eia practice: a global review

17
1 A REVIEW OF GLOBAL ENVIRONMENTAL IMPACT ASSESSMENT (EIA) PRACTICE SIMILARITIES AND DIFFERENCES IN THE PRACTICE OF EIA ASIGBAASE MICHAEL (March, 2012)

Upload: michael-asigbaase

Post on 29-Nov-2014

6.077 views

Category:

Technology


0 download

DESCRIPTION

Since the inception of EIA, there have been a worldwide adoption of the idea. However, its practice varies from country to country. This is a review of the practice of EIA, focusing on the similarities and differences that exist globally.

TRANSCRIPT

Page 1: EIA practice: a global review

1

A REVIEW OF GLOBAL ENVIRONMENTAL IMPACT ASSESSMENT

(EIA) PRACTICE

SIMILARITIES AND DIFFERENCES IN THE PRACTICE OF EIA

ASIGBAASE MICHAEL

(March, 2012)

Page 2: EIA practice: a global review

2

Introduction

Environmental Impact Assessment (EIA) has been variously defined since its inception

(Yanhua et al., 2011; Samarakoon and Rowan, 2008; Snell and Cowell, 2006; Bruhn-Tysk

and Eklund, 2002; Perez-Maqueo, 2001; Duinker and Greig, 2007; Lee and George, 2000). It

is therefore difficult to comprehensively define EIA, however, it can be described as a

systematic process for identifying, examining, analyzing, evaluating, and predicting the

impacts of planned activities or policies; involving consultation with affected stakeholders,

and using the results of the analysis and consultations in planning, authorising and

implementation of the activity (Toro et al., 2012; Kwiatkowski and Ooi, 2003; Yanhua et al.,

2011; Cashmore, 2004). In simple terms, EIA is just an information gathering exercise

carried out by the proponent or other recognized bodies which enables decision-making

bodies understand the potential environmental effects of a proposed project before deciding

whether or not it should go ahead. EIA is thus an anticipatory (futuring), participatory

environmental management tool and as such, it is based on principles such as transparency,

public involvement and accountability (CENN, 2004; RTPI, 2001). Environmental Impact

Assessment (EIA) is essential for sustainable development; it ensures a balance

economically, socially, and institutionally with the environment.

EIA development started with the adoption of the NEPA (National Environmental Protection

Act) in the USA in 1969 (El-Fadl and El-Fadel, 2004), and facilitated by the Stockholm

Conference in 1972, the Brundtland Report, and the Rio Conference, the idea has been

adopted and practiced by over 100 countries (Wood, 2003b; Jay et al., 2007), including

developed, developing and transitional economies. EIA is a useful tool for facilitating intra-

generational and intergenerational equity (Yanhua et al., 2011) hence promoting sustainable

development and ecosystems protection. It is therefore not surprising that it has been adopted

world-wide within four decades (Jay et al., 2007). However, though the basic components of

EIA (Figure 1) are relatively the same world-wide, the procedures and practice varies from

one nation to the other (Glasson et al., 2000). This write up therefore seeks to critically

review the global practice of EIA, focusing on similarities and differences. The essay

examined how the legal and institutional framework, and the screening and scoping

components of EIA vary globally, using information from 40 countries (Table 1). The

selected aspects of EIA for review in this essay were based on the fact that they form the back

bone and most essential parts of EIA (Heinma and Põder, 2010; Weston, 2000a).

Figure 1: Basic EIA Process and components

Proposed Project

Screening Scoping EIA

Conduction Public

Involvement Decision

Page 3: EIA practice: a global review

3

Table 1: Selected countries for essay write up

Continent Selected Countries (depended on available data)

Africa Ghana, Nigeria, South Africa, Egypt, Kenya, Rwanda, Tanzania and

Tunisia

Asia China, Bangladesh, Azerbaijan, India, Indonesia, Maldives, Pakistan,

Sri Lanka, Thailand, Lebanon, Syria, Korea and Vietnam

Australia Australia and Fiji

Europe Bulgaria, Denmark, UK, Finland, Estonia, Ireland, Italy, Lithuania,

Sweden, Turkey, Norway and France

North America US and Canada, and Alberta (province)

South America Brazil and Colombia

Legal and Institutional Framework or Procedures

As pointed out earlier, the practice of EIA differs from one country to another; EIA has been

adopted in the context of the institutional framework and political system of each country.

