email replacement project bcnet conference april 18, 2008

33
Email Replacement Project BCnet Conference April 18, 2008 Frances Atkinson, IT Services Director Steve Hillman, IT Services Architect Annay Slabikowska, User Experience Coordinator, Email Project

Upload: erma

Post on 22-Mar-2016

36 views

Category:

Documents


2 download

DESCRIPTION

Email Replacement Project BCnet Conference April 18, 2008. Frances Atkinson, IT Services Director Steve Hillman, IT Services Architect Annay Slabikowska, User Experience Coordinator, Email Project. Topics. Why Replace the Current System? In Scope – Out of Scope Structure of Project - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Email Replacement Project BCnet  Conference  April 18, 2008

Email Replacement Project BCnet Conference April 18, 2008

Frances Atkinson, IT Services DirectorSteve Hillman, IT Services Architect

Annay Slabikowska, User Experience Coordinator, Email Project

Page 2: Email Replacement Project BCnet  Conference  April 18, 2008

Topics• Why Replace the Current System?• In Scope – Out of Scope• Structure of Project• Technical Infrastructure • Automated Data Migration • User Perspective: Who, what, when, how• What we Learned• Future Possibilities

Page 3: Email Replacement Project BCnet  Conference  April 18, 2008

High-level overview

SFU’s implementation of new email/calendaring technology

Page 4: Email Replacement Project BCnet  Conference  April 18, 2008

Why we replaced the current system

Page 5: Email Replacement Project BCnet  Conference  April 18, 2008

How we selected Zimbra

Page 6: Email Replacement Project BCnet  Conference  April 18, 2008

Why we selected Zimbra

Page 7: Email Replacement Project BCnet  Conference  April 18, 2008

Scope – Replaced coloured components

Page 8: Email Replacement Project BCnet  Conference  April 18, 2008

Scope – Details• Moved 50,000 email accounts to new system• Moved 1300 Corporate Time calendar accounts• Trained the support staff & end users• Branded the new system• Scaled the infrastructure & support to handle fully loaded

conditions• Retired the old Calendaring system• Still to do - Retire the old Email system

Page 9: Email Replacement Project BCnet  Conference  April 18, 2008

Out of Scope - What we did not do

Page 10: Email Replacement Project BCnet  Conference  April 18, 2008

Structure of Project

Page 11: Email Replacement Project BCnet  Conference  April 18, 2008

6/1/2008 9/30/2009

1-Jul-08 1-Aug-08 1-Sep-08 1-Oct-08 1-Nov-08 1-Dec-08 1-Jan-09 1-Feb-091-Mar-09 1-Apr-09 1-May-09 1-Jun-09 1-Jul-09 1-Aug-09 1-Sep-09

Contests

Stud

Faculty/Staff

CT

Other

Overall project timeline

Train

Page 12: Email Replacement Project BCnet  Conference  April 18, 2008

Technical perspective

SFU’s implementation of new email/calendaring technology

Page 13: Email Replacement Project BCnet  Conference  April 18, 2008

Legacy Architecture

Barracuda

Barracuda

MTA

MailLists

Mail Store

IMAPPOP

WebmailWebmail

Store

Desktop

Home Directories

Amaint LDAP Directory

Page 14: Email Replacement Project BCnet  Conference  April 18, 2008

Single server - vulnerable to system failure – expensive to replace

Page 15: Email Replacement Project BCnet  Conference  April 18, 2008

Several dated components

Page 16: Email Replacement Project BCnet  Conference  April 18, 2008

Our Email infrastructure was fully understood by one person – me

Page 17: Email Replacement Project BCnet  Conference  April 18, 2008
Page 18: Email Replacement Project BCnet  Conference  April 18, 2008

Technical Objectives

Page 19: Email Replacement Project BCnet  Conference  April 18, 2008

Zimbra Server Architecture

HTTP/SOAP

IMAP/POP

Postfix

Page 20: Email Replacement Project BCnet  Conference  April 18, 2008

MTAMailLists

Mail Store

IMAPPOP

Smtpserver

Page 21: Email Replacement Project BCnet  Conference  April 18, 2008

MTA

PrimaryMail Store

Index DB

ZimbraMailboxServer

Amaint

LDAP

iSCSI

PrimaryMail Store

Index DB

SecondaryMail Store

NFS

ZimbraMailboxServer

ZimbraMailboxServer

ZimbraMailboxServer

Proxy

LDAP

MTA

Proxy

LDAP

Zimbra Multi-Server Architecture

Page 22: Email Replacement Project BCnet  Conference  April 18, 2008

Developed Automated Migration Scripts

Page 23: Email Replacement Project BCnet  Conference  April 18, 2008

End-user perspective

SFU’s implementation of new email/calendaring technology

Page 24: Email Replacement Project BCnet  Conference  April 18, 2008

Who: Stakeholders

Page 25: Email Replacement Project BCnet  Conference  April 18, 2008

What: New technology

Page 26: Email Replacement Project BCnet  Conference  April 18, 2008

When? 1 year implementation timeline

Page 27: Email Replacement Project BCnet  Conference  April 18, 2008

How: Obtaining buy-in

Page 28: Email Replacement Project BCnet  Conference  April 18, 2008

How: Voluntary student signup

Page 29: Email Replacement Project BCnet  Conference  April 18, 2008

How: Engaging departmental computer support staff

Page 30: Email Replacement Project BCnet  Conference  April 18, 2008

How: Voluntary staff / faculty signup

Page 31: Email Replacement Project BCnet  Conference  April 18, 2008

How/When: Moving calendaring users

Page 32: Email Replacement Project BCnet  Conference  April 18, 2008

Lessons Learned

Page 33: Email Replacement Project BCnet  Conference  April 18, 2008

Future Possibilities