EMC® Service Assurance Suite® 9.5.1
SolutionPack Performance and Scalability Guidelines
Abstract
The performance and scalability guidelines outlined here are based
on tests run on EMC M&R configured in a production-like
environment. Both live and simulated configuration items were
used to measure the performance and scalability of EMC M&R.
May 2018
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 2
Copyright © 2008-2018 Dell Inc, and its subsidiaries. All rights reserved. Published in the USA. Published
May 2018
Dell believes the information in this publication is accurate as of its publication date. The information is subject to change without notice.
The information in this publication is provided as is. Dell Corporation makes no representations or warranties of any kind with respect to the
information in this publication, and specifically disclaims implied warranties of merchantability or fitness for a particular purpose. Use, copying,
and distribution of any Dell software described in this publication requires an applicable software license.
Dell, EMC, and other trademarks of Dell Inc. or its subsidiaries. Other trademarks may be the property of their respective owners. EMC Corporation Hopkinton, Massachusetts 01748-9103 1-508-435-1000 In North America 1-866-464-7381 www.EMC.com
302-004-783 Rev 01
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 3
Table of Contents Table of Contents ................................................................................................................................. 3
1 Overview ........................................................................................................................................... 4
2 Audience ........................................................................................................................................... 4
3 Purpose ............................................................................................................................................. 4
4 Infrastructure planning guidelines ................................................................................................... 4
5 Deployment Planner tool .................................................................................................................. 5
I. Resource description and specification of deployment types ........................................................... 5
II. Guideline P2- Increase default disk space ......................................................................................... 5
6 SAS SolutionPacks Supported for Deployment ................................................................................ 6
6.1 SolutionPack for EMC Smarts .................................................................................................................. 6
I. Deployment Planner Inputs ............................................................................................................... 6
II. Steps to obtain Managed Ports and Interfaces ................................................................................. 6
III. Comparison of 9.5 Vs 9.5.1 .............................................................................................................. 7
IV. Reference ......................................................................................................................................... 7
6.2 SolutionPack for Optical Wavelength Services ........................................................................................ 7
I. Deployment Planner Inputs ............................................................................................................... 7
II. Comparison of 9.5 Vs 9.5.1 ............................................................................................................... 8
6.3 SolutionPack for Huawei iManager M2000 ............................................................................................. 8
I. Deployment Planner Inputs ............................................................................................................... 8
II. Comparison of 9.5 Vs 9.5.1 ............................................................................................................... 8
III. Reference ......................................................................................................................................... 8
6.4 SolutionPack for EMC Network Configuration Manager ......................................................................... 8
I. Sizing Inputs ....................................................................................................................................... 8
II. Comparison of 9.5 Vs 9.5.1 ............................................................................................................... 9
III. Reference ...................................................................................................................................... 10
6.5 SolutionPack for Transaction ................................................................................................................. 10
I. Deployment Planner Inputs ............................................................................................................. 10
II. Comparison of 9.5 Vs 9.5.1 ................................................................................................................. 10
6.6 SolutionPack for Traffic Flows ............................................................................................................... 10
I. Sizing Inputs ......................................................................................................................................... 10
6.7 SolutionPack for CUCM ......................................................................................................................... 11
I. Test Bed Details: ............................................................................................................................... 11
II. CDR/CMR report processing and report rendering results ............................................................. 11
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 4
1 Overview The guidelines for an optimized performance and scalability are related to planning the
hardware and virtual environment, disk space, network latency, and deployment and
configuration.
• Planning guidelines help determine the right ESX hardware and the number of
virtual machines needed for a specific data center environment.
• Disk space guidelines help prepare and configure datastore capacity before EMC
M&R deployment.
• Network latency guidelines help identify the proximity and placement of EMC
M&R virtual machines with respect to the configuration items.
• Deployment and configuration guidelines assist with deployment and
postdeployment.