Several studies including, Wood (2003a) and Okello et al (2008), suggests that legislation(s)

is/are essential for EIA to be effective. Evidently, the adoption, implementation, and practice

of EIA depend on the institutional framework and political context of the decision-making

process in each country (Leknes, 2001). The provision for EIA may be made through

legislation, administrative order or policy directive (Ahmad and Wood, 2002). Some

countries have EIA legislations requiring approval of projects before their commencement

but other countries rely on regulations, guidance or ad hoc procedures (Glasson et al., 2000).

For example, countries such as USA (Steinemann, 2001 ), Finland (Pölönen et al., 2011),

Ghana (Appiah-Opoku, 2001), India (Rajaram and Das, 2011), Korea (Song and Glasson,

2010), Colombia (Toro et al., 2010), Pakistan (Nadeem and Hameed, 2008), South Africa

(Sandham and Pretorius, 2008), Ireland (Geraghty, 1996), Scotland (Natural Heritage

Management, 2009), and Syria (Haydar and Pediaditi, 2010) have comprehensive or enabling

legislations requiring that certain projects must carry out EIA and be approved before the

commencement of such undertakings whilst Azerbaija (CENN, 2004) and Fiji (Turnbull,

2003) has no comprehensive EIA legislations but relies on unclear regulations and guidelines

from an EIA handbook. Also, in China, there was no comprehensive EIA legislation until

2003, though EIA had been practiced in the country for about three decades (Lui et al., 2011).

Despite this bold step by China, many assessments, including Lui et al. (2011) and Wang et

al. (2003), suggest that the new system is still weak, allowing little public participation

(though better than earlier systems), and deficient in the consideration of alternatives.

However, the research conducted by Wang et al. (2003) was shallow because their

methodology did not allow for fair representation of China’s major towns. The paper

concentrated in two major Town centres which do not provide any form of representative

picture of the practice of EIA under the new system across China as a nation.

Another form of disparity is that some countries have complex systems within which EIA is

performed whilst other countries have relatively simpler legal procedures for carrying out

EIA. In China, for example, EIA operates within a complex legal framework (Lui et al.,

2011) whiles in Ghana, the system is much simpler (Appiah-Opoku, 2001). Also, in other

countries where the legislative and administrative system are well defined and established

Page 4: EIA practice: a global review

4

such as UK (Salvador et al, 2000) and Canada (www.ceaa-acee.gc.ca), public participation

and project alternatives are treated as essential and provision is made to ensure effectiveness.

It can therefore be inferred that the legislative and administrative system of a country together

with its socio-economic growth determines how EIA is practiced. Despite the differences in

terms of legislation, most countries have well defined procedures by which EIA is executed,

and the process involves all the components shown in Figure 1. It is also worth noting that

Nigeria has three different independent EIA systems, all backed by laws, and therefore differs

significantly from other countries in their approach to EIA (Ogunba, 2004). The disadvantage

of such systems is that duplication of functions is not uncommon and the effectiveness of all

systems is questionable.

Screening

In all countries under review, the EIA process begins when a proponent applies to the

appropriate authority for permission (e.g. China), approval (e.g. Ghana), Clearance (e.g.

Bangladesh) or licence(s) (e.g. Colombia) to undertake a planned activity. In some countries,

such as Ghana and Bangladesh, only one agency or body has the power to approve projects

whiles in other countries such as Colombia, China, Canada, Syria, Denmark, India and Brazil

more than one agency or body can approve projects (Christensen, 2006; Paliwal, 2006). For

example, either the Government Administration (MEHLD), Regional Independent

Corporations, Sustainable Development Corporations, or Urban Community Corporations in

Colombia can issue the licence to developers to undertake projects (Toro et al., 2010)

whereas in Ghana, only the EPA has the authority to approve projects (Appiah-Opoku, 2001).

It is worth mentioning that unlike the other nations, Canada has a different system; the

process depends on ‘triggers’. The federal authority undertakes EIA whenever a project

meets at least one of the ‘triggers’. For example, a project will initiate the EIA process if it is

proposed by the federal authority (www.ceaa-acee.gc.ca).

