • 7/21/2019 EHS Overview Share

    144/214

  • 7/21/2019 EHS Overview Share

    145/214

  • 7/21/2019 EHS Overview Share

    146/214

  • 7/21/2019 EHS Overview Share

    147/214

  • 7/21/2019 EHS Overview Share

    148/214

  • 7/21/2019 EHS Overview Share

    149/214

  • 7/21/2019 EHS Overview Share

    150/214

  • 7/21/2019 EHS Overview Share

    151/214

  • 7/21/2019 EHS Overview Share

    152/214

  • 7/21/2019 EHS Overview Share

    153/214

  • 7/21/2019 EHS Overview Share

    154/214

    Date : 15/8/2011

    Rev : 0

    Project / work Routine sample analysis and result,

    verification sampling

    Every Year, result Gen C B101 result not

    comply with Standard B of the regulations

    and dust exceeding 0.4g/NM3

    Every Month resultmonitoring complied with Standard B of

    the regulations

    Complied

    Every Quarterly

    result monitoring complied with Clean Air

    regulations

    Complied ( 2nd

    Schedule registration to DOE in

    progress)

  • 7/21/2019 EHS Overview Share

    155/214

    Inspection record

    Inspection record

    Complied

    Complied

    Complied

    ( Last Management Review 31/10/10) No

    Changes

  • 7/21/2019 EHS Overview Share

    156/214

  • 7/21/2019 EHS Overview Share

    157/214

    Complied

    Complied

    Complied

    Complied

    Refer to Work Permit System

  • 7/21/2019 EHS Overview Share

    158/214

    Complied

    Complied

    Complied

    Complied

    Inprogress

    Complied

    Complied

  • 7/21/2019 EHS Overview Share

    159/214

  • 7/21/2019 EHS Overview Share

    160/214

  • 7/21/2019 EHS Overview Share

    161/214

  • 7/21/2019 EHS Overview Share

    162/214

  • 7/21/2019 EHS Overview Share

    163/214

  • 7/21/2019 EHS Overview Share

    164/214

  • 7/21/2019 EHS Overview Share

    165/214

    Objective & Target

    Aspect Objective Target

    Organizational Obj & Target

    1. Relative CO2 emission reduction Reduce CO2 emmision to

    environment

    204 / 198 / 192 year

    2011

    2. Reduce Accident Rate To reduce accident cases

    in RBMA

    1. Accident Free 360

    days in 2011

    2. 3.74 /3.5/3.3 year

    2011

    3. Comply with Legal and Other

    Requirements

    Meet all legal and other

    requirements

    100 % meet all legal

    and other

    requirements every

    year

    Departmental Obj & Target1. Awareness Training on ISO14001

    implementation

    Create awareness on

    ISO14001 Management

    System

    75 % employees are

    train and aware 75 /

    85 / 95 (2011)

    2. Awareness Training on HSE

    related issues : such as waste

    disposal, use of recycle bin,

    hazardous communication (legal),

    electrical safety

    Create awareness on

    HSE requirements

    75 % employees are

    train and aware 75 /

    85 / 95 (2011)

    Objective and Target

    Organization Objective and Target

    Departmental Objective and Target

    from Aspect Impact Analysis.

  • 7/21/2019 EHS Overview Share

    166/214

    Program Indicator Operational Control Monitoring & Measure

    Go Green

    - Shut off light

    - LED- Motion Sensor

    - PV installation

    Relative CO2 emission

    data

    Policy deployment Telecon: Tracking CO2

    reduction program every 2

    month

    1. Awareness LCD

    - Video/ ppt

    - Bulletin Board

    2. Safety Week

    3. HSE

    Accident Rate

    Number of participation

    for each event

    Policy deployment Monthly accident report

    HSE audit

    A.6, C/AU, tiPTop

    No of complaint received

    by gov or other interested

    parties

    Yearly Legal evaluation Legal evaluation report

    quaterly

    HSE Training by

    department

    No of NCR

    No of Feedback (MII)

    Follow N93 A.8 2012 Revise quaterly training

    attendance and evaluation

    HSE Training by

    department

    No of NCR

    No of Feedback (MII)

