![Page 1: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/1.jpg)
Ekota Dry Pond and Menisa Storm Upgades
Pre-Construction Public Open House 7:15 PM, March 21, 2016
![Page 2: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/2.jpg)
Presentation Outline
2
• Introduction of Project Team • Project Components • Construction Impacts • Access Maintenance and Traffic Control • Communication Plan • Construction Schedule • Questions / Feedback
![Page 3: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/3.jpg)
Project Team
3
• Project Owner – City of Edmonton – Utilities Infrastructure
• Engineering Consultant – Sameng Inc.
• Construction Contractor – Sureway Construction Ltd.
![Page 4: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/4.jpg)
Project Background and Components
4
• Severe rainfall events in July 2004 and July 2012 caused flood damages throughout the city including Satoo, Ekota and Menisa.
• Improvements were completed for Satoo in 2008. Downstream or system outlet improvements for Mill Woods being on-going with anticipated completion in 2017.
• The Ekota and Menisa Improvements were developed during 2013/2014. Detailed Design have been completed. Major Components Include: 1. Ekota Dry Pond located within Father Ivor Daniel Park. 2. Relief Sewer and Pond inlet/outlet connection between trunk sewer on
Mill Woods road and northwest corner of Ekota Dry Pond. 3. Relief Sewer and Pond inlet/outlet from south end of 75th Street to the
southeast corner of Ekota Dry Pond.
![Page 5: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/5.jpg)
Project Layout
5
![Page 6: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/6.jpg)
Pond Landscaping Design
6
• Developed in consultation with City Parks and school board.
• Flat side slopes adjacent to school. • Replanting of trees and bushes to
enhance appearance. • Concrete patio with benches for
school use. • Improve trail linkage.
• Pond Excavation is staged to allow
school use of designated areas. • All haul trucks will turn east on Mill
Woods Road towards 66 Street
Time to fill: 45 min Time to drain: 1h40 min
![Page 7: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/7.jpg)
How Do Dry Ponds Work?
7
This image cannot currently be displayed.
![Page 8: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/8.jpg)
Sewer through Walkway
8
Sewer in walkway area between Menisa and Father Ivor Daniel Park to be installed using trenchless (underground tunnelling) method.
![Page 9: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/9.jpg)
Construction Impacts
• Machine noise – noise bylaw will be adhered to • One lane road closure and sidewalk closures • Temporary full road closures (to be confirmed)
– Knottwood Road and 72nd Street
• No street parking near construction sites • Temporary water service disruption (affected residents
will be notified) • Temporary bus stop relocation and detour • Home access • Emergency access
9
![Page 10: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/10.jpg)
Access Maintenance and Traffic Control
• When school is in session there will be no heavy haul during the following times: – Monday to Friday, 8:00 AM to 9:00 AM – Monday, Tuesday,Wednesday and Friday, 2:30 PM to
3:30 PM – Thursday, 11:30 AM to 12:30 PM.
• Sewer installation along Knottwood Road to be completed between July and August 2016.
• All construction area will be fenced off.
10
![Page 11: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/11.jpg)
Communication Plan
11
• This Pre-Construction Open House on March 21, 2016: – Introduce project team and contacts – Provide construction information – Answer questions – Post information onto City Website after the open house
• Future Communication: – Construction notices to directly impacted residents by Sureway Construction Ltd. – Individual resident contacts – Road signs to inform public on road closure and detour – Social media to inform public on road closure and detour
![Page 12: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/12.jpg)
Projected Project Schedule
12
• Where We Are Now: Start of Construction • Dry Pond Construction:
– April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping repairs and final clean up: May – August, 2017 – Dry pond area re-open for public use: October 2017
• Sewer Construction: April 2016 – November 2016, may run into 2017 construction season if delayed by wet weather
• Site Restoration: Damaged landscaping, pavement and sidewalk will be restored upon project completion, or as weather permits.
![Page 13: Ekota Dry Pond Presentation - Edmonton · – April to October, 2016 weather permitting – School use area construction: July to August, 2016, weather permitting – Landscaping](https://reader033.vdocument.in/reader033/viewer/2022050421/5f9080560882543ec0728087/html5/thumbnails/13.jpg)
Thank You
13
Thank you for your attendance and we welcome any questions you have. For more information please contact: Minnan Liu Project Manager – Utilities Infrastructure, City of Edmonton 780-496-7962 [email protected]