Once the appropriate authority receives the application, the next stage in the EIA process is

screening. Screening is the process of determining whether a proposed undertaking requires

an EIA or not based on the expected impact of the proposed project on the environment and

its relative significance (Pölönen et al., 2011). Depending on the circumstances of the

proposed project, the existing environment, and the likely environmental effects, screenings

might vary significantly in time taken, length and depth of analysis, (Joa˜o, 2002; www.ceaa-

acee.gc.ca). In all nations, the screening stage produces one of four main outcomes; (i) no

need for EIA, (ii) need for a full and comprehensive EIA, (iii) need for a limited EIA or (iv)

need for further studies to determine the level of EIA required (Salvador et al., 2000; Clausen

et al., 2011). Three main approaches are employed during screening to determine whether or

not a proposed project requires EIA; legal (or policy), inclusion or exclusion list, or a criteria

for case-by-case (Figure 2). Every country uses at least one of these methods, though they

may differ significantly in the way they are applied based on applicable EIA law(s) or

regulations. Most countries use the list approach (Christensen and Kørnøv, 2011; Glasson et

al., 2000; Marara et al., 2011; El-Sayed et al., 2011). For instance, in Aberta, the inclusion

list defines projects that require a comprehensive EIA base on size and type, for example, the

construction, operation or reclamation of a quarry producing more than 45 000 tonnes per

year requires a full EIA (Alberta Regulation 62/2008).

Page 5: EIA practice: a global review

5

Figure 2: General screening approaches (Source: http://eia.unu.edu/course/?page_id=136)

The use of project lists offers two main merits; it provides a standardized framework for

screening and simplifies the screening process as well. However, despite these merits, it is

critical to note that use of project lists must be done with caution because it has its own

weaknesses. For example, a proposed surface coal mine project producing more than 45 000

tonnes per year will require an EIA in Alberta (Alberta Regulation 62/2008). In this case,

EIA can be avoided by reducing the proposed production level to a level just below the

threshold (e.g. 44 400 tonnes per year). It is therefore essential to have a discretionary

(secondary) list or other screening procedures to which such projects will be subject. Also,

project lists requires regular updates that will incorporate experiences from pass EIAs and to

meet new demands. The flowchart of Alberta’s EIA process is shown in Figure 3.

In Azerbaija, however, the screening is much different from Alberta because there are no

distinctive procedures by which projects are screened (CENN, 2004). Screening is based on

experience from past EIAs and sometimes recognized international bodies screening lists

(e.g. World Bank). This kind of screening is likely to be of poor quality because threshold

values are quite subjective, and the screening process is likely not to be comprehensive. As

such, usually, only the oil companies requires EIA but small scale activities, regardless of

their potential environment impact, do not go through the EIA process (CENN, 2004). It can

therefore be inferred that the procedure for screening in Azerbaija is not rigorous enough to

make EIA effective. Much like Azerbaija, is the Fijian state, where screening rest solely on

the discretionary power of the Town and Country Planning’s Director (Turnbull, 2003). Such

screening approaches are very subjective with high probability of producing poor results.

Page 6: EIA practice: a global review

6

Figure 3: Alberta EIA process (Source: Alberta’s Environmental Assessment Process, 2010)

Unlike Azerbaija, Bangladesh has defined screening procedures. All industrial projects are

grouped into; Green, Amber A, Amber B and Red, and requires Environmental Clearance

before their commencement, though not all projects requires EIA (Figure 4). The

categorization is based on the environmental significance and location of the proposed

industry. Projects location is critical because though they may be below the threshold size,

they may be located in or near to environmentally sensitive sites. Projects funded by

development partners such as the World Bank or Asian Development Bank follow different

screening procedures developed by them (Momtaz, 2002). There are three categorizations; A

(significant impact) - full EIA required; B (some impact) – partial EIA required; and C (no

impact) – no EIA required. This is quite true in most development countries to which such

bodies are development partners.

