electrical system comm procedure

60
x COMMISSIONING PROCEDURE ELECTRICAL SYSTEM

Upload: vaithy1990

Post on 15-Sep-2015

29 views

Category:

Documents


6 download

DESCRIPTION

COMMISSIONING

TRANSCRIPT

  • x

    COMMISSIONING PROCEDURE

    ELECTRICAL SYSTEM

  • REVISION HISTORY

    REVISION DESCRIPTION OF REVISION

    A1 Issued for IDC

    HOLD LIST

    HOLD NO. SECTION NO. DESCRIPTION

    1 5.0 Pre-Comm. & Comm. procedure for 220kV Switchyard

    2 5.0 Pre-Comm. & Comm. procedure for 4MVA (EL-199030197-N05-0001) & 350 kVA (EL-199030197-N05-0002) DG Sets

  • TABLE OF CONTENTS

    1.0 INTRODUCTION ................................................................... 5

    1.1 General ............................................................................. 5

    1.2 Overview - Electrical System ................................................... 5

    1.3 Abbreviation ....................................................................... 6

    1.4 Terminology ....................................................................... 8

    2.0 ELECTRICAL SYSTEM DESCRIPTION ........................................... 9

    2.1 System Voltage and Frequency ................................................. 9

    2.2 Power Distribution ............................................................... 12

    2.3 Switchgears ....................................................................... 13

    2.4 Gas Turbine Generator (GTG) .................................................. 14

    2.5 Transformers ..................................................................... 14

    2.6 Motors ............................................................................. 15

    2.7 UPSs ............................................................................... 16

    2.8 Essential Diesel Generators (EDG) ............................................. 16

    2.9 Lighting ........................................................................... 16

    2.10 Electrical Heat Tracing / Heaters ............................................. 17

    2.11 Power Factor Improvement .................................................... 17

    2.12 IPCS/ENMS/SCADA ............................................................... 17

    2.13 Cathodic Protection ............................................................. 17

    3.0 GENERAL SCOPE OF COMMISSIONING PROCEDURE ........................ 19

    4.0 GENERAL HEALTH, SAFETY AND ENVIRONMENT CONSIDERATIONS .... 20

    4.1 General ............................................................................ 20

    4.2 Compliance ....................................................................... 20

    4.3 Health Hazards ................................................................... 20

    4.4 Environment ...................................................................... 21

    4.5 Pre-start Safety Checks ......................................................... 21

    5.0 COMMISSIONING PROCEDURE ................................................. 22

    5.1 Test Preparation/Prerequisite ................................................. 23

    5.2 Tools and Test Equipment Required .......................................... 23

    5.3 Control and Auxiliary Power Supplies ......................................... 24

    5.4 Vendor Commissioning Assistance ............................................. 24

    5.5 Energisation of UPSs ............................................................. 25

    5.6 Energisation of Distribution Boards ........................................... 26

    5.7 Power Cables ..................................................................... 27

    5.8 Emergency Diesel Generators .................................................. 28

    5.9 Commissioning of 220kV Switchyard .......................................... 32

    5.9.1 Switchyard Configuration ....................................................... 32

    5.9.2 Pre-energisation Checks ........................................................ 34

    5.9.3 Order of Energisation ........................................................... 35

    5.9.4 Energization of Switchyard ..................................................... 36

  • 5.9.5 Synchronizing Grid Mains and GTG ............................................ 38

    5.9.6 Energization of outgoing feeders .............................................. 39

    5.10 Transformers and Switchgears ................................................. 40

    5.10.1 Pre-Energisation Checks ........................................................ 40

    5.10.2 Energisation of Transformers .................................................. 42

    5.10.3 Energisation Switchgears ....................................................... 44

    5.10.4 Functionality and Interlocks ................................................... 49

    5.10.5 Switchgear Configurations ...................................................... 50

    5.11 35kV & 10kV Overhead Lines ................................................... 52

    5.12 Motors ............................................................................. 53

    5.13 VSD/Soft Starters ................................................................ 53

    5.14 PF Improvement Capacitors .................................................... 54

    5.15 Gas Turbine Generator .......................................................... 54

    5.16 Cathodic Protection ............................................................. 56

    6.0 POST TEST STATUS ............................................................. 58

    7.0 COMMISSIONING SUPPORT DOCUMENTS ..................................... 59

    8.0 REFERENCE DOCUMENTS ...................................................... 60

  • 1.0 INTRODUCTION

    1.1 General

    This document provides basic information, guidance and support documents to

    carryout commissioning activities for the Electrical System at SYG in a

    planned, safe and controlled manner.

    This document shall be used in conjunction with the TMG specifications for

    commissioning and the manufacturers or vendors documents and drawings.

    In the mechanical completion/pre-commissioning phase, the Equipment,

    Systems and Units are tested and prepared so that the system, etc., are in a

    condition where they are ready for commissioning (RFC).

    During Commissioning, the Electrical Equipment, Systems and Units are

    energised and prepared to support the commissioning of other

    systems/Companys Start-up schedule.

    Commissioning includes activities that enable systematic and safe introduction

    of power supply into the electrical system and verification of performance

    parameters with the intended design, such as checks on Voltage, Phase

    sequence, Man Machine Interfaces, Automatic Changeover scheme and

    IPCS/ENMS/ICSS interfaces.

    1.2 Overview - Electrical System

    The Electrical system at SYG consists of Main intake power through two 220kV

    OHL from Turkmen Energo National Grid. The outdoor 220kV, 3 phase, 3 wire

    switchyard has 13 bays including above two OHL incomer bays from Mary SPS,

    four outgoing OHL feeders of two each for CPF-2(CNPC) & future

    development, four outgoing transformer feeders- two each for CPF-1 &

    CPF-1A(Hyundai), one GTG Incomer, one Bus coupler and one Bus Transfer

    breaker.

    The estimated total electrical power requirement for CPF-1 is 85MW and

    CPF-1A is 40MW. The 220kV power from Mary SPS is stepped down distributed

    within the facilities at 35kV, 10kV and 400V voltage levels. The electrical

    system at the facility includes transformers, GTG, motors, switchgears, UPSs,

    EDGs, electrical heaters, heat tracing, cathodic protection, PF improvement

    capacitors, lighting & power distribution.

  • During normal time, GTG is in standby mode keeping auxiliaries running.

    During Mains failure or at the requirement of authorities, GTG will be made to

    run. EDGs installed will come in line automatically during Mains failure and

    serve all the emergency power requirement. Separate EDGs are installed for

    CPF-1 as well as GTUs.

    For centralised monitoring and control of electrical systems, IPCS and ENMS

    are installed.

    This document provides the commissioning procedure for the Electrical system

    without compromising the safety and reliability.

    1.3 Abbreviation

    Abbreviation Description

    AC Alternating current

    AIS Air Insulated Switchgear

    APFC Automatic Power Factor Controller

    AVR Automatic Voltage Regulator

    ACSR Aluminium Conductor Steel Reinforced

    B/C Bus Coupler

    BVS Block Valve Station

    CB Circuit Breaker

    CBCT Core Balance Current Transformer

    CCR Central Control Room

    CP Cathodic Protection

    CPF Central Processing Facility

    CPU Central Processing Unit

    CT Current Transformer

    DC Direct Current

    EDG Emergency Diesel Generator

    E/F Earth Fault

    EMC Electromagnetic Compatibility

    ENMS Electrical Network Monitoring system

    ESD Emergency Shutdown System

    FEED Front End Engineering Design

    F&G Fire and Gas System

    GCP Generator Control Panel

    GIS Gas Insulated Switchgear

    GTG Gas Turbine Generator

    HMI Human Machine Interface

  • Abbreviation Description

    HSE Health Safety and Environment

    HV High Voltage

    HVAC Heating Ventilating & Air Conditioning

    ICCP Impressed Current Cathodic Protection

    I DMT Inverse Definite Minimum Time

    I EC International Electrotechnical Commission

    IP Ingress Protection

    ICSS Instrumentation Control & Safety System

    I/C Incomer

    I/O Input/Output

    IPCS Integrated Protection and Control System

    IPCD Integrated Protection and Control Device

    ITR Inspection and Test Report

    JSA/JHA Job Safety Analysis/Job Hazard Analysis

    LER Local Equipment Room

    LV Low Voltage

    MCB Miniature Circuit Breaker

    MCCB Moulded Case Circuit Breaker

    MCC Motor Control Centre

    MCS Motor Control Station

    MPR Motor Protection Relay

    MVA Mega Volt Ampere

    OHL Over Head Line

    O/L Over Load

    O/C Over Current

    OCTC Off Circuit Tap Changer

    OLTC On Load Tap Changer

    PCP Permanent Cathodic Protection

    PE Protective Earth

    Pf Power Factor

    PRC Power Factor Improvement Capacitor

    PLC Programmable Logic Controller

    RCD Residual Current Device

    REF Restricted Earth fault

    RMU Ring Main Unit

    RMS Root Mean Square

    RTCC Remote Tap Changer Cubicle

    RTD Resistance Temperature Device

    SACP Sacrificial Anode Cathodic Protection

  • Abbreviation Description

    SF6 Sulphur Hexafluoride

    TCP Temporary Cathodic Protection

    TEFC Totally Enclosed Fan Cooled

    UPS Uninterrupted Power Supply

    VCB Vacuum Circuit breaker

    VDU Visual Display Unit

    VSD Variable Speed Drive

    VT Voltage Transformer

    XLPE Cross Linked Polyethylene

    VCU Vacuum Contactor Unit

    1.4 Terminology

    Term Definition

    Procedure Specified directions or commands on how to undertake a particular task or series of tasks. A procedure generally comprises of a series of instructions presented within a specified sequence.

    Instructions A description of an action to be undertaken generally forms part of a procedure.