    Follow N93 A.8 2012 Revise quaterly training

    attendance and evaluation

  • 7/21/2019 EHS Overview Share

    167/214

    HEALTH SAFETY ENVIRON

    Programs Jan Feb Mar Apr

    Respiratory Protection Program

    ERT

    Handling and Storage

    of Flammable & Combustible

    Logout Tag out

    Fire Extinguisher Training Canteen Security FCM HR

    Compress Gas Safety

    Cafeteria Safety

    Chemical Spill

    Office Safety

    Update on Law & Regulation

    Hearing Conservation ProgramContarctor work procedure

    C/AU/ HSE Awarenss

    CPS

    ISO14001 Surveillance Evaluation

    Internal

    31

    EHS Week

    Bulletin Board

    Monthly Audit/Survey HR-Training Clinic Canteen MOE1

    EHS Admin/Finance/ Others EngineeringScheduled Waste

    Disposal Area Receiv

    Chiller TNB RoomSafety Committee Member Mapis Mapis Mapis Mapis

    Azman Azman Azman Azman A

    Yahya Yap Bee How

    Date 18 8 15 12

    Noise Monitoring Addition

    Industrial Hygine Monitoring

    Air Emission

    Send report to

    DOE

    Sewage Monitoring

    Completed Prepare

    Plan

    Number in the box is the date of a training conducted/plan for the month

    Training

    HSE -MS

    Awareness

    EHS / Safety Committee Audit

    Monitoring

  • 7/21/2019 EHS Overview Share

    168/214

    EHS ACTIVITIES FOR Y2013

    W1 W2 W3 W4

    ISO 14001 Internal Audit AAR Yearly Exec

    ISO 14001 3rd Party Audit AAR Yearly MGR/ENGDOSH Inspection (Cf) NOY As Requested F&MEHS Committee Meeting NOY Quartely MEMBERSEHS Workplace Audit (Pgp1) AAR Monthly HSE, PICEHS Plant Tour (Pgp2) NOY Bi-Weekly PM, DH & HSE

    EHS Workplace Audit (PgP2)NOY/MAS/

    HSECWeekly Selected Area PIC

    Fire / Emergency Drill NOY Yearly ERT, All

    EHS Week / Campaign NOY Yearly ALLEHS Ms Management Review AAR Monthly MGMT

    1. Awareness training on System AAR YearlyArea

    Representatives

    2. Revise HIRARC / EAIA NOY 1/2 Yearly AreaRepresentatives

    3. Review prosedure AAR 1/2 YearlyArea

    Representatives

    4. Review EHS Objective & Target AAR Yearly EHS1. Basic Fire Fighting Bomba 1/2 Yearly ERT2. First Aider Training 1/2 Yearly ERT

    3. Handling and Storage of

    Flammable & CombustibleMapis Yearly ERT / EMPLOYEE

    4. Log Out Tag Out TTT Yearly FCM / TEF / MOE

    5. Fire Extinguisher TrainingAAR /

    NOYMonthly EMPLOYEES

    6. Compressed Gas Safety NOY Yearly MOE7. Cafeteria Safety AAR Yearly Canteen Operators8. Chemical Spill TTT Yearly Chemical Handlers9. Office Safety AAR Yearly Office Occupiers

    10. Update on Laws & RegulationNIOSH /

    DOSHYearly FCM / MOE / HSE

    11. Hearing Conservation Program SOCSO Yearly Associates at noisy

    12. Contractor Work ProceduresNIOSH /

    DOSHYearly Contractors

    13. ERT Refresher Training NOY Monthly ERT

    14. EHS Management

    Commitment TrainingNOY 1/2 Yearly DHs

    1. Accident Data MAS Monthly HSE2. Sewage MAS Monthly HSE, FCM

    3. Air Emission MAS Quarterly HSE, FCM

    4. Scheduled Waste MAS Monthly HSE, FCM

    5. Relative CO2 Emission MAS Monthly HSE, FCM

    Legend

    EHSPERFORMANCE

    MONITORING

    MAINEVENTS

    ENVMS

    EHSAWARNESST

    RAINING

    DESCRIPTION OF ACTIVITIES PIC FREQTARGET

    PARTICIPANTSJAN

  • 7/21/2019 EHS Overview Share

    169/214

    Planned

    Delay

    On-time

    Rescheduled

  • 7/21/2019 EHS Overview Share

    170/214

    W5 W5 W6 W7 W8 W9 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W18 W19 W20 W21