EMC M&R is fully deployable on non-ESX hosts. EMC M&R Performance and Scalability
Guidelines do not address non-ESX host deployment scenarios.
EMC M&R Performance and Scalability Guidelines do not address all of the SolutionPacks
contained in EMC M&R.
2 Audience This article is for EMC M&R installers, administrators or anyone who manages the EMC M&R
application.
3 Purpose After reading this article, you will have guidelines to follow to ensure you can configure
EMC M&R for optimal performance based on the scale of your environment.
4 Infrastructure planning guidelines Use these guidelines to plan the infrastructure such as the right ESX hardware, number of
virtual machines needed, and other details described in the tables to ensure an optimum
performance and scalability.
Note: Any Solution Pack that generates more than 5M metrics should have an exclusive
EMC M&R deployment.
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 5
5 Deployment Planner tool The EMC M&R Deployment Planner tool can be used in conjunction with these guidelines
to help scope specific environment requirements. Using known data about the
environment, the tool will estimate EMC M&R hardware needs, provide metric counts
(with growth factor), and include pointers to performance and scalability guidelines
specific to the environment.
Access the Deployment Planner tool on the Downloads for EMC M&R page at:
https://support.emc.com/products/31946_Service-Assurance-Suite/Tools/
I. Resource description and specification of deployment types
Deployment Type Purpose of VM vCPUs Memory (GB) Disk Space(GB) VM Count
All-in-one (POC – Not for Production)
All components in
a single VM 4 32 600 1
Standard Deployment (SA Suite 4-VM)
Frontend 4 16 120 1
Backend-Primary 4 24 600 - 1000 1
Backend- Secondary
4 16 1,200 - 2650 1
Collector 4 16 120 1
Scale-out Deployment (Requires Standard Deployment)
Additional
Backend 4 16 1,200 - 2650 1
Additional
Collector 4 8 -16 120 1
Notes:
• It is recommended to remove the Generic RSC and Generic SNMP Collector
Managers from the Additional Collectors if there are no hosts or SNMP devices
being discovered, so as to reduce the Collector footprint.
• The Frontend has been tested for 10 concurrent users
• The disk space specification in this table assumes default retention policies.
II. Guideline P2- Increase default disk space
After deploying EMC M&R standard deployment (SA Suite 4-VM), the disk space
must be increased for both primary and secondary backends. The default disk space
on the primary and secondary backends is 150 GB.
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 6
The default disk space on Frontend is 150 GB. Increase the disk space on the
Frontend
6 SAS SolutionPacks Supported for Deployment The following SAS SolutionPacks are supported by the Deployment Planner:
o SolutionPack for EMC Smarts o SolutionPack for Optical Wavelength
Services o SolutionPack for Huawei iManager M2000 o SolutionPack
for Network Configuration Manager (NCM) o SolutionPack for
Transaction o SolutionPack for Traffic Flows o SolutionPack for Cisco
Unified Communication Manager (CUCM)
6.1 SolutionPack for EMC Smarts
I. Deployment Planner Inputs
Input Field Description
Devices Total number of Devices
Performance
Instrumentation Total number of Managed Ports and Interfaces with
Performance Instrumentation
Fault
Instrumentation Total number of Managed Ports and Interfaces with Fault
Instrumentation
II. Steps to obtain Managed Ports and Interfaces
Execute the following command to obtain the total number of Fault and
Performance Instrumentation per IP Domain Manager. This should be repeated for
the all the IP Domain Managers and the total across domains should be provided as
input.
# ./sm_tpmgr -s INCHARGE-AM-PM --sizes | grep "Total Number of NetworkAdapters"
Output: Total Number of NetworkAdapters: 20000 [20000/20000]
Note: In the square brackets, the first part is Fault and the second one is Performance
Instrumentation Numbers.
