electrical system comm procedure
DESCRIPTION
COMMISSIONINGTRANSCRIPT
-
x
COMMISSIONING PROCEDURE
ELECTRICAL SYSTEM
-
REVISION HISTORY
REVISION DESCRIPTION OF REVISION
A1 Issued for IDC
HOLD LIST
HOLD NO. SECTION NO. DESCRIPTION
1 5.0 Pre-Comm. & Comm. procedure for 220kV Switchyard
2 5.0 Pre-Comm. & Comm. procedure for 4MVA (EL-199030197-N05-0001) & 350 kVA (EL-199030197-N05-0002) DG Sets
-
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................... 5
1.1 General ............................................................................. 5
1.2 Overview - Electrical System ................................................... 5
1.3 Abbreviation ....................................................................... 6
1.4 Terminology ....................................................................... 8
2.0 ELECTRICAL SYSTEM DESCRIPTION ........................................... 9
2.1 System Voltage and Frequency ................................................. 9
2.2 Power Distribution ............................................................... 12
2.3 Switchgears ....................................................................... 13
2.4 Gas Turbine Generator (GTG) .................................................. 14
2.5 Transformers ..................................................................... 14
2.6 Motors ............................................................................. 15
2.7 UPSs ............................................................................... 16
2.8 Essential Diesel Generators (EDG) ............................................. 16
2.9 Lighting ........................................................................... 16
2.10 Electrical Heat Tracing / Heaters ............................................. 17
2.11 Power Factor Improvement .................................................... 17
2.12 IPCS/ENMS/SCADA ............................................................... 17
2.13 Cathodic Protection ............................................................. 17
3.0 GENERAL SCOPE OF COMMISSIONING PROCEDURE ........................ 19
4.0 GENERAL HEALTH, SAFETY AND ENVIRONMENT CONSIDERATIONS .... 20
4.1 General ............................................................................ 20
4.2 Compliance ....................................................................... 20
4.3 Health Hazards ................................................................... 20
4.4 Environment ...................................................................... 21
4.5 Pre-start Safety Checks ......................................................... 21
5.0 COMMISSIONING PROCEDURE ................................................. 22
5.1 Test Preparation/Prerequisite ................................................. 23
5.2 Tools and Test Equipment Required .......................................... 23
5.3 Control and Auxiliary Power Supplies ......................................... 24
5.4 Vendor Commissioning Assistance ............................................. 24
5.5 Energisation of UPSs ............................................................. 25
5.6 Energisation of Distribution Boards ........................................... 26
5.7 Power Cables ..................................................................... 27
5.8 Emergency Diesel Generators .................................................. 28
5.9 Commissioning of 220kV Switchyard .......................................... 32
5.9.1 Switchyard Configuration ....................................................... 32
5.9.2 Pre-energisation Checks ........................................................ 34
5.9.3 Order of Energisation ........................................................... 35
5.9.4 Energization of Switchyard ..................................................... 36
-
5.9.5 Synchronizing Grid Mains and GTG ............................................ 38
5.9.6 Energization of outgoing feeders .............................................. 39
5.10 Transformers and Switchgears ................................................. 40
5.10.1 Pre-Energisation Checks ........................................................ 40
5.10.2 Energisation of Transformers .................................................. 42
5.10.3 Energisation Switchgears ....................................................... 44
5.10.4 Functionality and Interlocks ................................................... 49
5.10.5 Switchgear Configurations ...................................................... 50
5.11 35kV & 10kV Overhead Lines ................................................... 52
5.12 Motors ............................................................................. 53
5.13 VSD/Soft Starters ................................................................ 53
5.14 PF Improvement Capacitors .................................................... 54
5.15 Gas Turbine Generator .......................................................... 54
5.16 Cathodic Protection ............................................................. 56
6.0 POST TEST STATUS ............................................................. 58
7.0 COMMISSIONING SUPPORT DOCUMENTS ..................................... 59
8.0 REFERENCE DOCUMENTS ...................................................... 60
-
1.0 INTRODUCTION
1.1 General
This document provides basic information, guidance and support documents to
carryout commissioning activities for the Electrical System at SYG in a
planned, safe and controlled manner.
This document shall be used in conjunction with the TMG specifications for
commissioning and the manufacturers or vendors documents and drawings.
In the mechanical completion/pre-commissioning phase, the Equipment,
Systems and Units are tested and prepared so that the system, etc., are in a
condition where they are ready for commissioning (RFC).
During Commissioning, the Electrical Equipment, Systems and Units are
energised and prepared to support the commissioning of other
systems/Companys Start-up schedule.
Commissioning includes activities that enable systematic and safe introduction
of power supply into the electrical system and verification of performance
parameters with the intended design, such as checks on Voltage, Phase
sequence, Man Machine Interfaces, Automatic Changeover scheme and
IPCS/ENMS/ICSS interfaces.
1.2 Overview - Electrical System
The Electrical system at SYG consists of Main intake power through two 220kV
OHL from Turkmen Energo National Grid. The outdoor 220kV, 3 phase, 3 wire
switchyard has 13 bays including above two OHL incomer bays from Mary SPS,
four outgoing OHL feeders of two each for CPF-2(CNPC) & future
development, four outgoing transformer feeders- two each for CPF-1 &
CPF-1A(Hyundai), one GTG Incomer, one Bus coupler and one Bus Transfer
breaker.
The estimated total electrical power requirement for CPF-1 is 85MW and
CPF-1A is 40MW. The 220kV power from Mary SPS is stepped down distributed
within the facilities at 35kV, 10kV and 400V voltage levels. The electrical
system at the facility includes transformers, GTG, motors, switchgears, UPSs,
EDGs, electrical heaters, heat tracing, cathodic protection, PF improvement
capacitors, lighting & power distribution.
-
During normal time, GTG is in standby mode keeping auxiliaries running.
During Mains failure or at the requirement of authorities, GTG will be made to
run. EDGs installed will come in line automatically during Mains failure and
serve all the emergency power requirement. Separate EDGs are installed for
CPF-1 as well as GTUs.
For centralised monitoring and control of electrical systems, IPCS and ENMS
are installed.
This document provides the commissioning procedure for the Electrical system
without compromising the safety and reliability.
1.3 Abbreviation
Abbreviation Description
AC Alternating current
AIS Air Insulated Switchgear
APFC Automatic Power Factor Controller
AVR Automatic Voltage Regulator
ACSR Aluminium Conductor Steel Reinforced
B/C Bus Coupler
BVS Block Valve Station
CB Circuit Breaker
CBCT Core Balance Current Transformer
CCR Central Control Room
CP Cathodic Protection
CPF Central Processing Facility
CPU Central Processing Unit
CT Current Transformer
DC Direct Current
EDG Emergency Diesel Generator
E/F Earth Fault
EMC Electromagnetic Compatibility
ENMS Electrical Network Monitoring system
ESD Emergency Shutdown System
FEED Front End Engineering Design
F&G Fire and Gas System
GCP Generator Control Panel
GIS Gas Insulated Switchgear
GTG Gas Turbine Generator
HMI Human Machine Interface
-
Abbreviation Description
HSE Health Safety and Environment
HV High Voltage
HVAC Heating Ventilating & Air Conditioning
ICCP Impressed Current Cathodic Protection
I DMT Inverse Definite Minimum Time
I EC International Electrotechnical Commission
IP Ingress Protection
ICSS Instrumentation Control & Safety System
I/C Incomer
I/O Input/Output
IPCS Integrated Protection and Control System
IPCD Integrated Protection and Control Device
ITR Inspection and Test Report
JSA/JHA Job Safety Analysis/Job Hazard Analysis
LER Local Equipment Room
LV Low Voltage
MCB Miniature Circuit Breaker
MCCB Moulded Case Circuit Breaker
MCC Motor Control Centre
MCS Motor Control Station
MPR Motor Protection Relay
MVA Mega Volt Ampere
OHL Over Head Line
O/L Over Load
O/C Over Current
OCTC Off Circuit Tap Changer
OLTC On Load Tap Changer
PCP Permanent Cathodic Protection
PE Protective Earth
Pf Power Factor
PRC Power Factor Improvement Capacitor
PLC Programmable Logic Controller
RCD Residual Current Device
REF Restricted Earth fault
RMU Ring Main Unit
RMS Root Mean Square
RTCC Remote Tap Changer Cubicle
RTD Resistance Temperature Device
SACP Sacrificial Anode Cathodic Protection
-
Abbreviation Description
SF6 Sulphur Hexafluoride
TCP Temporary Cathodic Protection
TEFC Totally Enclosed Fan Cooled
UPS Uninterrupted Power Supply
VCB Vacuum Circuit breaker
VDU Visual Display Unit
VSD Variable Speed Drive
VT Voltage Transformer
XLPE Cross Linked Polyethylene
VCU Vacuum Contactor Unit
1.4 Terminology
Term Definition
Procedure Specified directions or commands on how to undertake a particular task or series of tasks. A procedure generally comprises of a series of instructions presented within a specified sequence.
Instructions A description of an action to be undertaken generally forms part of a procedure.
-
2.0 ELECTRICAL SYSTEM DESCRIPTION
2.1 System Voltage and Frequency
Transmission and Primary Distribution System
220kV, 3ph, 3 wire, system neutral solidly earthed
HV distribution system: Central Processing Facilities (CPF-1)
35kV and 10kV, 3ph, 3 wire. 35kV earthed through Zigzag earthing transformer and 10kV neutral resistance earthed
Incoming supply to Gas Treatment Units (GTUs)
35kV, 3 ph, 3 wire
HV distribution system: GTUs 10kV, 3 ph, 3 wire, system neutral solid earthed
LV Distribution system for Gas Treatment Units (GTUs) and Wellheads.