  • 2.0 ELECTRICAL SYSTEM DESCRIPTION

    2.1 System Voltage and Frequency

    Transmission and Primary Distribution System

    220kV, 3ph, 3 wire, system neutral solidly earthed

    HV distribution system: Central Processing Facilities (CPF-1)

    35kV and 10kV, 3ph, 3 wire. 35kV earthed through Zigzag earthing transformer and 10kV neutral resistance earthed

    Incoming supply to Gas Treatment Units (GTUs)

    35kV, 3 ph, 3 wire

    HV distribution system: GTUs 10kV, 3 ph, 3 wire, system neutral solid earthed

    LV Distribution system for Gas Treatment Units (GTUs) and Wellheads.

    400V, 3 ph, 4 wire, system neutral solidly earthed

    Emergency Generation System (CPF-1)

    10kV, 3 ph, 3 wire, system neutral resistance earthed

    Emergency Generation System (GTU)

    400 V, 3 ph, 4 wire, system neutral solidly earthed

    Motors > 6000kW

    10kV, 3 ph, 3 wire, system neutral resistance earthed (motors are supplied from 35 kV system using unit transformers with Dyn11 vector group)

    Motors >150kW and < 6000kW 10kV, 3 ph, 3 wire, system neutral resistance earthed. Soft starter for above 1000 kW motors shall be used.

    Motors > 0.18kW and < 150kW (All Motors)

    400V, 3 ph, 3 wire, system neutral solidly earthed. Soft starter for above 100 kW motors shall be used.

    Motors < 0.18kW 230V, 1 ph, system neutral solidly earthed

    Motor operated valves 400V, 3 ph, 3 wire, system neutral solidly earthed

    Lighting, convenience socket outlets, electrical trace heating, single phase power tools, single phase consumers etc.

    400V, 3 ph, 4 wire/230V, 1 ph 2 wire + RE (TN-S system), system neutral solidly earthed

    Welding socket outlets: 400V, 3 ph, 4 wire, system neutral solidly earthed

    Escape lighting: 230V, 1 ph, (vital supply from UPS), system neutral solidly earthed

    Power tools 230V, 1 ph, system neutral solidly earthed

    Anti-condensation heaters 230V, 1 ph, system neutral solidly earthed

    Heaters up to 3kW 230V, 1 ph, system neutral solidly

  • earthed

    Heaters up to 250kW 400V, 3 ph, 4 wire, system neutral solidly earthed

    Non vital instruments 230V, 1 ph, 2 core + RE, system neutral solidly earthed

    Electrical ENMS and IPCS System 230V AC UPS

    ICSS, ESD, F&G and other vital instruments:

    230V, 1 ph, 2 core + PE, (vital supply from UPS), system neutral solidly earthed

    Communication system for CPF-1, GTU & Wellheads

    230V, 1 ph, (vital supply from UPS), system neutral solidly earthed

    Communication system for pipelines:

    230V, 1 ph, (vital supply from UPS), system neutral solidly earthed

    Control/protection of 220, 35 & 10kV Switchgear HV switchboards (circuit breakers) and power transformers.

    110V DC, unearthed (from UPS)

    Circuit breaker spring charging motors for HV switchgear

    110V DC, unearthed (from UPS)

    Electrical control of HV motor starters (contactor feeders)

    110V DC, unearthed (from UPS)

    Electrical control of 400V motor starters

    230V, 1 ph, solidly earthed

  • Fig. 1 - Key SLD with EDGs (Reference: SYG-PSH-04-EL-SLD-0001)

    400A 400A 400A 400A 400A 400A 400A 630A

    Bus A Earth

    Switch

    N/C

    2000A

    Bus E Earth

    Switch

    HV PF Improvement

    Cap. Bank (1600 KVAR)

    56" E

    xpor

    t

    Gas

    Pipeline

    OHLSpare

    For T

    MG

    (100

    0 kV

    A) M~M~

    Mot

    or F

    eede

    r

    up to

    1.6

    MW

    (Typ

    )

    Mot

    or F

    eede

    r

    abov

    e 1.

    6 M

    W

    (Typ

    )

    400A

    M~

    Mot

    or F

    eede

    r

    up to

    1.6

    MW

    (Typ

    )

    400A400A400A400A

    X1

    400A

    Spare

    For T

    MG

    (100

    0 kV

    A)

    400A

    HV PF Improvement

    Cap. Bank (1600 KVAR)

    M~

    M~

    400A 400A 630A 400A 400A

    Mot

    or F

    eede

    r

    abov

    e 1.

    6MW

    (Typ

    .)

    Mot

    or F

    eede

    r up

    to 1

    .6M

    W (T

    yp.)

    Bus B Earth

    Switch400A400A400A400A400A400A

    Spare

    ATS

    For T

    rans

    form

    er

    Spar

    e

    For O

    HL

    Spar

    e

    220 kV Two Single Circuit

    Overhead Line (OHL) to

    CNPC (CPF-2)

    220 kV Two Single Circuit

    Overhead Line (OHL) from

    Turkmenenergo 220 kV MARY

    SPS Switchyard for CPF-1

    220 kV Two Single Circuit

    Overhead Line (OHL) for Power

    Supply DevelopmentG GTG-1

    400A

    12.5/16 MVA

    35/10.5 kV

    Bus BBus E

    Bus A

    Motor

    Feeder for

    GTG starting

    Motor Unit

    Transformer

    12.5/16 MVA

    35/10.5 kV

    GG

    EDG

    3.32 MW

    10 kV

    EDG

    3.32 MW

    10 kV

    10 kV Switchgear

    91-SS01-ES01

    Loc: CPF-1 Main SS (04-SS01)

    2SB101

    Loc: SS-503

    Inst. & SS Building-1 CPF-1A

    35 kV GIS CB. 91-SS01-EP03

    Loc: CPF-1 Main SS (04-SS01)

    35 kV GIS CB. 91-SS01-EP02

    Loc: CPF-1 Main SS (04-SS01)

    Loc: 220 kV Switchyard Control Room

    220 kV Air Insulated

    Outdoor Switchyard

    Loc: CPF-1, Switchyard

    35 kV GIS 91-SS01-EP01

    Loc: CPF-1 (Main SS) 04-SS01

    15 kV

    128.8 MW 0.8 PF

    Transfer Bus

    15/0.42 kV

    Dyn11.

    1.2 MVA

    10/0.42 kV

    Dyn11.

    1.2 MVA

    Main Bus II

    Main Bus I

    Generator

    Transformer

    230 kV/181 MVA

    400V Aux. Switchboard

    For 220 kV Switchyard

    BAY 1 BAY 2 BAY 11 BAY 12 BAY 3 BAY 4 BAY 8 BAY 7 BAY 5 BAY 6 BAY 3 BAY 9 BAY 10

    To GTG

    Aux. MCC

    1.2 MVA

    Transformer

    220/36.6 kV

    100/125 MVA

    Transformer

    Bus Transfer

    Bus Coupler

  • 2.2 Power Distribution

    Electrical power is supplied to the Turkmen Gas field from Mary SPS 220kV

    grid by 2 single circuit overhead lines of 65km length. The outdoor 220kV, 3

    phase, 3 wire switchyard has 13 bays including 2 Nos OHL incomer bays from

    Mary SPS, 4 Nos outgoing OHL feeders of 2 each for CPF-2(CNPC) & future

    development, 4 Nos outgoing transformer feeder for CPF-1 & CPF-

    1A(Hyundai), 1 No GTG Incomer, 1 No Bus coupler and 1 No Bus Transfer

    breaker

    220kV OHL outgoing feeder conductors are terminated on the primary side of

    the 100/125MVA 220/36.5 kV Transformers 91-SY01-ET01A/B (CPF-1) & 91-

    SY01-ET02A/B (CPF-1A). Secondary side 35kV cables of the transformers of

    CPF-1 are terminated at 35kV GIS Switchgear 91-SS01-EP01 and 35kV cables of

    the transformers of CPF-1A are terminated at 35kV GIS Switchgear 91-SS01-

    EP02 & EP03. Further distribution from 91-SS01-EP02 & EP03 are taken care by

    Hyundai.

    The Electrical energy required for the operation of the facility is met from the

    Grid power during normal course of time. When grid fails or as and when

    required by the authorities, the energy is supplemented by the Gas Turbine

    Generator (GTG).

    During Mains failure, the Emergency Diesel Generators (EDG) kept in standby

    mode will automatically come in line and feed all the emergency services as

    well as auxiliary power to GTG. As and when Grid/GTG power is available, the

    power will be restored and EDGs will be kept in standby mode

    The power is stepped down distributed within the facilities at 35kV,10KV and

    400 Volts voltage levels. The electrical system at the facility includes

    transformers, GTG, motors, switchgears, UPSs, EDGs, electrical heaters, heat

    tracing, cathodic protection, PF improvement capacitors, lighting & power

    distribution.

    In the facility soft starters are provided for large motors (400V motors above

    100kW and 10kV motors above 1000kW) to avoid voltage dips in the system

    and to avoid heating of motors during starting.

    GTUs 5,6,7 & 8 located farther from the CPF-1 are powered through 35kV OHL

    from the CPF-1 Main SS, 04-SS01. 35kV is stepped down to 10kV at GTU and

    feeds power to connected well heads as well as GTU. Well heads are

  • connected through 10kV OHLs and at GTU 10kV is further stepped down to

    400V and distributed. A 350kVA 400V EDG installed at each GTU meets the

    emergency power requirement of respective GTU

    56 Export pipe line power requirements are met through 10kV OHLs powered

    from Main SS, 04-SS01, 91-SS01-ES01 10kV switchgear

    At Well heads and export pipe lines, 10kV is stepped down and distributed at

    400V and do not have any EDGs

    For centralised monitoring and control of electrical systems, IPCS and ENMS

    are installed. IPCDs mounted on the electrical feeders are interfaced with

    IPCS/ENMS. The interface between IPCS/ICSS provide control and operation of

    process feeders from CCR

    2.3 Switchgears

    Switchgears ranging from 220kV, 35kV, 10kV, and 0.40kV are installed in the

    facilities. Except 220kV, all the switchgears are indoor and metal enclosed.

    220kV switchgears are outdoor type AIS with SF6 circuit breakers. 35kV

    Switchgears at CPF-1 are Gas Insulated (GIS) and at GTUs are Air Insulated

    (AIS). 10kV switchgears are AIS type.

