electrical & control cm40 daresbury laboratory. cm40 electrical infrastructure update rrm2...

19
Electrical & Control CM40 Daresbury Laboratory

Upload: gwendoline-reeves

Post on 23-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Electrical & ControlCM40

Daresbury Laboratory

CM40 Electrical Infrastructure UpdateRRM2 Latest• Latest on Installation Progress• Rack AllocationsRacks Under Construction/Test • FC Controls/ Mag PSU Rack Install• SS Mag Power Supply Racks• SS Dump Tray RackMice Hall Infrastructure• Magnet Cable Termination Boxes• Main Cable tray Install• Tracker & Diffuser• Compressor Electrical Services• Vacuum• PPS System / ODD system

2

Rack Room 2 – UPS Inverter and Batteries

3

UPS for Critical Load

A second UPS (inverter) will be procured to support the SS racksA position has been allocated and a quote received

Same batteries will be used for both UPS.

Autonomy approx. 30 mins

Batteries

Inverter 2

Inverter 1

RR2 Layout – rack allocation

4

FC & SS Power Supply racks

FC & SS Control & Instrumentation racks

QD System racks

Auxiliary rack (Tracker & Diffuser)

FC & SS Power Converter Rack

5

FC Instrumentation rack already installed.

SS Instrumentation rack will be installed after tests at DL

Cooling Channel Controls rack will be installed after

tests at DL

FC & SS Power Converter Rack

6

SS Power Supply racks will be installed after tests at DL

FC Power Supply rack already installed.

FC & SS Power Converter Rack

7

FC Power Supply rack already installed.

• The Cooling channel controls rack will be installed early Nov.

• Inter-connecting controls cables can then be installed / terminated

• This rack has already been fully tested at DL.

• Instrumentation cables need to be installed between RR2 and FC magnet.

FC Power Converter Rack

8

FC instrumentation rack already installed.

• The Cooling channel controls rack will be installed early Nov.

• Inter-connecting controls cables can then be installed / terminated

• This rack has already been fully tested at DL.

• Instrumentation cables need to be installed between RR2 and FC magnet.

SS Power Supply Racks

9

• Thermal testing to be completed at DL this week• Installed in RR2 by end of October• AC supplies and water cooling required in RR2• Cable interconnections – need to be installed and terminated

SS Energy Absorber Rack

• Water connections changed from imperial to metric

• Insulation enhanced – maintaining thermal conductivity and electrical isolation

• Each diode module tested thermally to ensure optimum torque applied

• Water cooling arrangements agreed and installation initiated in RR2

• The water cooling will be maintained for a minimum of 1 hour during a loss of supply

• This will ensure the energy stored in the super conducting magnets is safety discharged.

10

DC magnet and Control Cables for SS & FC

• DC link boxes designed and delivered to RAL.• Currently installing DC link boxes / cable

management on upper South mezzanine.• There are 14 x 240mm2 and 4 x 70mm2

cables from RR2 to link boxes to install.• DC cable installation will require 4 staff due

to length and weight. Possibly completed before January.

• Controls cabling needs to be installed from RR2 to magnets - approx. 40 multicore cables with connectors.

• Estimated to be completion including terminations by end of February.

• Final dressing of cable / cable management installation after PRY installed is approx. 3 weeks.

11DC Link Box

Cable management for DC cables and link boxes for SS & FC

12

Auxiliary (Diffuser and Tracker) Control Rack

13

• Preparation under way for testing in November.• Final installation is in RR2 and will require installing / terminating

cables to Hall.• Assemble second tracker control crate.

Tracker Install For November

Tracker 1Rack to be Re-Used, expanded to cover two Cryostats 1 & 2

Tracker 2 Rack Installed in Hall, but will use Tracker control crate destined for RRM2.

All control will be via VME interface in temporary rack as for single Cryostat tests.

All Cryostat interlocks will be cabled locally in the Mice Hall & available for tests, as envisaged for final install.

After Hall tests on all four Cryostats, control crates will be relocated to RRM2.

It will include Vacuum control for Turbo & Roughing pump.

Working closely with Craig for planned tests.

14

Compressor and Vacuum Rack

15

• Vacuum / compressor rack positioned as shown.

• Sumitomo compressors relocated and some cable management installed.

• Cryomech compressors powered and control cables installed, but need terminating.

Compressor and Vacuum Rack

• Vacuum Specification has been finalised.

• Rack design should be completed within next 4 weeks.

• Rack hardware has already been assembled.

• Rack wiring will take a further 4 weeks.• Electrical commissioning expected in

January.• Delivered to RAL by the end of January.• Install vacuum cables and terminate in

Hall – some work completed prior to rack delivery?

• Commission Vacuum and compressor systems.

16

EMR Rack

17EMR Rack

Personnel Safety / ODD system

Two new light curtains installed to cover West Mezzanine link and bride from end of South Mezzanine.

Move of Search point and BOB button.

ODD (Oxygen Depletion Detection) system will be installed and trench system linked in.

18

Summary

• Control & Magnet PSU’s racks are progressing well, currently under test at DL.

• Cable management is well underway in the Mice Hall.

• Compressor power requirements are covered, controls to complete.

• Tracker testing in the hall is currently being finalised, with local/remote monitoring.

• Main cable install will commence when Magnet termination boxes are sited.

• Instrumentation cabling will follow, any last minute requirements please.

• Should be on program target, but a lot to do!!• Questions!!

19