400V, 3 ph, 4 wire, system neutral solidly earthed
Emergency Generation System (CPF-1)
10kV, 3 ph, 3 wire, system neutral resistance earthed
Emergency Generation System (GTU)
400 V, 3 ph, 4 wire, system neutral solidly earthed
Motors > 6000kW
10kV, 3 ph, 3 wire, system neutral resistance earthed (motors are supplied from 35 kV system using unit transformers with Dyn11 vector group)
Motors >150kW and < 6000kW 10kV, 3 ph, 3 wire, system neutral resistance earthed. Soft starter for above 1000 kW motors shall be used.
Motors > 0.18kW and < 150kW (All Motors)
400V, 3 ph, 3 wire, system neutral solidly earthed. Soft starter for above 100 kW motors shall be used.
Motors < 0.18kW 230V, 1 ph, system neutral solidly earthed
Motor operated valves 400V, 3 ph, 3 wire, system neutral solidly earthed
Lighting, convenience socket outlets, electrical trace heating, single phase power tools, single phase consumers etc.
400V, 3 ph, 4 wire/230V, 1 ph 2 wire + RE (TN-S system), system neutral solidly earthed
Welding socket outlets: 400V, 3 ph, 4 wire, system neutral solidly earthed
Escape lighting: 230V, 1 ph, (vital supply from UPS), system neutral solidly earthed
Power tools 230V, 1 ph, system neutral solidly earthed
Anti-condensation heaters 230V, 1 ph, system neutral solidly earthed
Heaters up to 3kW 230V, 1 ph, system neutral solidly
-
earthed
Heaters up to 250kW 400V, 3 ph, 4 wire, system neutral solidly earthed
Non vital instruments 230V, 1 ph, 2 core + RE, system neutral solidly earthed
Electrical ENMS and IPCS System 230V AC UPS
ICSS, ESD, F&G and other vital instruments:
230V, 1 ph, 2 core + PE, (vital supply from UPS), system neutral solidly earthed
Communication system for CPF-1, GTU & Wellheads
230V, 1 ph, (vital supply from UPS), system neutral solidly earthed
Communication system for pipelines:
230V, 1 ph, (vital supply from UPS), system neutral solidly earthed
Control/protection of 220, 35 & 10kV Switchgear HV switchboards (circuit breakers) and power transformers.
110V DC, unearthed (from UPS)
Circuit breaker spring charging motors for HV switchgear
110V DC, unearthed (from UPS)
Electrical control of HV motor starters (contactor feeders)
110V DC, unearthed (from UPS)
Electrical control of 400V motor starters
230V, 1 ph, solidly earthed
-
Fig. 1 - Key SLD with EDGs (Reference: SYG-PSH-04-EL-SLD-0001)
400A 400A 400A 400A 400A 400A 400A 630A
Bus A Earth
Switch
N/C
2000A
Bus E Earth
Switch
HV PF Improvement
Cap. Bank (1600 KVAR)
56" E
xpor
t
Gas
Pipeline
OHLSpare
For T
MG
(100
0 kV
A) M~M~
Mot
or F
eede
r
up to
1.6
MW
(Typ
)
Mot
or F
eede
r
abov
e 1.
6 M
W
(Typ
)
400A
M~
Mot
or F
eede
r
up to
1.6
MW
(Typ
)
400A400A400A400A
X1
400A
Spare
For T
MG
(100
0 kV
A)
400A
HV PF Improvement
Cap. Bank (1600 KVAR)
M~
M~
400A 400A 630A 400A 400A
Mot
or F
eede
r
abov
e 1.
6MW
(Typ
.)
Mot
or F
eede
r up
to 1
.6M
W (T
yp.)
Bus B Earth
Switch400A400A400A400A400A400A
Spare
ATS
For T
rans
form
er
Spar
e
For O
HL
Spar
e
220 kV Two Single Circuit
Overhead Line (OHL) to
CNPC (CPF-2)
220 kV Two Single Circuit
Overhead Line (OHL) from
Turkmenenergo 220 kV MARY
SPS Switchyard for CPF-1
220 kV Two Single Circuit
Overhead Line (OHL) for Power
Supply DevelopmentG GTG-1
400A
12.5/16 MVA
35/10.5 kV
Bus BBus E
Bus A
Motor
Feeder for
GTG starting
Motor Unit
Transformer
12.5/16 MVA
35/10.5 kV
GG
EDG
3.32 MW
10 kV
EDG
3.32 MW
10 kV
10 kV Switchgear
91-SS01-ES01
Loc: CPF-1 Main SS (04-SS01)
2SB101
Loc: SS-503
Inst. & SS Building-1 CPF-1A
35 kV GIS CB. 91-SS01-EP03
Loc: CPF-1 Main SS (04-SS01)
35 kV GIS CB. 91-SS01-EP02
Loc: CPF-1 Main SS (04-SS01)
Loc: 220 kV Switchyard Control Room
220 kV Air Insulated
Outdoor Switchyard
Loc: CPF-1, Switchyard
35 kV GIS 91-SS01-EP01
Loc: CPF-1 (Main SS) 04-SS01
15 kV
128.8 MW 0.8 PF
Transfer Bus
15/0.42 kV
Dyn11.
1.2 MVA
10/0.42 kV
Dyn11.
1.2 MVA
Main Bus II
Main Bus I
Generator
Transformer
230 kV/181 MVA
400V Aux. Switchboard
For 220 kV Switchyard
BAY 1 BAY 2 BAY 11 BAY 12 BAY 3 BAY 4 BAY 8 BAY 7 BAY 5 BAY 6 BAY 3 BAY 9 BAY 10
To GTG
Aux. MCC
1.2 MVA
Transformer
220/36.6 kV
100/125 MVA
Transformer
Bus Transfer
Bus Coupler
-
2.2 Power Distribution
Electrical power is supplied to the Turkmen Gas field from Mary SPS 220kV
grid by 2 single circuit overhead lines of 65km length. The outdoor 220kV, 3
phase, 3 wire switchyard has 13 bays including 2 Nos OHL incomer bays from
Mary SPS, 4 Nos outgoing OHL feeders of 2 each for CPF-2(CNPC) & future
development, 4 Nos outgoing transformer feeder for CPF-1 & CPF-
1A(Hyundai), 1 No GTG Incomer, 1 No Bus coupler and 1 No Bus Transfer
breaker
220kV OHL outgoing feeder conductors are terminated on the primary side of
the 100/125MVA 220/36.5 kV Transformers 91-SY01-ET01A/B (CPF-1) & 91-
SY01-ET02A/B (CPF-1A). Secondary side 35kV cables of the transformers of
CPF-1 are terminated at 35kV GIS Switchgear 91-SS01-EP01 and 35kV cables of
the transformers of CPF-1A are terminated at 35kV GIS Switchgear 91-SS01-
EP02 & EP03. Further distribution from 91-SS01-EP02 & EP03 are taken care by
Hyundai.
The Electrical energy required for the operation of the facility is met from the
Grid power during normal course of time. When grid fails or as and when
required by the authorities, the energy is supplemented by the Gas Turbine
Generator (GTG).
During Mains failure, the Emergency Diesel Generators (EDG) kept in standby
mode will automatically come in line and feed all the emergency services as
well as auxiliary power to GTG. As and when Grid/GTG power is available, the
power will be restored and EDGs will be kept in standby mode
The power is stepped down distributed within the facilities at 35kV,10KV and
400 Volts voltage levels. The electrical system at the facility includes
transformers, GTG, motors, switchgears, UPSs, EDGs, electrical heaters, heat
tracing, cathodic protection, PF improvement capacitors, lighting & power
distribution.
In the facility soft starters are provided for large motors (400V motors above
100kW and 10kV motors above 1000kW) to avoid voltage dips in the system
and to avoid heating of motors during starting.
GTUs 5,6,7 & 8 located farther from the CPF-1 are powered through 35kV OHL
from the CPF-1 Main SS, 04-SS01. 35kV is stepped down to 10kV at GTU and
feeds power to connected well heads as well as GTU. Well heads are
-
connected through 10kV OHLs and at GTU 10kV is further stepped down to
400V and distributed. A 350kVA 400V EDG installed at each GTU meets the
emergency power requirement of respective GTU
56 Export pipe line power requirements are met through 10kV OHLs powered
from Main SS, 04-SS01, 91-SS01-ES01 10kV switchgear
At Well heads and export pipe lines, 10kV is stepped down and distributed at
400V and do not have any EDGs
For centralised monitoring and control of electrical systems, IPCS and ENMS
are installed. IPCDs mounted on the electrical feeders are interfaced with
IPCS/ENMS. The interface between IPCS/ICSS provide control and operation of
process feeders from CCR
2.3 Switchgears
Switchgears ranging from 220kV, 35kV, 10kV, and 0.40kV are installed in the
facilities. Except 220kV, all the switchgears are indoor and metal enclosed.
220kV switchgears are outdoor type AIS with SF6 circuit breakers. 35kV
Switchgears at CPF-1 are Gas Insulated (GIS) and at GTUs are Air Insulated
(AIS). 10kV switchgears are AIS type.
35 and 10kV circuit breakers are draw out type. Earthing switches are
provided in incoming and outgoing circuits. Suitable mechanical Castell
Interlock keys are provided to ensure that the circuits are isolated before
closing earthing switches and to ensure opening of earthing switches before
energising the circuits.