    MAYFEB MAR APR

  • 7/21/2019 EHS Overview Share

    171/214

  • 7/21/2019 EHS Overview Share

    172/214

    W22 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W31 W32 W33 W34 W35 W35 W36

    JUNE JUL AUG

    2013

  • 7/21/2019 EHS Overview Share

    173/214

  • 7/21/2019 EHS Overview Share

    174/214

    W37 W38 W39 W40 W40 W41 W42 W43 W44 W44 W45 W46 W47 W48 W48 W49 W50 W51

    % of Completion Jan -

    NOV DECSEPT OCT

  • 7/21/2019 EHS Overview Share

    175/214

  • 7/21/2019 EHS Overview Share

    176/214

    W52

    Dec =

    STATUS JAN -

    DEC

    2013

  • 7/21/2019 EHS Overview Share

    177/214

    RESPONSIBILITY RELATED TO HSE LEGAL & OTHER REQUIREMENTS

    Responsibility Requirement Specific Act Retention Penalty (RM) MiscellaneousAR Back-Up

    Weekly

    DH meeting RBMA N/A 1 year N/A N/A Mapis Azman

    Monthly 01/11

    SHO Report to MD Legal OHSA (SHO) 10 years5000 or 6

    months jail

    3 calender

    month only w/o

    SHO Azman Mapis 4

    HSE audit SOP/Legal OHSA (SHO) 10 years NCR N/AMapis Azman 18

    HSE Management

    System Meeting

    SOP N/A 5 years N/A N/A

    Mapis Azman 7&8HSE accident CO2 data

    to Dr.SchmidtCM HSE report INF N/A N/A

    Mapis Azman 15

    Sewage Analysis Legal EQA INF10,000 or 2

    yearsN/A

    Pani Allen 29Sewage Analysis Report

    to DOELegal EQA INF

    10,000 or 2

    yearsN/A

    Mapis Azman 26/1Consigment notes to

    DOELegal EQA INF

    10,000 or 2

    yearsN/A

    Pani Name 1 29

    Quaterly

    HSE committee meeting Legal OHSA (SHC) 7 years5000 or 6

    months jailN/A

    Mapis Name 1

    Safety committee Audit Legal OHSA (SHC) 7 years5000 or 6

    months jailN/A

    Mapis Name 1

    HSE Management

    ReviewISO/OHSAS SOP 5 years NCR N/A

    Mapis Name 1 27

    ERT/First Aid Training SOP SOP 3 years NCR N/A Mapis Name 1Scheduled Waste

    Inventory to DOELegal EQA INF

    10,000 or 2

    yearsN/A

    Mapis Name 1 10

    Air Emission Analysis Legal EQA INF10,000 or 2

    yearsN/A

    Pani Name 2Air Emission Analysis

    Report to DOELegal EQA INF

    10,000 or 2

    yearsN/A

    Mapis Name 1 6

    Yearly

    ISO14001 Internal Audit ISO/OHSAS SOP 3 years NCR N/A Mapis Name 1ISO14001 Surveillance