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 7
III. Comparison of 9.5 Vs 9.5.1
Smarts SP 9.5 9.5 .1
Maximum Collector Instances 2 2
Maximum Metrics per collector 2M 2M
IV. Reference
The following sizing sheets to be used to size Smarts Domain Managers for your
environment:
• EMC Smarts IP Version 9.5.1 Performance Benchmarking and Sizing
Guidelines
• EMC Smarts SAM Version 9.5.1 Performance Benchmarking and Sizing
Guidelines
• EMC Smarts ESM Version 9.5.1 Performance Benchmarking and Sizing
Guidelines
6.2 SolutionPack for Optical Wavelength Services
I. Deployment Planner Inputs
Input Field Description
Optical Network
Elements Total number of Optical Network Elements
Equipments Average number of Equipments per Optical Network Element
Physical
Termination Points
Average number of Physical Termination Points per Optical
Network Element.
Subnetwork
Connections Total number of Subnetwork Connections(SNC)
Topological Links Total number of Topological Links
Example:-
An Optical Network Element could have ~600 Physical Termination Points. The input here will
be #OpticalNetworkElements * Avg. #PhysicalTerminationPoints.
An Optical Network Element could have ~50 Equipments. The input here will be
##OpticalNetworkElements * Avg. #Equipments
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 8
II. Comparison of 9.5 Vs 9.5.1
Optical Wavelength Services SP 9.5 9.5.1
Maximum Collector Instances 3 3
Maximum Metrics per collector 2M 2M
6.3 SolutionPack for Huawei iManager M2000
I. Deployment Planner Inputs
Input Field Description
Devices Total number of Devices = Cell + Station + Controller
Counters Average number of Counters per Counter-group.
Example: “67109376” is one of the Counter-groups and “VS.RAB.AbnormRel.CS” &
“VS.RAB.NormRel.CS” are 2 Counters part of this group. Get the average number of Counters
of all the Counter-groups and provide this average as input to “# Counters” in the deployment
planner.
II. Comparison of 9.5 Vs 9.5.1
Huawei iManager M2000 SP 9.5 9.5.1
Maximum Collector Instances 2 2
Maximum Metrics per collector 2M 2M
III. Reference
1. For Hard Disk space usage: Please refer SolutionPack for Huawei iManager M2000 ->
Performing post installation tasks-> Refer point 1
6.4 SolutionPack for EMC Network Configuration Manager
I. Sizing Inputs
Input Field Description
Devices Total number of Devices
Tests
Total number of Tests = Total number of policies *
Standards per policy * Tests per standard
Example: If there are 10 policies, each policy has 10 Standard
associated and Each standard has 5 Test associated
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 9
Jobs
Total number of Jobs data
II. Comparison of 9.5 Vs 9.5.1
Network Configuration Manager SP 9.5 9.5.1
Maximum Collector Instances 2* 2*
Maximum Metrics per collector 1.7M 1.7M
* Two collector manager instances are for Compliance and Jobs (jobs + inventory) respectively
The following are the deployment recommendations for NCM Solution Pack v3.1
Option1: (Recommended for <3.5M (Compliance and Jobs data))
• M&R Platform + NCM Solution Pack -> Single VM (32G, 4vCPU)
• NCM Distributed/Combo
• Heap size on collector manager instance increased to 8GB
• Hard disk space increased to 600GB
System instability observed beyond 4M with single VM configuration (High
Memory/CPU utilization, backend and UI unresponsiveness)
Option2: (Recommended for > 3.5M and <7.8M (Compliance and Jobs data))
• M&R Platform + NCM Solution Pack -> Distributed (4VMs)
• 1VM for Frontend (16G, 4 vCPU)
• 1VM for Collector (24G, 4 vCPU)
• 1VM for Backend Database (24G, 4vCPU) and
• 1VM for Additional Backend Database(16G, 4vCPU)
• NCM Distributed