    35 and 10kV circuit breakers are draw out type. Earthing switches are

    provided in incoming and outgoing circuits. Suitable mechanical Castell

    Interlock keys are provided to ensure that the circuits are isolated before

    closing earthing switches and to ensure opening of earthing switches before

    energising the circuits.

    400V Switchgears are metal clad, fully withdrawable and double front (single

    front panels with back to back arrangement) panels. Incomers are either ACBs

    or MCCBs based on the rating and outgoing isolation is provided by MCCBs.

    HV/LV Incomers, Bus sections and Outgoings are fitted with Intelligent

    Protection Control Devices (IPCDs). IPCDs are programmable and have

    communication facilities with IPCS/ENMS/ICSS for remote control and

    operation. Interface between IPCS/ICSS enable the control of process feeders

    from CCR. . Interface between IPCS/ENMS enable the control of switchgear

    incomers/bus-sections from SS01.

  • 2.4 Gas Turbine Generator (GTG)

    The Gas Turbine Generator installed in the facility is for standby purpose and

    is designed to the meet full load requirement of both CPF-1 & CPF-1A. The

    15kV, 116MW, 0.8PF GTG is connected to the 220kV switchyard through a unit

    step up generator transformer of 220/15kV, 115/165MVA. GTG control system

    is designed operate the GTG either in parallel with the Grid or in islanded

    mode. When running in parallel, the control system will allow set point

    control of GTG output power.

    GTG is a self contained complete package generating set and equipped with

    necessary protection, control and monitoring. GTG can be operated either

    from CCR remote GTG HMI (Remote- OWS) or from the local TCC HMI (Local

    UCP). Also local control permits operations such as commissioning, trouble

    shooting and maintenance. Operating Set points of the GTG can be

    programmed from the GTG HMI

    The 220kV switch yard has two main bus and one transfer bus. During normal

    operation GTG & the feeders of CPF 1/1A are connected one main bus II. The

    other bus (main bus I) is connected with the Grid incomers and third party

    feeders. The 220kV bus-tie breaker will be normally closed.

    2.5 Transformers

    Transformers with ratings are used in the facilities. Primary side of all the

    Transformers are connected through cables and secondary through cable/bus

    duct based on the ratings. Transformers are provided with Inter-Trip and

    necessary protection schemes. Operation and control part is discussed in the

    subsequent section.

    Except Main intake transformers at 220kV yard and GTU transformers, all the

    other transformers are fitted with Off Circuit Tap Changing (OCTC) facility.

    220/35kV Main intake transformers and 35/10.5kV step down transformer at

    GTUs have On Load Tap Changing (OLTC) facility. The Remote Tap Changer

    Control Panel (RTCC) for each transformer located in the SS operates the

    motorised tap changing mechanism fitted on the transformers. Voltage

    regulator equipped in the RTCC compares the transformer secondary voltage

    with the set value and sends the signal, if the voltage is different from set

    value, to the tap operating mechanism to increase or decrease the taps to

    maintain the desired secondary voltage. RTCC has got

    Master/Follower/Independent selection modes to operate in line with the

  • other transformer. This is also fixed with Local/Remote selection and Local

    mode allows the operation taps in the transformer bay. Tap changing

    mechanism can also be operated manually by the Handle exclusively provided

    for this. Mechanical as well as Electronic tap position indicators along with

    Voltage display in local and remote indication facilities are provided.

    Main intake Transformers being Star/Delta connected, as the neutral is not

    available for earthing, the earthing is derived through Zig-Zag transformer.

    The star point of the Zig-Zag transformer in turn is earthed through Resistor.

    All the other transformers have star connected secondary windings and their

    neutrals are earthed either through resistors or solidly grounded.

    2.6 Motors

    10kV & 400V, 3phase and 230V single phase motors are used in the facility and

    are of squirrel cage induction motors. Motors less than are equal to 0.18 kW

    are supplied from 230V power supply. Motors above 0.18kW and less than or

    equal to 150kW are 400V, 3 phase motors. Motors above 150kW are 10kV

    motors. 400V motors above 100kW and 10kV motors above 1000kW are

    provided with soft starters and the others are DOL type. 10kV motors with soft

    starters and above 1600kW are VCB controlled or otherwise controlled with

    Fuse & vacuum contactors. VSDs are provided for specific motors

    LV motors are controlled and protected through MCCB/soft starters/VSDs.

    MCCBs provide protection against S/C & O/L. Additional protections include

    Thermal Image O/L, phase imbalance, Sensitive earth fault for motors above

    30kw and locked rotor protection for EEx-e motors

    HV motors are provided with MPR with CBCT and motors above 1600kW are

    provided with differential protection.

    Motors can be controlled locally through MCS, located adjacent to the motor.

    Remote control of motor from ICSS is possible only when Auto mode is

    selected in MCS. MCS selector switch is having OFF-AUTO-ON selection and

    OFF position is lockable. Selector switch is having spring facility to return to

    Auto mode from ON position when operator removes his hand.

    IPCDs on the motor starter enables the motor to monitor/control from ICSS

    through IPCS. ESD trip signals hardwired from the ICSS/ESD.

  • 2.7 UPSs

    110V DC UPS system is connected to Electrical Switchgear controls. DC UPS

    consists of one set of battery, two sets of chargers and one set of integral DC

    DB. One charger is supplied from normal power and other charger is input is

    fed from emergency supply.

    240V AC UPS System is connected to IPCS, ENMS, ICSS, ESD, F&G and Telecom

    System. AC UPS systems consist of 2 set of single UPS with bypass supply and

    battery. Normally the bypass input is fed from normal supply and the inverter

    input is fed from Emergency Switchgears which in turn are fed from EDGs.

    400V UPS is with 3 Phase output and is used for Emergency and Escape

    Lighting in the CPF-1.This consists of single UPS with bypass supply and

    battery

    48V DC UPS system is exclusively used in the 220kV yard for PLC and RTU

    applications

    Batteries of all the UPS are located in a separate ventilated room with MCCB

    isolation. All the UPS have integral DB at their output. UPSs having dual input

    are fed normal and emergency switchgears. Emergency switchgears in turn are

    fed by EDGs during Mains failure.

    2.8 Essential Diesel Generators (EDG)

    The Essential Power requirement at CPF-1 is met by 2 Nos. 3.32MW, 10kV, 50%

    rated EDGs. Apart from essential process loads, Instrument Air Compressors,

    GTG starting motor, GTG auxiliary supply, fire water jockey pumps,

    emergency and escape lightings, UPSs and essential HVAC units are other

    essential loads connected with the EDG switchboards.

    All GTUs and Rotational camp have their exclusive 400V, 350kVA EDGs

    connected to their respective switchgears.

    EDGs on Auto mode will start against Mains failure have Auto/Manual

    provisions for Changeover, Synchronising, Mains restoration along with Test

    Trial Run facilities.

    2.9 Lighting

    Apart from general plant and indoor lighting, essential and emergency/escape

    lightings are provided. Essential lightings are fed from EDGs.

    Emergency/escape lights are fed from lighting UPS or in-built battery backup.

  • 2.10 Electrical Heat Tracing / Heaters

    Heat tracing avoids condensation of process gas in the pipelines and

    Instrumentation and maintains the temperature as specified in the design.

    Heating is carried out with Self regulating heat tracing cables with line sensing

    thermostats. Heaters operate at 230V AC supply and distributed through

    respective Distribution Boards. Part of the heat tracing circuits are fed

    through Emergency DBs based on the requirement

    Electrical heaters installed in the facility are either controlled through

    contactors or thyristor. Heaters have hardwired control from ICSS and

    additionally thyristor heaters have 4-20mA set point control

    2.11 Power Factor Improvement

    As system power factor need to be maintained at 0.98 lagging, PF

    improvement capacitors are installed in the facility. Both 10kV & 400V

    capacitors are installed in the facilities. 10kV Capacitors are outdoor type and

    IP54. Ratings above 500kVAR will have two step control through APFC

    controller.

    LV capacitors have multiple step controls and are indoor type and IP41. Once

    again step control is achieved through APFC controllers.

    2.12 IPCS/ENMS/SCADA

    For centralised monitoring and control of electrical systems, IPCS and ENMS

    are installed. IPCDs mounted on the electrical feeders are interfaced with

    IPCS/ENMS. The interface between IPCS/ICSS provide control and operation of

    process feeders from CCR

    35 kV, 10kV and 400V Switchgear incomers and bus tie can be controlled

    either locally in front of the panel or remotely through ENMS OWS. For ENMS

    operation, the remote mode shall be selected on the switchgear

    TurkmenEnergo will control the 220kV switchyard CBs through SCADA. GTG

    incomer and bus tie CBs will be controlled from GTG UCP

    2.13 Cathodic Protection

    To prevent corrosion of the buried pipelines, tanks, vessels and structures,

    Cathodic protection is installed throughout the plant depending on the

    requirement.

  • CP system is designed and installed considering site condition, soil resistivity,

    service (water, hydro carbon etc.), MOC, Interaction and Induced effects from

    foreign service crossings, parallelisms and buried/overhead transmission

    electrical power lines.

    The two main types of CP are Impressed Current and Sacrificial Anode.

    Impressed Current CP requires continuous power from the mains which in

    turn, stepped down through transformers and converted into DC through

    rectifiers and connected. Sacrificial anode requires no power.

    Infield & export pipe lines and tank external surfaces are protected by

    Impressed Current Cathodic protection. Mix of both Impressed and Sacrificial

    anode CP are used in in-plant buried pipe lines, hydrants and tank internals

    Temporary CP using sacrificial anode system is installed while laying the

    pipelines and will be disconnected while commissioning the Permanent CP

    system using Impressed Current.

  • 3.0 GENERAL SCOPE OF COMMISSIONING PROCEDURE

    The section provides basic information, guidance and support documents to

    carryout commissioning activities of the electrical system including HV/LV

    switchgears, transformers, cables, motors, VSDs, UPS, distribution boards and

    lighting system.

    During the pre-commissioning , all the equipment are tested and prepared to

    keep in a condition ready for commissioning.