400V Switchgears are metal clad, fully withdrawable and double front (single
front panels with back to back arrangement) panels. Incomers are either ACBs
or MCCBs based on the rating and outgoing isolation is provided by MCCBs.
HV/LV Incomers, Bus sections and Outgoings are fitted with Intelligent
Protection Control Devices (IPCDs). IPCDs are programmable and have
communication facilities with IPCS/ENMS/ICSS for remote control and
operation. Interface between IPCS/ICSS enable the control of process feeders
from CCR. . Interface between IPCS/ENMS enable the control of switchgear
incomers/bus-sections from SS01.
-
2.4 Gas Turbine Generator (GTG)
The Gas Turbine Generator installed in the facility is for standby purpose and
is designed to the meet full load requirement of both CPF-1 & CPF-1A. The
15kV, 116MW, 0.8PF GTG is connected to the 220kV switchyard through a unit
step up generator transformer of 220/15kV, 115/165MVA. GTG control system
is designed operate the GTG either in parallel with the Grid or in islanded
mode. When running in parallel, the control system will allow set point
control of GTG output power.
GTG is a self contained complete package generating set and equipped with
necessary protection, control and monitoring. GTG can be operated either
from CCR remote GTG HMI (Remote- OWS) or from the local TCC HMI (Local
UCP). Also local control permits operations such as commissioning, trouble
shooting and maintenance. Operating Set points of the GTG can be
programmed from the GTG HMI
The 220kV switch yard has two main bus and one transfer bus. During normal
operation GTG & the feeders of CPF 1/1A are connected one main bus II. The
other bus (main bus I) is connected with the Grid incomers and third party
feeders. The 220kV bus-tie breaker will be normally closed.
2.5 Transformers
Transformers with ratings are used in the facilities. Primary side of all the
Transformers are connected through cables and secondary through cable/bus
duct based on the ratings. Transformers are provided with Inter-Trip and
necessary protection schemes. Operation and control part is discussed in the
subsequent section.
Except Main intake transformers at 220kV yard and GTU transformers, all the
other transformers are fitted with Off Circuit Tap Changing (OCTC) facility.
220/35kV Main intake transformers and 35/10.5kV step down transformer at
GTUs have On Load Tap Changing (OLTC) facility. The Remote Tap Changer
Control Panel (RTCC) for each transformer located in the SS operates the
motorised tap changing mechanism fitted on the transformers. Voltage
regulator equipped in the RTCC compares the transformer secondary voltage
with the set value and sends the signal, if the voltage is different from set
value, to the tap operating mechanism to increase or decrease the taps to
maintain the desired secondary voltage. RTCC has got
Master/Follower/Independent selection modes to operate in line with the
-
other transformer. This is also fixed with Local/Remote selection and Local
mode allows the operation taps in the transformer bay. Tap changing
mechanism can also be operated manually by the Handle exclusively provided
for this. Mechanical as well as Electronic tap position indicators along with
Voltage display in local and remote indication facilities are provided.
Main intake Transformers being Star/Delta connected, as the neutral is not
available for earthing, the earthing is derived through Zig-Zag transformer.
The star point of the Zig-Zag transformer in turn is earthed through Resistor.
All the other transformers have star connected secondary windings and their
neutrals are earthed either through resistors or solidly grounded.
2.6 Motors
10kV & 400V, 3phase and 230V single phase motors are used in the facility and
are of squirrel cage induction motors. Motors less than are equal to 0.18 kW
are supplied from 230V power supply. Motors above 0.18kW and less than or
equal to 150kW are 400V, 3 phase motors. Motors above 150kW are 10kV
motors. 400V motors above 100kW and 10kV motors above 1000kW are
provided with soft starters and the others are DOL type. 10kV motors with soft
starters and above 1600kW are VCB controlled or otherwise controlled with
Fuse & vacuum contactors. VSDs are provided for specific motors
LV motors are controlled and protected through MCCB/soft starters/VSDs.
MCCBs provide protection against S/C & O/L. Additional protections include
Thermal Image O/L, phase imbalance, Sensitive earth fault for motors above
30kw and locked rotor protection for EEx-e motors
HV motors are provided with MPR with CBCT and motors above 1600kW are
provided with differential protection.
Motors can be controlled locally through MCS, located adjacent to the motor.
Remote control of motor from ICSS is possible only when Auto mode is
selected in MCS. MCS selector switch is having OFF-AUTO-ON selection and
OFF position is lockable. Selector switch is having spring facility to return to
Auto mode from ON position when operator removes his hand.
IPCDs on the motor starter enables the motor to monitor/control from ICSS
through IPCS. ESD trip signals hardwired from the ICSS/ESD.
-
2.7 UPSs
110V DC UPS system is connected to Electrical Switchgear controls. DC UPS
consists of one set of battery, two sets of chargers and one set of integral DC
DB. One charger is supplied from normal power and other charger is input is
fed from emergency supply.
240V AC UPS System is connected to IPCS, ENMS, ICSS, ESD, F&G and Telecom
System. AC UPS systems consist of 2 set of single UPS with bypass supply and
battery. Normally the bypass input is fed from normal supply and the inverter
input is fed from Emergency Switchgears which in turn are fed from EDGs.
400V UPS is with 3 Phase output and is used for Emergency and Escape
Lighting in the CPF-1.This consists of single UPS with bypass supply and
battery
48V DC UPS system is exclusively used in the 220kV yard for PLC and RTU
applications
Batteries of all the UPS are located in a separate ventilated room with MCCB
isolation. All the UPS have integral DB at their output. UPSs having dual input
are fed normal and emergency switchgears. Emergency switchgears in turn are
fed by EDGs during Mains failure.
2.8 Essential Diesel Generators (EDG)
The Essential Power requirement at CPF-1 is met by 2 Nos. 3.32MW, 10kV, 50%
rated EDGs. Apart from essential process loads, Instrument Air Compressors,
GTG starting motor, GTG auxiliary supply, fire water jockey pumps,
emergency and escape lightings, UPSs and essential HVAC units are other
essential loads connected with the EDG switchboards.
All GTUs and Rotational camp have their exclusive 400V, 350kVA EDGs
connected to their respective switchgears.
EDGs on Auto mode will start against Mains failure have Auto/Manual
provisions for Changeover, Synchronising, Mains restoration along with Test
Trial Run facilities.
2.9 Lighting
Apart from general plant and indoor lighting, essential and emergency/escape
lightings are provided. Essential lightings are fed from EDGs.
Emergency/escape lights are fed from lighting UPS or in-built battery backup.
-
2.10 Electrical Heat Tracing / Heaters
Heat tracing avoids condensation of process gas in the pipelines and
Instrumentation and maintains the temperature as specified in the design.
Heating is carried out with Self regulating heat tracing cables with line sensing
thermostats. Heaters operate at 230V AC supply and distributed through
respective Distribution Boards. Part of the heat tracing circuits are fed
through Emergency DBs based on the requirement
Electrical heaters installed in the facility are either controlled through
contactors or thyristor. Heaters have hardwired control from ICSS and
additionally thyristor heaters have 4-20mA set point control
2.11 Power Factor Improvement
As system power factor need to be maintained at 0.98 lagging, PF
improvement capacitors are installed in the facility. Both 10kV & 400V
capacitors are installed in the facilities. 10kV Capacitors are outdoor type and
IP54. Ratings above 500kVAR will have two step control through APFC
controller.
LV capacitors have multiple step controls and are indoor type and IP41. Once
again step control is achieved through APFC controllers.
2.12 IPCS/ENMS/SCADA
For centralised monitoring and control of electrical systems, IPCS and ENMS
are installed. IPCDs mounted on the electrical feeders are interfaced with
IPCS/ENMS. The interface between IPCS/ICSS provide control and operation of
process feeders from CCR
35 kV, 10kV and 400V Switchgear incomers and bus tie can be controlled
either locally in front of the panel or remotely through ENMS OWS. For ENMS
operation, the remote mode shall be selected on the switchgear
TurkmenEnergo will control the 220kV switchyard CBs through SCADA. GTG
incomer and bus tie CBs will be controlled from GTG UCP
2.13 Cathodic Protection
To prevent corrosion of the buried pipelines, tanks, vessels and structures,
Cathodic protection is installed throughout the plant depending on the
requirement.
-
CP system is designed and installed considering site condition, soil resistivity,
service (water, hydro carbon etc.), MOC, Interaction and Induced effects from
foreign service crossings, parallelisms and buried/overhead transmission
electrical power lines.
The two main types of CP are Impressed Current and Sacrificial Anode.
Impressed Current CP requires continuous power from the mains which in
turn, stepped down through transformers and converted into DC through
rectifiers and connected. Sacrificial anode requires no power.
Infield & export pipe lines and tank external surfaces are protected by
Impressed Current Cathodic protection. Mix of both Impressed and Sacrificial
anode CP are used in in-plant buried pipe lines, hydrants and tank internals
Temporary CP using sacrificial anode system is installed while laying the
pipelines and will be disconnected while commissioning the Permanent CP
system using Impressed Current.
-
3.0 GENERAL SCOPE OF COMMISSIONING PROCEDURE
The section provides basic information, guidance and support documents to
carryout commissioning activities of the electrical system including HV/LV
switchgears, transformers, cables, motors, VSDs, UPS, distribution boards and
lighting system.
During the pre-commissioning , all the equipment are tested and prepared to
keep in a condition ready for commissioning.
During Commissioning, the Equipment, Systems and Units are prepared for
Ready for Startup (RFSU) and this will be in a sequence that supports the
facilitys Startup schedule.