    AuditISO/OHSAS SOP 3 years NCR N/A

    Mapis Name 1

    Annual Report Data CMHSE

    Database3 years NCR N/A

    Mapis Name 1 19

    CSR Report Data CMHSE

    Database3 years NCR N/A

    Mapis Name 1

    Fire Drill Legal Fire Act INF 5,000 or 3years

    N/AMapis Name 1

    Noise Monitoring Legal OHSA INF 1,000 Competency Mapis Azman

    Lead Monitoring Legal FMA 30 years 2,000 Competency Mapis Azman

    NADOOPOD Report Legal OSHA 5 years10,000 or 1

    yearN/A

    Mapis Azman 30

    IH Monitoring Corp No Corp Req INF NCR IH Certified Lab Lab 2

    Duty

    To Keep Secrect Legal OHSA N/A20,000 or 2

    yearsN/A

    Mapis Azman

    Chemical Approver

    SOP/Legal SOP 3 years

    10,000 or 1

    year N/A Azman Mapis

    Permit to work Legal OSHA INF 1000 Competency Azman Mapis

    Impairment (Fire

    Supression System) SOP SOP 3 years NCR N/A Azman Mapis

    Machine/Tooling Buy-off SOP SOP 3 years NCR N/A Azman Mapis

    Scheduled Waste

    Shipment Legal EQA INF 2,000 N/A Pani Name 1 29

    Training related to HSE

    TO

  • 7/21/2019 EHS Overview Share

    178/214

  • 7/21/2019 EHS Overview Share

    179/214

    Clause ISO14001:2004 Requirements4.1 General Requirements New defination

    4.2 Environmental Policy Clearly reflect clause 4.2

    4.3 Planning4.3.1 Environmental Aspects

    Identify AI

    4.3.2 Legal and other requirements AI link to legal

    4.3.3 Objectives, Targets &

    Programme(s)

    Establish,

    maintain &

    implement.

    4.4 Implementation And Operation4.4.1 Resources, roles,

    responsibility and Availability of resources

    authority

    4.4.2 Competence, Training and

    Awareness

    Competence

    4.4.3 Communication To in form or not.

    4.4.4 Documentation EMS and their interaction

    4.4.5 Control of Documents Approval-review-control

    4.4.6 Operational control Associate - Significant Aspect

  • 7/21/2019 EHS Overview Share

    180/214

    4.4.7 Emergency preparedness

    and response

    Potential emergency, incident

  • 7/21/2019 EHS Overview Share

    181/214

    4.5 Checking4.5.1 Monitoring and measurement Time- equipments-analysis

    4.5.2 Evaluation Of Compliance. Evaluate

    4.5.3 Nonconformity, corrective

    action and

    Identify,investigate,evaluate,record,

    preventive action. revision.

    4.5.4 Control of Records Record demonstrate compliance

    4.5.5 Internal Audit Plan ,implement,result -

    management

    4.6Management Review Ensure continuing suitability,adequacy, effectiveness.

  • 7/21/2019 EHS Overview Share

    182/214

    ABC SdnBHD

    Level 0 Level 1RBMA Mgmt System

    N93 Manual

    Mgmt System Manual

  • 7/21/2019 EHS Overview Share

    183/214

  • 7/21/2019 EHS Overview Share

    184/214

  • 7/21/2019 EHS Overview Share

    185/214

    ISO SOP

    Level 2 Level 3

    I01-01 Organisation Chart

    I00-09 Environmental / Aspect / Impact Assessment.

    N93-A5 Env.Aspect / Impact Requirements.

    I06.-01 Suppliers Assessment

    N93-A12 Suppliers Audit.

    I00-06 Legal and Other requirements

    I00-07 Env. Objectives & Targets

    I00-05 OHS & Environment

    SMAN-0010 Safety, Health & Env.

    committee

    I18-01 Training.

    N93-A8 Training

    SPER-0001 Training needs Analysis

    SPER-0003 Training effectiveness and

    evaluation.

    I00-08 Communication on Environment related issues.

    I21-01 Customer Specific Requirements (CSR)

    I05-02 Handling of procedures from CM/QMM.

    I05-01 Document control.

    I06-02 Control of sub-contractor.

  • 7/21/2019 EHS Overview Share

    186/214

    I06-03 Suppliers selection & qualification.

    I06-04 Purchasing

    I09-07 Maintenance and Servicing.

    I09-08 General / Hot work permit.

    I13-03 Disposition of Non-conforming products.

    I13-05 Waste Management.

    N93-A13 Waste Management (guide only)

    I15-02 Chemical Handling and storage.

    SMAN-0013 Waste water control.

    SMAN-0007 Fire loss control.

    SMAN-0009 Fire Protection Servicing

    procedure.

    SMAN-0010 Safety, Health and Env.

    committee.SPER-0007 Vendors/Contractors SH&Q

    awareness training.

    SPUR2-0014 Handling of Chemical

    purchase.

    SPUR2-0016 Evaluation of Service

    suppliers.

    SQAS5-0005 Suppliers Audits.

    CMAN-002-003 Segregation of waste

    at source.

    CMAN-002-002 Schedule waste

    segregation at source.

    CMAN-002-001 Waste Master list.

    I00-11 Emergency response procedure.

    SMAN-004 Aisles & Exit.

  • 7/21/2019 EH