    During Commissioning, the Equipment, Systems and Units are prepared for

    Ready for Startup (RFSU) and this will be in a sequence that supports the

    facilitys Startup schedule.

    Commissioning includes activities that enable systematic and safe introduction

    of power supply into the electrical system and verification of performance

    parameters with the intended design, such as checks on Voltage, Phase

    sequence, Man Machine Interfaces, Automatic Changeover scheme, IPCS/ENMS

    and IPCS/ICSS interfaces.

  • 4.0 GENERAL HEALTH, SAFETY AND ENVIRONMENT CONSIDERATIONS

    4.1 General

    HSE assurance is provided by identifying and managing HSE risks, according to

    the principles of risk tolerance, risk reduction and continuous performance

    improvement. All employees are responsible for complying with the TMG

    Safety Guidelines. Safe work practices are discussed and followed prior to

    starting any activity

    4.2 Compliance

    All personnel familiarise themselves with the safety rules and guidelines

    provided in TMG HSE guidelines.

    4.3 Health Hazards

    Shock and Fire/Explosion Hazards

    Mitigate possibilities of the hazards by following correct procedure, systemic

    approach and by using correct PPE and additional PPE:

    Eye: Handling Electrolyte of the batteries may cause physical damage

    Skin Contact: Contact with Electrolyte may cause irritation and burns of

    exposed area.

    Contact with Hazardous Voltage: Contact with live electrical parts can cause

    mild shock to fatality, depending on path of the current flow through the body

    and other factors such as sweat, moisture, body resistance, level of voltage

    etc.

    First Aid

    Eye: Wash thoroughly with water immediately. Repeat as needed till the

    irritation subsides. If irritation persists, consult medical personnel.

    Skin Contact: Wash with clean water till the irritation or pain subsides.

    Contact with Electric Voltage: Isolate power supply, remove the victim from

    the equipment contact and perform first aid if needed, call for medical help

    Systemic and Other Effects: Mild shock, burns, shivering, de-hydration and

    fatality

    Personnel Protection

  • Eye Protection: Safety glasses with side shield should be worn and eye wash

    arrangements should be available.

    Skin Protection: Acid resistant gloves, Apron, Boots.

    Protection Equipment (for Electricity): Depending on the voltages, Gloves,

    Boots, insulation mats, voltage detectors, insulated tools, etc., are

    recommended to be worn and used.

    4.4 Environment

    The Electrical substations, GTG, EDGs, Switch yards and the surroundings shall

    be well protected, clean and dry.

    4.5 Pre-start Safety Checks

    Before starting any activity the minimum required safety checks are followed

    and approval from the supervisors/Engineers and relevant inter discipline

    engineers is obtained.

    Prior to any electrical activity, ensure the following safety items in place:

    1. Safety signboards

    2. Escape route markings

    3. Emergency exit lighting

    4. Electrical emergency safety equipment

  • 5.0 COMMISSIONING PROCEDURE

    Commissioning involves energisation of electrical equipment and system.

    Commissioning is to be taken up only after the completion pre-commissioning

    activities. The procedure outlined in the following sections describes activities

    involved during commissioning

    Commissioning includes test preparation, energisation and demonstration as

    explained below:

    A. Test Preparation

    The individual equipment or components such as switch gears, cables,

    transformers etc., of the electrical system considered for commissioning are

    already tested during pre-commissioning whereas the commissioning test

    preparation is the preparation of the electrical system as a whole with its

    interfaces, controls, interlocks, etc.

    The test preparation may include the following depending on the position of

    the system in the overall electrical system:

    1. Preparation of safety equipment

    2. Preparation of test equipment and tools

    3. Isolation and locking of outgoing feeders of the equipment

    4. Energisation of control circuits

    5. Energisation of the upstream side of the equipment

    B. Energisation and Demonstration

    After the system is made ready for its first energisation, the equipment will be

    energised following a detailed step-by-step procedure which is included in this

    procedure or the one that is provided by the manufacturer/vendor. The

    electrical equipment is energised for the first time and kept energised for a

    significant period so that any abnormality may be discovered and problems

    identified may be rectified.

    After the equipment is energised, the live testing of the system commences.

    The live test sequence is provided below:

    1. Check the voltage presence and value

    2. Check all controls on the equipment

    3. Check interfaces and indications

    4. Check the phase sequence of the supply voltages, where applicable

  • 5. Verification of the main equipment (example: Transformers) of the

    Electrical Distribution System for its mechanical aspects by monitoring and

    taking required readings during soaking period after energisation.

    a. Noise

    b. Equipment vibration

    c. Oil leaks, where applicable

    d. Temperature readings

    5.1 Test Preparation/Prerequisite

    The following are the prerequisites of the equipment and system:

    1. Ensure the availability of competent and authorised Commissioning

    Engineer for the activities

    2. Ensure that all the required documents such as marked-up drawings,

    PetroPCS-B check sheets, etc., are available.

    3. Ensure that the available documents are the latest "As built" mark-

    ups/Latest revision.

    4. Ensure that safety and fire fighting systems are ready for use.

    5. Barricade the area with barrier tape and place warning signs to prevent

    entry by unauthorised personnel.

    6. Ensure that the required Isolation Certificates, Limitation-of-Access and

    Sanction-for-Test are obtained specific to the equipment.

    7. Ensure availability of Approved switching program for Electrical Switching

    Activity

    8. Ensure that the Electrical Permit to Work is obtained,

    9. Ensure that the TRA is complete and available for the activities

    10. Conduct Tool Box Talk prior to the commencement of activities for the

    day.

    11. Ensure that the surroundings and the equipment are clean, tidy and are

    accessible without any obstruction.

    12. Ensure that the radio and alternate communication is available.

    13. Ensure that the earthing system testing is complete

    14. Ensure that the Control and auxiliary power supplies are available

    15. Ensure that the temporary power for auxiliary/control, essential lighting

    and HVAC are available

    5.2 Tools and Test Equipment Required

    1. Megger 500V, 1000V, 2500V, 5000V (AC/DC)

    2. Multimeter

  • 3. Clamp meter for AC/DC Current measurement

    4. Phase rotation meter

    5. Galvanometer

    6. Arc Flashing Jacket Kit (If applicable in PTW)

    7. Hot stick

    8. IR Temperature Gun

    9. Insulated hand tools, Rubber gloves

    10. 3 Phase, 400V AC Supply

    11. Lux meter

    12. Electrical discharge device

    5.3 Control and Auxiliary Power Supplies

    220kV, 35kV, 10kV, 400V switchgears control & protection

    110V DC

    Electrical control of HV motor starters- Contactor feeders

    110V DC

    Spring Charging motors of HV switchgear 110V DC

    400V motors feeder controls 230V AC

    Switchgear anti-condensation heating, cubicle lighting

    230V AC

    IPCS/ENMS 230V AC

    ICSS, ESD, F&G and other vital Instrumentation 230V AC

    Communication systems 230V AC

    Switchgear control supply 110V DC is supplied by 110V DC UPS system.

    230V/400V auxiliary supplies are derived from Substation Miscellaneous DBs.

    IPCS/ENMS/ICSS/F&G/ESD/Instrumentation and Telecom are powered from

    230V AC UPS.

    Along with the above, Lighting and HVAC DBs need to be initially energised

    with temporary power supply in the respective substations to enable

    commissioning of the electrical distribution systems.

    The above equipment will be switched over to normal power supply after the

    commissioning of the upstream side equipment is completed. With the normal

    power supply, the above equipment has to be fully commissioned and

    functionalities have to be demonstrated as per the relevant procedures.

    5.4 Vendor Commissioning Assistance

    Vendor commissioning assistance may be utilized for commissioning the

    following systems:

  • 220kV switchyard

    Switchgears and MCC

    Protective Relays

    Power Transformers

    UPS / Battery System

    Soft starters/VSDs

    Emergency Diesel Generator

    Gas Turbine Generator

    5.5 Energisation of UPSs

    UPSs and DBs provide control and auxiliary power supply to the Switchgear.

    These systems need to be commissioned prior to the main equipment of the

    substation. These systems are already commissioned using a temporary source

    of power supply in order to make the upstream side equipment available.

    When the normal power switchgear which are going to feed the UPSs/DBs are

    ready, re-commissioning of UPS shall be carried out as per the vendors

    procedure having completed the necessary checks.

    Note:

    Commissioning of the UPS system will be with the vendors support.

    Commissioning reports and checks shall be as per the vendor formats.

    UPSs with dual input power supply and bypass supply shall be tested for their

    operability while re-commissioning.

    Interface facilities with IPCS/ENMS/ICSS shall be verified.

    A. DC UPS

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed

    2. Carryout Megger test on the system before energising

    3. Ensure that all checks required as per vendor commissioning procedure are completed

    4. Switch on the feeders on Incoming power supplies to rectifiers and verify voltage and phase rotation

    5. Check indications/meter readings/alarm/abnormal noise/temperature

    6. Ensure operation of Unit Cooling Fans

    7. Energise the DC Distribution Board

  • B. AC UPS

    The following AC UPS is to be commissioned. Ensure that the pre-

    commissioning activities are completed before taking up commissioning.

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed

    2. Carryout Megger test on the system before energising

    3. Ensure that all checks required as per vendor commissioning procedure are completed

    4. Switch on the feeders on Incoming power supplies to rectifiers and verify voltage and phase rotation

    5. Check indications/meter readings/alarm/abnormal noise/temperature

    6. Ensure operation of Unit Cooling Fans

    7. Switch ON Inverter and check output Voltage & Frequency

    8. Check Inverter synchronism and by-pass modes

    9. Energise the AC Distribution Board

    5.6 Energisation of Distribution Boards

    Distribution boards are tested during the pre-commissioning phase itself and

    further following shall be ensured before energizing the DBs.

    A. Lighting (Normal & Essential) DBs

    The Lighting Distribution Boards are commissioned following the steps, after

    completing pre-commissioning activity of the system.