Commissioning includes activities that enable systematic and safe introduction
of power supply into the electrical system and verification of performance
parameters with the intended design, such as checks on Voltage, Phase
sequence, Man Machine Interfaces, Automatic Changeover scheme, IPCS/ENMS
and IPCS/ICSS interfaces.
-
4.0 GENERAL HEALTH, SAFETY AND ENVIRONMENT CONSIDERATIONS
4.1 General
HSE assurance is provided by identifying and managing HSE risks, according to
the principles of risk tolerance, risk reduction and continuous performance
improvement. All employees are responsible for complying with the TMG
Safety Guidelines. Safe work practices are discussed and followed prior to
starting any activity
4.2 Compliance
All personnel familiarise themselves with the safety rules and guidelines
provided in TMG HSE guidelines.
4.3 Health Hazards
Shock and Fire/Explosion Hazards
Mitigate possibilities of the hazards by following correct procedure, systemic
approach and by using correct PPE and additional PPE:
Eye: Handling Electrolyte of the batteries may cause physical damage
Skin Contact: Contact with Electrolyte may cause irritation and burns of
exposed area.
Contact with Hazardous Voltage: Contact with live electrical parts can cause
mild shock to fatality, depending on path of the current flow through the body
and other factors such as sweat, moisture, body resistance, level of voltage
etc.
First Aid
Eye: Wash thoroughly with water immediately. Repeat as needed till the
irritation subsides. If irritation persists, consult medical personnel.
Skin Contact: Wash with clean water till the irritation or pain subsides.
Contact with Electric Voltage: Isolate power supply, remove the victim from
the equipment contact and perform first aid if needed, call for medical help
Systemic and Other Effects: Mild shock, burns, shivering, de-hydration and
fatality
Personnel Protection
-
Eye Protection: Safety glasses with side shield should be worn and eye wash
arrangements should be available.
Skin Protection: Acid resistant gloves, Apron, Boots.
Protection Equipment (for Electricity): Depending on the voltages, Gloves,
Boots, insulation mats, voltage detectors, insulated tools, etc., are
recommended to be worn and used.
4.4 Environment
The Electrical substations, GTG, EDGs, Switch yards and the surroundings shall
be well protected, clean and dry.
4.5 Pre-start Safety Checks
Before starting any activity the minimum required safety checks are followed
and approval from the supervisors/Engineers and relevant inter discipline
engineers is obtained.
Prior to any electrical activity, ensure the following safety items in place:
1. Safety signboards
2. Escape route markings
3. Emergency exit lighting
4. Electrical emergency safety equipment
-
5.0 COMMISSIONING PROCEDURE
Commissioning involves energisation of electrical equipment and system.
Commissioning is to be taken up only after the completion pre-commissioning
activities. The procedure outlined in the following sections describes activities
involved during commissioning
Commissioning includes test preparation, energisation and demonstration as
explained below:
A. Test Preparation
The individual equipment or components such as switch gears, cables,
transformers etc., of the electrical system considered for commissioning are
already tested during pre-commissioning whereas the commissioning test
preparation is the preparation of the electrical system as a whole with its
interfaces, controls, interlocks, etc.
The test preparation may include the following depending on the position of
the system in the overall electrical system:
1. Preparation of safety equipment
2. Preparation of test equipment and tools
3. Isolation and locking of outgoing feeders of the equipment
4. Energisation of control circuits
5. Energisation of the upstream side of the equipment
B. Energisation and Demonstration
After the system is made ready for its first energisation, the equipment will be
energised following a detailed step-by-step procedure which is included in this
procedure or the one that is provided by the manufacturer/vendor. The
electrical equipment is energised for the first time and kept energised for a
significant period so that any abnormality may be discovered and problems
identified may be rectified.
After the equipment is energised, the live testing of the system commences.
The live test sequence is provided below:
1. Check the voltage presence and value
2. Check all controls on the equipment
3. Check interfaces and indications
4. Check the phase sequence of the supply voltages, where applicable
-
5. Verification of the main equipment (example: Transformers) of the
Electrical Distribution System for its mechanical aspects by monitoring and
taking required readings during soaking period after energisation.
a. Noise
b. Equipment vibration
c. Oil leaks, where applicable
d. Temperature readings
5.1 Test Preparation/Prerequisite
The following are the prerequisites of the equipment and system:
1. Ensure the availability of competent and authorised Commissioning
Engineer for the activities
2. Ensure that all the required documents such as marked-up drawings,
PetroPCS-B check sheets, etc., are available.
3. Ensure that the available documents are the latest "As built" mark-
ups/Latest revision.
4. Ensure that safety and fire fighting systems are ready for use.
5. Barricade the area with barrier tape and place warning signs to prevent
entry by unauthorised personnel.
6. Ensure that the required Isolation Certificates, Limitation-of-Access and
Sanction-for-Test are obtained specific to the equipment.
7. Ensure availability of Approved switching program for Electrical Switching
Activity
8. Ensure that the Electrical Permit to Work is obtained,
9. Ensure that the TRA is complete and available for the activities
10. Conduct Tool Box Talk prior to the commencement of activities for the
day.
11. Ensure that the surroundings and the equipment are clean, tidy and are
accessible without any obstruction.
12. Ensure that the radio and alternate communication is available.
13. Ensure that the earthing system testing is complete
14. Ensure that the Control and auxiliary power supplies are available
15. Ensure that the temporary power for auxiliary/control, essential lighting
and HVAC are available
5.2 Tools and Test Equipment Required
1. Megger 500V, 1000V, 2500V, 5000V (AC/DC)
2. Multimeter
-
3. Clamp meter for AC/DC Current measurement
4. Phase rotation meter
5. Galvanometer
6. Arc Flashing Jacket Kit (If applicable in PTW)
7. Hot stick
8. IR Temperature Gun
9. Insulated hand tools, Rubber gloves
10. 3 Phase, 400V AC Supply
11. Lux meter
12. Electrical discharge device
5.3 Control and Auxiliary Power Supplies
220kV, 35kV, 10kV, 400V switchgears control & protection
110V DC
Electrical control of HV motor starters- Contactor feeders
110V DC
Spring Charging motors of HV switchgear 110V DC
400V motors feeder controls 230V AC
Switchgear anti-condensation heating, cubicle lighting
230V AC
IPCS/ENMS 230V AC
ICSS, ESD, F&G and other vital Instrumentation 230V AC
Communication systems 230V AC
Switchgear control supply 110V DC is supplied by 110V DC UPS system.
230V/400V auxiliary supplies are derived from Substation Miscellaneous DBs.
IPCS/ENMS/ICSS/F&G/ESD/Instrumentation and Telecom are powered from
230V AC UPS.
Along with the above, Lighting and HVAC DBs need to be initially energised
with temporary power supply in the respective substations to enable
commissioning of the electrical distribution systems.
The above equipment will be switched over to normal power supply after the
commissioning of the upstream side equipment is completed. With the normal
power supply, the above equipment has to be fully commissioned and
functionalities have to be demonstrated as per the relevant procedures.
5.4 Vendor Commissioning Assistance
Vendor commissioning assistance may be utilized for commissioning the
following systems:
-
220kV switchyard
Switchgears and MCC
Protective Relays
Power Transformers
UPS / Battery System
Soft starters/VSDs
Emergency Diesel Generator
Gas Turbine Generator
5.5 Energisation of UPSs
UPSs and DBs provide control and auxiliary power supply to the Switchgear.
These systems need to be commissioned prior to the main equipment of the
substation. These systems are already commissioned using a temporary source
of power supply in order to make the upstream side equipment available.
When the normal power switchgear which are going to feed the UPSs/DBs are
ready, re-commissioning of UPS shall be carried out as per the vendors
procedure having completed the necessary checks.
Note:
Commissioning of the UPS system will be with the vendors support.
Commissioning reports and checks shall be as per the vendor formats.
UPSs with dual input power supply and bypass supply shall be tested for their
operability while re-commissioning.
Interface facilities with IPCS/ENMS/ICSS shall be verified.
A. DC UPS
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed
2. Carryout Megger test on the system before energising
3. Ensure that all checks required as per vendor commissioning procedure are completed
4. Switch on the feeders on Incoming power supplies to rectifiers and verify voltage and phase rotation
5. Check indications/meter readings/alarm/abnormal noise/temperature
6. Ensure operation of Unit Cooling Fans
7. Energise the DC Distribution Board
-
B. AC UPS
The following AC UPS is to be commissioned. Ensure that the pre-
commissioning activities are completed before taking up commissioning.
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed
2. Carryout Megger test on the system before energising
3. Ensure that all checks required as per vendor commissioning procedure are completed
4. Switch on the feeders on Incoming power supplies to rectifiers and verify voltage and phase rotation
5. Check indications/meter readings/alarm/abnormal noise/temperature
6. Ensure operation of Unit Cooling Fans
7. Switch ON Inverter and check output Voltage & Frequency
8. Check Inverter synchronism and by-pass modes
9. Energise the AC Distribution Board
5.6 Energisation of Distribution Boards
Distribution boards are tested during the pre-commissioning phase itself and
further following shall be ensured before energizing the DBs.
A. Lighting (Normal & Essential) DBs
The Lighting Distribution Boards are commissioned following the steps, after
completing pre-commissioning activity of the system.
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed
2. Carryout Megger test on the system before energising
3. Ensure arrangement of lighting fixtures/sockets against approved drawing.
4. Energize the Distribution Board.
5. Verify all lighting fixtures are working/verify correct voltage and phase sequences in the sockets.
6. Check and record lighting intensity level and lighting projection points.
7. Simulate and check the operation of timers/photocell switches (as applicable).
8. Allow Emergency and escape lighting (in built battery fixtures) for initial charge, disconnect the supply and verify the operation of lighting fixtures.