• Heap size on collector manager instances, load balancer, Front-end, APG
backend(apg, apg1, apg2, apg3, apg4) increased to 8GB
• All the 4 VMs Hard disk space increased to 600GB
System instability observed beyond 7.8M with distributed VM configuration
(High Memory/CPU utilization, backend and UI unresponsiveness)
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 1
0
III. Reference
The following sizing sheets to be used to size NCM Core for your environment:
EMC Network Configuration Manager Version 9.5.1 Performance
Benchmarking and Sizing Guidelines
6.5 SolutionPack for Transaction
I. Deployment Planner Inputs
Input Field Description
HTTP Servers Total Number of HTTP & HTTP HEAD Servers
Authentication
Servers Total Number of LDAP Servers
Other Servers
Total Number of DNS, FTP, SFTP, TCP CONNECT, RADIUS, SQL
and SCRIPT
II. Comparison of 9.5 Vs 9.5.1
Transaction SP 9.5 9.5.1
Maximum Collector Instances 3 3
Maximum Metrics per collector 40000 40000
6.6 SolutionPack for Traffic Flows
I. Sizing Inputs
Input Field Description
Devices Total number of Devices
Ports & Interfaces Total number of Ports & Interfaces
Flows per second Total number of Flows per second
The following are the deployment recommendations for Traffic flow Solution Pack v4.1
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 1
1
Option1: Combo /Single Server Deployment
• M&R Platform + Traffic Flow Solution Pack -> Single VM (32GB, 4vCPU)
• Heap size on event processing manager instance increased to 8GB
• 3 GHz Dual-processor server
• 600GB (OS and Application) Disk
• Separate 1TB Flow storage
Up to 10K Flows per second (per Core CPU) are processed on a single VM
configuration.
Option2: Distributed Deployment
• M&R Platform + Traffic Flow Solution Pack -> Distributed (3 VMs)
• 1VM for Frontend (32GB, 4 vCPU)
• 1VM for Collector (32GB, 4 vCPU)
• 1VM for Backend Database (32GB, 4vCPU)
• Heap size on event processing manager instances, Front-end, APG backend
increased to 8GB
• 3 GHz Dual-processor server
• 600GB (OS and Application) Disk Separate 1TB Flow storage
Up to 10K Flows per second (per Core CPU) per event processing manager on a
collector VM are processed. There can be only one event processing manager per
collector VM.
6.7 SolutionPack for CUCM
I. Test Bed Details:
Setup is created on a Single VM with CentOS 6.8 Operating System, 200 GB of Disk Space, RAM 32GB (dedicated), and 4 CPUs per host. Captured below are the readings for CDR/CMR records that were processed and their rendering times.
II. CDR/CMR report processing and report rendering results
Note: Average number of calls that are incrementally updated on the front-end is
7200 calls per hour.
EMC Service Assurance Suite 9.5.1 SolutionPack Performance and Scalability Guidelines 1
2
Solution Pack for CUCM v1.1.1 with 6.5u4 beyond 250K events observed High CPU
utilization, backend and UI unresponsiveness.
Scenarios CUCM SP v1.1.1
(6.5u4)
CUCM SP v2.1
(6.7u1)
CUCM SP v3.0
(6.8u2)
CUCM SP v3.1
(6.8u5)
Time taken for Cisco-
VoIPCUCM Collector to
process 10k events
2.750s 2.75s 8s 8s
Number of events -> 170K 170k 170K 170K
Time taken for rendering Call
OverView Report
0.303s 0.356s 0.550s 0.550s
Time taken for rendering Call
Duration OverView Report
0.795s 0.549s 0.470s 0.470s
Time taken for rendering QoS
Report
0.393s 0.409s 1.018s 1.018s
Time taken for
rendering Voice Quality by
Streams
2.897s 0.377s 1.760s 1.760s
Time taken for rendering Calls
Statistics
2.897s 1.167s 2.5s 2.5s
Note: Average number of calls that are incrementally updated on the front-end is 7200
calls per hour.
Solution Pack for CUCM v1.1.1 with 6.5u4 beyond 250K events observed High CPU
utilization, backend and UI unresponsiveness.