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed

    2. Carryout Megger test on the system before energising

    3. Ensure arrangement of lighting fixtures/sockets against approved drawing.

    4. Energize the Distribution Board.

    5. Verify all lighting fixtures are working/verify correct voltage and phase sequences in the sockets.

    6. Check and record lighting intensity level and lighting projection points.

    7. Simulate and check the operation of timers/photocell switches (as applicable).

    8. Allow Emergency and escape lighting (in built battery fixtures) for initial charge, disconnect the supply and verify the operation of lighting fixtures.

  • B. Miscellaneous Power & HVAC DBs

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed.

    2. Carryout Megger test on the system before energising.

    3. Energize Distribution Board.

    4. Ensure Indicating lamps are working

    5. Verify correct voltage and phase sequences.

    6. Ensure DB ON status at IPCS/ENMS/ICSS

    C. Heat Tracing & MOV DBs

    The Heat Tracing and MOV Distribution Boards are commissioned following the

    steps, after completing pre-commissioning activity of the system.

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed.

    2. Carryout Megger test on the system before energising.

    3. Energize Distribution Board.

    4. Ensure Indicating lamps are working

    5. Verify correct voltage and phase sequences.

    6. Ensure DB ON status at IPCS /ENMS/ICSS

    7. Ensure Atmospheric thermostat is connected and set for Automatic operation of Heat Tracing

    8. Ensure Auto/Manual/Off selector function is working properly for Heat Tracing

    9. Ensure ON status at IPCS for each MOV outgoing feeder

    10. Ensure Space heater is working

    11. Ensure Indicating lamps & measuring circuits are in order

    5.7 Power Cables

    All the HV/LV/Control Cables are tested during pre-commissioning phase itself

    and further they may be ensured for the following:

    Step Actions Sign/Date

    1. Ensure that all the cables are tested and relevant ITRs are available

    2. Ensure that the tests specific to 220kV cables are carried out before energising

    3. Ensure all the 35kV, 10kV HV Power cables are tested

  • Step Actions Sign/Date

    4. Ensure that the control cables are checked

    Note:

    Commissioning of the 220 kV Cables will be with the vendors support.

    5.8 Emergency Diesel Generators

    Following are the Emergency Diesel Generators (EDGs) installed in the facility

    Location Rating EDG Tag Number

    Downstream Switchgear Tag

    Number

    CPF-1 10kV, 4.15MVA, 50Hz 99-SS01-EG01 91-SS01-ES01, Bus E

    CPF-1 10kV, 4.15MVA, 50Hz 99-SS01-EG02 91-SS01-ES01, Bus E

    GTU-5 400V, 350kVA, 50Hz 99-SS51-EG01 91-SS51-EL01, Bus C

    GTU-6 400V, 350kVA, 50Hz 99-SS61-EG01 91-SS61-EL01, Bus C

    GTU-7 400V, 350kVA, 50Hz 99-SS71-EG01 91-SS71-EL01, Bus C

    GTU-8 400V, 350kVA, 50Hz 99-SS81-EG01 91-SS81-EL01, Bus C

    Note:

    Commissioning of EDG will be with the vendors support. Commissioning

    reports and checks shall be as per the vendor formats.

  • Fig. 2 - Key SLD with EDGs at CPF-1 (Reference: Key SLD SYG-PSH-04-EL-SLD-0101 CPF-1 Main S/S)

    Motor Feeder

    M~

    M~

    M~

    Power

    Feeder

    Power Factor

    Improvement

    Capacitor Bank

    Motor Feeder

    Power

    Feeder

    Motor Feeder

    Power

    Feeder

    Power Factor

    Improvement

    Capacitor Bank

    NC

    BUS A10kV

    91-SS01-ES01

    91-SS01-ET01A

    35/10.5 kV

    12.5/16 MVA

    NO NC

    BUS B BUS C

    ATS+AMF

    G~

    G~

    ATSATS

    NC

    91-SS01-ET01B

    35/10.5 kV

    12.5/16 MVA99-SS01-EG01

    10 kV, 4150 kVA

    99-SS01-EG02

    10 kV, 4150 kVA

    Power

    Feeder

    Power

    Feeder

    NO NO

  • Fig. 3 - Key SLD with EDG at GTUs Typical (Reference: Key SLD SYG-PSH-04-EL-SLD-0534 GTU-5)

    Motor Feeder

    M~

    M~

    M~

    M~

    M~

    Power

    Feeder

    LV Power

    Factor

    Improvement

    Capacitor Bank

    Motor Feeder

    Power

    Feeder

    VFD FeederMotor Feeder

    Power

    Feeder

    VFD FeederLV Power

    Factor

    Improvement

    Capacitor Bank

    G~

    MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB

    NCNC

    BUS A400V

    91-SS51-EL01

    91-SS51-ET02A

    10/0.42kV, 1.6 MVA

    91-SS51-ET02B

    10/0.42kV, 1.6 MVA99-SS51-EG01

    350 kVA, 400V EDG

    NO NC

    BUS B BUS C

    ATS

  • EDGs are tested and commissioned during pre-commissioning phase itself and

    further they may be ensured for the following

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed.

    2. Ensure that all the piping, valves and instruments in the system are lined up.

    3. Ensure that IPCS/ENMS/ICSS/F&G system are in line and functional.

    4. Ensure system is free from leaks and spillage.

    5. Breathing and draining devices are satisfactory.

    6. Ensure that gas/flame/heat detectors are fixed and connected properly.

    7. Switch on auxiliary and control power supply.

    8. Ensure that the control/starting battery (starting battery is only for GTU sets and CPF-1 EDGs are Air start) is getting charged

    9. Ensure that all Electrical, Instrumentation, other controls and protections are in order and lined up.

    10. Ensure that all the safety controls such as thermostats, engine governor, automatic voltage regulator and protections are set to their values and tested.

    11. Select the manual mode

    12. Set the Governor just above the idle speed

    13. Set the excitation to minimum

    14. Give the start command from the engine control panel

    15. Air motor (CPF-1 EDGs) / Battery (GTU EDGs) cranks the engine and engine picks up speed and runs at idle speed

    16. Observe all the parameters such as speed, vibration and temperature

    17. Observe any abnormal noise from the engine

    18. If satisfied, increase the speed slowly up to normal speed (1000 RPM for CPF-1 EDGs & 1500 RPM for GTU EDGs) and monitor continuously.

    19. Increase the excitation gradually and record alternator voltage versus excitation current to conduct open circuit tests.

    20. When the engine reaches operating speed, observe other parameters including the above and additionally voltage, current, frequency, etc.

    21. Check the phase rotation with the grid

    22. If required, adjust AVR for voltage adjustment and speed for frequency

  • Step Actions Sign/Date

    23. Switch on the loads with 25%, 50% and 75% each with 15 minutes duration and record all the parameters

    24. Connect 100% load and observe for 4 Hrs and record all the parameters

    25. Check ventilation and CB interlocks

    26. With the maximum load on the engine, leaving cushion for the highest rated motor to start, start the highest rated motor and observe.

    27. Connect 110% load and observe for 1 Hr and ensure that the parameters are within the limits.

    28. After restoration of power, switch off the EDG.

    29. Check the timing for auto start, auto close of EDG CBs, Interlock between EDG & Mains CBs, auto Mains restoration and auto stop of EDGs.

    30. Check synchronisation between the EDGs, Grid synchronisation ( as applicable)

    31. Check interface at IPCS/ENMS/ICSS

    5.9 Commissioning of 220kV Switchyard

    220kV Switchyard commissioning is package vendors scope and following may

    be ensured prior to energising.

    5.9.1 Switchyard Configuration

    Description Quantity Bay Nos. Normally

    Connected to

    Bus sections Main Bus I, II & Transfer Bus

    - -

    Grid Incomers OHL-3 & 4 5&6 Main Bus I

    220kV 3rd party OHL O/Gs OHL1 &2 1&2 Main Bus I

    220kV Future OHL O/Gs OHL-5 &6 9&10 Main Bus I

    220kV O/Gs 2 Nos CPF-1 3&4 Main Bus II

    220kV O/Gs 2 Nos CPF-1A 11&12 Main Bus II

    GTG Incomer 1 No 13 Main Bus II

    Bus Coupler 1 No 8 Normally Closed

    Bus Transfer 1 No 7 -

  • Fig. 4 220 kV Switchyard (Reference: SYG-PSH-04-EL-SLD-0001)

  • 5.9.2 Pre-energisation Checks

    Step Actions Sign/Date

    1. Ensure that all the isolators are checked and available for operation

    2. Check and confirm that the incomer breaker is ready and its spring is charged.

    3. Ensure that earthing connections have been reinstated after the pre-commissioning tests.

    4. Ensure that the busbar earth switch, bus coupler earth switch and cable side earth switch are kept open and locked with safety pad lock (wherever applicable).

    5. Ensure all outgoing feeders of the 220kV yard are isolated and locked.

    6. Ensure that the upstream side equipment is commissioned and is ready to energise the downstream equipment.

    7. Ensure that the CT shorting links are reinstated after the pre-commissioning test; ensure that connections are tight.

    8. Ensure that the protection relays and their settings are correct.

    9. Ensure that all Voltage Transformer fuses are healthy and the earth connections are correct

    10. Ensure that the control and auxiliary power supply 110V DC/48V DC/400V AC are available.

    11. Ensure that the PLCC & Teleprotection panels are lined up for the OHL feeders

    12. Ensure that communication systems, SCADA & RTU, relay protection and emergency control systems between CPF-1 220kV switchyard and Mary SPS, Maryenergo & Turmenenergo are ready as applicable

    13. Ensure that the communication between 220kV yard SCADA and ENMS are ready.

    14. Ensure that the preparatory checks/steps given in vendor procedures and commissioning manual are carried out.

    15. Ensure clearance from Mary SPS/Turkmen energo to enrgise the yard

    16. Inform control room about the energisation

    17. Keep all the other isolators, CBs in Off position

    18. Ensure all the other isolators are open and not earthed

    19. At every stages of energisation, observe for any abnormality and take corrective action as required.

    20. Ensure availability of status indication of

  • Step Actions Sign/Date

    Isolators/CBs at yard control room/ENMS for every operation

    5.9.3 Order of Energisation

    The following order shall be applied for initial energisation of the switchyard:

    A. Energization of 220kV Switchyard

    Energization of Switchyard Main Bus-I & Main Bus-II from OHL-3, OHL-4 & GTG (Single feeder to Switchyard as per the Procedure 5.9.4).