-
B. Miscellaneous Power & HVAC DBs
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed.
2. Carryout Megger test on the system before energising.
3. Energize Distribution Board.
4. Ensure Indicating lamps are working
5. Verify correct voltage and phase sequences.
6. Ensure DB ON status at IPCS/ENMS/ICSS
C. Heat Tracing & MOV DBs
The Heat Tracing and MOV Distribution Boards are commissioned following the
steps, after completing pre-commissioning activity of the system.
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed.
2. Carryout Megger test on the system before energising.
3. Energize Distribution Board.
4. Ensure Indicating lamps are working
5. Verify correct voltage and phase sequences.
6. Ensure DB ON status at IPCS /ENMS/ICSS
7. Ensure Atmospheric thermostat is connected and set for Automatic operation of Heat Tracing
8. Ensure Auto/Manual/Off selector function is working properly for Heat Tracing
9. Ensure ON status at IPCS for each MOV outgoing feeder
10. Ensure Space heater is working
11. Ensure Indicating lamps & measuring circuits are in order
5.7 Power Cables
All the HV/LV/Control Cables are tested during pre-commissioning phase itself
and further they may be ensured for the following:
Step Actions Sign/Date
1. Ensure that all the cables are tested and relevant ITRs are available
2. Ensure that the tests specific to 220kV cables are carried out before energising
3. Ensure all the 35kV, 10kV HV Power cables are tested
-
Step Actions Sign/Date
4. Ensure that the control cables are checked
Note:
Commissioning of the 220 kV Cables will be with the vendors support.
5.8 Emergency Diesel Generators
Following are the Emergency Diesel Generators (EDGs) installed in the facility
Location Rating EDG Tag Number
Downstream Switchgear Tag
Number
CPF-1 10kV, 4.15MVA, 50Hz 99-SS01-EG01 91-SS01-ES01, Bus E
CPF-1 10kV, 4.15MVA, 50Hz 99-SS01-EG02 91-SS01-ES01, Bus E
GTU-5 400V, 350kVA, 50Hz 99-SS51-EG01 91-SS51-EL01, Bus C
GTU-6 400V, 350kVA, 50Hz 99-SS61-EG01 91-SS61-EL01, Bus C
GTU-7 400V, 350kVA, 50Hz 99-SS71-EG01 91-SS71-EL01, Bus C
GTU-8 400V, 350kVA, 50Hz 99-SS81-EG01 91-SS81-EL01, Bus C
Note:
Commissioning of EDG will be with the vendors support. Commissioning
reports and checks shall be as per the vendor formats.
-
Fig. 2 - Key SLD with EDGs at CPF-1 (Reference: Key SLD SYG-PSH-04-EL-SLD-0101 CPF-1 Main S/S)
Motor Feeder
M~
M~
M~
Power
Feeder
Power Factor
Improvement
Capacitor Bank
Motor Feeder
Power
Feeder
Motor Feeder
Power
Feeder
Power Factor
Improvement
Capacitor Bank
NC
BUS A10kV
91-SS01-ES01
91-SS01-ET01A
35/10.5 kV
12.5/16 MVA
NO NC
BUS B BUS C
ATS+AMF
G~
G~
ATSATS
NC
91-SS01-ET01B
35/10.5 kV
12.5/16 MVA99-SS01-EG01
10 kV, 4150 kVA
99-SS01-EG02
10 kV, 4150 kVA
Power
Feeder
Power
Feeder
NO NO
-
Fig. 3 - Key SLD with EDG at GTUs Typical (Reference: Key SLD SYG-PSH-04-EL-SLD-0534 GTU-5)
Motor Feeder
M~
M~
M~
M~
M~
Power
Feeder
LV Power
Factor
Improvement
Capacitor Bank
Motor Feeder
Power
Feeder
VFD FeederMotor Feeder
Power
Feeder
VFD FeederLV Power
Factor
Improvement
Capacitor Bank
G~
MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB MCCB
NCNC
BUS A400V
91-SS51-EL01
91-SS51-ET02A
10/0.42kV, 1.6 MVA
91-SS51-ET02B
10/0.42kV, 1.6 MVA99-SS51-EG01
350 kVA, 400V EDG
NO NC
BUS B BUS C
ATS
-
EDGs are tested and commissioned during pre-commissioning phase itself and
further they may be ensured for the following
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed.
2. Ensure that all the piping, valves and instruments in the system are lined up.
3. Ensure that IPCS/ENMS/ICSS/F&G system are in line and functional.
4. Ensure system is free from leaks and spillage.
5. Breathing and draining devices are satisfactory.
6. Ensure that gas/flame/heat detectors are fixed and connected properly.
7. Switch on auxiliary and control power supply.
8. Ensure that the control/starting battery (starting battery is only for GTU sets and CPF-1 EDGs are Air start) is getting charged
9. Ensure that all Electrical, Instrumentation, other controls and protections are in order and lined up.
10. Ensure that all the safety controls such as thermostats, engine governor, automatic voltage regulator and protections are set to their values and tested.
11. Select the manual mode
12. Set the Governor just above the idle speed
13. Set the excitation to minimum
14. Give the start command from the engine control panel
15. Air motor (CPF-1 EDGs) / Battery (GTU EDGs) cranks the engine and engine picks up speed and runs at idle speed
16. Observe all the parameters such as speed, vibration and temperature
17. Observe any abnormal noise from the engine
18. If satisfied, increase the speed slowly up to normal speed (1000 RPM for CPF-1 EDGs & 1500 RPM for GTU EDGs) and monitor continuously.
19. Increase the excitation gradually and record alternator voltage versus excitation current to conduct open circuit tests.
20. When the engine reaches operating speed, observe other parameters including the above and additionally voltage, current, frequency, etc.
21. Check the phase rotation with the grid
22. If required, adjust AVR for voltage adjustment and speed for frequency
-
Step Actions Sign/Date
23. Switch on the loads with 25%, 50% and 75% each with 15 minutes duration and record all the parameters
24. Connect 100% load and observe for 4 Hrs and record all the parameters
25. Check ventilation and CB interlocks
26. With the maximum load on the engine, leaving cushion for the highest rated motor to start, start the highest rated motor and observe.
27. Connect 110% load and observe for 1 Hr and ensure that the parameters are within the limits.
28. After restoration of power, switch off the EDG.
29. Check the timing for auto start, auto close of EDG CBs, Interlock between EDG & Mains CBs, auto Mains restoration and auto stop of EDGs.
30. Check synchronisation between the EDGs, Grid synchronisation ( as applicable)
31. Check interface at IPCS/ENMS/ICSS
5.9 Commissioning of 220kV Switchyard
220kV Switchyard commissioning is package vendors scope and following may
be ensured prior to energising.
5.9.1 Switchyard Configuration
Description Quantity Bay Nos. Normally
Connected to
Bus sections Main Bus I, II & Transfer Bus
- -
Grid Incomers OHL-3 & 4 5&6 Main Bus I
220kV 3rd party OHL O/Gs OHL1 &2 1&2 Main Bus I
220kV Future OHL O/Gs OHL-5 &6 9&10 Main Bus I
220kV O/Gs 2 Nos CPF-1 3&4 Main Bus II
220kV O/Gs 2 Nos CPF-1A 11&12 Main Bus II
GTG Incomer 1 No 13 Main Bus II
Bus Coupler 1 No 8 Normally Closed
Bus Transfer 1 No 7 -
-
Fig. 4 220 kV Switchyard (Reference: SYG-PSH-04-EL-SLD-0001)
-
5.9.2 Pre-energisation Checks
Step Actions Sign/Date
1. Ensure that all the isolators are checked and available for operation
2. Check and confirm that the incomer breaker is ready and its spring is charged.
3. Ensure that earthing connections have been reinstated after the pre-commissioning tests.
4. Ensure that the busbar earth switch, bus coupler earth switch and cable side earth switch are kept open and locked with safety pad lock (wherever applicable).
5. Ensure all outgoing feeders of the 220kV yard are isolated and locked.
6. Ensure that the upstream side equipment is commissioned and is ready to energise the downstream equipment.
7. Ensure that the CT shorting links are reinstated after the pre-commissioning test; ensure that connections are tight.
8. Ensure that the protection relays and their settings are correct.
9. Ensure that all Voltage Transformer fuses are healthy and the earth connections are correct
10. Ensure that the control and auxiliary power supply 110V DC/48V DC/400V AC are available.
11. Ensure that the PLCC & Teleprotection panels are lined up for the OHL feeders
12. Ensure that communication systems, SCADA & RTU, relay protection and emergency control systems between CPF-1 220kV switchyard and Mary SPS, Maryenergo & Turmenenergo are ready as applicable
13. Ensure that the communication between 220kV yard SCADA and ENMS are ready.
14. Ensure that the preparatory checks/steps given in vendor procedures and commissioning manual are carried out.
15. Ensure clearance from Mary SPS/Turkmen energo to enrgise the yard
16. Inform control room about the energisation
17. Keep all the other isolators, CBs in Off position
18. Ensure all the other isolators are open and not earthed
19. At every stages of energisation, observe for any abnormality and take corrective action as required.
20. Ensure availability of status indication of
-
Step Actions Sign/Date
Isolators/CBs at yard control room/ENMS for every operation
5.9.3 Order of Energisation
The following order shall be applied for initial energisation of the switchyard:
A. Energization of 220kV Switchyard
Energization of Switchyard Main Bus-I & Main Bus-II from OHL-3, OHL-4 & GTG (Single feeder to Switchyard as per the Procedure 5.9.4).