Page 7: EIA practice: a global review

7

Figure 4: Process of obtaining environmental clearance in Bangladesh (Source: Momtaz,

2002)

Page 8: EIA practice: a global review

8

Projects in China are categorized into A, B, and C and the screening procedure is much

similar to that of Bangladesh, though it may differ significantly in content, size and time. The

administration of EIA screening is however much complex because of the political

framework within which it operates. For example, Environmental Impact Reports (EIRs) of

all projects involving nuclear facilities or high confidentiality, cross-boundaries or worth

more than RMB 20 million approved by the State Council are approved by the State

Environmental Protection Agency (SEPA). All other projects are approved by the

Environmental Protection Bureaus (EPBs) on agreed terms (Lui et al., 2011). The definition

of what is significant is dependent on the nature and quantity of the ‘pollutant discharge’ as

well as the ‘sensitivity’ of the area. Therefore projects are classified into Category A, B or C

based on their features, output and environmental parameters. It is critical to note that the

screening process is biased towards construction projects with potential to cause pollution.

Also, monetary values are used to set thresholds unlike Bangladesh and Alberta where project

size and type are used.

Screening in Pakistan (Figure 5 presents EIA flowchart) is much simpler but similar to that of

China because thresholds for determining whether a project requires EIA or IEE depends on

its cost and capacity (Nadeem and Hameed, 2008). For example, a 50 million rupees (0.806

million US$) or more highway project requires an EIA but if the cost is less than 50 million

rupees, an IEE is required; a 50MW (MG) or less hydro power project does not require an

EIA whereas capacities greater than 50MW must undergo EIA (GoP, 2000). Projects that

require EIA form the Schedule II list and those that require IEE constitute Schedule I list.

These Schedules are regularly updated to incorporate new experiences and to meet current

demands. The downside of this procedure is that size and location has not been well

considered. Large or small scale housing schemes’ located in sensitive areas is likely to have

significant adverse impact on the environment yet it may not require EIA. Like China,

provincial EPAs approve EIAs within their jurisdictions whiles the state EPA (Pakistan EPA)

is responsible for state projects or trans-provincial projects. However, IEEs for public sector

projects are approved by the Planning and Development Department(s) (Federal or

provincial) with the exception of military projects and trans-country impact projects (Nadeem

and Hameed, 2008). Ghana’s EPA decides what constitutes a significant environmental

impact in consultation with a committee drawn from various government sectors, and experts.

Once a project will have significant adverse impacts on the environment, the Proponent is

asked to consult with the affectees and interested parties and prepare a scoping report

(Appiah-Opoku, 2001).

Page 9: EIA practice: a global review

9

Figure 5: Pakistan’s EIA process (Source: Nadeem and Hameed, 2008)

Scoping

Screening establishes the basis for scoping, which identifies the main issues that need to be

covered in an EIA yet ensuring that indirect, secondary and cumulative effects are not down

played (Rajaram and Das, 2011). Scoping should therefore be timely, comprehensive and

Page 10: EIA practice: a global review

10

focused, flexible but systematic, and involve public participation (Glynn, 2004). Globally,

scoping is done using one of three major approaches; proponent prepares scope solely,

proponent prepares scope in consultation with competent authority with or without public

input or competent authority prepares the scope for the proponent (Wood et al., 2006;

Mulvihill, 2003; Zubair, 2001). In cases where the competent authority prepares the scope for

the proponent, it can be very burdensome, especially in developed countries where proposed

projects may range from hundreds to thousands in a short period. If scoping is also left solely

to the proponent, the general public and affectees are likely to be left out in most cases.

Therefore, it is better to use the second approach, where the proponent prepares the scope in

consultation with the competent authority, the public and affectees. In Alberta, once a project

requires an EIA, the Proponent prepares and provides the public and Alberta Environment

with copies of Proposed Terms of Reference (PTOF). The Assessment Director based on the

EPEA guidelines and public input, issues the Final Terms of Reference (scope) and the

Proponent conducts the assessment. A quite different approach is used in Azerbaija, the scope

is agreed upon at a meeting held by the Environmental Authority for the Developer involving

affectees, experts and the Developer. Where consensus cannot be reached, the Environmental

Authority decides the scope and the Developer conduct the assessment. There are no explicit

guidelines for scoping in Azerbaija. In Pakistan, the EPA plays just a suggestive role in

scoping; the Developer has the sole responsibility of developing the Terms of Reference,

after which the assessment is conducted. This is because scoping is not mandatory in Pakistan