    Energisation of 220kV switchyard through OHL-3

    1. Dead bus closing to Main Bus-I

    2. Dead bus closing Bus coupler to Main Bus-II

    3. Dead bus closing to Transfer Bus

    4. Open Transfer Bus CB

    5. Open OHL-3 CB

    Energisation of 220kV switchyard through OHL-4

    1. Dead bus closing to Main Bus-I (As Bus coupler already closed, Main

    Bus-II also gets energized)

    2. Open OHL-4 CB

    Energisation of 220kV switchyard through GTG

    1. Dead bus synchro to Main Bus-I (As Bus coupler already closed, Main

    Bus-II also gets energized)

    2. Open GTG CB

    3. Open bus coupler

    B. Energization of Switchyard with OHL-3, OHL-4 and Synchronizing with

    GTG (as per Procedure 5.9.5)

    1. Dead bus closing to Main Bus-I through OHL-3

    2. Closing OHL-4 after synchro check with OHL-3

    3. Start GTG and energise Main Bus-II

    4. Synchronize GTG with Main Bus-I through Bus-coupler

    5. Switch Off GTG and keep in standby

    6. System is ready

    C. Energization of Switchyard outgoing feeders with OHL-3 & OHL-4 (as per Procedure 5.9.6)

    1. Ensure Transformers are ready for energisation

    2. Energise Transformers one by one

  • 3. Energise OHL bay -1&2 only after obtaining approval and switch off

    when not required

    4. Energise OHL bay - 5 &6 only after obtaining approval and switch off

    when not required

    5.9.4 Energization of Switchyard

    Energization of Switchyard Main Bus-I through OHL-3, OHL-4 & GTG (Single

    feeder to Switchyard) and ensure clearance for energizing.

    Step Actions Sign/Date

    A. Energization of Switchyard Main Bus-I through OHL-3

    1. Confirm that all the Pre - energisation checks are completed as per relevant section of section 5.9.2

    2. Carryout Megger test on the system before energising

    3. Check for presence of 110V DC/48V DC/400V AC control supply to the control circuits.

    4. Ensure that communication systems, telemetry, relay protection and emergency control systems between220kV switchyard and Mary SPS, Maryenergo & Turmenenergo are ready as applicable

    5. Ensure that the inter panel wiring, Metering panel, Control panel, Relay panel, PLC Panel, SCADA Panel wiring are tested

    6. Ensure that all the Isolators, CBs and Earth switches are open

    7. Check that the indication lamps are healthy by using Lamp Test Switch.

    8. Ensure that the close/open interlocks of all the isolators, CB and earth switches are tested and verified

    9. Ensure that the closing spring of the CB of OHL-3 is charged

    10. Ensure that all the conditions required for closing the CB of OHL-3 are satisfied

    Bus-I not earthed

    CB Mechanism healthy

    Protective relays are healthy

    Line & Bus earth switches are open

    Trip & Closing coil supervision circuits are healthy

    Ensure trip from Distance protection, Backup distance protection and line differential are not active

    Ensure carrier inter trip protections are not active

  • Step Actions Sign/Date

    Ensure bus bar protection is not active

    Ensure no Phase Under Voltage is active

    11. Ensure all checks recommended by the vendor for energization of the yard are completed.

    12. Check with upstream CB for close permissive/inhibits/Inter trip as applicable

    13. Check CB tripping by Remote through SCADA

    14. Ensure that the Surge arrestors, CVTs & Line traps are lined up and yard is ready to receive the power

    15. Ensure availability 220kV Power supply from Mary PP-1

    16. Switch ON the MCBs for OHL-3 and Main Bus-1 to get 110V AC PT voltage to metering and protection.

    17. Check presence of voltage on all three phases on Metering and Protective Relays

    18. Check Phase sequence from line VT secondary three phase voltage and record (Normal/Clockwise)

    19. Turn OHL-3 CB selector to S 453 to Local position

    20. Ensure synchro permissive from distance relay

    21. Close the Isolator Q9 of OHL-3 and observe for any abnormality

    22. Close the Isolator Q1 of OHL-3

    23. Close OHL-3 Circuit Breaker Q0 through S0 and this energises Main Bus-I and observe for any abnormality and carryout corrective action, if required

    24. Check interface signals are correct

    B. Energisation of Main Bus-II through Bus Coulper

    1. Ensure Bus-coupler and Main Bus-II are ready for energisation

    2. Close Main Bus-I VT Isolator Q3-A08 and availability of three phase Voltage and record phase sequence (Normal/Clockwise)

    3. Close the isolator Q1-A08 of BC and observe for any abnormality

    4. Close the isolator Q2-A08 of BC

    5. Close the CB Q0-A08 of BC, energise Main Bus-II and observe for any abnormality

    6. Close Main Bus-II VT Isolator Q3-A08 and availability of three phase Voltage and record phase sequence (Normal/Clockwise)

    7. Check interface signals are correct

    C. Energisation of Transfer Bus through Main Bus-1

    1. Ensure that the Transfer Bus is ready for energisation

  • Step Actions Sign/Date

    2. Close the isolator Q1-A07 and observe for any abnormality

    3. Close the isolator Q7-A07

    4. Close the CB Q0-A07, energise Transfer Bus and observe for any abnormality

    5. Check Transfer Bus VT and availability of three phase Voltage and record phase sequence (Normal/Clockwise)

    6. Check interface signals are correct

    7. Open CB Q0-A07, then isolator Q1-A07 & Q7-A07 and de-energise the Transfer Bus

    8. Earth the Transfer Bus through Earth Switch Q72-A07, later open earth switch

    9. Open CB Q0-A08, then isolator Q1-A08 & Q2-A08 and de-energise the Main Bus-II

    10. Earth the Main Bus-II through Earth Switch Q11-A08, later open earth switch

    11. Open CB Q0-A05, then isolator Q1-A05 & Q2-A05 and de-energise the Main Bus-I

    12. Earth the Main Bus-I through Earth Switch Q11-A05, later open earth switch

    D. Energization of Switchyard through OHL-4

    1. Follow steps 1 to 43 with respective Isolators & CB

    2. Check the phase sequence and compare the same with OHL-3 phase sequence and ensure that they are same

    E. Energization of Switchyard through GTG

    1. Start GTG and ensure availability of Voltage

    2. Follow steps 1 to 43 with respective Isolators & CB as applicable

    3. Check the phase sequence and compare the same with OHL-3 phase sequence and ensure that they are same

    5.9.5 Synchronizing Grid Mains and GTG

    Grid Incomers paralleling and Synchronising with GTG requires prior approval

    from Mary PP and Turkmen Energo. Grid incomers shall be tested and

    paralleled later GTG shall be synchronised. Ensure that the GTG is already

    tested and ready for energizing and loading.

    Step Actions Sign/Date

    1. Energise Main Bus-I through OHL-3 and record the VT phase sequence (Normal/Clockwise)

  • Step Actions Sign/Date

    2. Record the VT phase sequence of OHL-4 (Normal/Clockwise)

    3. Compare phase sequences of OHL-3 & OHL-4, across voltage on the same phase shall be zero and cross voltages between the phases shall be 110V

    4. Ensure synchro check permissive through distance relay to close CB of OHL-4

    5. Close CB of OHL-4 and observe for any abnormality

    6. Run GTG and Energise Main Bus-II through GTG and record the VT phase sequence (Normal/Clockwise)

    7. At Bus-coupler VTs compare Voltage and phase sequence of OHLs and GTG. Across voltage on the same phase shall be zero and cross voltages between the phases shall be 110V

    8. Ensure synchro check permissive through distance relay to close CB of Bus-coupler

    9. Close Bus-coupler CB and observe for any abnormality

    10. Ensure that there is no abnormal circulation current at the bus-coupler ammeter

    11. Switch Off GTG CB and connected Isolators and switch off GTG

    12. Record all the details

    13. Now the 220kV yard is ready for energising outgoing feeders and loading

    5.9.6 Energization of outgoing feeders

    Step Actions Sign/Date

    A. Energisation of Transformer feeders

    1. Main Bus-I is energised through OHL-3 & OHL-4 and Main Bus-II is energised through closed Bus coupler

    2. Ensure that 220kV Yard is and ready and clearance available for loading

    B. Energisation of Transformer feeder A-11 (CPF-1A HEC)

    1. Ensure that the pre-energisation checks on Transformer is completed as 5.9.2

    2. Ensure that the Transformer and connected downstream switchgear is ready to receive the power

    3. Ensure that the secondary side CB and earth switches of the transformer are open in the switchgear

    4. Close the isolator Q2-A11 and observe for any

  • Step Actions Sign/Date

    abnormality

    5. Close the isolator Q9-A11 and

    6. Close the CB Q0-A11 and observe for any abnormality

    7. Ensure that all the position indicators are correct with respect to actual position of the Isolators/Circuit Breakers

    8. Ensure that the indicating lamps are showing the correct status

    9. Ensure status indications of Isolators/CBs in SCADA/ENMS

    C. Energisation of Transformer feeders A-12 (CPF-1A HEC), A-3&A-4 (CPF-1)

    1. Repeat steps with respective isolators & circuit breaker of the concerned transformer

    D. Energisation 3rd party outgoing OHL feeders

    1. Energisation 3rd party outgoing OHL feeders is with Turkmen Energo and this is to be done as per their requirement

    5.10 Transformers and Switchgears

    5.10.1 Pre-Energisation Checks

    A. General

    The sequence of energisation of the equipment is listed below:

    (The following commissioning description is shown for switchgear having two

    bus sections and a normally open bus coupler. The same logic can be extended

    for commissioning other type of switchgears by applying their respective

    configurations. The pre-energisation checks applicable to Transformers shall

    be followed to commission NETs)

