Election Assistance Commission United States VVSG 1.1 www.eac.gov 1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg, MD

Upload: dominic-smith

Post on 11-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

1

Election Assistance Commission

United States

VVSG 1.1

www.eac.gov

Technical Guidelines Development Committee (TGDC)NIST

July 20, 2015Gaithersburg, MD

Page 2: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

2

Background on VVSG

www.eac.gov

• 2005 VVSG (1.0)• The revision to the 2005 VVSG (1.1)• The next iteration of the VVSG (2.0)

Page 3: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

3www.eac.gov

2005 VVSG (1.0)

• 2005 VVSG was adopted by the EAC in December of 2005 as required by the Help America Vote Act (HAVA) • Refer to it as 1.0.•December 2007 - voting systems could no longer be approved for testing to the 2002 VSS and the 2005 VVSG (1.0) was fully implemented.

Page 4: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

4www.eac.gov

VVSG 1.1

• Revisions to the 2005 VVSG• The purpose of revision?• Clarify the guidelines to make them

more testable; • Enable NIST to create test assertions;• Update portions of VVSG without

dramatically altering the guidelines.

Page 5: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

5www.eac.gov

2007 VVSG – “Next Iteration” (2.0)• Was the next iteration of the VVSG • Draft created by the EAC’s Technical

Guidelines Development Committee (TGDC) in August of 2007

• Refer to it as 2.0

Page 6: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

6

Revising 2005 VVSG

www.eac.gov

• Human factors requirements; • Security (VVPAT, Electronic records, Cryptography,

System security specifications and external interface);

• Core requirements (S/W workmanship, reliability, accuracy, and humidity);

• Incorporate RFIs issued on the 2005 VVSG during test campaigns;

• and two public comment periods with a combined review period of 250 days.

Page 7: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

7

First Comment Period

www.eac.gov

• 120 days – 6/1/2009 through 9/28/2009• Received 244 public comments• 159 accepted• 78 not accepted

Page 8: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

8www.eac.gov

Changes Prior to Second Comment Period

• Telecommunications• Remove references to NSRL• Software Validation • Access Control• Quality Assurance and Configuration Management• Coding Conventions• Required Languages• Audit and Election Logging• All relevant RFIs

Page 9: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

www.eac.gov 9

Second Comment Period

• 130 days – 9/6/2012 through 1/14/2013• Received 706 public comments• 178 accepted• 157 not accepted• 367 not highlighted/not open for comment

Page 10: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

10www.eac.gov

Changes from Second Public Comment Period

• Definitions added to glossary; • Reliability validation added to Appendix C in Volume

II; • Updated references and links throughout the

document; • Clarifications of specific HW, SW, Accessibility and

Security requirements;• Numbering scheme corrected; • Clean up grammatical errors;• Formatting cleaned up

Page 11: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

www.eac.gov 11

Implementation Plan

• After Commissioner approval, VVSG 1.1 is immediately available for testing and certifying voting systems.

• By October, the Commissioners will identify the timeline for transitioning fully from the 2005 VVSG to VVSG 1.1.

• Modifications to systems certified to the 2005 VVSG can still be submitted for testing and certification to the 2005 VVSG after the transition to VVSG 1.1.

Page 12: Election Assistance Commission United States VVSG 1.1  1 Technical Guidelines Development Committee (TGDC) NIST July 20, 2015 Gaithersburg,

12www.eac.gov

Contact

Jessica MyersCertification Program Specialist

[email protected](202) 468-7580