(Nadeem and Hameed, 2008), though it is in most countries. The approach in China also

differs significantly from the already discussed procedures. Upon the Developer’s request, a

licensed agency prepares the EIA action-outline for them. The Developer then hires a

licensed agency to conduct the EIA once the action-outline is approved by EPB. In

determining the significance of a project, China uses the Benefit-Cost Analysis (BCA)

approach, in addition to level of potential pollution. Though significant differences exist in

the way scoping is done in various countries, the content of the EIA report are basically the

same differing very little. Comparing the countries under discussion, the content includes;

project description,

project location and environmental setting information,

project options and alternatives

baseline information (environmental, social and cultural),

potential negative and positive impact (environmental, social, health, economic and

cultural),

mitigation plans, and

environmental management proposal for monitoring and decommissioning (Paliwal,

2006; El-Fadel et al., 2000; Kruopienė et al., 2009; Saengsupavanich, 2011).

A Summary of the other stages

The report is reviewed by; a multi-disciplinary team of experts co-ordinated by Alberta

Environment in Alberta (Alberta’s Environmental Assessment Process Updated, 2010);

Environmental Review Expert Group (EREG) chaired by the Environmental authority in

Page 11: EIA practice: a global review

11

Azerbaijan (CENN, 2004); EPB, in consultation with other relevant authorities in China (Lui

et al., 2011); and EPA, in consultation with a committee of experts in Ghana (Appiah-Opoku,

2001). The purpose of the review is basically the same in all countries under discussion; to

identify any project-related risks or uncertainties and determine if the information provided

meets the Terms of Reference (TOR) (Lui et al., 2011; Kruopienė et al., 2010). In Ghana, the

report is graded; A (excellent), B (good), C (satisfactory), D (attempted), E (poor) and F

(very poor), and depending on the nature of the project and potential impacts, grades D, E,

and F are might be asked to provide the appropriate additional information (Appiah-Opoku,

2001). Once the reviewed report is satisfactory; in Alberta, the Director formally refers the

report to the Board or the Minister to become part of the Public Interest Decision process

(Alberta’s Environmental Assessment Process Updated, 2010); in the other countries under

review, a decision is given and the project may commence on ground while other

requirements are being processed. Globally, most countries (e.g. Lithuania, Figure 6) have

provision for public participation and appeal in case of dissatisfaction on proponent’s part

(O'Faircheallaigh, 2010; Elling, 2004; Li et al., 2012; Furia and Wallace-Jones, 2000;

Soneryd, 2004; Almer and Koontz, 2004); however, it is poorly practiced in most developing

countries. Finally, all countries have provisions for monitoring but it is usually done poorly or

not all, even in some developed nations (Morrison-Saunders et al., 2007; Zubair et al., 2011).

Figure 6: Lithuania EIA process (involves much public participation) (Source: Kruopienė et

al, 2009)

Page 12: EIA practice: a global review

12

Conclusion

EIA is practiced world-wide but differing greatly in procedures and practices. Most countries

have well defined procedures for carrying out EIA though in practice it may be poorly done.

Well defined procedures for EIA but poor practices are not uncommon in most developing

countries. Categorization of projects is based on factors such as type, magnitude, capacity,

costs, duration, location, and impact significance. In all countries, the EIA process begins

when a proponent applies to the appropriate authority for permission to undertake an activity

or project. Screening determines whether a project requires EIA or not. The most common

screening procedure involves the use of lists with thresholds set by project cost, location,

size, type or capacity. Some countries have discretionary lists which enlist projects not

covered (in term of threshold) in the inclusion and exclusion lists. Decision on EIA

requirements for such projects is dependent on location and level of significance of impact.

Most countries’ scoping involves the proponent, affectees, experts and the public. However,

in China, the action-outline (which provides the scope) is given by a licensed agency and

approved by the state’s environmental authority. Scoping is not mandatory in Pakistan hence

the proponent decides what to include; the state’s environmental authority only plays a

suggestive role in this stage. Globally, the impact assessment is mostly conducted by the

Proponent in developed countries but in developing countries, a licensed agency or the state’s

environmental authority does the assessment. The cost of the assessment, however, is borne

by the proponent in all countries. Public participation in the EIA process is not uncommon in

developed countries but much limited in developing countries. Though there are great

variations in EIA procedures and practice, the contents of EIA report are much similar with

little variations.