    Transformers with their respective NET/NER

    Bus Section A

    Bus Section B

    Bus Coupler

    B. Pre-energisation Checks on Transformers

    Step Actions Sign/Date

    1. Check and confirm that the oil level is correct in the conservator tank

    2. Ensure that the upstream side panel is commissioned and the breaker is ready to energise the downstream

  • Step Actions Sign/Date

    equipment

    3. Ensure that the secondary side circuit breaker is isolated and locked

    4. Ensure that earthing connections and NET/NER connections (where applicable) are reinstated correctly after pre-commissioning tests

    5. Ensure that the tap setting of the transformer is in normal tap and pad locked

    6. Ensure that all radiator valves are open

    7. Ensure that CT shorting links are reinstated in Marshalling kiosk and in panels after pre-commissioning tests

    8. Ensure that CT circuit connections are tight

    9. Ensure that the auxiliary supply to the transformer is on and the indications are working correctly

    10. Ensure that protective relays are set as per relay co-ordination documents

    11. Ensure that Alarm and Trip settings of transformer Winding and Oil temperatures are set as per the vendors recommendations

    12. Check the condition of silica gel breather and record the colour

    13. Ensure that the any other preparatory checks/steps given in vendor procedure/commissioning manual are carried out

    C. Pre-energisation Checks on Switchgears

    Step Actions Sign/Date

    1. Check and confirm that the incomer breaker is in service position and its spring is charged.

    2. Ensure that earthing connections have been reinstated after the pre-commissioning tests.

    3. Ensure that the busbar earth switch, bus coupler earth switch and cable side earth switch are kept open and locked with safety pad lock (wherever applicable).

    4. Ensure all outgoing feeders of the Switchgear are isolated and locked.

    5. In case of HV Switchgear, all the outgoing feeders shall be racked out to Test/Isolated position; busbar shutters/cable side shutters shall be locked with safety padlock and doors shall be closed and locked.

    6. In case of 400V Board with non-isolatable type feeders, all the fuses in the outgoing feeders shall be removed and fuses shall be duly marked with feeder

  • Step Actions Sign/Date

    numbers.

    7. Ensure that the upstream side equipment is commissioned and is ready to energise the downstream equipment.

    8. Ensure that the CT shorting links are reinstated after the pre-commissioning test; ensure that connections are tight.

    9. Ensure that the protection relays and their settings are correct.

    10. Ensure that all Voltage Transformer fuses are healthy and the earth connections are correct

    11. Ensure that the Bus Coupler Breaker is open and in isolated position

    12. Ensure that IPCS/ENMS/ICSS are ready and communicating to the Switchgear.

    13. Ensure that the control power supply 110V DC/230V AC (UPS) /230V AC (wherever applicable) are on and the indications are working; verify the control supply voltages using a Multi-meter.

    14. Ensure that the preparatory checks/steps given in vendor procedures and commissioning manual are carried out.

    5.10.2 Energisation of Transformers

    Step Actions Sign/Date

    1. Confirm that all the preparatory works are completed as per Section 5.10.1-B, Pre-energisation checks.

    2. Ensure the presence of primary power supply at the upstream Switchgear and the supply is within the tolerance limits.

    3. Ensure that the secondary side Circuit Breaker of the Downstream Switchgears in Incomer and Earth Switch of the respective Transformer are open.

    4. Check and ensure that all the indication lamps are healthy in primary and secondary breaker panels

    5. At the upstream Switchgear, perform feeder de-earthing operation.

    6. Operate the disconnector to ON position (wherever applicable) as per the vendors operating instructions.

    7. Switch ON the primary circuit breaker of the concerned transformer feeder from the upstream panel as per the vendors operating instructions.

    8. Check that the position indicators are correct with respect to the actual position of the disconnector

  • Step Actions Sign/Date

    and breaker.

    9. Check that the indication lamp is showing correct status of the breaker.

    10. Check that the primary voltage and current are balanced.

    11. Check that the voltage indications are working

    12. Record the readings of the meters in the check sheet

    13. Check the indications related signals to IPCS/ENMS/ICSS

    14. Check the indications on the respective downstream Switchgear incomer for the presence of voltage.

    15. Measure phase to phase and phase to neutral voltages to confirm secondary voltage of the transformer. Check and record the phase sequence across the secondary of the VT circuit.

    16. Observe the transformer for any abnormal conditions noise, vibration, etc.

    17. Put the transformer on no-load soak for 12 hours (duration to be decided at site in consultation with the vendor representative).

    18. Monitor the transformer and record the winding temperature, oil temperature and voltages (primary and secondary) during the soak period.

    19. After soaking period, switch OFF the transformer and check the Bucholz relay for collection of Air/Gas and vent off.

    20. Correct the abnormalities identified during soaking.

    21. Re-energise the transformer from upstream panel.

    22. Close the secondary side circuit breaker in the downstream switchgear and ensure the following interlocks:

    Ensure when downstream incomer CB is tripped, upstream primary CB trips on inter-trip and further inhibits closing of upstream CB, till fault gets reset at secondary side

    Ensure downstream incomer gets tripped when upstream CB is opened or tripped

    Ensure fault/close/open status in IPCS/ ENMS/ ICSS, upstream and downstream switchgears.

  • 5.10.3 Energisation Switchgears

    A. Energisation of Switchgear (Bus-A)

    The transformers are now ready for loading. Initial energisation of Switchgear

    will be done in bus sections with the Bus Coupler in open condition. Bus-A will

    be initially energised.

    Step Actions Sign/Date

    1. Confirm that all the preparatory works are complete as per Section 5.10.1-C, Pre-energisation checks.

    2. Ensure the availability of 110V DC/230V AC (UPS) /230V AC (wherever applicable) control supply to the control and auxiliary circuits

    3. On Incomer Panel of Bus-A, ensure that the Earth Switch is open and the Circuit Breaker is in service position.

    4. Ensure that the IPCS system is ready and the communications are established between ENMS & ICSS

    5. Ensure that the line VT of incomer-1 is in service position.

    6. Switch ON the MCB to provide 110 V AC line VT voltage signals to Relays, Meters and Indication lamps

    7. On Incomer-1, check all the Phase Indicating Lamps to ensure the presence of voltage

    8. Ensure that the indication lamps (on/off/auto trip/TCS Healthy) are healthy

    9. Rack in the incomer-1 Circuit Breaker to service position

    10. Ensure that all the conditions required for closing the Circuit Breaker are satisfied

    a. Transformer is not faulty

    b. Bus-A is not earthed

    c. CB Mechanism is healthy

    d. Cable side earth switch is open

    e. Incomer under voltage relay is healthy

    f. Incomer-1 is not faulty

    g. Incomer-1 breaker is in service position

    h. Incomer-1 Trip Circuit Supervision is healthy

    i. Close permissive for Incomer-1

    j. Bus Coupler CB is in open position/not in service

    k. Upstream feeder CB is in service and ON

    11. Ensure that the Bus-A VT is in service position.

    12. Switch ON the MCB to provide 110V AC Bus VT voltage signals to relays, meters and indication

  • Step Actions Sign/Date

    lamps

    13. Ensure that all commissioning checks recommended for initial energisation by the vendor are complete

    14. Ensure that the closing spring of the Circuit Breaker is charged

    15. Close the Incomer-1 Circuit Breaker

    16. Check the presence of bus voltage on all three phases using panel mounted voltmeter

    17. Record the readings of the meters check sheet

    18. Check the phase sequence of the voltage signals and record

    19. Trip the Incomer Circuit Breaker via Transformer Protection. Ensure this CB trips, Inter trip of upstream and corresponding indications in all the places. Switch on the upstream and Incomer CB of the Switchgear under commissioning from remote, if applicable.

    20. Check that the signals to IPCS/ENMS/ICSS system are correct

    21. Check controls and indication to and from EWS

    22. Observe the Switchgear for any abnormal conditions and take corrective action, if required.

    23. After satisfactory initial energisation, the bus Section A of the Switchgear is ready for further checks with the Bus Coupler.

    B. Energisation of Switchgear (Bus-B)

    Step Actions Sign/Date

    1. Confirm that all the preparatory works are completed as per Section 5.10.1-C, Pre-energisation checks.

    2. Ensure the availability of 110V DC/230V AC (UPS) /230V AC (wherever applicable) control supply to the control and auxiliary circuits

    3. On Incomer Panel of Bus-B, ensure that the Earth Switch is open and the Circuit Breaker is in service position.

    4. Ensure that the IPCS system is ready and the communications are established between ENMS/ICSS

    5. Ensure that the line VT of incomer-2 is in service position.

    6. Switch ON the MCB to provide 110 V AC line VT voltage signals to relays, meters and indication lamps

    7. On Incomer-2, check all the Phase Indicating

  • Step Actions Sign/Date

    Lamps to ensure the presence of voltage

    8. Ensure that the indication lamps (on/off/auto trip/TCS Healthy) are healthy

    9. Rack in the Incomer-2 Circuit Breaker to service position

    10. Ensure that all the conditions required for closing the Circuit Breaker are satisfied

    a. Transformer is not faulty

    b. Bus-B is not earthed

    c. CB Mechanism is healthy

    d. Cable side earth switch is open

    e. Incomer under voltage relay is healthy

    f. Incomer-1 is not faulty

    g. Incomer-1 breaker is in service position

    h. Incomer-1 Trip Circuit Supervision is healthy

    i. Close permissive for Incomer-2

    j. Bus Coupler CB is in open position/Not in service

    k. Upstream feeder CB is in service and ON

    11. Ensure that Bus-B VT is in service position.

    12. Switch ON the MCB to provide 110V AC Bus VT voltage signals to relays, meters and indication lamps

    13. Ensure that all commissioning checks recommended for initial energisation by the vendor are complete

    14. Ensure that the closing spring of the Circuit Breaker is charged

    15. Close the Incomer Circuit Breaker

    16. Check the presence of bus voltage on all the three phases using panel mounted voltmeter

    17. Record the readings of the meters in the check sheet

    18. Check the phase sequence of voltage signals and record

    19. Trip the Incomer Circuit Breaker via Transformer Protection. Ensure this CB trips, inter trip of upstream and corresponding indications in all the places. Switch on the upstream and the Incomer CB of the Switchgear under commissioning from remote, if applicable.