Energisation of 220kV switchyard through OHL-3
1. Dead bus closing to Main Bus-I
2. Dead bus closing Bus coupler to Main Bus-II
3. Dead bus closing to Transfer Bus
4. Open Transfer Bus CB
5. Open OHL-3 CB
Energisation of 220kV switchyard through OHL-4
1. Dead bus closing to Main Bus-I (As Bus coupler already closed, Main
Bus-II also gets energized)
2. Open OHL-4 CB
Energisation of 220kV switchyard through GTG
1. Dead bus synchro to Main Bus-I (As Bus coupler already closed, Main
Bus-II also gets energized)
2. Open GTG CB
3. Open bus coupler
B. Energization of Switchyard with OHL-3, OHL-4 and Synchronizing with
GTG (as per Procedure 5.9.5)
1. Dead bus closing to Main Bus-I through OHL-3
2. Closing OHL-4 after synchro check with OHL-3
3. Start GTG and energise Main Bus-II
4. Synchronize GTG with Main Bus-I through Bus-coupler
5. Switch Off GTG and keep in standby
6. System is ready
C. Energization of Switchyard outgoing feeders with OHL-3 & OHL-4 (as per Procedure 5.9.6)
1. Ensure Transformers are ready for energisation
2. Energise Transformers one by one
-
3. Energise OHL bay -1&2 only after obtaining approval and switch off
when not required
4. Energise OHL bay - 5 &6 only after obtaining approval and switch off
when not required
5.9.4 Energization of Switchyard
Energization of Switchyard Main Bus-I through OHL-3, OHL-4 & GTG (Single
feeder to Switchyard) and ensure clearance for energizing.
Step Actions Sign/Date
A. Energization of Switchyard Main Bus-I through OHL-3
1. Confirm that all the Pre - energisation checks are completed as per relevant section of section 5.9.2
2. Carryout Megger test on the system before energising
3. Check for presence of 110V DC/48V DC/400V AC control supply to the control circuits.
4. Ensure that communication systems, telemetry, relay protection and emergency control systems between220kV switchyard and Mary SPS, Maryenergo & Turmenenergo are ready as applicable
5. Ensure that the inter panel wiring, Metering panel, Control panel, Relay panel, PLC Panel, SCADA Panel wiring are tested
6. Ensure that all the Isolators, CBs and Earth switches are open
7. Check that the indication lamps are healthy by using Lamp Test Switch.
8. Ensure that the close/open interlocks of all the isolators, CB and earth switches are tested and verified
9. Ensure that the closing spring of the CB of OHL-3 is charged
10. Ensure that all the conditions required for closing the CB of OHL-3 are satisfied
Bus-I not earthed
CB Mechanism healthy
Protective relays are healthy
Line & Bus earth switches are open
Trip & Closing coil supervision circuits are healthy
Ensure trip from Distance protection, Backup distance protection and line differential are not active
Ensure carrier inter trip protections are not active
-
Step Actions Sign/Date
Ensure bus bar protection is not active
Ensure no Phase Under Voltage is active
11. Ensure all checks recommended by the vendor for energization of the yard are completed.
12. Check with upstream CB for close permissive/inhibits/Inter trip as applicable
13. Check CB tripping by Remote through SCADA
14. Ensure that the Surge arrestors, CVTs & Line traps are lined up and yard is ready to receive the power
15. Ensure availability 220kV Power supply from Mary PP-1
16. Switch ON the MCBs for OHL-3 and Main Bus-1 to get 110V AC PT voltage to metering and protection.
17. Check presence of voltage on all three phases on Metering and Protective Relays
18. Check Phase sequence from line VT secondary three phase voltage and record (Normal/Clockwise)
19. Turn OHL-3 CB selector to S 453 to Local position
20. Ensure synchro permissive from distance relay
21. Close the Isolator Q9 of OHL-3 and observe for any abnormality
22. Close the Isolator Q1 of OHL-3
23. Close OHL-3 Circuit Breaker Q0 through S0 and this energises Main Bus-I and observe for any abnormality and carryout corrective action, if required
24. Check interface signals are correct
B. Energisation of Main Bus-II through Bus Coulper
1. Ensure Bus-coupler and Main Bus-II are ready for energisation
2. Close Main Bus-I VT Isolator Q3-A08 and availability of three phase Voltage and record phase sequence (Normal/Clockwise)
3. Close the isolator Q1-A08 of BC and observe for any abnormality
4. Close the isolator Q2-A08 of BC
5. Close the CB Q0-A08 of BC, energise Main Bus-II and observe for any abnormality
6. Close Main Bus-II VT Isolator Q3-A08 and availability of three phase Voltage and record phase sequence (Normal/Clockwise)
7. Check interface signals are correct
C. Energisation of Transfer Bus through Main Bus-1
1. Ensure that the Transfer Bus is ready for energisation
-
Step Actions Sign/Date
2. Close the isolator Q1-A07 and observe for any abnormality
3. Close the isolator Q7-A07
4. Close the CB Q0-A07, energise Transfer Bus and observe for any abnormality
5. Check Transfer Bus VT and availability of three phase Voltage and record phase sequence (Normal/Clockwise)
6. Check interface signals are correct
7. Open CB Q0-A07, then isolator Q1-A07 & Q7-A07 and de-energise the Transfer Bus
8. Earth the Transfer Bus through Earth Switch Q72-A07, later open earth switch
9. Open CB Q0-A08, then isolator Q1-A08 & Q2-A08 and de-energise the Main Bus-II
10. Earth the Main Bus-II through Earth Switch Q11-A08, later open earth switch
11. Open CB Q0-A05, then isolator Q1-A05 & Q2-A05 and de-energise the Main Bus-I
12. Earth the Main Bus-I through Earth Switch Q11-A05, later open earth switch
D. Energization of Switchyard through OHL-4
1. Follow steps 1 to 43 with respective Isolators & CB
2. Check the phase sequence and compare the same with OHL-3 phase sequence and ensure that they are same
E. Energization of Switchyard through GTG
1. Start GTG and ensure availability of Voltage
2. Follow steps 1 to 43 with respective Isolators & CB as applicable
3. Check the phase sequence and compare the same with OHL-3 phase sequence and ensure that they are same
5.9.5 Synchronizing Grid Mains and GTG
Grid Incomers paralleling and Synchronising with GTG requires prior approval
from Mary PP and Turkmen Energo. Grid incomers shall be tested and
paralleled later GTG shall be synchronised. Ensure that the GTG is already
tested and ready for energizing and loading.
Step Actions Sign/Date
1. Energise Main Bus-I through OHL-3 and record the VT phase sequence (Normal/Clockwise)
-
Step Actions Sign/Date
2. Record the VT phase sequence of OHL-4 (Normal/Clockwise)
3. Compare phase sequences of OHL-3 & OHL-4, across voltage on the same phase shall be zero and cross voltages between the phases shall be 110V
4. Ensure synchro check permissive through distance relay to close CB of OHL-4
5. Close CB of OHL-4 and observe for any abnormality
6. Run GTG and Energise Main Bus-II through GTG and record the VT phase sequence (Normal/Clockwise)
7. At Bus-coupler VTs compare Voltage and phase sequence of OHLs and GTG. Across voltage on the same phase shall be zero and cross voltages between the phases shall be 110V
8. Ensure synchro check permissive through distance relay to close CB of Bus-coupler
9. Close Bus-coupler CB and observe for any abnormality
10. Ensure that there is no abnormal circulation current at the bus-coupler ammeter
11. Switch Off GTG CB and connected Isolators and switch off GTG
12. Record all the details
13. Now the 220kV yard is ready for energising outgoing feeders and loading
5.9.6 Energization of outgoing feeders
Step Actions Sign/Date
A. Energisation of Transformer feeders
1. Main Bus-I is energised through OHL-3 & OHL-4 and Main Bus-II is energised through closed Bus coupler
2. Ensure that 220kV Yard is and ready and clearance available for loading
B. Energisation of Transformer feeder A-11 (CPF-1A HEC)
1. Ensure that the pre-energisation checks on Transformer is completed as 5.9.2
2. Ensure that the Transformer and connected downstream switchgear is ready to receive the power
3. Ensure that the secondary side CB and earth switches of the transformer are open in the switchgear
4. Close the isolator Q2-A11 and observe for any
-
Step Actions Sign/Date
abnormality
5. Close the isolator Q9-A11 and
6. Close the CB Q0-A11 and observe for any abnormality
7. Ensure that all the position indicators are correct with respect to actual position of the Isolators/Circuit Breakers
8. Ensure that the indicating lamps are showing the correct status
9. Ensure status indications of Isolators/CBs in SCADA/ENMS
C. Energisation of Transformer feeders A-12 (CPF-1A HEC), A-3&A-4 (CPF-1)
1. Repeat steps with respective isolators & circuit breaker of the concerned transformer
D. Energisation 3rd party outgoing OHL feeders
1. Energisation 3rd party outgoing OHL feeders is with Turkmen Energo and this is to be done as per their requirement
5.10 Transformers and Switchgears
5.10.1 Pre-Energisation Checks
A. General
The sequence of energisation of the equipment is listed below:
(The following commissioning description is shown for switchgear having two
bus sections and a normally open bus coupler. The same logic can be extended
for commissioning other type of switchgears by applying their respective
configurations. The pre-energisation checks applicable to Transformers shall
be followed to commission NETs)
Transformers with their respective NET/NER
Bus Section A
Bus Section B
Bus Coupler
B. Pre-energisation Checks on Transformers
Step Actions Sign/Date
1. Check and confirm that the oil level is correct in the conservator tank
2. Ensure that the upstream side panel is commissioned and the breaker is ready to energise the downstream
-
Step Actions Sign/Date
equipment
3. Ensure that the secondary side circuit breaker is isolated and locked
4. Ensure that earthing connections and NET/NER connections (where applicable) are reinstated correctly after pre-commissioning tests
5. Ensure that the tap setting of the transformer is in normal tap and pad locked
6. Ensure that all radiator valves are open
7. Ensure that CT shorting links are reinstated in Marshalling kiosk and in panels after pre-commissioning tests
8. Ensure that CT circuit connections are tight
9. Ensure that the auxiliary supply to the transformer is on and the indications are working correctly
10. Ensure that protective relays are set as per relay co-ordination documents
11. Ensure that Alarm and Trip settings of transformer Winding and Oil temperatures are set as per the vendors recommendations
12. Check the condition of silica gel breather and record the colour
13. Ensure that the any other preparatory checks/steps given in vendor procedure/commissioning manual are carried out
C. Pre-energisation Checks on Switchgears
Step Actions Sign/Date
1. Check and confirm that the incomer breaker is in service position and its spring is charged.
2. Ensure that earthing connections have been reinstated after the pre-commissioning tests.
3. Ensure that the busbar earth switch, bus coupler earth switch and cable side earth switch are kept open and locked with safety pad lock (wherever applicable).