Page 13: EIA practice: a global review

13

References

Ahmad, B. and Wood, C. (2002): A comparative evaluation of the EIA systems in Egypt,

Turkey and Tunisia. Environmental Impact Assessment Review, 22, 213 – 234.

Alberta Regulation 62/2008; Environmental protection and enhancement act, environmental

assessment (Mandatory and exempted activities) regulation. Alberta Queen’s Printer: Alberta

Province.

Alberta’s Environmental Assessment Process (2010): Alberta Environment, Environmental

Assessment Program, Edmonton, Alberta, 5pp.

Almer, H.L. and Koontz, T.M. (2004): Public hearings for EIAs in post-communist Bulgaria;

do they work? Environmental Impact Assessment Review 24; 473 – 493.

Appiah-Opoku, S (2001): Environmental impact assessment in developing countries; the

case of Ghana. Environmental Impact Assessment Review, 21, 59 – 71.

Bruhn-Tysk S and Eklund M, (2002): Environmental impact assessment—a tool for

sustainable development? A case study of biofuelled energy plants in Sweden. Environmental

Impact Assessment Review, 22, 129–144.

Canadian Environmental Assessment Agency; http://www.ceaa-

acee.gc.ca/default.asp?lang=En&n=B053F859-1, Accessed on 11/02/2012

Cashmore, M. (2004): The role of science in environmental impact assessment; process and

procedure versus purpose in the development theory. Environmental Impact Assessment

Review, 24, 403 – 426.

Caucasus Environmental NGO Network (CENN) (2004): Assessment of effectiveness of

Environmental Impact Assessment (EIA) system in Azerbaijan. Baku, Azerbaijan CENN,

55pp.

Christensen, P (2006): Danish experiences on EIA of livestock projects. Environmental

Impact Assessment Review, 26, 468 – 480.

Christensen, P and Kørnøv, L (2011): EIA screening and nature in Denmark. Journal of

Environmental Management, 92, 1097 – 1103.

Clausen, A., Vu, H.H. and Pedrono, M. (2011): An evaluation of the environmental impact

assessment system in Vietnam; the gap between theory and practice. Environmental Impact

Assessment Review, 31, 136 – 143.

Duinker, P.N. and Greig, L.A. (2007): Scenario analysis in environmental impact assessment;

improving explorations of the future. Environmental Impact Assessment Review, 27, 206 –

219.

El-Fadel, M. Zeinati, M. and Jamali, D (2000): Framework for environmental impact

assessment in Lebanon. Environmental Impact Assessment Review, 20, 570 – 604.

Page 14: EIA practice: a global review

14

El-Fadl, K. and El-Fadel, M. (2004): Comparative assessment of EIA systems in MENA

countries; challenges and prospects. Environmental Impact Assessment Review, 24, 553 –

593.

Elling, B. (2004): Modernity and communicative reflection in environmental assessment. In:

Hilding-Rydevik, T and TheodorsdottirAH (eds.); Planning for sustainable development – the

practice and potentials of environmental assessment. Nordregio R20044:2. Stockholm:

Nordregio; p. 53 – 67.

El-Sayed, A. B., Zahran, A.A. and Casmore, M. (2011): Benchmarking performance;

environmental impact statements in Egypt. Environmental Impact Assessment Review, 31,

279 – 285.

Environmental impact assessment course module: http://eia.unu.edu/course/?page_id=136,

accessed on 04/02/2012

Furia, L.D. and Wallace-Jones, J. (2000): The effectiveness of provisions and quality of

practices concerning public participation in EIA in Italy. Environmental Impact Assessment

Review, 20, 457 – 479.

Geraghty P.J. (1996): Assessment practice in Ireland following the adoption of the European

directive. Environmental Impact Assessment Review, 16, 189 – 211.

Glasson J and Salvador N.N.B. (2000): EIA in Brazil; a procedures–practice gap. A

comparative study with reference to the European Union, and especially the UK.