    20. Check that signals to ENMS/ICSS system are correct

    21. Check controls and indication to and from EWS

    22. Observe the Switchgear for any abnormal conditions and take corrective action, if required.

    23. After satisfactory initial energisation, the bus Section B of the Switchgear is ready for further checks with the Bus Coupler.

  • C. Energisation of Bus Couplers

    Note: All the switchgears having bus sections have bus VTs. The phase

    sequence of the section will be checked individually and the phase sequence

    will be compared using volt meters.

    Step Actions Sign/Date

    1. Check the phase sequence of each section of the bus section as listed below, and record the results in the check sheet.

    2. Check the phasing of busbars in the Bus Coupler panel as listed below and record the result in form

    3. LV Switchgears

    a. Rack out the Bus Coupler Circuit Breaker from the compartment

    b. Open the top and bottom busbar shutters manually and temporarily latch it at the open position

    c. Ensure that the meters used for testing have valid safety and calibration certificates

    d. Use fused test leads

    e. Select the appropriate voltage range for 600V AC

    f. Check and ensure that there is voltage at each spout

    g. Check the voltage across the similar phases of busbar at top and bottom; the voltage should be zero

    h. Check the cross voltages across the top and bottom busbars; the value must be the same as the system voltage in all cases.

    i. Record the results of phasing out measurements in the check sheet

    j. Release the busbar shutter temporary latches and close the shutters

    k. Return the coupler breaker into the compartment

    l. Rack in the breaker to service position

    4. HV Switchgears

    a. Rack out the Bus Coupler Circuit Breaker from the compartment

    b. Open the metering compartment and ensure that the respective PT terminals of each bus section (Bus-A & Bus-B) selected are correct

    c. Ensure that the meters used for testing have valid safety and calibration certificates

    d. Use fused test leads

    e. Select the appropriate voltage range 110V AC

    f. Check and ensure that there is voltage at each PT terminals

  • Step Actions Sign/Date

    g. Check the voltage across the respective PTs of similar phases of Bus-A & Bus-B; the voltage should be zero

    h. Check the cross voltages across the respective PTs of Bus-A & Bus-B; the value must be the same as the system voltage in all cases.

    i. Record the results of phasing out measurements in the check sheet

    j. Return the coupler breaker into the compartment

    k. Rack in the breaker to service position

    5. Dead Bus closing of the Bus Coupler with Incomer-2 open (Section B without power):

    a. Ensure that all conditions required to close the Bus Coupler in Manual mode is satisfied.

    i. Bus Coupler is in service

    ii. Trip Circuit Supervision is healthy

    iii. Incomer-2 Lockout relay is not operated

    iv. Incomer-2 is open

    b. Close the Bus Coupler Breaker

    c. Check the indications and presence of voltage on bus Section B

    d. Check the phase sequence on Section B at Bus VT and compare it with the phase sequence which was checked with the Incomer-2 CB closed. The phase sequence with Incomer-1 and this step shall be the same.

    e. With successful Dead Bus closing checks and conditions satisfied, the Bus Coupler is ready for Live Bus closing check.

    6. Dead Bus closing of the Bus Coupler with lncomer-1 open (Section A without power):

    a. Ensure that all conditions required to close the Bus Coupler is satisfied.

    i. Bus Coupler is in service

    ii. Trip Circuit Supervision is healthy

    iii. Incomer-1 Lockout relay is not operated

    iv. Incomer-1 is open

    b. Close the Bus Coupler Breaker

    c. Check the indications and presence of voltage on bus Section A

    d. Check the phase sequence on Section A at Bus VT and compare it with the phase sequence which was checked with the Incomer-1 CB closed. The phase sequence with Incomer-2 and this step shall be the same.

    e. With successful Dead Bus closing checks and conditions satisfied, the Bus Coupler is ready for Live Bus closing check.

  • Step Actions Sign/Date

    7. Live Bus closing of the Bus Coupler with Incomer-1 and Incomer-2 closed (Both the bus sections are live):

    a. Ensure that all conditions required to close the Bus Coupler in Manual mode is satisfied.

    i. Auto/Manual Selector Switch is in manual position

    ii. Bus Coupler is in service position

    iii. Trip circuit supervision is healthy

    b. Close the Bus Coupler Breaker.

    c. Check and ensure that there is no abnormal circulation current at the Bus Coupler ammeters.

    d. Demonstrate the scheme checks in live/service condition and record the result in the form.

    5.10.4 Functionality and Interlocks

    A. Transformers

    1. Functionality of the Transformers are checked and demonstrated during

    soaking.

    2. Interlocks of the Transformer breakers are tested during pre-

    commissioning checks.

    B. HV/LV Switchgears

    Auto Transfer Scheme (ATS) Checking

    Only 10kV and 400V Switchgears Bus Couplers are in normally open condition

    and ATS may be checked on them. 35kV Bus coupler is kept in normally closed

    condition.

    After Auto Transfer changeover, returning to normal operating condition of

    the breakers is completed manually.

    Normal Condition

    Step Actions Sign/Date

    1. Both the incomer breakers of the Switchgears are in service and ON.

    2. Supply voltages are within the limits

    3. Auto/Manual Selector of the ATS selected to Auto

    4. Vendor operation instruction and final drawings specific to the Switchgear shall be reviewed and followed to demonstrate the scheme.

    5. Create Under Voltage on Incomer-1 (Bus-A) by opening the upstream Incomer Breaker for the Transformer

  • Step Actions Sign/Date

    a. Ensure that the Bus Coupler CB closes to feed from Bus-B.

    b. Check the voltage presence on Bus-A after Auto Transfer.

    c. Normalise the bus sections by manual mode

    d. Ensure that the Incomer Breaker closes and after that the Bus Coupler Breaker opens.

    6. Create Under Voltage on Incomer-2 (Bus-B)

    a. Ensure that the Bus Coupler CB closes to feed from Bus-A.

    b. Check the voltage presence on Bus-B after Auto Transfer.

    c. Normalise the bus sections by manual mode

    d. Ensure that the Incomer Breaker closes and after that the Bus Coupler Breaker opens.

    7. Check blocking of ATS for the following conditions (whichever is practical):

    a. Simultaneous Under Voltage on both buses

    b. Short time Under Voltage

    c. Any Breaker is in test position

    d. Lock out on any of the two Incomers except for Transformer fault

    8. Check interface with IPCS/ENMS/ICSS for the following conditions during ATS demonstration:

    a. Incomer CB tripped, ATS allowed

    b. Incomer CB tripped, ATS inhibited

    c. Inter trip of Upstream CB

    9. Normalise the Switchgear after the tests by closing Incomer-1 & Incomer-2 CBs and by opening Bus Coupler CB

    Note: For energizing switchgears of following configurations, the energization

    procedure as outlined shall be followed with respective incomer with

    concerned bus-coupler and applicable configurations.

    5.10.5 Switchgear Configurations

    Following are the different configurations of switchgear available in the facility.

    A. 3 Bus sections/2 Bus couplers/2 Normal Incomers/2 Emergency Incomers from DG Sets

    10kV Switchgear 04-SS01 (With Emergency Bus-E)

  • Fig. 5 Configuration with 3 Bus & 2B/C-SS01

    1/C-A

    N/C

    B/C-A-E

    N/O

    1/C-E1

    EDG 1

    N/O

    1/C-E2

    EDG 2

    N/C

    B/C-E-B

    1/C-B

    B. 2 Bus sections/1 Bus coupler/2 Normal Incomers

    35 kV Switchgear 04-SS01 (B/C-NC)

    10 kV Switchgear 04-SS01 (B/C-NO)

    400V Switchgear 04-SS01/02/03/04/05/06 (B/C-NO)

    Fig. 6 - Configuration with 2 Bus & 1B/C

    NORMAL INCOMER-A NORMAL INCOMER-B

    1/C-A1/C-B

    N/C

    B/C

    N/O

    N/C

    BUS-A BUS-B

    C. 3 Bus sections/2 Bus couplers/2 Normal Incomers/1 Emergency Incomer from DG Set

    400V Switchgear GTU-5,6,7 &8 (With Emergency Bus-C)

  • Fig. 7 - Configuration with 3 Bus & 2B/C-GTU

    1/C-CN/C

    N/O

    B/C-A-B

    1/C-B N/C

    B/C-B-C

    N/C

    N/O

    EDG

    D. 1 Bus section/1 Normal Incomer/1 Emergency Incomer through transformer

    400V Switchgear 04-SS01/02/03/04/05/06 (Emergency)

    Fig. 8 Configuration with 1 Bus-LV Emergency CPF-1

    NORMAL INCOMER EMERGENCY INCOMER

    1/C-A 1/C-BN/C N/O

    E. 1 Bus section/1 Normal Incomer

    400V Switchgear - Infield pipeline

    400V Switchgear - Export pipeline

    400V Switchgear - Well head

    5.11 35kV & 10kV Overhead Lines

    Step Actions Sign/Date

    1. Ensure that pre-commissioning checks are completed on the OHLs

    2. Ensure that the downstream equipments are tested and ready to receive power

    3. Prior to energisation, visually check the entire overhead line and the associated equipment

  • Step Actions Sign/Date

    4. Megger the OHL and record the results

    5. Give clearance to energise the OHL by switching on relevant Circuit Breaker

    6. Observe for any abnormality

    5.12 Motors

    Step Actions Sign/Date

    1. Ensure that all Pre-requisite checks are completed

    2. Carryout Megger test on the system before energising.

    3. Ensure that the protection settings are as per the relay setting document.

    4. Check Anti Condensation heaters and record IR values.

    5. With the motor uncoupled, run the motor from both local and remote to check the sequence interlocks. Also, check the correct operation, operation of emergency stop push button, indication and annunciation of devices like lamps, alarms, etc.

    6. Rotation of the motor, whether clockwise or anticlockwise, is recorde