8/27/2019 1 EMBANKMENTS! ±~DITCH PLUGS EMBANKMENTS! Process – 1. Layout embankment as shown on plan. 2. Strip and stockpile topsoil (aka. ‘subcut’). This is a pay item. 3. Locate borrow source a minimum of 100’ from upstream embankment toe, strip borrow area. 4. Backfill and compact embankment in lifts according to the compaction method specified on the plans. This is a pay item. 5. Take elevations of top of finished embankment grade, prior to topsoil being reapplied, to confirm design elevation has been met, including the needed amount of overbuild for settlement. 6. Seeding. This is a pay item. 7. Mulching, if required. This is a pay item. EMBANKMENTS! Possible Extra Embankmentrelated items: 1. Core trench. May or may not be called out on the plans. This is a pay item. 2. Wave or rodent berm. Should be called out on the plans. May or may not be a pay item. 3. Rodent rock trench or rodent fence. This will be called out on the plans. This is a pay item. Stripping Topsoil - Subcut Standard Depth = ±6 inches. Intent is to remove vegetation, organic matter and the bulk of the root mass.

Upload: others

Post on 24-Jan-2021

6 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/27/2019

    1

    EMBANKMENTS!±~DITCH PLUGS

    EMBANKMENTS!Process –1. Layout embankment as shown on plan.2. Strip and stockpile topsoil (aka. ‘subcut’). This is a pay item.3. Locate borrow source a minimum of 100’ from upstream 

    embankment toe, strip borrow area.4. Backfill and compact embankment in lifts according to the 

    compaction method specified on the plans. This is a pay item.5. Take elevations of top of finished embankment grade, prior to 

    topsoil being reapplied, to confirm design elevation has been met, including the needed amount of overbuild for settlement.

    6. Seeding. This is a pay item.7. Mulching, if required. This is a pay item.

    EMBANKMENTS!

    Possible Extra Embankment‐related items:1. Core trench. May or may not be called out on the plans.  

    This is a pay item.2. Wave or rodent berm. Should be called out on the plans.  

    May or may not be a pay item.3. Rodent rock trench or rodent fence. This will be called out 

    on the plans. This is a pay item.

    Stripping Topsoil - SubcutStandard Depth = ±6 inches.  Intent is to remove vegetation, organic matter and the bulk of the root mass.

  • 8/27/2019

    2

    Stripping Topsoil - Subcut Core Trench

    Needed when foundation soil after topsoil is stripped (subcut) is unsuitable or undesirable for supporting the embankment.

  • 8/27/2019

    3

    Borrow Area

    Needs to be located a minimum of 100’ from the upstream toe of the embankment, preferably in the wetland, or on the edge of the wetland footprint if at all possible.

    Sometimes, the borrow material can be a little TOO wet!

    After the embankment is completed, the borrow area should be finished in such a manner that it relatively smooth on bottom, not more than 3’ deep, have 6:1 or flatter side slopes and have topsoil re‐spread across it as conditions allow.

  • 8/27/2019

    4

    Backfill in lifts using the compaction method specified on the plans. There are multiple ways for the contractor to get the borrow material to the embankment.

    Backfill/Building the Embankment

  • 8/27/2019

    5

  • 8/27/2019

    6

    Seeding

    There are multiple ways to seed the completed embankments, spillways and other components that require seeding:1. Based on the timing of construction, they could get seeded when the 

    entire site gets seeded (although that’s not what the specs say ).  The Contractors generally LOVE this idea, but in reality, it rarely happens.

    2. Hire a subcontractor – can be cost prohibitive, unless it’s a larger project. Not our problem, however!

    3. Contractor does it, of which there are several methods (listed in order of this inspector’s preference):1. Rent an SWCD seeder.2. Use a PTO‐driven broadcast spreader.3. Use an ATV‐mounted broadcast spreader of some type.4. Use hand‐operated broadcast spreader.

    In the Specs, there are rules to follow regarding times when the embankments should be seeded, dormant seeding, temporary seeding for cover, as well as seedbed prep prior to seeding, etc.

  • 8/27/2019

    7

    MulchingRequired for late‐season construction to protect dormant‐seeded embankments and spillways from erosion due to spring snow melt run‐off, as well as heavy precipitation events prior to successful vegetation establishment.

    Good Mulching

    Not so Good Mulching

    QUESTIONS?

  • 8/27/2019

    8

    SPILLWAYSThe purpose of a spillway is to convey excess water from the wetland to a downstream waterway in a controlled manner.Spillways can be referred to as either ‘principle’ or ‘emergency’, and oftentimes there may be only one spillway, which functions as both.This is a pay item.

    Spillways can be either ‘natural’ or ‘constructed’.  On sites with existing vegetation, natural spillways can be desirable, as the vegetation is already established, therefore the potential for erosion is greatly diminished.

    For constructed spillways, the control section is critical.  It needs to be level and flat, both lengthwise and crosswise. 

  • 8/27/2019

    9

    CONTROL SECTION

    QUESTIONS?