Environmental Impact Assessment Review, 20, 191–225.

Glynn, T (2004): Environmental impact assessment (EIA); a guide for Reviewers. MSc.

Thesis, Memorial University of Newfoundland, 26pp.

Government of Pakistan (GoP), (2000): Pakistan environmental protection agency (review of

IEE and EIA) regulations. Islamabad: Pak-EPA.

Haydar, F. and Pediaditi, K. (2010): evaluation of the environmental impact assessment

systems in Syria. Environmental Impact Assessment Review, 3, 363 – 370.

Heinma, K and Põder, T (2010): Effectiveness of environmental impact assessment systems

in Estonia. Environmental Impact Assessment Review, 30, 272 – 277.

Jay, S., Jones, C., Slinn, P. and Wood, C. (2007): Environmental impact assessment;

retrospect and prospect. Environmental Impact Assessment Review, 2, 287 – 300.

Joa˜o, E. (2002): How scale affects environmental impact assessment. Environmental Impact

Assessment Review, 22, 289 – 310.

Kruopienė, J., Židonienė, S. and Dvarionienė, J. (2009): Current practice and shortcomings of

EIA in Lithuania. Environmental Impact Assessment Review, 29, 305 – 309.

Page 15: EIA practice: a global review

15

Kwiatkowski, R.E. and Ooi, M. (2003): Integrated environmental impact assessment; a

Cannadian example. Bulletin of the World Health Organization, 81, 434 – 438.

Lee and George, (eds.) (200b): Environmental assessment in developing and transitional

countries. Chichester: Wiley.

Leknes, E. (2001): The role of EIA in the decision-making process. Environmental Impact

Assessment Review, 21, 309 – 334.

Li, T.H.Y., Ng, S.T. and Skitmore, M. (2012): Public participation in infrastructure and

construction projects in China; from an EIA-based to a whole-cycle process. Habitat

International, 36, 47 – 56.

Lui, Q., Zhu, T. and Sun. Z (2011): Exploration and prospects; the systemization process of

environmental impact assessment in China. Energy Procedia, 11, 3679 – 3687.

Marara, M., Okello, N., Kuhanwa, Z., Douven, W., Beevers, L. and Leentvaar, J. (2011): The

importance of context in delivering effective EIA; case studies from East Africa.

Environmental Impact Assessment Review, 31, 286 – 296.

Momtaz, S. (2002): Environmental Impact Assessment in Bangladesh: a critical review.

Environmental Impact Assessment Review, 22, 163 – 179.

Morrison-Saunders, A., Marshall, R. And Arts, J. (2007); EIA follow-up; international best

practice principles. International Association for Impact Assessment Special publication

series 6.

Mulvihill, P.R. (2003): Expanding the scoping community. Environmental Impact

Assessment Review, 23, 39 – 49.

Nadeem, O. and Hameed, R. (2008): Evaluation of environmental impact assessment system

in Pakistan. Environmental Impact Assessment Review, 28, 562 – 571.

Natural Heritage Management, (2009): A handbook on environmental impact assessment;

guidance for Competent Authorities, Consultees, and others involved in the Environmental

Impact Assessment process in Scotland. 3rd

Edition. Natural Heritage Management,

Edinburgh, 239pp.

O'Faircheallaigh, C. (2010): Public participation and environmental impact assessment;

purposes, implications, and lessons for public policy making. Environmental Impact

Assessment Review, 30, 19 – 27.

Ogunba, O.A. (2004): EIA systems in Nigeria; evolution, current practice and shortcomings.

Environmental Impact Assessment Review, 24, 643 – 660.

Okello, N., Douven, D., Leentvaar, J. and Beevers, J (2008): Breaking Kenyan barriers to

public involvement in environment impact assessment. The Art and Science of Impact

Page 16: EIA practice: a global review

16

Assessment 28th

Annual Conference of the International Association for Impact assessment,

4-10 May 2008, Perth convention Exhibition Centre, Perth, Australia.

Paliwal, R. (2006): EIA practice in India and its evaluation using SWOT analysis.

Environmental Impact Assessment Review, 26, 492 – 510.