4. Ensure all outgoing feeders of the Switchgear are isolated and locked.
5. In case of HV Switchgear, all the outgoing feeders shall be racked out to Test/Isolated position; busbar shutters/cable side shutters shall be locked with safety padlock and doors shall be closed and locked.
6. In case of 400V Board with non-isolatable type feeders, all the fuses in the outgoing feeders shall be removed and fuses shall be duly marked with feeder
-
Step Actions Sign/Date
numbers.
7. Ensure that the upstream side equipment is commissioned and is ready to energise the downstream equipment.
8. Ensure that the CT shorting links are reinstated after the pre-commissioning test; ensure that connections are tight.
9. Ensure that the protection relays and their settings are correct.
10. Ensure that all Voltage Transformer fuses are healthy and the earth connections are correct
11. Ensure that the Bus Coupler Breaker is open and in isolated position
12. Ensure that IPCS/ENMS/ICSS are ready and communicating to the Switchgear.
13. Ensure that the control power supply 110V DC/230V AC (UPS) /230V AC (wherever applicable) are on and the indications are working; verify the control supply voltages using a Multi-meter.
14. Ensure that the preparatory checks/steps given in vendor procedures and commissioning manual are carried out.
5.10.2 Energisation of Transformers
Step Actions Sign/Date
1. Confirm that all the preparatory works are completed as per Section 5.10.1-B, Pre-energisation checks.
2. Ensure the presence of primary power supply at the upstream Switchgear and the supply is within the tolerance limits.
3. Ensure that the secondary side Circuit Breaker of the Downstream Switchgears in Incomer and Earth Switch of the respective Transformer are open.
4. Check and ensure that all the indication lamps are healthy in primary and secondary breaker panels
5. At the upstream Switchgear, perform feeder de-earthing operation.
6. Operate the disconnector to ON position (wherever applicable) as per the vendors operating instructions.
7. Switch ON the primary circuit breaker of the concerned transformer feeder from the upstream panel as per the vendors operating instructions.
8. Check that the position indicators are correct with respect to the actual position of the disconnector
-
Step Actions Sign/Date
and breaker.
9. Check that the indication lamp is showing correct status of the breaker.
10. Check that the primary voltage and current are balanced.
11. Check that the voltage indications are working
12. Record the readings of the meters in the check sheet
13. Check the indications related signals to IPCS/ENMS/ICSS
14. Check the indications on the respective downstream Switchgear incomer for the presence of voltage.
15. Measure phase to phase and phase to neutral voltages to confirm secondary voltage of the transformer. Check and record the phase sequence across the secondary of the VT circuit.
16. Observe the transformer for any abnormal conditions noise, vibration, etc.
17. Put the transformer on no-load soak for 12 hours (duration to be decided at site in consultation with the vendor representative).
18. Monitor the transformer and record the winding temperature, oil temperature and voltages (primary and secondary) during the soak period.
19. After soaking period, switch OFF the transformer and check the Bucholz relay for collection of Air/Gas and vent off.
20. Correct the abnormalities identified during soaking.
21. Re-energise the transformer from upstream panel.
22. Close the secondary side circuit breaker in the downstream switchgear and ensure the following interlocks:
Ensure when downstream incomer CB is tripped, upstream primary CB trips on inter-trip and further inhibits closing of upstream CB, till fault gets reset at secondary side
Ensure downstream incomer gets tripped when upstream CB is opened or tripped
Ensure fault/close/open status in IPCS/ ENMS/ ICSS, upstream and downstream switchgears.
-
5.10.3 Energisation Switchgears
A. Energisation of Switchgear (Bus-A)
The transformers are now ready for loading. Initial energisation of Switchgear
will be done in bus sections with the Bus Coupler in open condition. Bus-A will
be initially energised.
Step Actions Sign/Date
1. Confirm that all the preparatory works are complete as per Section 5.10.1-C, Pre-energisation checks.
2. Ensure the availability of 110V DC/230V AC (UPS) /230V AC (wherever applicable) control supply to the control and auxiliary circuits
3. On Incomer Panel of Bus-A, ensure that the Earth Switch is open and the Circuit Breaker is in service position.
4. Ensure that the IPCS system is ready and the communications are established between ENMS & ICSS
5. Ensure that the line VT of incomer-1 is in service position.
6. Switch ON the MCB to provide 110 V AC line VT voltage signals to Relays, Meters and Indication lamps
7. On Incomer-1, check all the Phase Indicating Lamps to ensure the presence of voltage
8. Ensure that the indication lamps (on/off/auto trip/TCS Healthy) are healthy
9. Rack in the incomer-1 Circuit Breaker to service position
10. Ensure that all the conditions required for closing the Circuit Breaker are satisfied
a. Transformer is not faulty
b. Bus-A is not earthed
c. CB Mechanism is healthy
d. Cable side earth switch is open
e. Incomer under voltage relay is healthy
f. Incomer-1 is not faulty
g. Incomer-1 breaker is in service position
h. Incomer-1 Trip Circuit Supervision is healthy
i. Close permissive for Incomer-1
j. Bus Coupler CB is in open position/not in service
k. Upstream feeder CB is in service and ON
11. Ensure that the Bus-A VT is in service position.
12. Switch ON the MCB to provide 110V AC Bus VT voltage signals to relays, meters and indication
-
Step Actions Sign/Date
lamps
13. Ensure that all commissioning checks recommended for initial energisation by the vendor are complete
14. Ensure that the closing spring of the Circuit Breaker is charged
15. Close the Incomer-1 Circuit Breaker
16. Check the presence of bus voltage on all three phases using panel mounted voltmeter
17. Record the readings of the meters check sheet
18. Check the phase sequence of the voltage signals and record
19. Trip the Incomer Circuit Breaker via Transformer Protection. Ensure this CB trips, Inter trip of upstream and corresponding indications in all the places. Switch on the upstream and Incomer CB of the Switchgear under commissioning from remote, if applicable.
20. Check that the signals to IPCS/ENMS/ICSS system are correct
21. Check controls and indication to and from EWS
22. Observe the Switchgear for any abnormal conditions and take corrective action, if required.
23. After satisfactory initial energisation, the bus Section A of the Switchgear is ready for further checks with the Bus Coupler.
B. Energisation of Switchgear (Bus-B)
Step Actions Sign/Date
1. Confirm that all the preparatory works are completed as per Section 5.10.1-C, Pre-energisation checks.
2. Ensure the availability of 110V DC/230V AC (UPS) /230V AC (wherever applicable) control supply to the control and auxiliary circuits
3. On Incomer Panel of Bus-B, ensure that the Earth Switch is open and the Circuit Breaker is in service position.
4. Ensure that the IPCS system is ready and the communications are established between ENMS/ICSS
5. Ensure that the line VT of incomer-2 is in service position.
6. Switch ON the MCB to provide 110 V AC line VT voltage signals to relays, meters and indication lamps
7. On Incomer-2, check all the Phase Indicating
-
Step Actions Sign/Date
Lamps to ensure the presence of voltage
8. Ensure that the indication lamps (on/off/auto trip/TCS Healthy) are healthy
9. Rack in the Incomer-2 Circuit Breaker to service position
10. Ensure that all the conditions required for closing the Circuit Breaker are satisfied
a. Transformer is not faulty
b. Bus-B is not earthed
c. CB Mechanism is healthy
d. Cable side earth switch is open
e. Incomer under voltage relay is healthy
f. Incomer-1 is not faulty
g. Incomer-1 breaker is in service position
h. Incomer-1 Trip Circuit Supervision is healthy
i. Close permissive for Incomer-2
j. Bus Coupler CB is in open position/Not in service
k. Upstream feeder CB is in service and ON
11. Ensure that Bus-B VT is in service position.
12. Switch ON the MCB to provide 110V AC Bus VT voltage signals to relays, meters and indication lamps
13. Ensure that all commissioning checks recommended for initial energisation by the vendor are complete
14. Ensure that the closing spring of the Circuit Breaker is charged
15. Close the Incomer Circuit Breaker
16. Check the presence of bus voltage on all the three phases using panel mounted voltmeter
17. Record the readings of the meters in the check sheet
18. Check the phase sequence of voltage signals and record
19. Trip the Incomer Circuit Breaker via Transformer Protection. Ensure this CB trips, inter trip of upstream and corresponding indications in all the places. Switch on the upstream and the Incomer CB of the Switchgear under commissioning from remote, if applicable.