Perez-Maqueo, O., Equihua, M., Hernandez, A. and Benitez, G. (2001): Visual programming

languages as a tool to identify and communicate the effects of a development project

evaluated by means of an environmental impact assessment. Environmental Impact

Assessment Review, 21, 291 – 306.

Pölönen, I., Hokkanen, P. and Jalava, K. (2011): The effectiveness of the Finnish EIA system

– what works, what doesn’t, and what could be improved? Environmental Impact Assessment

Review, 31, 120 – 128.

Rajaram, T. and Das, A. (2011): Screening for EIA in India; enhancing effectiveness through

ecological carrying capacity approach. Journal of Environmental Management, 92, 140 –

148.

Royal Town Planning Institute (RTPI) (2001): Planning practice standard; environmental

impact assessment. The Royal Town Planning Institute, London, 34pp.

Saengsupavanich, C. (2011): A current environmental impact assessment of a port in

Thailand; marine physical aspects. Ocean and Coastal Management, 54, 101 – 109.

Salvador, N.N.B., Glasson, J. and Piper, J.M. (2000): Cleaner production and environmental

impact assessment; a UK perspective. Journal of Cleaner Production, 8, 127 – 132.

Samarakoon, M. and Rowan, J.S. (2008): A critical review of environmental impact

assessments in Sri Lanka with particular reference to Ecological Impact Assessment.

Environmental Impact Assessment Review, 41, 441 – 460.

Sandham, L.A. and Pretorius, H.M. (2008): a review of EIA report quality in the North West

province of South Africa. Environmental Impact Assessment Review, 28, 229 – 240.

Snell, T. and Cowell, R. (2006): Scoping in environmental assessment; balancing precaution

and efficiency? Environmental Impact Assessment Review, 26, 359 – 376

Soneryd, L. (2004): Public involvement in the planning process; EIA and lessons from the

Orebro airport extension, Sweden. Environmental Science and Policy, 7, 59 – 68.

Song, Y.-I. and Glasson, J. (2010): A new paradigm for environmental assessment (EA) in

Korea. Environmental Impact Assessment Review, 30, 90 – 99.

Steinemann, A. (2001): Improving alternatives for environmental impact assessment.

Environmental Impact Assessment Review, 21, 3 – 21.

Page 17: EIA practice: a global review

17

Toro J, Requena I and Zamorano M (2010): Environmental impact assessment in Colombia:

Critical analysis and proposals for change. Environmental Impact Assessment Review, 30,

247 – 261.

Toro, J., Duarte, O., Requena, I. and Zamorano, M. (2012): Determining vulnerability

importance in environmental impact assessment, the case of Colombia. Environmental

Impact Assessment Review, 32, 107 – 117.

Turnbull, J (2003): Environmental impact assessment in the Fijian state sector.

Environmental Impact Assessment Review, 23, 73 – 89.

Wang, Y., Morgan, R.K. and Casmore, M. (2003): Environmental Impact Assessment of

Projects in the People’s Republic of China: new law, old problems. Environmental Impact

Assessment Review, 23, 543 – 579.

Weston, J. (2000a): EIA, decision making theory and screening and scoping in UK practice.

Journal of Environmental Planning and Management, 43, 183 – 203.

Wood, C. (2003a): Environmental impact assessment in developing countries; an overview.

Paper presented at the conference on the new directive in impact assessment for development,

Manchester.

Wood, C. (2003b): Environmental impact assessment; a comparative review. 2nd

Edition.

London; Pearson-Prentice Hall.

Wood, G., Glasson, J. and Becker, J. (2006): EIA scoping in England and Wales; practitioner

approaches, perspectives and constraints. Environmental Impact Assessment Review, 26, 221

– 241.

Yanhua, Z., Song, H., Hongyan, L. and Beibei, N. (2011): Global environmental assessment

research trends (1973 – 2009). Procedia Environmental Sciences, 11, 1499 – 1507.

Zubair, L. (2001): Challenges for environmental impact assessment in Sri Lanka.

Environmental Impact Assessment, Review 21, 469 – 478.

Zubair, S., Bowen, D. and Elwin, J. (2011): Not quite paradise; inadequacies of

environmental impact assessment in Maldives. Tourism Management, 32, 225 – 234.