20. Check that signals to ENMS/ICSS system are correct
21. Check controls and indication to and from EWS
22. Observe the Switchgear for any abnormal conditions and take corrective action, if required.
23. After satisfactory initial energisation, the bus Section B of the Switchgear is ready for further checks with the Bus Coupler.
-
C. Energisation of Bus Couplers
Note: All the switchgears having bus sections have bus VTs. The phase
sequence of the section will be checked individually and the phase sequence
will be compared using volt meters.
Step Actions Sign/Date
1. Check the phase sequence of each section of the bus section as listed below, and record the results in the check sheet.
2. Check the phasing of busbars in the Bus Coupler panel as listed below and record the result in form
3. LV Switchgears
a. Rack out the Bus Coupler Circuit Breaker from the compartment
b. Open the top and bottom busbar shutters manually and temporarily latch it at the open position
c. Ensure that the meters used for testing have valid safety and calibration certificates
d. Use fused test leads
e. Select the appropriate voltage range for 600V AC
f. Check and ensure that there is voltage at each spout
g. Check the voltage across the similar phases of busbar at top and bottom; the voltage should be zero
h. Check the cross voltages across the top and bottom busbars; the value must be the same as the system voltage in all cases.
i. Record the results of phasing out measurements in the check sheet
j. Release the busbar shutter temporary latches and close the shutters
k. Return the coupler breaker into the compartment
l. Rack in the breaker to service position
4. HV Switchgears
a. Rack out the Bus Coupler Circuit Breaker from the compartment
b. Open the metering compartment and ensure that the respective PT terminals of each bus section (Bus-A & Bus-B) selected are correct
c. Ensure that the meters used for testing have valid safety and calibration certificates
d. Use fused test leads
e. Select the appropriate voltage range 110V AC
f. Check and ensure that there is voltage at each PT terminals
-
Step Actions Sign/Date
g. Check the voltage across the respective PTs of similar phases of Bus-A & Bus-B; the voltage should be zero
h. Check the cross voltages across the respective PTs of Bus-A & Bus-B; the value must be the same as the system voltage in all cases.
i. Record the results of phasing out measurements in the check sheet
j. Return the coupler breaker into the compartment
k. Rack in the breaker to service position
5. Dead Bus closing of the Bus Coupler with Incomer-2 open (Section B without power):
a. Ensure that all conditions required to close the Bus Coupler in Manual mode is satisfied.
i. Bus Coupler is in service
ii. Trip Circuit Supervision is healthy
iii. Incomer-2 Lockout relay is not operated
iv. Incomer-2 is open
b. Close the Bus Coupler Breaker
c. Check the indications and presence of voltage on bus Section B
d. Check the phase sequence on Section B at Bus VT and compare it with the phase sequence which was checked with the Incomer-2 CB closed. The phase sequence with Incomer-1 and this step shall be the same.
e. With successful Dead Bus closing checks and conditions satisfied, the Bus Coupler is ready for Live Bus closing check.
6. Dead Bus closing of the Bus Coupler with lncomer-1 open (Section A without power):
a. Ensure that all conditions required to close the Bus Coupler is satisfied.
i. Bus Coupler is in service
ii. Trip Circuit Supervision is healthy
iii. Incomer-1 Lockout relay is not operated
iv. Incomer-1 is open
b. Close the Bus Coupler Breaker
c. Check the indications and presence of voltage on bus Section A
d. Check the phase sequence on Section A at Bus VT and compare it with the phase sequence which was checked with the Incomer-1 CB closed. The phase sequence with Incomer-2 and this step shall be the same.
e. With successful Dead Bus closing checks and conditions satisfied, the Bus Coupler is ready for Live Bus closing check.
-
Step Actions Sign/Date
7. Live Bus closing of the Bus Coupler with Incomer-1 and Incomer-2 closed (Both the bus sections are live):
a. Ensure that all conditions required to close the Bus Coupler in Manual mode is satisfied.
i. Auto/Manual Selector Switch is in manual position
ii. Bus Coupler is in service position
iii. Trip circuit supervision is healthy
b. Close the Bus Coupler Breaker.
c. Check and ensure that there is no abnormal circulation current at the Bus Coupler ammeters.
d. Demonstrate the scheme checks in live/service condition and record the result in the form.
5.10.4 Functionality and Interlocks
A. Transformers
1. Functionality of the Transformers are checked and demonstrated during
soaking.
2. Interlocks of the Transformer breakers are tested during pre-
commissioning checks.
B. HV/LV Switchgears
Auto Transfer Scheme (ATS) Checking
Only 10kV and 400V Switchgears Bus Couplers are in normally open condition
and ATS may be checked on them. 35kV Bus coupler is kept in normally closed
condition.
After Auto Transfer changeover, returning to normal operating condition of
the breakers is completed manually.
Normal Condition
Step Actions Sign/Date
1. Both the incomer breakers of the Switchgears are in service and ON.
2. Supply voltages are within the limits
3. Auto/Manual Selector of the ATS selected to Auto
4. Vendor operation instruction and final drawings specific to the Switchgear shall be reviewed and followed to demonstrate the scheme.
5. Create Under Voltage on Incomer-1 (Bus-A) by opening the upstream Incomer Breaker for the Transformer
-
Step Actions Sign/Date
a. Ensure that the Bus Coupler CB closes to feed from Bus-B.
b. Check the voltage presence on Bus-A after Auto Transfer.
c. Normalise the bus sections by manual mode
d. Ensure that the Incomer Breaker closes and after that the Bus Coupler Breaker opens.
6. Create Under Voltage on Incomer-2 (Bus-B)
a. Ensure that the Bus Coupler CB closes to feed from Bus-A.
b. Check the voltage presence on Bus-B after Auto Transfer.
c. Normalise the bus sections by manual mode
d. Ensure that the Incomer Breaker closes and after that the Bus Coupler Breaker opens.
7. Check blocking of ATS for the following conditions (whichever is practical):
a. Simultaneous Under Voltage on both buses
b. Short time Under Voltage
c. Any Breaker is in test position
d. Lock out on any of the two Incomers except for Transformer fault
8. Check interface with IPCS/ENMS/ICSS for the following conditions during ATS demonstration:
a. Incomer CB tripped, ATS allowed
b. Incomer CB tripped, ATS inhibited
c. Inter trip of Upstream CB
9. Normalise the Switchgear after the tests by closing Incomer-1 & Incomer-2 CBs and by opening Bus Coupler CB
Note: For energizing switchgears of following configurations, the energization
procedure as outlined shall be followed with respective incomer with
concerned bus-coupler and applicable configurations.
5.10.5 Switchgear Configurations
Following are the different configurations of switchgear available in the facility.
A. 3 Bus sections/2 Bus couplers/2 Normal Incomers/2 Emergency Incomers from DG Sets
10kV Switchgear 04-SS01 (With Emergency Bus-E)
-
Fig. 5 Configuration with 3 Bus & 2B/C-SS01
1/C-A
N/C
B/C-A-E
N/O
1/C-E1
EDG 1
N/O
1/C-E2
EDG 2
N/C
B/C-E-B
1/C-B
B. 2 Bus sections/1 Bus coupler/2 Normal Incomers
35 kV Switchgear 04-SS01 (B/C-NC)
10 kV Switchgear 04-SS01 (B/C-NO)
400V Switchgear 04-SS01/02/03/04/05/06 (B/C-NO)
Fig. 6 - Configuration with 2 Bus & 1B/C
NORMAL INCOMER-A NORMAL INCOMER-B
1/C-A1/C-B
N/C
B/C
N/O
N/C
BUS-A BUS-B
C. 3 Bus sections/2 Bus couplers/2 Normal Incomers/1 Emergency Incomer from DG Set
400V Switchgear GTU-5,6,7 &8 (With Emergency Bus-C)
-
Fig. 7 - Configuration with 3 Bus & 2B/C-GTU
1/C-CN/C
N/O
B/C-A-B
1/C-B N/C
B/C-B-C
N/C
N/O
EDG
D. 1 Bus section/1 Normal Incomer/1 Emergency Incomer through transformer
400V Switchgear 04-SS01/02/03/04/05/06 (Emergency)
Fig. 8 Configuration with 1 Bus-LV Emergency CPF-1
NORMAL INCOMER EMERGENCY INCOMER
1/C-A 1/C-BN/C N/O
E. 1 Bus section/1 Normal Incomer
400V Switchgear - Infield pipeline
400V Switchgear - Export pipeline
400V Switchgear - Well head
5.11 35kV & 10kV Overhead Lines
Step Actions Sign/Date
1. Ensure that pre-commissioning checks are completed on the OHLs
2. Ensure that the downstream equipments are tested and ready to receive power
3. Prior to energisation, visually check the entire overhead line and the associated equipment
-
Step Actions Sign/Date
4. Megger the OHL and record the results
5. Give clearance to energise the OHL by switching on relevant Circuit Breaker
6. Observe for any abnormality
5.12 Motors
Step Actions Sign/Date
1. Ensure that all Pre-requisite checks are completed
2. Carryout Megger test on the system before energising.
3. Ensure that the protection settings are as per the relay setting document.
4. Check Anti Condensation heaters and record IR values.
5. With the motor uncoupled, run the motor from both local and remote to check the sequence interlocks. Also, check the correct operation, operation of emergency stop push button, indication and annunciation of devices like lamps, alarms, etc.
6. Rotation of the motor, whether clockwise or anticlockwise, is recorde